CN210887297U CN201920858370.7U CN201920858370U CN210887297U CN 210887297 U CN210887297 U CN 210887297U CN 201920858370 U CN201920858370 U CN 201920858370U CN 210887297 U CN210887297 U CN 210887297U
Authority
CN
China
Prior art keywords
concrete carrier
passageway
concrete
water supply
channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920858370.7U
Other languages
Chinese (zh)
Inventor
钱冬旭
凌建强
陆敏博
张卫萍
陈晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCDI Suzhou Exploration and Design Consultant Co Ltd
Original Assignee
CCDI Suzhou Exploration and Design Consultant Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCDI Suzhou Exploration and Design Consultant Co Ltd filed Critical CCDI Suzhou Exploration and Design Consultant Co Ltd
Priority to CN201920858370.7U priority Critical patent/CN210887297U/en
Application granted granted Critical
Publication of CN210887297U publication Critical patent/CN210887297U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a pipeline embedded structure, including the concrete carrier, the inboard symmetry of lower extreme of concrete carrier is provided with information channel and electric power passageway, and the upper end surface symmetry of mixing the earth carrier is provided with gas channel and water supply channel, and gas channel is provided with the overlap joint piece with water supply channel's inner wall, and the apron has been placed to the upper end of overlap joint piece. Apron and ground parallel and level when this kind of pipeline embedded structure installs, concrete carrier has adopted concrete cooperation E shape stirrup, circular stirrup to connect the strengthening rib and has strengthened concrete carrier's crushing when the crushing nature makes its installation and ground parallel and level and has made things convenient for laying and the inspection of pipeline, and concrete carrier inside is provided with information passageway, electric power passageway, gas passageway and water supply channel, and one time pre-buried saves excavation many times and has practiced thrift construction cost.

Description

Pipeline pre-buried structure
Technical Field
The utility model relates to a civil engineering technical field specifically is a pipeline embedded structure.
Background
The pipeline is pre-buried for the pipe to pass through the holes reserved in the members such as soil, brick wall, concrete beam and concrete wall. It is suitable for water supply, drainage, weak current and strong current engineering.
The existing subzone auxiliary engineering often uses a single pipeline to pre-embed a single line when pipelines are pre-embedded, multiple excavation is needed in the construction process to pre-embed different pipelines, and the pre-embedding is usually inconvenient in the subsequent laying and maintenance at a deep position.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a pipeline embedded structure to solve and conveniently lay the problem that the maintenance pipeline provided.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a pre-buried structure of pipeline, includes the concrete carrier, the inboard symmetry of lower extreme of concrete carrier is provided with information channel and electric power passageway, the upper end surface symmetry of concrete carrier is provided with gas channel and water supply channel, gas channel is provided with the overlap joint piece with water supply channel's inner wall, the apron has been placed to the upper end of overlap joint piece.
Preferably, the inboard of concrete carrier is provided with E shape stirrup, and the surface ligature of E shape stirrup has the strengthening rib, the inboard of concrete carrier is provided with circular stirrup, and circular stirrup sets up in the outside of information channel and electric power passageway, and the surface ligature of circular stirrup has the strengthening rib.
Preferably, the side surface of the cover plate is provided with a toilet groove.
Preferably, a conical bulge is arranged at the upper end of the concrete carrier between the water supply channel and the fuel gas channel.
Compared with the prior art, the beneficial effects of the utility model are that: apron and ground parallel and level when this kind of pipeline embedded structure installs, concrete carrier has adopted concrete cooperation E shape stirrup, circular stirrup to connect the strengthening rib and has strengthened concrete carrier's crushing when the crushing nature makes its installation and ground parallel and level and has made things convenient for laying and the inspection of pipeline, and concrete carrier inside is provided with information passageway, electric power passageway, gas passageway and water supply channel, and one time pre-buried saves excavation many times and has practiced thrift construction cost.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
in the figure: 1 concrete carrier, 11E-shaped stirrups, 12 reinforcing ribs, 13 circular stirrups, 14 conical bulges, 2 information channels, 3 power channels, 4 gas channels, 41 lap-joint blocks, 5 water supply channels, 6 cover plates and 61 urinal grooves.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1, a pipeline pre-buried structure includes a concrete carrier 1, an information channel 2 and an electric power channel 3 are symmetrically disposed on the inner side of the lower end of the concrete carrier 1, a gas channel 4 and a water supply channel 5 are symmetrically disposed on the upper end surface of the concrete carrier 1, a lapping block 41 is disposed on the inner walls of the gas channel 4 and the water supply channel 5, and a cover plate 6 is disposed on the upper end of the lapping block 41.
Referring to fig. 1, an E-shaped stirrup 11 is arranged on the inner side of a concrete carrier 1, a reinforcing rib 12 is bound on the surface of the E-shaped stirrup 11, a circular stirrup 13 is arranged on the inner side of the concrete carrier 1, the circular stirrup 13 is arranged on the outer side of an information channel 2 and an electric power channel 3, and the reinforcing rib 12 is bound on the surface of the circular stirrup 13.
Referring to fig. 1, a toilet groove 61 is formed on a side surface of the cover plate 6 to facilitate lifting the cover plate 6.
Referring to fig. 1, a conical protrusion 14 is provided at the upper end of the concrete carrier 1 between the water supply passage 5 and the gas passage 4, and is conveniently inserted into the inner side of the excrement tank 61 along the conical protrusion 14.
The utility model discloses when concrete implementation: apron 6 and ground parallel and level when this pipeline embedded structure installs, concrete carrier 1 has adopted concrete cooperation E shape stirrup 11, circular stirrup 13 is connected strengthening rib 12 and has strengthened concrete carrier 1's crushing resistance, avoid the crushing when making concrete carrier 1 install and ground parallel and level, consequently, concrete carrier 1 and ground parallel and level have made things convenient for laying of pipeline because concrete carrier 1, gas channel 4 can be examined the pipeline of gas channel 4 and water supply channel 5 with the convenience of lifting through inserting the instrument along toper arch 14 with the inner wall overlap joint piece 41 surface cover 6 of water supply channel 5 just groove 61, 1 inside information channel 2 that is provided with of concrete carrier, electric power channel 3, gas channel 4 and water supply channel 5, once pre-buried save excavation many times and practiced thrift construction cost.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. The utility model provides a pre-buried structure of pipeline, includes concrete carrier (1), its characterized in that: the inboard symmetry of lower extreme of concrete carrier (1) is provided with information channel (2) and electric power passageway (3), the upper end surface symmetry of concrete carrier (1) is provided with gas passageway (4) and water supply channel (5), the inner wall of gas passageway (4) and water supply channel (5) is provided with overlap joint piece (41), apron (6) have been placed to the upper end of overlap joint piece (41).
2. The pipeline embedded structure according to claim 1, wherein: the inboard of concrete carrier (1) is provided with E shape stirrup (11), and the surface ligature of E shape stirrup (11) has strengthening rib (12), the inboard of concrete carrier (1) is provided with circular stirrup (13), and circular stirrup (13) set up in the outside of information passageway (2) and electric power passageway (3), and the surface ligature of circular stirrup (13) has strengthening rib (12).
3. The pipeline embedded structure according to claim 1, wherein: the side surface of the cover plate (6) is provided with a urinal groove (61).
4. The pipeline embedded structure according to claim 1, wherein: and a conical bulge (14) is arranged at the upper end of the concrete carrier (1) between the water supply channel (5) and the fuel gas channel (4).
CN201920858370.7U 2019-06-10 2019-06-10 Pipeline pre-buried structure Active CN210887297U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920858370.7U CN210887297U (en) 2019-06-10 2019-06-10 Pipeline pre-buried structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920858370.7U CN210887297U (en) 2019-06-10 2019-06-10 Pipeline pre-buried structure

Publications (1)

Publication Number Publication Date
CN210887297U true CN210887297U (en) 2020-06-30

Family

ID=71333259

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920858370.7U Active CN210887297U (en) 2019-06-10 2019-06-10 Pipeline pre-buried structure

Country Status (1)

Country Link
CN (1) CN210887297U (en)

Similar Documents

Publication Publication Date Title
CN103184747B (en) Method and structure for leakage seepage prevention construction for two-walls-in-one structure of deep-underground engineering
CN213174793U (en) Mounting structure of pre-buried sleeve on floor
CN102535519A (en) I-shaped steel joint structure for underground continuous wall and construction method for I-shaped steel joint structure
CN110700237A (en) Construction method of diaphragm wall for preventing concrete from flowing around
CN201605599U (en) Integrated prefabricated inspection well
CN210887297U (en) Pipeline pre-buried structure
CN210767048U (en) Same-floor drainer for sunken toilet
CN108798775A (en) A kind of jacking construction active well
CN203365760U (en) Optical cable channel
CN103726514B (en) The anti-leakage structure of diaphragm wall and anti-seepage construction method
CN211623450U (en) Construction structure for treating water seepage of tunnel
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN211312560U (en) Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures
CN204940330U (en) A kind of pipeline foundation
CN114045880A (en) Basement post-cast strip treatment process
CN108086542A (en) A kind of concrete structure pipe construction through walls reserves structure and construction method
CN206233254U (en) A kind of underground captation
CN110747983A (en) Prefabricated assembled filter beam for filter tank
CN206359996U (en) Prefabricated assembled pipe gallery assembled up and down
CN219386371U (en) Plugging structure of underground foundation pit dewatering well
CN204163178U (en) Push pipe interval combinations manhole
CN103437408A (en) Built-in impermeable floor drain
CN217630384U (en) Visual pond structure of seepage
KR101175907B1 (en) Supporting construct for hume pipe
CN214629178U (en) Be used in drainage in honeycomb pond

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant