CN211623450U - Construction structure for treating water seepage of tunnel - Google Patents

Construction structure for treating water seepage of tunnel Download PDF

Info

Publication number
CN211623450U
CN211623450U CN202020159583.3U CN202020159583U CN211623450U CN 211623450 U CN211623450 U CN 211623450U CN 202020159583 U CN202020159583 U CN 202020159583U CN 211623450 U CN211623450 U CN 211623450U
Authority
CN
China
Prior art keywords
secondary lining
drainage tube
new secondary
double
infiltration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020159583.3U
Other languages
Chinese (zh)
Inventor
袁松
张生
王希宝
廖沛源
黎良仆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Communication Surveying and Design Institute Co Ltd
Original Assignee
Sichuan Communication Surveying and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Communication Surveying and Design Institute Co Ltd filed Critical Sichuan Communication Surveying and Design Institute Co Ltd
Priority to CN202020159583.3U priority Critical patent/CN211623450U/en
Application granted granted Critical
Publication of CN211623450U publication Critical patent/CN211623450U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a handle construction structures of tunnel infiltration, include that the toroidal cavity who leaves behind the former secondary lining brick of certain width is dug away along whole hoop direction from secondary lining brick layer infiltration department, pour new secondary lining in the toroidal cavity, the surrounding rock stratum that the new secondary lining outside corresponds also digs along the hoop and is equipped with the recess, be provided with the double-walled bellows that sets up along the back hoop of new secondary lining in the recess, the drainage tube has been inserted to the trompil ann in the surrounding rock stratum of new secondary lining top, the outlet has been seted up on the drainage tube wall, the lower extreme and the double-walled bellows intercommunication of drainage tube. The utility model discloses a prevention of seepage water structure replaces into new secondary lining through the secondary lining with the infiltration position, then installs drainage tube and double-walled bellows, and the rivers that pass through the infiltration are led through drainage tube and double-walled bellows and are arranged to the unified discharge tunnel of road surface ditch, avoid among the new secondary lining of rivers infiltration, increased tunnel prevention of seepage nature.

Description

Construction structure for treating water seepage of tunnel
Technical Field
The utility model relates to a tunnel disease renovation field, concretely relates to handle construction structures of tunnel infiltration.
Background
In recent years, existing tunnels are built, the defects of cracking and water leakage of linings mostly appear, and the industry has a statement of 'ten tunnels and nine leaks'. The reason is that the water leakage tunnel mostly develops in a surrounding rock structure and passes through a fault, a fold and a fracture zone, joints and fractures develop extremely, and a geological structure is abnormal and complex, so that the shearing stress of the tunnel lining is concentrated, the lining is cracked, and a waterproof layer is damaged; when the tunnel passes through a limestone area, hidden karst and karst caves can be encountered, and the drainage quantity of the existing drainage system of the tunnel is insufficient, so that lining cracks or construction joints are infiltrated. How to treat the tunnel seepage is an engineering problem which needs to be solved urgently.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem how to handle the tunnel infiltration, aim at provides a construction structures who handles the tunnel infiltration, replaces new secondary lining through the secondary lining with the infiltration position, then installs drainage tube and double-walled bellows, leads the rivers of infiltration to the unified discharge tunnel of road surface ditch through drainage tube and double-walled bellows, avoids among the new secondary lining of rivers infiltration, has increased tunnel anti-seepage nature.
The utility model discloses a following technical scheme realizes:
the utility model relates to a handle construction structures of tunnel infiltration, include and dig out the toroidal cavity that leaves behind the former secondary lining brick of certain width along whole hoop direction from secondary lining brick layer infiltration department, pour new secondary lining in the toroidal cavity, the surrounding rock stratum that the new secondary lining outside corresponds also digs along the hoop and is equipped with the recess, be provided with the double-walled bellows that sets up along new secondary lining back hoop in the recess, it has the drainage tube to punch a hole in the surrounding rock stratum of new secondary lining top, the outlet has been seted up on the drainage tube wall, the lower extreme and the double-walled bellows intercommunication of drainage tube.
The utility model discloses a prevention of seepage water structure replaces into new secondary lining through the secondary lining with the infiltration position, then installs drainage tube and double-walled bellows, and the rivers that pass through the infiltration are led through drainage tube and double-walled bellows and are arranged to the unified discharge tunnel of road surface ditch, avoid among the new secondary lining of rivers infiltration, increased tunnel prevention of seepage nature. The utility model discloses a direct secondary lining brick that digs out in infiltration department pours again and carries out secondary lining brick structure to lean on the country rock side to hug closely the installation double-walled bellows in the new secondary lining brick structure outside, the rivers of country rock stratum just collect the bellows through the drainage tube earlier like this and arrange the unified discharge tunnel of both sides ditch after again outside, can not carry out large-scale repair work like this, improve repair efficiency and quality. Wherein, the pipe diameter of the double-wall corrugated pipe is reasonably selected according to the width of the dug-out original secondary lining brick.
The upper end of the drainage tube is coated with non-woven fabrics.
And a cement-based crystallization layer is coated on the empty face of the new secondary lining facing the inner side, so that the seepage resistance of the joint between the new secondary lining and the original secondary lining is improved.
The drainage tube adopts a steel flower tube with the diameter of 42mm and the wall thickness of 4mm, the aperture of the drainage hole is 10mm, the longitudinal distance between the holes is 10cm, and the drainage holes are distributed in a quincunx shape.
And the gap between the double-wall corrugated pipe and the new secondary lining is filled with leakage-stopping cement.
Compared with the prior art, the utility model, following advantage and beneficial effect have:
1. the utility model relates to a construction structure for treating tunnel infiltration, which replaces the secondary lining of the infiltration part with a new secondary lining, then installs a drainage tube and a double-wall corrugated pipe, leads the infiltrated water flow to a road ditch through the drainage tube and the double-wall corrugated pipe to be uniformly discharged out of the tunnel, avoids the water flow from infiltrating into the new secondary lining, and increases the tunnel impermeability;
2. the utility model relates to a handle construction structures of tunnel infiltration can not carry out large-scale repair work, improves repair efficiency and quality.
Drawings
The accompanying drawings, which are included to provide a further understanding of the embodiments of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the principles of the invention. In the drawings:
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural diagram of the present invention.
Reference numbers and corresponding part names in the drawings:
1-annular cavity, 2-double-wall corrugated pipe, 3-drainage pipe, 4-water drainage hole, 5-cement-based crystallization layer and 6-leaking stoppage mucilage.
Detailed Description
To make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail below with reference to the following examples and drawings, and the exemplary embodiments and descriptions thereof of the present invention are only used for explaining the present invention, and are not intended as limitations of the present invention.
Example 1
As shown in fig. 1 and fig. 2, the utility model relates to a handle construction structures of tunnel infiltration, include that the cliff body 1 that leaves behind the former secondary lining brick of certain width is dug away along whole hoop direction from secondary lining brick layer infiltration department, new secondary lining has been pour in the cliff body, the surrounding rock stratum that the new secondary lining outside corresponds also digs along the hoop and is equipped with the recess, be provided with the double-walled bellows 2 that sets up along the back hoop of new secondary lining in the recess, the drainage tube 3 has been installed in the drilling in the surrounding rock stratum of new secondary lining top, drainage hole 4 has been seted up on the 3 walls of drainage tube, the lower extreme and the 2 intercommunications of double-walled bellows of drainage tube 3.
The utility model discloses a prevention of seepage water structure replaces into new secondary lining through the secondary lining with the infiltration position, then installs drainage tube and double-walled bellows, and the rivers that pass through the infiltration are led through drainage tube and double-walled bellows and are arranged to the unified discharge tunnel of road surface ditch, avoid among the new secondary lining of rivers infiltration, increased tunnel prevention of seepage nature. The utility model discloses a direct secondary lining brick that digs out in infiltration department pours again and carries out secondary lining brick structure to lean on the country rock side to hug closely the installation double-walled bellows in the new secondary lining brick structure outside, the rivers of country rock stratum just collect the bellows through the drainage tube earlier like this and arrange the unified discharge tunnel of both sides ditch after again outside, can not carry out large-scale repair work like this, improve repair efficiency and quality. Wherein, the pipe diameter of the double-wall corrugated pipe is reasonably selected according to the width of the dug-out original secondary lining brick.
Preferably, the upper end of the drainage tube is coated with a non-woven fabric.
Preferably, the face of the new secondary lining facing the inner side is coated with a cement-based crystalline layer 5, so that the seepage resistance of the joint between the new secondary lining and the original secondary lining is improved.
Preferably, the drainage tube is a steel flower tube with the diameter of 42mm and the wall thickness of 4mm, the aperture of the drainage holes is 10mm, the longitudinal distance between the holes is 10cm, and the drainage holes are distributed in a quincunx shape.
Preferably, the gap between the double-wall corrugated pipe and the new secondary lining is filled with plugging mortar 6.
The above-mentioned embodiments, further detailed description of the objects, technical solutions and advantages of the present invention, it should be understood that the above description is only the embodiments of the present invention, and is not intended to limit the scope of the present invention, and any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the scope of the present invention.

Claims (5)

1. The utility model provides a handle construction structures of tunnel infiltration, a serial communication port, include that annular cavity (1) that leaves behind the former secondary lining brick of certain width is dug away along whole hoop direction from secondary lining brick layer infiltration department, pour new secondary lining in the annular cavity, the surrounding rock stratum that new secondary lining outside corresponds also digs along the hoop and is equipped with the recess, be provided with double-walled bellows (2) along the setting of new secondary lining back hoop in the recess, drainage tube (3) have been installed in the surrounding rock stratum of new secondary lining top hole punching, drainage hole (4) have been seted up on drainage tube (3) wall, the lower extreme and double-walled bellows (2) intercommunication of drainage tube (3).
2. The construction structure for treating water seepage of a tunnel according to claim 1, wherein the upper end of the drainage tube (3) is coated with a non-woven fabric.
3. A construction structure for treating seepage water in tunnels according to claim 1, wherein the facing surface of the new secondary lining facing the inside is coated with a cement-based crystalline layer (5).
4. The construction structure for treating the water seepage of the tunnel according to claim 1, wherein the drainage tube (3) is a steel perforated tube with a diameter of 42mm and a wall thickness of 4mm, the diameter of the drainage holes (4) is 10mm, the longitudinal distance between the holes is 10cm, and the drainage holes (4) are distributed in a quincunx shape.
5. The construction structure for treating seepage water of a tunnel according to claim 1, wherein the gap between the double-wall corrugated pipe (2) and the new secondary lining is filled with the plugging cement (6).
CN202020159583.3U 2020-02-10 2020-02-10 Construction structure for treating water seepage of tunnel Active CN211623450U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020159583.3U CN211623450U (en) 2020-02-10 2020-02-10 Construction structure for treating water seepage of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020159583.3U CN211623450U (en) 2020-02-10 2020-02-10 Construction structure for treating water seepage of tunnel

Publications (1)

Publication Number Publication Date
CN211623450U true CN211623450U (en) 2020-10-02

Family

ID=72619128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020159583.3U Active CN211623450U (en) 2020-02-10 2020-02-10 Construction structure for treating water seepage of tunnel

Country Status (1)

Country Link
CN (1) CN211623450U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111156037A (en) * 2020-02-10 2020-05-15 四川省交通勘察设计研究院有限公司 Construction structure and method capable of intensively treating large-scale water seepage of tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111156037A (en) * 2020-02-10 2020-05-15 四川省交通勘察设计研究院有限公司 Construction structure and method capable of intensively treating large-scale water seepage of tunnel

Similar Documents

Publication Publication Date Title
CN110566273B (en) Drainage system and drainage method for treating tunnel surrounding rock fracture water
CN110409510B (en) Water stopping structure at joint of engagement pile and ground continuous wall
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN108166989A (en) The asymmetric twin-arch tunnel interval wall construction method of water rich strata " OC " shape
CN109208651A (en) Underground engineering super-long structural body deformation joint waterproof/drainage structure construction method and structure
CN104763435A (en) Construction method of shallow-buried excavation type large cross section of tunnel in tail slag filling area
CN211623450U (en) Construction structure for treating water seepage of tunnel
CN109723071B (en) Construction method of double-layer steel drum drainage system built in basement floor post-cast strip
CN205714215U (en) Tunnel-liner decompression section of jurisdiction and pipe-plate lining structure
CN104099946A (en) Novel jacking pipe intersegment overhaul well
CN112900294A (en) Lining structure for box culvert repair and construction method thereof
CN208252157U (en) A kind of dual-drainage structure of Tunnel Karst crevice water
CN100451247C (en) Bomb-shelter reinforcing construction process
CN208153035U (en) A kind of waterproof system for vcehicular tunnel corrugated steel preliminary bracing structure
CN108930323A (en) A kind of pipe jacking construction method
CN203569575U (en) Plastic blind ditch pipe sandless precipitation well
CN114737979A (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region
CN211312560U (en) Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures
CN110565740B (en) Method for connecting open hole of submarine tunnel and riser
CN209619870U (en) Box culvert is used in a kind of transformation of underground piping
CN111156037A (en) Construction structure and method capable of intensively treating large-scale water seepage of tunnel
CN204080861U (en) Inspection-pit between a kind of Novel top pipeline section
CN209430248U (en) A kind of buried Central drain discharge structure of novel tunnel
CN209308068U (en) A kind of underground pipe arragement construction
CN208106432U (en) The asymmetric twin-arch tunnel median septum constructing device of water rich strata " OC " shape

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant