CN206233254U - A kind of underground captation - Google Patents
A kind of underground captation Download PDFInfo
- Publication number
- CN206233254U CN206233254U CN201621318783.9U CN201621318783U CN206233254U CN 206233254 U CN206233254 U CN 206233254U CN 201621318783 U CN201621318783 U CN 201621318783U CN 206233254 U CN206233254 U CN 206233254U
- Authority
- CN
- China
- Prior art keywords
- steel plate
- underground
- layer
- fine sand
- base plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 60
- 239000010959 steel Substances 0.000 claims abstract description 60
- 239000004576 sand Substances 0.000 claims abstract description 33
- XEEYBQQBJWHFJM-UHFFFAOYSA-N iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 15
- 229910052742 iron Inorganic materials 0.000 claims description 8
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 6
- 239000010865 sewage Substances 0.000 description 16
- 238000010276 construction Methods 0.000 description 8
- 230000000694 effects Effects 0.000 description 5
- 238000009412 basement excavation Methods 0.000 description 4
- 239000012535 impurity Substances 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000006011 modification reaction Methods 0.000 description 2
- 238000001556 precipitation Methods 0.000 description 2
- 238000000746 purification Methods 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 238000007599 discharging Methods 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000002035 prolonged Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Abstract
The utility model discloses a kind of underground captation, it is used to the pump housing of effluent sewerage including dewatering well and positioned at dewatering well inside, the madial wall of the dewatering well sets gradually spongy layer, fine sand layer and rubble sublayer from inside to outside, and the first steel plate is set between the spongy layer and the fine sand layer, second steel plate is set between the fine sand layer and the rubble sublayer, and first steel plate sets through hole with second steel plate;The lower section of the pump housing sets the base plate with opening, and the base plate is brought into close contact with the spongy layer, the fine sand layer and the rubble sublayer, and the base plate sets the bottom for being used to cover the opening and can open.Above-mentioned underground captation, can to catchmenting in mud absorb, it is convenient to carry out pump drainage to catchmenting.
Description
Technical field
The utility model is related to construction engineering technical field, more particularly to a kind of underground captation.
Background technology
As domestic high-rise building is more and more, in the busy areas reconstruction and extension project of downtown, contrary sequence method is by more next
More utilizations, the influence topmost factor of reverse construction is exactly earth excavation, and precipitation problem is earth excavation in foundation ditch
Have to the key factor for considering.
Wherein, contrary sequence method refers to first along building basement axis or surrounding construction diaphram wall or other supporting knots
Structure, while the off position that has of interior of building pours or lay intermediate sup-poning pile, held as construction period before base plate back cover
Supported by superstructure deadweight and construction loads.Then the beam slab floor structure of one layer of construction ground, as diaphram wall
The very big support of rigidity, then successively downward earth excavation and pours each layer underground structure, until base plate back cover.Simultaneously as
The floor structure that one layer of ground has been completed, and is that Superstructure Construction creates condition, it is possible to while successively carrying out ground upwards
The construction of upper structure.Such ground is upper and lower while constructed, until engineering terminates.
Usual similar engineering be using the direct pump drainage of submersible sewage pump, the problems such as because of earth excavation, collection in basement water collection pit
Water is more muddy, directly uses submersible sewage pump pump drainage, easily causes pump to block, and as water is more muddy, mud is more, at all cannot
Pump drainage.
Utility model content
The purpose of this utility model is to provide a kind of underground captation, the underground captation can to catchmenting in silt
Mud is absorbed, convenient to carry out pump drainage to catchmenting.
To achieve the above object, the utility model provides a kind of underground captation, including dewatering well and positioned at described
Dewatering well inside is used to the pump housing of effluent sewerage, and the madial wall of the dewatering well sets gradually spongy layer, fine sand layer from inside to outside
First steel plate, the fine sand layer and the rubble sublayer are set between rubble sublayer, and the spongy layer and the fine sand layer
Between the second steel plate is set, first steel plate and second steel plate set through hole;The lower section of the pump housing sets to have and opens
Mouthful base plate, and the base plate is brought into close contact with the spongy layer, the fine sand layer and the rubble sublayer, and the base plate is set
It is used to the bottom that cover the opening and can open.
Relative to above-mentioned background technology, the underground captation that the utility model is provided, its core is, dewatering well it is interior
Side wall sets gradually spongy layer, fine sand layer and rubble sublayer from inside to outside, and the first steel plate is set between spongy layer and fine sand layer,
Second steel plate is set between fine sand layer and rubble sublayer, and the first steel plate and the second steel plate set through hole;So, positioned at precipitation
The impurity such as the sewage inside well, the mud in sewage sequentially pass through spongy layer, the through hole of the first steel plate, fine sand layer, the second steel plate
Through hole and rubble sublayer, and then purified sewage to a certain extent, and using the pump housing inside dewatering well by after purification
Sewage discharges dewatering well;Because sewage is purified to a certain extent so that the pump housing can to greatest extent play effect;
Be arranged such, can to catchmenting in mud absorb, it is convenient to carry out pump drainage to catchmenting.
Preferably, the base plate is specially bottom steel plate, and the bottom steel plate and first steel plate and described second
Steel plate is welded.
Preferably, the side of the bottom is articulated with the base plate, and the bottom is located at the lower end of the base plate.
Preferably, the bottom sets the iron wire that can cover and open the opening.
Preferably, the spongy layer, the fine sand layer are identical with the thickness of the rubble sublayer.
Preferably, the through hole is uniformly distributed in first steel plate and second steel plate.
Preferably, the pump housing is specially immersible pump.
Brief description of the drawings
In order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art, below will be to embodiment
Or the accompanying drawing to be used needed for description of the prior art is briefly described, it should be apparent that, drawings in the following description are only
It is embodiment of the present utility model, for those of ordinary skill in the art, on the premise of not paying creative work, also
Other accompanying drawings can be obtained according to the accompanying drawing for providing.
The structural representation of the underground captation that Fig. 1 is provided by the utility model embodiment;
Structural representation when Fig. 2 is Fig. 1 midsole plate closings;
Fig. 3 is structural representation when base plate is opened in Fig. 1.
Wherein:
The 1- pump housings, 2- spongy layers, 3- fine sand layers, 4- rubbles sublayer, 5- base plates, 6- bottoms, 7- iron wires.
Specific embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment for being obtained, belongs to the scope of the utility model protection.
In order that those skilled in the art more fully understand the utility model scheme, below in conjunction with the accompanying drawings and specifically
The utility model is described in further detail for implementation method.
Fig. 1, Fig. 2 and Fig. 3 are refer to, Fig. 1 is shown by the structure of the underground captation that the utility model embodiment is provided
It is intended to;Structural representation when Fig. 2 is Fig. 1 midsole plate closings;Fig. 3 is structural representation when base plate is opened in Fig. 1.
A kind of underground captation that the utility model is provided, mainly including dewatering well, the pump housing 1, spongy layer 2, fine sand layer
3rd, rubble sublayer 4, the first steel plate, the second steel plate, base plate 5 and bottom 6, as shown in Figure of description 1.
The set-up mode of dewatering well may be referred to prior art, and the pump housing 1 is located at the inside of dewatering well, in dewatering well
The sewage in portion carries out pump drainage.Core of the present utility model is, the madial wall of dewatering well set gradually from inside to outside spongy layer 2,
First steel plate is set between fine sand layer 3 and rubble sublayer 4, and spongy layer 2 and fine sand layer 3, fine sand layer 3 and rubble sublayer 4 it
Between the second steel plate is set, the first steel plate and the second steel plate are respectively provided with through hole;It is intended that the impurity such as mud in sewage can be with
Spongy layer 2, the through hole of the first steel plate, fine sand layer 3, the through hole of the second steel plate and rubble sublayer 4 are sequentially passed through, and then plays purification
The purpose of sewage.
Dewatering well be usually arranged as it is cylindric, diameter between 300mm~400mm, spongy layer 2, fine sand layer 3 and blinding
Three layers of thickness can be set identical by layer 4 as three layers of filter layer of unlike material, and thickness can be arranged on 45mm~55mm
Between.
First steel plate and the second steel plate can support spongy layer 2, fine sand layer 3 and rubble sublayer 4, due to the first steel plate and
Two steel plates are arranged between spongy layer 2, fine sand layer 3 and rubble sublayer 4, thus the first steel plate is not perishable with the second steel plate, energy
Enough play preferable support effect.
The thickness of the first steel plate and the second steel plate can be arranged between 5mm~10mm;First steel plate and the second steel plate
Through hole can pass through for impurity such as the mud in sewage;By actual test, the madial wall of dewatering well sets gradually from inside to outside
Spongy layer 2, fine sand layer 3 and rubble sublayer 4 can to greatest extent purify sewage, and coordinate the first steel plate and the second steel plate
Supporting role so that the service life of underground captation is obviously prolonged;Certainly, the first steel plate and the second steel plate can be using not
Depending on the clear size of opening of rust steel steel plate, the first steel plate and the second steel plate can be according to actual conditions with quantity;The utility model is excellent
Through hole is uniformly arranged on the first steel plate and the second steel plate by choosing, and the size of through hole is identical.
The lower section of the pump housing 1 sets the base plate 5 with opening, and base plate 5 is tight with spongy layer 2, fine sand layer 3 and rubble sublayer 4
Closely connected conjunction, base plate 5 sets the bottom 6 for being used to cover opening and can open.
Base plate 5 could be arranged to circular metal base plate, and thickness is between 15mm~25mm;In order to realize base plate 5 with sea
Being brought into close contact for continuous layer 2, fine sand layer 3 and rubble sublayer 4, can be welded in the first steel plate and second steel plate by base plate 5, real
Existing base plate 5 is brought into close contact with the bottom of spongy layer 2, fine sand layer 3 and rubble sublayer 4, it is ensured that effect of catchmenting.Certainly, base plate 5 may be used also
Its being brought into close contact with spongy layer 2, fine sand layer 3 and rubble sublayer 4 is realized with using other techniques, be will not be described in great detail herein.
The purpose that base plate 5 sets bottom 6 is, when needing using 1 effluent sewerage of the pump housing, the pump housing 1 is located in sewage, this
When bottom 6 opening of base plate 5 is covered, realize the sealing effectiveness of dewatering well.After sewage discharge is finished, bottom 6 is opened, realized
The bottom of dewatering well is consistent with ambient pressure, it is to avoid cannot be taken out from dewatering well because vacuum causes the pump housing 1.
The opening size of base plate 5 could be arranged to the round mouth of diameter 80mm~120mm, and the diameter dimension of bottom 6 can be
Between 100mm~140mm, to realize covering the opening of base plate 5, it is ensured that the sealing effectiveness of underground captation.
For the set-up mode of bottom 6, as shown in Figure of description 2 and accompanying drawing 3;The side of bottom 6 is articulated with base plate 5,
And bottom 6 is located at the lower end of base plate 5.
In order to realize opening and closing of the bottom 6 relative to base plate 5, opening ways of the prior art can be used;This
Utility model sets iron wire 7 in bottom 6, and iron wire 7 is parallel with the madial wall of dewatering well, and iron wire 7 is perpendicular to bottom 6 and base plate 5;When
When pulling up iron wire 7, you can realize the closing of bottom 6;When iron wire 7 is unclamped, you can realize the unlatching of bottom 6.
The pump housing 1 herein can be immersible pump.It is well known that immersible pump is generally used for normal temperature clear water, it is insoluble in water
The content of solid impurity is no more than 0.1%, and granularity is not more than 0.2mm, and pH value is in the range of 6.5--8;Can have using immersible pump
Effect excludes the sewage after being filtered through spongy layer 2, fine sand layer 3 and rubble sublayer 4, and for the physicochemical properties of sewage, profit
Preferable filth-discharging effect can be realized with immersible pump.
It should be noted that in this manual, such as first and second etc relational terms are used merely to one
Entity makes a distinction with other several entities, and not necessarily require or imply between these entities exist it is any this actual
Relation or order.
Underground captation provided by the utility model is described in detail above.It is used herein specifically individual
Example is set forth to principle of the present utility model and implementation method, and the explanation of above example is only intended to help and understands this reality
With new method and its core concept.It should be pointed out that for those skilled in the art, not departing from this
On the premise of utility model principle, some improvement and modification can also be carried out to the utility model, these are improved and modification also falls
Enter in the utility model scope of the claims.
Claims (7)
1. a kind of underground captation, including dewatering well and positioned at the dewatering well inside to effluent sewerage the pump housing, its
It is characterised by, the madial wall of the dewatering well sets gradually spongy layer, fine sand layer and rubble sublayer, and the sponge from inside to outside
The first steel plate is set between layer and the fine sand layer, the second steel plate is set between the fine sand layer and the rubble sublayer, it is described
First steel plate sets through hole with second steel plate;The lower section of the pump housing sets the base plate with opening, and the base plate with
The spongy layer, the fine sand layer and the rubble sublayer are brought into close contact, and the base plate sets and is used to cover the opening and energy
Enough bottoms opened.
2. underground captation according to claim 1, it is characterised in that the base plate is specially bottom steel plate, and institute
Bottom steel plate is stated to be welded with first steel plate and second steel plate.
3. underground captation according to claim 1, it is characterised in that the side of the bottom is articulated with the bottom
Plate, and the bottom is located at the lower end of the base plate.
4. underground captation according to claim 3, it is characterised in that the bottom sets and can cover and open institute
State the iron wire of opening.
5. the underground captation according to Claims 1 to 4 any one, it is characterised in that the spongy layer, described thin
Layer of sand is identical with the thickness of the rubble sublayer.
6. the underground captation according to Claims 1 to 4 any one, it is characterised in that the through hole is uniformly distributed
In first steel plate and second steel plate.
7. the underground captation according to Claims 1 to 4 any one, it is characterised in that the pump housing is specially latent
Water pump.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621318783.9U CN206233254U (en) | 2016-12-02 | 2016-12-02 | A kind of underground captation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621318783.9U CN206233254U (en) | 2016-12-02 | 2016-12-02 | A kind of underground captation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206233254U true CN206233254U (en) | 2017-06-09 |
Family
ID=58978853
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621318783.9U Expired - Fee Related CN206233254U (en) | 2016-12-02 | 2016-12-02 | A kind of underground captation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206233254U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700296A (en) * | 2019-09-27 | 2020-01-17 | 中国十七冶集团有限公司 | Foundation pit dewatering system with high water level and weak permeability soil and implementation method |
-
2016
- 2016-12-02 CN CN201621318783.9U patent/CN206233254U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700296A (en) * | 2019-09-27 | 2020-01-17 | 中国十七冶集团有限公司 | Foundation pit dewatering system with high water level and weak permeability soil and implementation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203947484U (en) | A kind of drainage of foundation pit and circulating water utilization system | |
CN208088344U (en) | With waterproof, the underground pipe gallery structure of drain function | |
CN105735406B (en) | A kind of public building rain water on roof utilizes collection and storage device | |
CN206801581U (en) | A kind of tunnel lining structure defect reinforcing device | |
CN109723071B (en) | Construction method of double-layer steel drum drainage system built in basement floor post-cast strip | |
CN106088684B (en) | The sunk type square and its construction method that a kind of rainwater-collecting recycles | |
CN203173911U (en) | Precipitation device | |
CN207268009U (en) | A kind of underground pipe gallery drainage system based on existing blowdown canal | |
CN206233254U (en) | A kind of underground captation | |
CN106013400A (en) | Integrated pipe network and water storage and drainage system for pavements | |
CN109763552A (en) | A kind of basis is dark to apply gravity type draining regeneration application system and its construction method | |
CN110005144A (en) | A kind of drainage riser structure and its setting method suitable for upper cover exploitation | |
CN205369281U (en) | Radial precipitation structure | |
CN211948590U (en) | Anti pressure relief device that floats of basement bottom plate | |
CN213038444U (en) | Temporary device for screening sludge in river channel culvert | |
CN106988330A (en) | Soft soil foundation is layered dewatering construction structure and construction method | |
CN204529449U (en) | A kind of septic tank | |
CN103696485B (en) | A kind of nuclear island drainage device | |
CN207295866U (en) | Caisson of toilet secondary drainage system | |
CN205954791U (en) | People moving walkways complex pipe network and hold drainage system | |
CN207176874U (en) | A kind of pavement comprehensive pipe network and drainage system | |
CN206396790U (en) | A kind of comprehensive pipe gallery structure for being easy to rainwater to discharge | |
CN110258660A (en) | The manufacture craft and shut-in well technique of the decompression drainage sump of basement anti-floating | |
CN204850003U (en) | Rainwater sinks mud inspection shaft | |
CN216156737U (en) | Rainwater pipeline discharge port elevation structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170609 Termination date: 20211202 |
|
CF01 | Termination of patent right due to non-payment of annual fee |