CN211091090U - Mine tailing slope maintenance system - Google Patents

Mine tailing slope maintenance system Download PDF

Info

Publication number
CN211091090U
CN211091090U CN201921778743.6U CN201921778743U CN211091090U CN 211091090 U CN211091090 U CN 211091090U CN 201921778743 U CN201921778743 U CN 201921778743U CN 211091090 U CN211091090 U CN 211091090U
Authority
CN
China
Prior art keywords
tailing
slope
side slope
collecting tank
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921778743.6U
Other languages
Chinese (zh)
Inventor
张千新
高苒
尹泰旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Urad Houqi Zijin Mining Co Ltd
Original Assignee
Urad Houqi Zijin Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Urad Houqi Zijin Mining Co Ltd filed Critical Urad Houqi Zijin Mining Co Ltd
Priority to CN201921778743.6U priority Critical patent/CN211091090U/en
Application granted granted Critical
Publication of CN211091090U publication Critical patent/CN211091090U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a mine tailing slope maintenance system, which comprises a tailing slope, wherein the top of the tailing slope is provided with an inwards concave chute, a water collecting tank is arranged in the center of the concave chute, a submersible pressure pump is arranged in the water collecting tank, the outlet of the submersible pressurizing pump is communicated and fixed with an annular arrangement pipe arranged at the upper part of the tailing side slope through a conveying pipe, the bottom of the annular arrangement pipe is evenly communicated and fixed with a plurality of greening branch pipes, the top of the tailing slope is provided with an inward concave chute for collecting rainwater, and the inward concave chute is provided with a water collecting tank for collecting water, the collected rainwater is conveyed to the tailing side slope in dry seasons for green plant maintenance, manpower and water resources are saved, and the plant roots on the tailing side slope can absorb moisture and nutrients, so that plants can grow normally, the environment of a mine is greatly improved, and the ecological effect of maintaining the tailings is good.

Description

Mine tailing slope maintenance system
Technical Field
The utility model relates to a mine field, concretely relates to mine tailing side slope maintenance system.
Background
China is a big country with resources such as mineral products, but due to laggard technical and thought consciousness, the disordered mining of the mineral resources causes the destruction of a large amount of resources such as land, water and the like. The method is especially important for recovering and treating the mine in order to improve the utilization rate of mineral resources and leave a good environment of green water of the green hills. Researches on the aspects of mine environment treatment and ecological reconstruction show that main limiting factors for slope greening of mine tailings are drought soil matrix and barren nutrients, rainwater cannot be collected in rainy seasons, and frequent watering is needed in dry seasons due to poor water retention capacity of soil, so that manpower and resource waste is caused, the absorption of plant root systems to water and nutrients is influenced, and the normal growth and development of plants are further influenced.
SUMMERY OF THE UTILITY MODEL
In order to solve the problem of the existence, the utility model provides a mine tailing side slope maintenance system.
The utility model discloses a realize through following technical scheme:
the utility model provides a mine tailing side slope maintenance system, includes the tailing side slope, open at the top of tailing side slope has the indent chute, the central authorities of indent chute are provided with the header tank, the inside dive force (forcing) pump that is provided with of header tank, dive force (forcing) pump export is fixed through conveyer pipe and the annular arrangement pipe intercommunication that sets up on tailing side slope upper portion, the bottom that the annular arrangement was managed evenly communicates and is fixed with a plurality of afforestation branch pipe.
The annular arrangement pipes are placed on the upper portions of the side slopes of the tailing slopes, and the plurality of greening branch pipes are obliquely arranged on the side slopes of the tailing slopes.
The water collecting tank is deeply buried at the top of the tailing slope, the upper edge of the water collecting tank extends to the upper part of the inward concave chute by about 15cm-20cm, and the middle part of the upper edge of the water collecting tank extending to the inward concave chute is provided with a plurality of overflow holes.
The greening branch pipe is provided with a plurality of atomizing nozzles, and the conveying pipe is provided with a control valve.
Compared with the prior art, the beneficial effects of the utility model are that: this practicality is through setting up the indent chute of collecting the rainwater at tailing side slope top to set up the header tank that catchments on the indent chute, carry the rainwater of collecting to the tailing side slope in dry season and carry out the maintenance of green planting, saved manpower and water resource, thereby it makes the normal growth of plant to guarantee the absorption of plant roots on the tailing side slope to moisture and nutrient and develops, great improvement the environment in mine, play fine maintenance effect to the ecology of tailing.
Drawings
Fig. 1 is a perspective view of the structure of the present invention;
FIG. 2 is an enlarged view of a portion of the structure of FIG. 1;
FIG. 3 is another perspective view of FIG. 1;
FIG. 4 is a schematic structural view of the greening branch pipe of the present invention;
in the figure: the device comprises a tailing slope 1, a water collecting tank 2, an inwards concave chute 3, an overflow hole 4, a submersible pressure pump 5, a conveying pipe 6, a control valve 7, an annular arrangement pipe 8, a greening branch pipe 9 and an atomizing spray head 10.
Detailed Description
The invention will be described in further detail with reference to the following detailed description and accompanying drawings:
as shown in fig. 1, 2, 3 and 4, a mine tailing slope maintenance system comprises a tailing slope 1, an inward concave chute 3 is formed in the top of the tailing slope 1, a water collection tank 2 is arranged in the center of the inward concave chute 3, a submersible pressure pump 5 is arranged inside the water collection tank 2, the outlet of the submersible pressure pump 5 is fixedly communicated with an annular arrangement pipe 8 arranged on the upper portion of the tailing slope 1 through a conveying pipe 6, and a plurality of greening branch pipes 9 are uniformly communicated and fixed to the bottom of the annular arrangement pipe 8.
The annular arrangement pipes 8 are placed at the upper parts of the side slopes of the tailing side slopes 1, and the plurality of greening branch pipes 9 are obliquely arranged on the side slopes of the tailing side slopes 1.
The water collecting tank 2 is deeply buried at the top of the tailing side slope 1, the upper edge of the water collecting tank 2 extends to the upper part of the inward concave chute 3 by about 15cm-20cm, and the middle part of the upper edge of the water collecting tank 2 extending to the inward concave chute 3 is provided with a plurality of overflow holes 4.
The greening branch pipe 9 is provided with a plurality of atomizing nozzles 10, and the conveying pipe 6 is provided with a control valve 7.
The working principle is as follows: when raining in rainy season, rainwater falls on the top of the tailing slope 1, is gathered in the concave chute 3 and flows into the water collecting tank 2 through the overflow hole 4 to be collected, the upper edge of the water collecting tank 2 extends to the upper part of the concave chute 3 by about 15cm-20cm, the overflow hole 4 is arranged in the middle of the upper edge, sand and mud on the top of the tailing slope 1 can be effectively prevented from entering the water collecting tank 2, and the cleanness of the water collecting tank 2 is guaranteed;
when raining less in dry seasons, can start dive force (forcing) pump 5 and open control valve 7, dive force (forcing) pump 5 carries the rainwater of header tank 2 collection in the annular arrangement pipe 8 through conveyer pipe 6, in the distribution of annular arrangement pipe 8 carries each afforestation minute pipe 9 with the rainwater, through the atomizer 10 blowout on afforestation minute pipe 9 of distribution on 1 side slope of tailing side slope, afforest for green plant on the tailing side slope 1, manpower and water resource have been saved, thereby guarantee the plant root system on the tailing side slope 1 and make the normal growth of plant develop to the absorption of moisture and nutrient, great improvement the environment in mine, play fine maintenance guard action to the ecology of tailing.
The foregoing illustrates and describes the principles, general features, and advantages of the present invention. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (4)

1. The utility model provides a mine tailing side slope maintenance system, includes tailing side slope (1), its characterized in that: the top of tailing side slope (1) is opened there is indent chute (3), the central authorities of indent chute (3) are provided with header tank (2), header tank (2) inside is provided with dive force (forcing) pump (5), dive force (forcing) pump (5) export is fixed with the annular arrangement pipe (8) intercommunication that sets up on tailing side slope (1) upper portion through conveyer pipe (6), the bottom that the annular was arranged pipe (8) evenly communicates and is fixed with a plurality of afforestation and is in charge of (9).
2. The mine tailing slope maintenance system according to claim 1, characterized in that: the annular arrangement pipes (8) are placed on the upper portions of the side slopes of the tailing slopes (1), and the plurality of greening branch pipes (9) are obliquely arranged on the side slopes of the tailing slopes (1).
3. The mine tailing slope maintenance system according to claim 1, characterized in that: the water collecting tank (2) is deeply buried at the top of the tailing side slope (1), the upper edge of the water collecting tank (2) extends to about 15cm-20cm of the upper part of the inward concave chute (3), and the middle part of the upper edge of the water collecting tank (2) extending to the inward concave chute (3) is provided with a plurality of overflow holes (4).
4. The mine tailing slope maintenance system according to claim 1, characterized in that: the greening branch pipe (9) is provided with a plurality of atomizing nozzles (10), and the conveying pipe (6) is provided with a control valve (7).
CN201921778743.6U 2019-10-22 2019-10-22 Mine tailing slope maintenance system Expired - Fee Related CN211091090U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921778743.6U CN211091090U (en) 2019-10-22 2019-10-22 Mine tailing slope maintenance system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921778743.6U CN211091090U (en) 2019-10-22 2019-10-22 Mine tailing slope maintenance system

Publications (1)

Publication Number Publication Date
CN211091090U true CN211091090U (en) 2020-07-28

Family

ID=71687414

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921778743.6U Expired - Fee Related CN211091090U (en) 2019-10-22 2019-10-22 Mine tailing slope maintenance system

Country Status (1)

Country Link
CN (1) CN211091090U (en)

Similar Documents

Publication Publication Date Title
CN101642768B (en) Method for restoring uranium milltailings by utilizing plants
CN113649409B (en) Ecological restoration method for acid mine tailing pond/waste dump
CN202907427U (en) Saline and alkaline land salt-insulating salt-discharging greening device
CN111099927A (en) Biomass fertilizer production and tree cultivation method
CN102783402A (en) Bag culture system for large-scale production of solanaceous vegetables
CN103704105A (en) Dendrobium candidum dedicated cultivation substrate and application thereof
CN104996016A (en) Self-propelled double-layer straw and surface soil mulching machine for orchard
CN101518186A (en) Method of recovering and reconstructing vegetation of mining land
CN102511279B (en) Method for promoting growth of evergreen arbors in manganese ore degraded area
CN105580684A (en) Tailing dam plant remediation cultivation method
CN104429385B (en) The double-deck mulch-laying machine of a kind of orchard stalk
CN101082079A (en) Plant arsenic-extraction pretreatment method for lowering smelting selection cost of high-arsenic gold ore
CN213755599U (en) Fruit and vegetable fertilization management device after flood
CN211091090U (en) Mine tailing slope maintenance system
CN113273426A (en) Method for comprehensively planting shaddock trees on waste barren hills by using medium containing traditional Chinese medicine residues
CN210226428U (en) Water collecting device for deep irrigation of soil
CN206365243U (en) A kind of hillside Chinese medicine combined seed and fertilizer drill
CN106717226A (en) One kind application Stalk blanket carries out method for greening desert
CN110122143A (en) A kind of walnut forest land water-retaining method
CN112930746B (en) Soil improvement method for planting vegetables in agriculture
CN104541872A (en) Mining area afforestation and reclamation method
CN204859930U (en) Self -propelled orchard straw and double -deck mulch laying machine of surface soil
CN204907243U (en) Streamside area soil configuration
CN105993843B (en) A kind of winter jujube brackish water trickle irrigation mode for alleviating the soil salinization
CN204888034U (en) Double -deck mulch laying machine of self -propelled orchard straw

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200728

CF01 Termination of patent right due to non-payment of annual fee