CN210134340U - Assembled landing stage guardrail - Google Patents

Assembled landing stage guardrail Download PDF

Info

Publication number
CN210134340U
CN210134340U CN201920315049.4U CN201920315049U CN210134340U CN 210134340 U CN210134340 U CN 210134340U CN 201920315049 U CN201920315049 U CN 201920315049U CN 210134340 U CN210134340 U CN 210134340U
Authority
CN
China
Prior art keywords
guardrail
box
vertical
plates
type clamping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920315049.4U
Other languages
Chinese (zh)
Inventor
吴曼
王安文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201920315049.4U priority Critical patent/CN210134340U/en
Application granted granted Critical
Publication of CN210134340U publication Critical patent/CN210134340U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides an assembled landing stage rail guard is equipped with two box-type cardboards at the junction of guardrail pole setting and worker's steel, box-type cardboard includes two risers that are parallel to each other and have certain interval, open with the middle of one side of two risers and be equipped with a U type bayonet socket, the screw to wearing is seted up above the U type bayonet socket of two risers, weld a bottom plate between two riser bottom edges, weld a roof between two riser topside, two box-type cardboards pass through the U type bayonet socket card on the riser respectively in the both sides of worker's steel upper flange, the lower extreme of pole setting inserts the clearance between two box-type cardboard roofs, and support at worker's steel upper flange top surface, alternate a bolt that crosses the pole setting in the to wearing screw on two risers of box-type cardboard; the guardrail cross rod passes through the guardrail vertical rods, and a positioning bolt is inserted into the position, close to each guardrail vertical rod, of the guardrail cross rod. The utility model discloses need not weld during the installation, the installation rate is fast, dismantles the back not damaged, can have enough to meet the need the use.

Description

Assembled landing stage guardrail
Technical Field
The utility model relates to a structure of the rail guard on the landing stage or the drilling platform that the aquatic bridge construction was set up, concretely relates to assembled landing stage rail guard.
Background
Common aquatic landing stage and drilling platform all can install the rail guard in the outside to guarantee constructor's safety. The upright bars of the guard rails are connected with the end parts of bearing beams positioned on the outer sides of trestles or drilling platforms, the I-steel bearing beams are usually made of I-steel, and a plurality of rows of cross bars are arranged on the upright bars. Traditional guardrail bar installation all adopts the welding between pole setting and worker's steel bearing beam, horizontal pole and the pole setting, all needs on-the-spot welding construction, and welding work volume is big. The welding mode can damage the material, and the material needs to be cut during disassembly, so that the material is not favorable for repeated use, and the material waste is caused; the method is greatly influenced by weather, construction cannot be carried out in rainy and snowy weather, the project progress is influenced, and the method cannot meet the construction requirement under the conditions of large installation project amount and tight construction period requirement.
Disclosure of Invention
An object of the utility model is to provide an assembled guardrail structure to the problem that present rail guard welding mode exists, and the installation is on-the-spot does not have welding process, is applicable to the rail guard quick installation on landing stage, the drilling platform.
The technical scheme of the utility model as follows:
the utility model provides an assembled landing stage guardrail, has the guardrail pole setting at the worker steel bearing beam end connection of landing stage both sides, is connected with multirow guardrail horizontal pole, its characterized in that between the guardrail pole setting of landing stage every side: the connecting part of the guardrail vertical rod and the I-steel is provided with two box-type clamping plates, each box-type clamping plate comprises two vertical plates which are parallel to each other and have a certain interval, the middle of one side edge of each vertical plate is provided with a U-shaped bayonet, a threaded hole which penetrates through the U-shaped bayonets of the two vertical plates is arranged above the U-shaped bayonets of the two vertical plates, a bottom plate is welded between the bottom edges of the two vertical plates, a top plate is welded between the top edges of the two vertical plates, and the width; the two box-type clamping plates are respectively clamped on two sides of the I-steel upper flange plate through U-shaped bayonets on the vertical plates, a gap is formed between the two box-type clamping plate top plates, the lower end of the vertical rod is inserted into the gap between the two box-type clamping plate top plates and is supported on the top surface of the I-steel upper flange plate, and a bolt which transversely penetrates through the vertical rod is inserted into a penetrating screw hole on the two vertical plates of each box-type clamping plate and is fixed by mounting a nut; through holes are formed in the vertical rods at certain intervals, each row of guardrail cross rods penetrate through the through holes in the guardrail vertical rods, and a positioning bolt is inserted into the position, close to each guardrail vertical rod, of each guardrail cross rod.
The utility model discloses an all components are accomplished in processing field preparation in advance, pass through bolt or bolt connection during the installation, and on-the-spot no welding operation does not receive weather change's influence, and the installation rate is fast, can realize quick installation, can lift off after the engineering and continue to use, and the turnover rate is high, practices thrift the cost.
Drawings
Fig. 1 is a schematic view of the transverse vertical structure of the present invention;
fig. 2 is a schematic side view of the present invention;
FIG. 3 is a schematic side view of the box pallet;
FIG. 4 is a front view of the box pallet
FIG. 5 is an enlarged view of the connecting structure between the guardrail upright and the I-steel in FIG. 1;
FIG. 6 is an enlarged view of the connecting structure between the guardrail upright and the I-steel in FIG. 2;
fig. 7 is a schematic view of the plane structure of the connecting structure between the guardrail vertical rod and the I-steel of the present invention.
Detailed Description
As shown in fig. 1 and 2, the utility model provides a pair of assembled landing stage guardrail has guardrail pole setting 3 at 2 end connection of spandrel girder worker steel of 1 both sides of landing stage, is connected with multirow guardrail horizontal pole 4 between 3 guardrail pole settings of landing stage every side. Two box-type clamping plates 5 are arranged at the joint of each guardrail upright rod 3 and the I-steel 2.
The box-type clamping plate 5 is structurally shown in fig. 3 and 4, and comprises two vertical plates 51 which are parallel to each other and have a certain interval, a U-shaped bayonet 52 is arranged in the middle of the same side of the two vertical plates 51, a threaded hole 53 which penetrates through the two vertical plates is arranged above the U-shaped bayonet 52, a bottom plate 54 is welded between the bottom edges of the two vertical plates, a top plate 55 is welded between the top edges of the two vertical plates, and the width of the top plate 55 is smaller than the length of the top edge of the vertical plate 51.
As shown in fig. 5, 6 and 7, the two box-type clamping plates 5 are respectively clamped on two sides of the upper flange plate of the i-steel 2 through the U-shaped bayonets 52 on the vertical plates 51, because the width of the top plate 55 is smaller than the length of the top edge of the vertical plate 51, a gap is formed between the top plates 51 of the two box-type clamping plates 5, the lower end of the vertical rod 3 is inserted into the gap between the top plates of the two box-type clamping plates 5 and is supported on the top surface of the upper flange plate of the i-steel 2, and a bolt 6 crossing the vertical rod is inserted into the through screw hole on the two vertical plates of each box-; a through hole is formed in the upright rod 3 at intervals, each row of guardrail cross rods 4 penetrate through the through holes in the upright rods, and a positioning bolt 7 is inserted into the position, close to each guardrail upright rod, of each guardrail cross rod.
The positioning bolts inserted on the guardrail cross rod can be L-shaped and inserted into bolt holes preset on the guardrail cross rod from top to bottom.
The utility model discloses a through-hole on box cardboard, guardrail pole setting and the guardrail horizontal pole is all accomplished in processing field processing in advance, and the guardrail pole setting can adopt square steel pipe or channel-section steel, is convenient for set up horizontal through-hole above that, and the guardrail horizontal pole can adopt little steel pipe, during the guardrail installation at on-the-spot be assembled between/be connected can, the installation rate is fast, and on-the-spot weldless operation does not receive weather effect, pulls down the guardrail after the construction is accomplished, can have enough to meet the need the use.

Claims (2)

1. The utility model provides an assembled landing stage guardrail, has the guardrail pole setting at the worker steel bearing beam end connection of landing stage both sides, is connected with multirow guardrail horizontal pole, its characterized in that between the guardrail pole setting of landing stage every side: the connecting part of the guardrail vertical rod and the I-steel is provided with two box-type clamping plates, each box-type clamping plate comprises two vertical plates which are parallel to each other and have a certain interval, the middle of one side edge of each vertical plate is provided with a U-shaped bayonet, a threaded hole which penetrates through the U-shaped bayonets of the two vertical plates is arranged above the U-shaped bayonets of the two vertical plates, a bottom plate is welded between the bottom edges of the two vertical plates, a top plate is welded between the top edges of the two vertical plates, and the width; the two box-type clamping plates are respectively clamped on two sides of the I-steel upper flange plate through U-shaped bayonets on the vertical plates, a gap is formed between the two box-type clamping plate top plates, the lower end of the vertical rod is inserted into the gap between the two box-type clamping plate top plates and is supported on the top surface of the I-steel upper flange plate, and a bolt which transversely penetrates through the vertical rod is inserted into a penetrating screw hole on the two vertical plates of each box-type clamping plate and is fixed by mounting a nut; through holes are formed in the vertical rods at certain intervals, each row of guardrail cross rods penetrate through the through holes in the guardrail vertical rods, and a positioning bolt is inserted into the position, close to each guardrail vertical rod, of each guardrail cross rod.
2. The fabricated trestle fence of claim 1, wherein: the positioning bolts inserted on the guardrail cross rod are L-shaped and inserted into bolt holes preset on the guardrail cross rod from top to bottom.
CN201920315049.4U 2019-03-12 2019-03-12 Assembled landing stage guardrail Active CN210134340U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920315049.4U CN210134340U (en) 2019-03-12 2019-03-12 Assembled landing stage guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920315049.4U CN210134340U (en) 2019-03-12 2019-03-12 Assembled landing stage guardrail

Publications (1)

Publication Number Publication Date
CN210134340U true CN210134340U (en) 2020-03-10

Family

ID=69702549

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920315049.4U Active CN210134340U (en) 2019-03-12 2019-03-12 Assembled landing stage guardrail

Country Status (1)

Country Link
CN (1) CN210134340U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541256A (en) * 2022-04-01 2022-05-27 江西省交通工程集团建设有限公司 Method for connecting special track for bridge maintenance vehicle and main bridge steel cross beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541256A (en) * 2022-04-01 2022-05-27 江西省交通工程集团建设有限公司 Method for connecting special track for bridge maintenance vehicle and main bridge steel cross beam

Similar Documents

Publication Publication Date Title
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN204266124U (en) The pre-assembled moulding bed of large sections steel box-girder
CN210134340U (en) Assembled landing stage guardrail
CN110512517B (en) Bridge engineering construction platform
CN204024045U (en) A kind of movable assembled high-supported formwork bracing or strutting arrangement
CN201786008U (en) Automatic follow-up unloading platform for outer climb frame
CN103758024A (en) Quick assembling and disassembling steel-structure pedestrian overpass
CN203684061U (en) Steel pedestrian overcrossing fast to disassemble or assemble
CN211772862U (en) Adjustable support frame for cast-in-place beam template
CN111648229A (en) Assembled hoop platform for bent cap construction and mounting method thereof
CN215107109U (en) Sash roof beam stock construction platform
CN212294367U (en) Assembled steel pipe support for cast-in-situ beam construction
CN210032670U (en) Mounting device for steel truss
CN102913007A (en) Steel reinforcement processing shed and construction method therefor
CN208023608U (en) A kind of post-cast strip can have enough to meet the need steel channel formwork system
CN110005210A (en) The mounting device and its construction method of steel truss
CN103043521A (en) Moving sidewalk and upper head guide-rail ladder way for same
CN216999353U (en) Assembled pier stud protection platform
CN203095376U (en) Automatic sidewalk upper head portion guide rail type ladder way and automatic sidewalk thereof
CN209194954U (en) A kind of Node In Large-span Pipe Truss on-site hoisting span centre bracket
CN215164753U (en) A assembled guardrail for high mound top construction
CN218263465U (en) Cable tower X supports and sets up
CN217348185U (en) Bulk carrier bottom side cabin segmentation scaffold
CN219887632U (en) Guardrail assembly and be used for steel reinforced concrete roof beam to face limit safety protection's portable guardrail
CN218091956U (en) Movable steel pipe positioning pile for building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant