CN210216655U CN201920792581.5U CN201920792581U CN210216655U CN 210216655 U CN210216655 U CN 210216655U CN 201920792581 U CN201920792581 U CN 201920792581U CN 210216655 U CN210216655 U CN 210216655U
Authority
CN
China
Prior art keywords
shaft
wall
drainage
steel sleeve
drainage inspection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920792581.5U
Other languages
Chinese (zh)
Inventor
Bo Quan
全波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong No2 Construction Engineering Co
Original Assignee
Guangdong No2 Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong No2 Construction Engineering Co filed Critical Guangdong No2 Construction Engineering Co
Priority to CN201920792581.5U priority Critical patent/CN210216655U/en
Application granted granted Critical
Publication of CN210216655U publication Critical patent/CN210216655U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a steel casing pipe brick drainage inspection shaft, including apron, pit shaft and bed course, the apron sets up the upper end opening part at the pit shaft, and the bed course setting is at the lower extreme opening part of pit shaft, and it has the inspection socket to open on the apron, installs the inspection socket closing cap on the inspection socket, its characterized in that: the shaft comprises a steel sleeve shaft outer wall and a brick masonry shaft inner wall, the inner side face of the steel sleeve shaft outer wall is tightly combined with the outer side face of the brick masonry shaft inner wall, and the lower end of the steel sleeve shaft outer wall is provided with at least two notches for the drainage pipes to penetrate through. The beneficial effects of the utility model reside in that: the drainage inspection well can complete the construction of the drainage inspection well with larger burial depth under the conditions of not needing large-area earthwork excavation and not needing other earthwork supporting measures, and is more convenient to construct by newly adding the drainage inspection well on the drainage pipeline which completes the construction.

Description

Steel casing brick drainage inspection shaft
Technical Field
The utility model relates to a drainage structures, in particular to steel casing pipe brick drainage inspection shaft.
Background
In a water supply and drainage pipeline system, a drainage inspection well is suitable for rain and sewage drainage pipelines, has important functions of connecting pipelines, inspecting and maintaining pipelines and the like, is a necessary accessory structure convenient for regular inspection and dredging of pipelines and preventing pipeline blockage, and generally comprises a cover plate, a well cover, a shaft and a base, various pipelines such as rainwater, sewage, water supply and the like need to be buried at the lower part of an urban road, and a corresponding drainage inspection well is arranged on a road surface layer. At present, drainage inspection wells for drainage pipelines mainly have the following three types: (1) laying a drainage inspection well by bricks; (2) a concrete module type drainage inspection well; (3) prefabricated assembled reinforced concrete drainage inspection shaft. The construction process of the drainage inspection well (2) and the drainage inspection well (3) is complex, and the process of the drainage inspection well (1) is simpler than the processes of the drainage inspection well (2) and the drainage inspection well (3), so that most of the drainage inspection wells used in the construction engineering are of the form (1). However, the drainage inspection well constructed by using the bricks and the cement mortar generally adopts a construction mode of excavating and taking earthwork and then constructing, when the drainage inspection well with larger burial depth needs to be constructed or a drainage inspection well is newly added on a drainage pipeline which is already constructed, the range of excavated earthwork needs to be gradually enlarged from bottom to top during construction, corresponding protection and support measures need to be taken to avoid collapse of the earthwork during construction, and the earthwork needs to be refilled to the outer side of the drainage inspection well after construction, so that the construction difficulty is high, the risk coefficient is high, and the construction period is long.
Disclosure of Invention
The utility model aims to solve the technical problem that a steel casing pipe brick drainage inspection shaft is provided, this kind of drainage inspection shaft can accomplish great buried depth's drainage inspection shaft construction under the condition that need not large tracts of land earthwork excavation and do not have other earthwork to it is more convenient to newly add the drainage inspection shaft construction on the drainage pipe to accomplishing the construction.
In order to solve the technical problems, the technical scheme is as follows:
the utility model provides a steel casing pipe brick drainage inspection shaft, includes apron, pit shaft and bed course, and the apron sets up at the upper end opening part of pit shaft, and the bed course setting is opened at the lower extreme opening part of pit shaft on the apron has the inspection socket, installs inspection socket closing cap on the inspection socket, its characterized in that: the shaft comprises a steel sleeve shaft outer wall and a brick masonry shaft inner wall, the inner side face of the steel sleeve shaft outer wall is tightly combined with the outer side face of the brick masonry shaft inner wall, and the lower end of the steel sleeve shaft outer wall is provided with at least two notches for the drainage pipes to penetrate through.
When the steel sleeve brick drainage inspection well is constructed, firstly, the outer wall of a steel sleeve shaft is directly sunk at the position where the drainage inspection well needs to be arranged, so that a drainage pipe passes through the outer wall of the steel sleeve shaft through a gap; excavating the earthwork at the inner side of the outer wall of the steel sleeve shaft to expose the drain pipe; then breaking the drain pipe, arranging a bottom cushion layer, and sealing the lower end opening of the outer wall of the steel sleeve shaft and a gap between the notch and the drain pipe; and finally, building the inner wall of the brick masonry shaft on the inner side of the outer wall of the steel sleeve shaft, enabling the outer side surface of the inner wall of the brick masonry shaft to be tightly combined with the inner side surface of the outer wall of the steel sleeve shaft, and sequentially arranging the cover plate and the well cover, thereby completing the integral construction of the drainage inspection well. When the drainage inspection well is constructed, the outer wall of the steel sleeve shaft is firstly sunk into the drainage pipe, the drainage pipe penetrates through the outer wall of the steel sleeve shaft through the gap, and then earthwork in the outer wall of the steel sleeve shaft is excavated, so that the range to be excavated is limited through the outer wall of the steel sleeve shaft, meanwhile, the outer wall of the steel sleeve shaft can play a role in supporting and protecting when earthwork is excavated and the inner wall of the brick masonry shaft is built, the drainage inspection well with larger burial depth is arranged or a drainage inspection well is newly added on the completed drainage inspection well with larger burial depth, large-area excavation is not needed, the drainage inspection well is more convenient to add, and earthwork does not need to be backfilled to the outer side of the drainage inspection well after building, so that the construction difficulty and the construction risk coefficient are reduced; the pit shaft adopts the mode that steel casing pit shaft outer wall and brick brickwork pit shaft inner wall combined together, makes the section of thick bamboo wall of pit shaft have higher intensity to steel casing pit shaft outer wall can increase the leakproofness of pit shaft, effectively prevents that the problem of poor, the easy infiltration of well casing wall rigidity in traditional brick brickwork inspection shaft from appearing in the drainage inspection shaft in this application.
In a preferred scheme, the bottom cushion layer is a concrete cushion layer.
The number of the gaps through which the water supply and drainage pipes penetrate can be two or more, the trend of the drainage pipes generally comprises a straight line trend, a T-shaped trend or a cross trend when the drainage inspection well is arranged, and the positions and the number of the gaps can be set according to the trend of the drainage pipes.
The lower extreme of above-mentioned brickwork pit shaft inner wall is sealed with the junction of bed course, and brickwork pit shaft inner wall is sealed with the junction of drain pipe surface.
The beneficial effects of the utility model reside in that: the drainage inspection well can complete the construction of the drainage inspection well with larger burial depth under the conditions of not needing large-area earthwork excavation and not needing other earthwork supporting measures, and is more convenient to construct by newly adding the drainage inspection well on the drainage pipeline which completes the construction.
Drawings
FIG. 1 is a cross-sectional view of an embodiment of the present invention after the outer wall of a steel casing shaft is submerged;
FIG. 2 is a cross-sectional view of an embodiment of the present invention with a bottom cushion layer;
FIG. 3 is a sectional view of the drainage inspection well according to an embodiment of the present invention;
fig. 4 is a top view of the drainage inspection well according to an embodiment of the present invention.
Detailed Description
The invention will be further described with reference to the following drawings and specific embodiments:
1-4, the steel casing brick drainage inspection well comprises a cover plate 1, a shaft 2 and a bottom cushion layer 3, wherein the cover plate 1 is arranged at an upper opening of the shaft 2, the bottom cushion layer 3 is arranged at a lower opening of the shaft 2, an inspection hole 101 is formed in the cover plate 1, and an inspection hole sealing cover 102 is arranged on the inspection hole 101; the shaft 2 comprises a steel sleeve shaft outer wall 201 and a brick masonry shaft inner wall 202, the inner side surface of the steel sleeve shaft outer wall 201 is tightly combined with the outer side surface of the brick masonry shaft inner wall 202, and the lower end of the steel sleeve shaft outer wall 201 is provided with two notches 2011 for the drainage pipe 4 to pass through.
When the steel sleeve brick drainage inspection well is constructed, firstly, the outer wall 201 of the steel sleeve shaft is directly sunk at the position where the drainage inspection well needs to be arranged, so that the drainage pipe 4 penetrates through the outer wall 201 of the steel sleeve shaft through the notch 2011; then excavating the earthwork 5 at the inner side of the outer wall 201 of the steel sleeve shaft to expose the drain pipe 4; then, the drain pipe 4 is broken, the bottom cushion layer 3 is arranged, the lower end opening of the outer wall 201 of the steel sleeve shaft and the gap 2011 between the drain pipe 4 are sealed, and the joint of the lower end of the inner wall 202 of the brick masonry shaft and the bottom cushion layer 3 is sealed; and finally, building the inner wall 202 of the brick masonry shaft on the inner side of the outer wall 201 of the steel sleeve shaft, enabling the outer side surface of the inner wall 202 of the brick masonry shaft to be tightly combined with the inner side surface of the outer wall 201 of the steel sleeve shaft, sealing the joint of the inner wall 202 of the brick masonry shaft and the outer surface of the drain pipe 4, and sequentially arranging the cover plate 1 and the well cover, thereby completing the integral construction of the drainage inspection well. When the drainage inspection well is constructed, the outer wall 201 of the steel sleeve shaft is firstly sunk into the drainage pipe 4, the drainage pipe 4 penetrates through the outer wall 201 of the steel sleeve shaft through the notch 2011, and then the earthwork 5 in the outer wall 201 of the steel sleeve shaft is excavated, so that the range to be excavated is limited through the outer wall 201 of the steel sleeve shaft, meanwhile, the outer wall 201 of the steel sleeve shaft can play a role in supporting and protecting when the earthwork 5 is excavated and the inner wall 202 of the brick masonry shaft is built, so that when the drainage inspection well with larger burial depth is arranged or a drainage inspection well is newly added on the finished drainage inspection well with larger burial depth, large-area excavation is not needed, the drainage inspection well is more convenient to construct, and the backfill earthwork 5 to the outer side of the drainage inspection well after the building is not needed, thereby reducing the construction difficulty and the construction risk coefficient; shaft 2 adopts the mode that steel casing shaft outer wall 201 and brick brickwork shaft inner wall 202 combined together, makes the section of thick bamboo wall of shaft 2 have higher intensity to steel casing shaft outer wall 201 can increase shaft 2's leakproofness, effectively prevents that the problem of 2 section of thick bamboo walls rigidity differences of shaft, easy infiltration in traditional brick brickwork inspection shaft from appearing in the drainage inspection shaft in this application.
The bottom cushion layer 3 is a concrete cushion layer.

Claims (2)

1. The utility model provides a steel casing pipe brick drainage inspection shaft, includes apron, pit shaft and bed course, and the apron sets up at the upper end opening part of pit shaft, and the bed course setting is opened at the lower extreme opening part of pit shaft on the apron has the inspection socket, installs inspection socket closing cap on the inspection socket, its characterized in that: the shaft comprises a steel sleeve shaft outer wall and a brick masonry shaft inner wall, the inner side face of the steel sleeve shaft outer wall is tightly combined with the outer side face of the brick masonry shaft inner wall, and the lower end of the steel sleeve shaft outer wall is provided with at least two notches for the drainage pipes to penetrate through.
2. The steel casing brick drainage inspection well as defined in claim 1, wherein: the bottom cushion layer is a concrete cushion layer.
CN201920792581.5U 2019-05-29 2019-05-29 Steel casing brick drainage inspection shaft Active CN210216655U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920792581.5U CN210216655U (en) 2019-05-29 2019-05-29 Steel casing brick drainage inspection shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920792581.5U CN210216655U (en) 2019-05-29 2019-05-29 Steel casing brick drainage inspection shaft

Publications (1)

Publication Number Publication Date
CN210216655U true CN210216655U (en) 2020-03-31

Family

ID=69928470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920792581.5U Active CN210216655U (en) 2019-05-29 2019-05-29 Steel casing brick drainage inspection shaft

Country Status (1)

Country Link
CN (1) CN210216655U (en)

Similar Documents

Publication Publication Date Title
CN103741714B (en) Underground engineering full sheltered reverse excavation construction method
CN210031914U (en) Assembled inspection shaft
CN203174616U (en) Clay foundation rain falling and water saving system
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN104099946B (en) Inspection-pit between a kind of Novel top pipeline section
CN111827331A (en) Supporting structure with seepage-proofing structure combined with underground continuous wall and construction method thereof
CN108331024B (en) Assembled rectangular inspection well and installation method thereof
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN102425228A (en) Multifunctional environment-friendly movable water tank
CN211368806U (en) Waterproof and drainage system of prefabricated open caisson structure
CN112302136A (en) Connecting structure of new and old drainage pipelines under non-closure working condition and construction method thereof
CN110117959B (en) Construction method for foundation pit support near river
CN210216655U (en) Steel casing brick drainage inspection shaft
CN208982058U (en) Vertical shaft surrounding rock supporting structure
CN110924438A (en) Prefabricated member of assembled rectangular inspection well
CN111335445B (en) Construction method of concrete catch basin by using steel pipe as inner mold
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN114810128A (en) Construction method of multi-arch tunnel supporting structure without middle pilot tunnel
CN204080861U (en) Inspection-pit between a kind of Novel top pipeline section
CN110056012B (en) Waterproof and drainage system of prefabricated open caisson structure
CN210315908U (en) Immersed tube type inspection well
CN106088762A (en) The prefabricated assembled circular underground granary of a kind of insertion slot type encased steel plate

Legal Events