CN208918221U - A kind of Novel drawer formula scaffold - Google Patents

A kind of Novel drawer formula scaffold Download PDF

Info

Publication number
CN208918221U
CN208918221U CN201821246932.4U CN201821246932U CN208918221U CN 208918221 U CN208918221 U CN 208918221U CN 201821246932 U CN201821246932 U CN 201821246932U CN 208918221 U CN208918221 U CN 208918221U
Authority
CN
China
Prior art keywords
standard knot
drawer plate
drawer
rectangular shaped
quadrangle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821246932.4U
Other languages
Chinese (zh)
Inventor
管玉洋
徐浩博
刘泉昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201821246932.4U priority Critical patent/CN208918221U/en
Application granted granted Critical
Publication of CN208918221U publication Critical patent/CN208918221U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a kind of Novel drawer formula scaffold, is related to construction field of tool;Including standard knot, standard knot top quadrangle opens up standard knot socket joint hole, standard knot bottom end quadrangle is inserting column, grafting is carried out using inserting column and standard knot socket joint hole between standard knot, reinforcement by connection diagonal brace between standard knot inner top surface and bottom surface, standard knot side is also connected with ladder, weld drawer plate interlayer in standard knot top, drawer plate interlayer includes rectangular shaped rim, connection is uniformly distributed and parallel reinforcing rib between two long sides of rectangular shaped rim, rectangular shaped rim quadrangle opens up pin hole, drawer plate is placed on drawer plate interlayer, drawer plate edge opens up guardrail jack, drawer plate quadrangle opens up pin hole, when drawer plate extraction or placement, drawer plate is fixed on drawer plate interlayer using bolt.

Description

A kind of Novel drawer formula scaffold
Technical field
The utility model discloses a kind of Novel drawer formula scaffold, is related to construction field of tool.
Background technique
In decoration construction, there are some special-shaped work surfaces for ceiling or metope, height is not less than 10 meters of space again, Costly if setting up full hall scaffold, the duration is longer;If it is door-type scaffold is used, safety coefficient is not high, some works It industry face even can not operation.And the utility model provides a kind of Novel drawer formula scaffold, including standard knot, and it is different to meet part The work surface decoration construction built demand of type facilitates the safety that construction is in turn ensured while worker's construction.
Utility model content
The utility model is directed to the demand and shortcoming of current technology development, provides a kind of Novel drawer formula scaffold, Have the characteristics that design is reasonable, structure is simple and safe, easy to process, thus, it is possible to effectively save work, has and use valence well Value.
The specific technical proposal is:
A kind of Novel drawer formula scaffold, including standard knot, standard knot top quadrangle open up standard knot socket joint hole, standard knot Bottom end quadrangle is inserting column,
Grafting, reinforcement by connection between standard knot inner top surface and bottom surface are carried out using inserting column and standard knot socket joint hole between standard knot Diagonal brace, standard knot side are also connected with ladder,
Drawer plate interlayer is welded on standard knot top, and drawer plate interlayer includes rectangular shaped rim, between two long sides of rectangular shaped rim Connection is uniformly distributed and parallel reinforcing rib, rectangular shaped rim quadrangle open up pin hole, and drawer plate is placed on drawer plate interlayer, drawer Plate edge opens up guardrail jack, and drawer plate quadrangle opens up pin hole and utilizes bolt by drawer when drawer plate is extracted out or placed Plate is fixed on drawer plate interlayer.
Also connection is uniformly distributed and in parallel between two short sides of rectangular shaped rim in a kind of Novel drawer formula scaffold Reinforcing rib.
Parallel reinforcing rib is connected between two long side of drawer plate in a kind of Novel drawer formula scaffold.
Castor is installed in undermost standard knot bottom in a kind of Novel drawer formula scaffold.
The utility model has the beneficial effect that compared with prior art
The utility model provides a kind of Novel drawer formula scaffold, including standard knot, welds drawer plate interlayer on standard knot, Drawer plate can be placed, when special-shaped work surface carries out operation in part, extends the use scope of scaffold, and take out because being placed on In drawer plate interlayer, it is not take up space, structure is simple, detachably, suitable for different work surface demands, while drawer plate interlayer knot Structure is firm, also opens up guardrail jack on drawer plate, and grafting guardrail further ensures the safety of construction personnel when use.
Detailed description of the invention
Fig. 1 the utility model front schematic view;
The schematic top plan view of Fig. 2 drawer plate amplification;
The schematic top plan view of Fig. 3 drawer plate interlayer amplification.
Appended drawing reference: 1 standard knot, 2 drawer plates, 3 drawer plate interlayers, 4 inserting columns, 5 ladders, 6 reinforce diagonal brace, 7 castors, 8 shields Column jack, 9 reinforcing ribs, 10 pin holes.
Specific embodiment
It is right below in conjunction with specific embodiment for the purpose of this utility model, technical solution and advantage is more clearly understood The utility model is further described.
Embodiment 1:
A kind of Novel drawer formula scaffold, including 3 section standard knots 1,1 top quadrangle of standard knot open up standard knot socket joint hole, 1 bottom end quadrangle of standard knot is inserting column 4,
Grafting is carried out using inserting column 4 and standard knot socket joint hole between standard knot 1, is connected between 1 inner top surface of standard knot and bottom surface Diagonal brace 6 is reinforced, ladder 5 is also connected on the left of standard knot 1, strap brake castor 7 is installed in undermost 1 bottom of standard knot,
Drawer plate interlayer 3 is welded on 1 top of standard knot, and drawer plate interlayer 3 includes rectangular shaped rim, two long sides of rectangular shaped rim it Between connection be uniformly distributed and 5 parallel reinforcing ribs 9, rectangular shaped rim quadrangle open up pin hole 10, drawer plate 2 is placed on drawer plate folder On layer 3,2 parallel reinforcing ribs 9 are connected between two long side of drawer plate, 2 edge of drawer plate opens up guardrail jack 8, drawer Plate quadrangle is opened up pin hole 10 and drawer plate 2 is fixed on drawer plate interlayer 3 using bolt when drawer plate 2 is extracted out or placed.
Embodiment 2:
A kind of Novel drawer formula scaffold, including 4 section standard knots 1,1 top quadrangle of standard knot open up standard knot socket joint hole, 1 bottom end quadrangle of standard knot is inserting column 4,
Grafting is carried out using inserting column 4 and standard knot socket joint hole between standard knot 1, is connected between 1 inner top surface of standard knot and bottom surface Diagonal brace 6 is reinforced, ladder 5 is also connected on the left of standard knot 1, universal caster wheel 7 is installed in undermost 1 bottom of standard knot,
Drawer plate interlayer 3 is welded on 1 top of standard knot, and drawer plate interlayer 3 includes rectangular shaped rim, two long sides of rectangular shaped rim it Between connection be uniformly distributed and 5 parallel reinforcing ribs 9, also connection is uniformly distributed and parallel 2 between two short sides of rectangular shaped rim Root reinforcing rib 9, rectangular shaped rim quadrangle open up pin hole 10, and drawer plate 2 is placed on drawer plate interlayer 3, between two long side of drawer plate 2 parallel reinforcing ribs 9 of connection, 2 edge of drawer plate open up guardrail jack 8, and drawer plate quadrangle opens up pin hole 10, drawer plate When 2 extractions or placement, drawer plate 2 is fixed on drawer plate interlayer 3 using bolt.
Coating steel pipe can be used in the utility model Plays section 1 or aluminium side leads to welding production, enumerates a size, for example select Logical with 50 coating steel pipe of φ or the aluminium side 50mm, wall thickness must not be lower than 3mm, production 3000mm long * 3000mm wide * 1500mm's high Standard knot, drawer plate 2 can be fabricated to the plate of 3000mm long * 950mm wide, and edge stays guardrail jack 8, is easily installed spigot-and-socket Guardrail.
When the utility model is used, it first combines the standard knot of needs 1 to positive along short transverse, it is ensured that standard knot installs Finish, be fixed on drawer plate interlayer further according to needing to extract out drawer plate 2. using bolt, after guardrail is installed, can be constructed.This Between utility model saving construction manpower is timely, such as certain training base engineering project, wherein meeting room is special-shaped ceiling, and area is about It is 1000 square metres.Because of its ceiling height and different shapes, frame pipe or door-type scaffold are set up according to traditional approach, it is time-consuming to take Work seriously affects construction speed.
Engineering uses the utility model drawer type scaffold, it is only necessary to which installment work can be completed in 1 people assembling, substantially increases The installation effectiveness of scaffold is easy to remove simultaneously, shortens construction period and has saved recruitment cost.This engineering uses the drawer altogether Formula scaffold can shorten the construction period 15 days.
Recruitment expense is about 150 yuan daily, 10 workers, 15 days total 10*150*15=22500 yuan;Duration cost and its It is 5000 yuan that its process interts expense in advance daily, 15 days total 5000*15=75000 yuan;Direct saving cost total more than 90,000 Member.

Claims (4)

1. a kind of Novel drawer formula scaffold, it is characterised in that including standard knot, standard knot top quadrangle opens up standard knot socket joint Hole, standard knot bottom end quadrangle are inserting column,
Grafting is carried out using inserting column and standard knot socket joint hole between standard knot, reinforcement by connection is oblique between standard knot inner top surface and bottom surface Support, standard knot side are also connected with ladder,
Drawer plate interlayer is welded on standard knot top, and drawer plate interlayer includes rectangular shaped rim, is connected between two long sides of rectangular shaped rim It is uniformly distributed and parallel reinforcing rib, rectangular shaped rim quadrangle opens up pin hole, drawer plate is placed on drawer plate interlayer, drawer plate four Circumferential edges open up guardrail jack, and drawer plate quadrangle is opened up pin hole and consolidated drawer plate using bolt when drawer plate is extracted out or placed It is scheduled on drawer plate interlayer.
2. a kind of Novel drawer formula scaffold according to claim 1, it is characterised in that between two short sides of rectangular shaped rim Also connection is uniformly distributed and parallel reinforcing rib.
3. a kind of Novel drawer formula scaffold according to claim 2, it is characterised in that connected between two long side of drawer plate Parallel reinforcing rib.
4. a kind of Novel drawer formula scaffold according to claim 3, it is characterised in that undermost standard knot bottom peace Fill castor.
CN201821246932.4U 2018-08-03 2018-08-03 A kind of Novel drawer formula scaffold Active CN208918221U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821246932.4U CN208918221U (en) 2018-08-03 2018-08-03 A kind of Novel drawer formula scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821246932.4U CN208918221U (en) 2018-08-03 2018-08-03 A kind of Novel drawer formula scaffold

Publications (1)

Publication Number Publication Date
CN208918221U true CN208918221U (en) 2019-05-31

Family

ID=66702692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821246932.4U Active CN208918221U (en) 2018-08-03 2018-08-03 A kind of Novel drawer formula scaffold

Country Status (1)

Country Link
CN (1) CN208918221U (en)

Similar Documents

Publication Publication Date Title
CN102704672A (en) Installation construction method for large all-steel formwork at internal corner of shear wall
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN204960296U (en) Adjustable shaped steel stencil assembly
CN203487803U (en) Safety protection structure for elevator shaft construction
CN204418662U (en) A kind of building vertical structure typified form negative and positive angle bracing means
CN109404010A (en) A kind of aluminum tunnel modular system and its operating method
CN206545386U (en) Sheet metal forming formwork drops in a kind of toilet
CN103774838B (en) A kind of construction of lift well assembling safe operation platform and using method
CN205206284U (en) Detachable assembly type elevator shaft operating platform
CN208918221U (en) A kind of Novel drawer formula scaffold
CN202064281U (en) Slip form frame
CN206616765U (en) Large span is without depending on huge bandy truss pull bar
CN204001702U (en) A kind of J-shaped wall plastic formwork
CN208072912U (en) A kind of Easy opened scaffold that construction site auxiliary is built
CN203640257U (en) Support of overhanging type scaffold
CN206591443U (en) Pier stud vertical stratification integrative protection template
CN206591818U (en) Pier stud vertical stratification integrative protection template
CN206667741U (en) A kind of construction template
CN106245615A (en) A kind of block assembly auxiliary mould
CN205617770U (en) Overhanging movable type edge construction operation platform
CN205954972U (en) Steel structure floor slab
CN204492173U (en) Elevator shaft integral lifting template operation platform
CN210767970U (en) Assembled foundation pit ladder
CN107829553A (en) A kind of elevator hoistways construction platform system
CN211548680U (en) Scaffold for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant