CN209549104U - Equipment for treating industrial waste gas - Google Patents

Equipment for treating industrial waste gas Download PDF

Info

Publication number
CN209549104U
CN209549104U CN201821745594.9U CN201821745594U CN209549104U CN 209549104 U CN209549104 U CN 209549104U CN 201821745594 U CN201821745594 U CN 201821745594U CN 209549104 U CN209549104 U CN 209549104U
Authority
CN
China
Prior art keywords
cabinet
equipment
industrial waste
waste gas
treating industrial
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821745594.9U
Other languages
Chinese (zh)
Inventor
刘佳婕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Zhixin Rubik's Cube Technology Consulting Co Ltd
Original Assignee
Hangzhou Zhixin Rubik's Cube Technology Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Zhixin Rubik's Cube Technology Consulting Co Ltd filed Critical Hangzhou Zhixin Rubik's Cube Technology Consulting Co Ltd
Priority to CN201821745594.9U priority Critical patent/CN209549104U/en
Application granted granted Critical
Publication of CN209549104U publication Critical patent/CN209549104U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses equipment for treating industrial waste gas, equipment for treating industrial waste gas, including absorbing cabinet, condensation cabinet, electrostatic precipitation cabinet and combustion furnace, the absorption cabinet, condensation cabinet, electrostatic precipitation cabinet and combustion furnace are sequentially communicated, the inside for absorbing cabinet is equipped with absorbing liquid, the absorption cabinet is equipped with, the bottom interior wall that cabinet is condensed described in air inlet pipe is equipped with semiconductor chilling plate, cathode electrode plate and anode electrode plate are equipped in the electrostatic precipitation cabinet, the combustion furnace is for receiving remaining gas in electrostatic precipitation cabinet and burning.The present apparatus has reasonable setting sequence, and continuous exhaust-gas treatment structure can handle the multiple harmful substances in exhaust gas, finally burn, and exhaust gas nocuousness is reduced to minimum.

Description

Equipment for treating industrial waste gas
Technical field
The utility model relates to equipment for treating industrial waste gas technical fields, specially equipment for treating industrial waste gas.
Background technique
A large amount of exhaust gas and carbon monoxide, sulfur dioxide, hydrocarbon etc. pair can be generated in industrial processes The harmful substance of human body, wherein volatile organic compounds (VOC) is strong carcinogen.Existing processing mode is only setting The exhaust gas high altitude discharge of generation, though slightly cleaning in operation plant area room, the only transfer of pollution, atmosphere and surrounding enviroment are still full of Pollution, it is very harmful.
General emission-control equipment is all simply to filter, then exhaust gas is discharged into high-altitude.The purification efficiency of this exhaust gas Not high, the various harmful substances in exhaust gas are unable to get to be removed one by one, so that filtered gas harmful ingredient is still more, it is right Environment still has biggish pollution.
Summary of the invention
It, can a variety of nuisances in integrated treatment exhaust gas the purpose of this utility model is to provide equipment for treating industrial waste gas Matter, and processing sequence is rationally set, make its efficient, environmental protection.
In order to solve the above-mentioned technical problem, the utility model provides the following technical solutions: equipment for treating industrial waste gas, including Absorb cabinet, condensation cabinet, electrostatic precipitation cabinet and combustion furnace, the absorption cabinet, condensation cabinet, electrostatic precipitation cabinet and combustion It burns furnace to be sequentially communicated, the inside for absorbing cabinet is equipped with absorbing liquid, and the absorption cabinet is equipped with air inlet pipe, the condensation cabinet Bottom interior wall semiconductor chilling plate is installed, cathode electrode plate and anode electrode plate, institute are equipped in the electrostatic precipitation cabinet Combustion furnace is stated for receiving remaining gas in electrostatic precipitation cabinet and burning.
Further, the absorption cabinet, condensation cabinet, electrostatic precipitation cabinet and combustion furnace pass sequentially through the first connection Pipe, the second connecting tube and the connection of third connecting tube.
Further, first connecting tube and one end for connecting of condensation cabinet are equipped with the first air-introduced machine, and described second Connecting tube and electrostatic precipitation cabinet junction one end are equipped with the second air-introduced machine, the third connecting tube and combustion furnace junction one End is equipped with third air-introduced machine.
Further, cathode electrode plate is fixed on the top of electrostatic precipitation cabinet wall, and the anode electrode plate is fixed on The bottom of electrostatic precipitation cabinet wall.
Further, the side for absorbing cabinet is fixed with electric cabinet, and the electric cabinet is equipped with control panel, described automatically controlled The inside of case is equipped with battery.
Further, condensate film is also installed in the middle part of the condensation cabinet wall.The condensation that can be more convenient condensed water is fallen.
Further, the top of the combustion furnace stores cabinet by being welded with raw material.
Further, first connecting tube, the second connecting tube and third connecting tube pass through flange and its two sides respectively Cabinet connection.
Further, the anode of the battery is electrically connected anode electrode plate, and the cathode of the battery is electrically connected Cathode electrode plate.
Further, the semiconductor chilling plate is connect by seccotine with condensation cabinet.
Compared with prior art, the utility model beneficial effect achieved is: the present apparatus has reasonable setting sequence, Continuous exhaust-gas treatment structure, can handle the multiple harmful substances in exhaust gas, finally burn, exhaust gas nocuousness is dropped As low as minimum.Exhaust gas is entered by air inlet pipe to be absorbed in cabinet, and cleaning of the exhaust gas Jing Guo absorbing liquid will be dissolved in having for absorbing liquid Evil substance removes, then into condensation cabinet, when the pernicious gas in exhaust gas being made to reach set point, is condensed, become condensed water, It is collected, in electrostatic precipitation cabinet, encounters grit in anode process when electronics marches on towards, make grit is negatively charged to be adsorbed onto anode electricity Pole plate is collected, and removes the tiny particles content in exhaust gas, then exhaust gas is drawn into combustion by third connecting tube by third air-introduced machine It burns in furnace and burns.
Detailed description of the invention
Attached drawing is used to provide a further understanding of the present invention, and constitutes part of specification, practical with this Novel embodiment is used to explain the utility model together, does not constitute limitations of the present invention.In the accompanying drawings:
Fig. 1 is the utility model equipment for treating industrial waste gas structural schematic diagram;
Fig. 2 is the electric cabinet schematic diagram of internal structure of the utility model equipment for treating industrial waste gas;
Fig. 3 is the utility model equipment for treating industrial waste gas schematic diagram of internal structure.
In figure: 1- absorbs cabinet;2- air inlet pipe;The first connecting tube of 3-;4- condenses cabinet;The second connecting tube of 5-;6- electrostatic Dust-removing box;7- third connecting tube;8- combustion furnace;9- raw material stores cabinet;10- electric cabinet;11- control panel;12- battery; The first air-introduced machine of 13-;14- condensate film;15- semiconductor chilling plate;The second air-introduced machine of 16-;17- cathode electrode plate;18- anode electricity Pole plate;19- third air-introduced machine.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Equipment for treating industrial waste gas, including cabinet 1, condensation cabinet 4, electrostatic precipitation cabinet 6 and combustion furnace 8 are absorbed, it is described It absorbs cabinet 1, condensation cabinet 4, electrostatic precipitation cabinet 6 and combustion furnace 8 to be sequentially communicated, the inside for absorbing cabinet 1, which is equipped with, inhales Liquid is received, the absorption cabinet 1 is equipped with air inlet pipe 2, and the bottom interior wall of the condensation cabinet 4 is equipped with semiconductor chilling plate 15, institute It states and is equipped with cathode electrode plate 17 and anode electrode plate 18 in electrostatic precipitation cabinet 6, the combustion furnace 8 is for receiving electrostatic precipitation It remaining gas and burns in cabinet 6.
The absorption cabinet 1, condensation cabinet 4, electrostatic precipitation cabinet 6 and combustion furnace 8 pass sequentially through the first connecting tube 3, the Two connecting tubes 5 and third connecting tube 7 are connected to.One end that first connecting tube 3 is connect with condensation cabinet 4 is equipped with the first air inducing Machine 13, second connecting tube 5 are equipped with the second air-introduced machine 16, the third connection with 6 junction one end of electrostatic precipitation cabinet Pipe 7 and 8 junction one end of combustion furnace are equipped with third air-introduced machine 19.
, cathode electrode plate 17 is fixed on the top of 6 inner wall of electrostatic precipitation cabinet, and the anode electrode plate 18 is fixed on quiet The bottom of 6 inner wall of electric precipitation cabinet.
The side for absorbing cabinet 1 is fixed with electric cabinet 10, and the electric cabinet 10 is equipped with control panel 11, the electric cabinet 10 inside is equipped with battery 12.
Condensate film 14 is also installed in the middle part of 4 inner wall of condensation cabinet.
The top of the combustion furnace 8 stores cabinet 9 by being welded with raw material.
First connecting tube 3, the second connecting tube 5 and third connecting tube 7 are connected by flange and the cabinet of its two sides respectively It connects.The connection of first connecting tube 3 absorbs cabinet 1, condensation cabinet 4.Second connecting tube 5 connection condensation cabinet 4, electrostatic precipitation cabinet. Third connecting tube 7 connects electrostatic precipitation cabinet 6 and combustion furnace 8.
The anode of the battery 12 is electrically connected anode electrode plate 18, and the cathode of the battery 12 is electrically connected cathode Electrode plate 17.
The semiconductor chilling plate 15 is connect by seccotine with condensation cabinet 4.
The course of work:
By manipulating control panel 11, make the first air-introduced machine 13, condensate film 14, semiconductor chilling plate 15, the second air-introduced machine 16 It works with third air-introduced machine 19.
Exhaust gas is entered by air inlet pipe 2 to be absorbed in cabinet 1, and cleaning of the exhaust gas Jing Guo absorbing liquid will be dissolved in absorbing liquid Harmful substance removes.
The exhaust gas cleaned is drawn into condensation cabinet 4 by the first air-introduced machine 13 by the first connecting tube 3.Semiconductor refrigerating Freeze in 15 pairs of condensation cabinets 4 of piece, make to condense the temperature decline in cabinet 4, exhaust gas is condensed by condensate film 14, made Moisture in exhaust gas becomes condensed water, while when the pernicious gas in exhaust gas being made to reach set point, being condensed, becoming condensed water It is collected.
Exhaust gas is drawn into electrostatic precipitation cabinet 6 by the second air-introduced machine 16 by the second connecting tube 5 again.Work as cathode electrode plate Plus after Current Voltage between 17 and anode electrode plate 18, electric field is generated between cathode electrode plate 17 and anode electrode plate 18, benefit Make gas ionization with electrostatic field to make dust particles be adsorbed onto the collecting method on electrode, air molecule is electric in strong electrical field From for cation and electronics, electronics, which marches on towards, encounters grit in anode process, make grit is negatively charged to be adsorbed onto 18 quilt of anode electrode plate It collects, removes the tiny particles content in exhaust gas.
Exhaust gas is drawn into combustion furnace 8 by third air-introduced machine 19 by third connecting tube 7 again and is burnt.
Finally, it should be noted that the above descriptions are merely preferred embodiments of the present invention, it is not limited to this Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art For, it is still possible to modify the technical solutions described in the foregoing embodiments, or to part of technical characteristic It is equivalently replaced.Within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on, It should be included within the scope of protection of this utility model.

Claims (10)

1. equipment for treating industrial waste gas, which is characterized in that including absorbing cabinet (1), condensation cabinet (4), electrostatic precipitation cabinet (6) And combustion furnace (8), the absorption cabinet (1), condensation cabinet (4), electrostatic precipitation cabinet (6) and combustion furnace (8) are sequentially communicated, institute The inside for absorbing cabinet (1) is stated equipped with absorbing liquid, the absorption cabinet (1) is equipped with air inlet pipe (2), condensation cabinet (4) Bottom interior wall is equipped with semiconductor chilling plate (15), and cathode electrode plate (17) and anode are equipped in the electrostatic precipitation cabinet (6) Electrode plate (18), the combustion furnace (8) is for receiving remaining gas in electrostatic precipitation cabinet (6) and burning.
2. equipment for treating industrial waste gas according to claim 1, which is characterized in that the absorption cabinet (1), condensation cabinet (4), electrostatic precipitation cabinet (6) and combustion furnace (8) pass sequentially through the first connecting tube (3), the second connecting tube (5) and third connecting tube (7) it is connected to.
3. equipment for treating industrial waste gas according to claim 2, which is characterized in that first connecting tube (3) and condensation One end of cabinet (4) connection is equipped with the first air-introduced machine (13), and second connecting tube (5) connect with electrostatic precipitation cabinet (6) Place one end is equipped with the second air-introduced machine (16), and the third connecting tube (7) is equipped with third with combustion furnace (8) junction one end and draws Blower (19).
4. equipment for treating industrial waste gas according to claim 1, which is characterized in that cathode electrode plate (17) is fixed on electrostatic The top of dust-removing box (6) inner wall, the anode electrode plate (18) are fixed on the bottom of electrostatic precipitation cabinet (6) inner wall.
5. equipment for treating industrial waste gas according to claim 1, which is characterized in that the side for absorbing cabinet (1) is solid Surely have electric cabinet (10), the electric cabinet (10) is equipped with control panel (11), and the inside of the electric cabinet (10) is equipped with battery (12)。
6. equipment for treating industrial waste gas according to claim 1, which is characterized in that in the middle part of condensation cabinet (4) inner wall Also it is installed with condensate film (14).
7. equipment for treating industrial waste gas according to claim 1, which is characterized in that pass through at the top of the combustion furnace (8) It is welded with raw material storage cabinet (9).
8. equipment for treating industrial waste gas according to claim 2, which is characterized in that first connecting tube (3), second connect Adapter tube (5) and third connecting tube (7) are connect by flange with the cabinet of its two sides respectively.
9. equipment for treating industrial waste gas according to claim 5, which is characterized in that the anode electricity of the battery (12) Property jointed anode electrode plate (18), the cathode of the battery (12) is electrically connected cathode electrode plate (17).
10. equipment for treating industrial waste gas according to claim 5, which is characterized in that the semiconductor chilling plate (15) is logical Seccotine is crossed to connect with condensation cabinet (4).
CN201821745594.9U 2018-10-26 2018-10-26 Equipment for treating industrial waste gas Expired - Fee Related CN209549104U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821745594.9U CN209549104U (en) 2018-10-26 2018-10-26 Equipment for treating industrial waste gas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821745594.9U CN209549104U (en) 2018-10-26 2018-10-26 Equipment for treating industrial waste gas

Publications (1)

Publication Number Publication Date
CN209549104U true CN209549104U (en) 2019-10-29

Family

ID=68299004

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821745594.9U Expired - Fee Related CN209549104U (en) 2018-10-26 2018-10-26 Equipment for treating industrial waste gas

Country Status (1)

Country Link
CN (1) CN209549104U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685829A (en) * 2021-08-11 2021-11-23 上海协微环境科技有限公司 Waste gas treatment device suitable for semiconductor manufacturing process

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685829A (en) * 2021-08-11 2021-11-23 上海协微环境科技有限公司 Waste gas treatment device suitable for semiconductor manufacturing process
CN113685829B (en) * 2021-08-11 2023-07-21 上海协微环境科技有限公司 Exhaust gas treatment device suitable for semiconductor manufacturing process

Similar Documents

Publication Publication Date Title
CN205851109U (en) A kind of fume purifying electrostatic equipment and comprise its fume purifier of fume
CN203793080U (en) Automatic roof air purification device
CN203949286U (en) A kind of small home air purifier
CN206577536U (en) A kind of new mist of oil gas sampling treatment and purification equipment
CN209549104U (en) Equipment for treating industrial waste gas
CN205351559U (en) Low temperature plasma exhaust gas purifying apparatus
CN104138699B (en) A kind of electrostatic water smoke air cleaning unit
CN204017613U (en) A kind of electrostatic water smoke air cleaning unit
CN202185246U (en) Welding fume purification equipment
CN210584145U (en) Air filtering equipment convenient to clean
CN209123582U (en) A kind of multi-functional air dedusting and purifying device
CN209531138U (en) A kind of multistage combined wet electrostatic off-gas cleaning equipment
CN207929416U (en) A kind of pipeline self cleaning type fume clarifier
CN213762329U (en) Efficient rotary closed type electrostatic dust collector
CN208115985U (en) A kind of multichannel electrostatic oil and smoke cleaner
CN206905193U (en) New blower fan with multiple heat function of exchange
CN104048306B (en) Energy-saving environmental-protection boiler exhaust emissions tower
CN208287749U (en) A kind of recyclable emission-control equipment
CN207187997U (en) A kind of dynamic dust treatment equipment
CN208124470U (en) A kind of detachable multifunctional cleaning device
CN206509624U (en) A kind of use for laboratory purifier for welding smoke
CN206222520U (en) A kind of ionic tube air purifier
CN106871285B (en) Negative oxygen ion formaldehyde-removing warm air humidifying air purifier
CN105194967A (en) Smoke dust treatment system of electric furnace
CN211189572U (en) A waste gas adsorbs purifier for VOCs administers

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191029

Termination date: 20211026

CF01 Termination of patent right due to non-payment of annual fee