CN210457366U - High-rise ALC wallboard corollary equipment - Google Patents

High-rise ALC wallboard corollary equipment Download PDF

Info

Publication number
CN210457366U
CN210457366U CN201821441135.1U CN201821441135U CN210457366U CN 210457366 U CN210457366 U CN 210457366U CN 201821441135 U CN201821441135 U CN 201821441135U CN 210457366 U CN210457366 U CN 210457366U
Authority
CN
China
Prior art keywords
equipment
wallboard
installation
alc
alc wallboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821441135.1U
Other languages
Chinese (zh)
Inventor
李予新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinotech Jingu prefabricated construction industry research center (Shenzhen) Co.,Ltd.
Original Assignee
李予新
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 李予新 filed Critical 李予新
Priority to CN201821441135.1U priority Critical patent/CN210457366U/en
Application granted granted Critical
Publication of CN210457366U publication Critical patent/CN210457366U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a high-rise ALC wallboard corollary equipment, compared with the installation mode of the traditional ALC wallboard for the current building, the installation mode of the utility model has a set of special installation equipment, compared with the traditional scaffold and tower crane equipment, the mechanical equipment is lighter and more flexible; by embedding the pre-buried mounting parts into the panel in advance (the mounting parts are connected with the steel reinforcement net cage of the wall panel, the integrity is stronger), the mounting nodes are more scientific and firm; secondary holing on the wallboard on site and secondary surface treatment are not needed, so that the site installation time is greatly reduced, the site installation efficiency is improved, and the site labor cost is reduced; because the positioning angle iron is reserved in advance, the installation process is more accurate, time-saving and labor-saving; the upper part and the lower part are hinged with the main body structure, so that the anti-seismic performance is more reasonable.

Description

High-rise ALC wallboard corollary equipment
Technical Field
The utility model belongs to prefabricated wallboard construction field of building, concretely relates to high-rise ALC wallboard and corollary equipment.
Background
At present, the installation mode of building traditional light external wall panel mainly has several following types:
1. and (3) building a scaffold, namely building the scaffold on the periphery of the building, hoisting the plate indoors in advance, carrying the external wall panel to an installation place by indoor personnel, erecting the plate indoors through manual work or small equipment, and standing the outdoor personnel on the scaffold for auxiliary installation.
2. Hoisting by a tower crane: the tower crane is arranged beside a main building to be installed, plates are hoisted to a place to be installed through the tower crane, and then the plates are manually positioned and the wallboard is installed by indoor personnel in cooperation with the tower crane.
The above-mentioned several light wallboard mounting means: firstly, the cost consumption is extremely high no matter a scaffold is built or a tower crane is set; the wallboard needs to be provided with holes for the second time during installation, and the hook head bolt is sleeved in the holes and then fixed with the main structure; the outer wall surface needs secondary treatment and plastering, the construction process is complex, the construction efficiency is not high, and the manual and mechanical costs are too high.
SUMMERY OF THE UTILITY MODEL
In order to solve the above problems, the utility model provides a high-rise ALC wallboard, the ALC wallboard includes wallboard body, first fixed orifices and second fixed orifices, the first fixed orifices and second fixed orifices are respectively and symmetrically arranged at two ends of the wallboard body;
furthermore, the high-rise ALC wallboard matching equipment comprises hoisting equipment, hanging basket equipment and a light rail, wherein one end of the hoisting equipment is fixed on the light rail, and the other end of the hoisting equipment is connected with the ALC wallboard through two safety ropes; the hanging basket equipment comprises a hanging basket and a lifting rope, wherein one end of the hanging basket equipment is connected with the light rail, and the other end of the hanging basket equipment is connected with the hanging basket through the lifting rope;
furthermore, the light rail is perpendicular to the surface to be fixed of the ALC wallboard, the bottom of the light rail is provided with a rail and a pulley, and the light rail is connected with the rail through the pulley and is fixed on the ground;
furthermore, the corollary equipment also comprises positioning angle steel, wherein a plurality of hinge holes are formed in the positioning angle steel at equal intervals, and the hinge holes are hinged with the first fixing holes or the second fixing holes;
furthermore, the positioning angle steel is fixed on the ground or between the ALC wallboards adjacent in the vertical direction;
the utility model has the advantages as follows:
1): compared with the traditional installation mode of the ALC wallboard for the building at present, the installation mode of the utility model has a set of special installation equipment, and compared with the traditional erection of a scaffold and tower crane equipment, the mechanical equipment is lighter and more flexible;
2): by embedding the pre-buried mounting parts into the panel in advance (the mounting parts are connected with the steel reinforcement net cage of the wall panel, the integrity is stronger), the mounting nodes are more scientific and firm;
3): secondary holing on the wallboard on site and secondary surface treatment are not needed, so that the site installation time is greatly reduced, the site installation efficiency is improved, and the site labor cost is reduced;
4): because the positioning (mounting) angle iron is reserved in advance, the mounting process is more accurate, time-saving and labor-saving;
5) the upper part and the lower part are hinged with the main body structure, so that the anti-seismic performance is more reasonable.
Drawings
FIG. 1 is a schematic view of the high-rise ALC wallboard construction process of the present invention;
FIG. 2 is a schematic diagram of the high-rise ALC wallboard hoisting of the present invention;
FIG. 3 is a schematic view of the lower connection of the high-rise ALC wallboard of the present invention;
FIG. 4 is the high-rise ALC wallboard upper portion connection scheme of the utility model.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention. On the contrary, the invention is intended to cover alternatives, modifications, equivalents and alternatives which may be included within the spirit and scope of the invention as defined by the appended claims. Furthermore, in order to provide a better understanding of the present invention to the public, certain specific details are set forth in the following detailed description of the invention. It will be apparent to those skilled in the art that the present invention may be practiced without these specific details.
The present invention will be further described with reference to the accompanying drawings and specific examples, which are not intended to limit the present invention. The following are the best embodiments of the present invention:
as shown in FIGS. 1-4, the utility model provides a high-rise ALC wallboard and corollary equipment, ALC wallboard 1 includes wallboard body, first fixed orifices 11 and second fixed orifices 12 symmetry respectively set up wallboard body both ends.
The matched equipment comprises hoisting equipment 2, hanging basket equipment 3 and a light rail 4, wherein one end of the hoisting equipment 2 is fixed on the light rail 4, and the other end of the hoisting equipment is connected with the ALC wallboard through two safety ropes 41; the hanging flower basket equipment includes hanging flower basket 31 and lifting rope 32, light track 4 is connected to hanging flower basket 31 equipment one end, and the other end passes through lifting rope 32 and connects hanging flower basket 31, hanging flower basket 31 is used for carrying out the ascending lift of hoist on the vertical direction with the commander, the stationary plane is treated to light track 4 perpendicular to ALC wallboard, light track 4 is portable to be set up on ground, corollary equipment still includes location angle steel 5, equidistant a plurality of hinge holes 51 that are provided with on the location angle steel 5, hinge hole 51 with first fixed orifices 11 or second fixed orifices 12 are articulated, location angle steel 5 is fixed subaerial or between the adjacent ALC wallboard 1 of vertical direction. The light rail 4 is used for moving on the ground and hoisting the hanging basket equipment and the hoisting equipment.
High-rise ALC wallboard and corollary equipment are under construction through following method:
s1: placing the ALC wallboard on a specified floor before installation to prepare for wallboard installation;
s2: paving a light rail 4, a hoisting device 2 and a hanging basket device on a floor on the side needing to be installed;
s3: installing the hanging basket equipment 3 and the hoisting equipment 2 in place;
s4: a commander stands in the hanging basket 31 to control the hoisting equipment to hoist the external wall panel;
s5: the outer wall panel is lifted out of the room from the room through the first fixing hole 11, two measures of safety ropes 41 need to be added when the wall panel is lifted, and the wall panel is positioned and placed through the positioning angle steel 5 which is fixed in advance;
s6: after the wall boards are placed as required by indoor personnel, fixing lower nodes;
s7: after the lower node is fixed by indoor personnel, the lifting hook at the first fixing hole 11 is loosened, and the upper node is fixed through the first fixing hole 11;
s8: after the upper connecting node is fixed by indoor personnel, the safety rope is loosened to install the next plate.
The lower node fixing is specifically hinged fixing of the second fixing hole 12 and the hinge hole 51.
The upper node fixing is specifically hinged and fixed by the first fixing hole 11 and the hinge hole 51.
The above-mentioned embodiments are only one of the preferred embodiments of the present invention, and the general changes and substitutions performed by those skilled in the art within the technical scope of the present invention should be included in the protection scope of the present invention.

Claims (4)

1. The high-rise ALC wallboard matching equipment is characterized by comprising hoisting equipment (2), hanging basket equipment (3) and a light rail (4), wherein one end of the hoisting equipment (2) is fixed on the light rail (4), and the other end of the hoisting equipment is connected with an ALC wallboard through two safety ropes (41); the hanging basket equipment (3) comprises a hanging basket (31) and a lifting rope (32), one end of the hanging basket equipment (3) is connected with the light rail (4), and the other end of the hanging basket equipment (3) is connected with the hanging basket (31) through the lifting rope (32).
2. The corollary equipment of claim 1, characterized in that, light rail (4) is perpendicular to the ALC wallboard surface of waiting to fix, and the light rail (4) bottom is equipped with track and pulley, and light rail (4) passes through the pulley and connects the track and fix on ground.
3. The corollary equipment of claim 2, wherein the ALC wallboard (1) comprises a wallboard body, a first fixing hole (11) and a second fixing hole (12), the first fixing hole (11) and the second fixing hole (12) are symmetrically arranged at two ends of the wallboard body, the corollary equipment further comprises a positioning angle steel (5), the positioning angle steel (5) is provided with a plurality of hinge holes (51) at equal intervals, and the hinge holes (51) are hinged with the first fixing hole (11) or the second fixing hole (12).
4. The kit according to claim 3, characterized in that the positioning angle (5) is fixed on the ground or between vertically adjacent ALC wallboards.
CN201821441135.1U 2018-09-04 2018-09-04 High-rise ALC wallboard corollary equipment Active CN210457366U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821441135.1U CN210457366U (en) 2018-09-04 2018-09-04 High-rise ALC wallboard corollary equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821441135.1U CN210457366U (en) 2018-09-04 2018-09-04 High-rise ALC wallboard corollary equipment

Publications (1)

Publication Number Publication Date
CN210457366U true CN210457366U (en) 2020-05-05

Family

ID=70428289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821441135.1U Active CN210457366U (en) 2018-09-04 2018-09-04 High-rise ALC wallboard corollary equipment

Country Status (1)

Country Link
CN (1) CN210457366U (en)

Similar Documents

Publication Publication Date Title
CN106121255A (en) Apparatus installed by a kind of Super High glass curtain wall
CN115538792A (en) Residential building machine installation construction method and structure
CN206859698U (en) A kind of high-rise building air conditioner water vertical shaft Large Diameter Pipeline standpipe inverted construction facility
CN210460016U (en) Integrated form single power lift material platform
CN106121259B (en) The hanging apparatus and its hanging method of embedded integrated outer wall plate
CN113062584A (en) Multipoint elevator shaft construction lifting platform and construction method
CN202441045U (en) Rail-type electric attached lifting scaffold
CN210457366U (en) High-rise ALC wallboard corollary equipment
CN213923842U (en) Wallboard lifting device in assembled
CN215367748U (en) Assembled balcony
CN209760761U (en) Construction platform and elevator core section of thick bamboo construction structures in a core section of thick bamboo
CN204357138U (en) Simple steel structure lifting upending frame
JP6646220B2 (en) Construction method of suspended steel frame for suspended ceiling
CN213950418U (en) Portable prefabricated plate hoist device
CN113323368A (en) Lifting construction method for external protection hanging frame of assembled building
CN107700854B (en) Steel plate wall sliding installation device and installation method for super high-rise core tube
CN112627543A (en) Shaft inner lifting frame for mounting steel beams of core tube elevator shaft and steel beam construction method
CN206203763U (en) Self-driving floor hanging apparatus
CN206376578U (en) A kind of monoblock type fire water pump house
KR20210068283A (en) Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing
CN215291319U (en) Multi-point elevator shaft construction lifting platform
CN213569141U (en) Concrete wall body hoist device
CN219044810U (en) Simple material lifting device in hoistway
KR100916292B1 (en) Temporary system for building facing construction and Building facing construction method using the same
CN214114696U (en) Lifting type operation platform for assembling large-diameter tower equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220302

Address after: 518052 pengrunda Commercial Plaza, No. 3368, Houhaibin Road, Haizhu community, Yuehai street, Nanshan District, Shenzhen, Guangdong 2625

Patentee after: Sinotech Jingu prefabricated construction industry research center (Shenzhen) Co.,Ltd.

Address before: Room 2803, tower a, Dongfang Ruijing, No. 16, Jianguomenwai street, Chaoyang District, Beijing 100022

Patentee before: Li Yuxin

TR01 Transfer of patent right