Overhanging movable type edge construction operation platform Download PDFInfo
- Publication number
- CN205617770U CN205617770U CN201620447151.6U CN201620447151U CN205617770U CN 205617770 U CN205617770 U CN 205617770U CN 201620447151 U CN201620447151 U CN 201620447151U CN 205617770 U CN205617770 U CN 205617770U
- Authority
- CN
- China
- Prior art keywords
- platform
- main frame
- angle steel
- encorbelmenting
- outrigger
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 19
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 35
- 239000010959 steel Substances 0.000 claims abstract description 35
- 241000282326 Felis catus Species 0.000 claims abstract description 7
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 238000009434 installation Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 238000007596 consolidation process Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Ladders (AREA)
Abstract
The utility model relates to a portable limit construction operation platform that faces of encorbelmenting, a serial communication port, include the main frame that connects into by angle steel and square steel, moving mechanism, configuration case and the platform of encorbelmenting that connects into through angle steel and square steel, set up moving mechanism on the base of main frame, one side that the platform of encorbelmenting was kept away from to the main frame sets up the weight box, and one side that the main frame is close to the platform of encorbelmenting sets up the cat ladder, sets up the angle steel bracing between platform and the main frame middle part of encorbelmenting, sets up the angle steel bracing between platform and the weight box base of enco. The utility model discloses an operation platform beneficial effect lies in that the installation is consuming time weak point, use manpower sparingly, safe and reliable.
Description
Technical field
This utility model belongs to aid field in construction engineering, particularly relates to narrow field in construction
Or unconditionally set up and land the indoor and outdoor of crosshead and face limit construction and encorbelment movable operation platform.
Background technology
Along with domestic construction industry development, Commercial Complex building continues to bring out, and exterior wall faces limit and light shaft
The construction technology facing limit construction operation platform is always emphasis and the difficult point of Commercial Complex construction.Tradition
Technique often take to set up on ground land steel pipe crosshead even expire hall frame as facing limit construction operation platform,
Not only material occupancy is relatively big, sets up time-consuming long, and efficiency of construction is low, and floor space is big, serious shadow
Ring other each specialty cross-operation, be problem demanding prompt solution in current Commercial Complex construction.
Utility model content
Technical problem to be solved in the utility model is, overcome above-mentioned tradition to land defect that crosshead sets up,
Propose a kind of novel movable type of encorbelmenting and face limit construction operation platform.
The technical scheme that this utility model is used is:
One movable type of encorbelmenting faces limit construction operation platform, it is characterised in that include being connected by angle steel and square steel
The main frame of one-tenth, travel mechanism, configuration case and the outrigger platform connected into by angle steel and square steel, main frame
Arranging travel mechanism on the base of frame, main frame arranges ballast box away from the side of outrigger platform, and main frame leans on
The side of nearly outrigger platform arranges angle steel diagonal brace between arranging in the middle part of cat ladder, outrigger platform and main frame, encorbelments
Angle steel diagonal brace is set between platform and ballast box base, outrigger platform is provided with preventer.
Angle steel diagonal brace is set in the middle part of main frame and between top.
Angle steel diagonal brace is set in the middle part of main frame and between ballast box base.
Described travel mechanism includes the universal wheel being arranged on main frame base.
Described outrigger platform is provided with bed board.
Described preventer includes flak jacket railing and is arranged on the foot guard plate bottom flak jacket railing.
Main frame described in the utility model, framework are fixed component, cat ladder, ballast box, outrigger platform and protect
Body railing all uses angle steel and square steel matched combined by being welded to connect, and assembles enough yellow sands by ballast box,
By support body steadily of centre of gravity in the ground at counter weight base position, thus ensure security and stability, by test, this
The operating platform of utility model has the beneficial effects that installation process is the shortest, save manpower, safe and reliable.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present embodiment.
Fig. 2 is the front view of the present embodiment.
Wherein, 1 main frame, 2 ballast boxes, 3 outrigger platforms, 4 universal wheels, 5 first diagonal braces,
6 second diagonal braces, 7 the 3rd diagonal braces, 8 the 4th diagonal braces, 9 cat ladders, 10 flak jacket railings, 11-bed board,
12 foot guard plates.
Detailed description of the invention
Below in conjunction with the accompanying drawings this utility model is further described, as shown in Figure 1 and Figure 2.
The movable type of encorbelmenting of the present embodiment faces limit construction operation platform, and main frame 1 is passed through weldering by angle steel and square steel
Connecing in succession, main frame includes four square steel columns, surrounding subcontracting process, the chassis outer side three limit side of being mounted laterally
Steel, base surrounding subcontracting process, inner edge is put down and is easy to ballast box 2 and installs, by angle steel and square steel to installing square steel
The outrigger platform 1 being welded into, the full bed board 11 of outrigger platform 1 welding, the base of main frame arranges universal wheel 4,
Universal wheel is fixed by actually used period, and operator can complete construction operation at operating platform;Platform ten thousand
Position can be realized move after wheel unlocks, thus complete whole to face limit construction operation.Main frame is flat away from encorbelmenting
The side of platform arranges ballast box, and main frame arranges cat ladder 9, outrigger platform and main frame near the side of outrigger platform
First diagonal brace 5 is set between in the middle part of frame, angle steel the second diagonal brace 6 is set between outrigger platform and ballast box base,
3rd diagonal brace 7 is set in the middle part of main frame and between top, in the middle part of main frame and between ballast box base, arranges the 4th
Diagonal brace 8, each diagonal brace uses angle steel to be welded and fixed the reinforcing carried out between operating platform component.Arrange on outrigger platform
There is flak jacket railing 9 and be arranged on the foot guard plate 10 bottom flak jacket railing.
Component, overhanging type operating platform, scaffold board, flak jacket is fixed by described main frame member, framework
Railing, Weighting system, steel cat ladder, universal wheel on-site consolidation, formed encorbelment movable type face limit constructing operation put down
Platform, installation process is the shortest, save manpower, safe and reliable.
Claims (6)
1. a movable type of encorbelmenting faces limit construction operation platform, it is characterised in that include being connected into by angle steel and square steel
Main frame, travel mechanism, configuration case and the outrigger platform that connected into by angle steel and square steel, main frame
Base on travel mechanism is set, main frame arranges ballast box away from the side of outrigger platform, and main frame is close
The side of outrigger platform arranges angle steel diagonal brace between arranging in the middle part of cat ladder, outrigger platform and main frame, encorbelment flat
Angle steel diagonal brace is set between platform and ballast box base, outrigger platform is provided with preventer.
Operating platform the most according to claim 1, it is characterised in that in the middle part of described main frame and between top
Angle steel diagonal brace is set.
Operating platform the most according to claim 2, it is characterised in that in the middle part of described main frame with ballast box at the bottom of
Angle steel diagonal brace is set between Zuo.
Operating platform the most according to claim 1, it is characterised in that described travel mechanism includes being arranged on master
Universal wheel on frame base.
Operating platform the most according to claim 1, it is characterised in that described outrigger platform is provided with bed board.
Operating platform the most according to claim 1, it is characterised in that described preventer includes flak jacket railing
And it is arranged on the foot guard plate bottom flak jacket railing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620447151.6U CN205617770U (en) | 2016-05-17 | 2016-05-17 | Overhanging movable type edge construction operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620447151.6U CN205617770U (en) | 2016-05-17 | 2016-05-17 | Overhanging movable type edge construction operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205617770U true CN205617770U (en) | 2016-10-05 |
Family
ID=57023789
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620447151.6U Expired - Fee Related CN205617770U (en) | 2016-05-17 | 2016-05-17 | Overhanging movable type edge construction operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205617770U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106930518A (en) * | 2017-05-11 | 2017-07-07 | 中国建筑第二工程局有限公司 | Construction support and construction system |
CN110565930A (en) * | 2019-08-22 | 2019-12-13 | 中建四局第六建筑工程有限公司 | Telescopic movable operation platform for top construction of light well and construction method thereof |
-
2016
- 2016-05-17 CN CN201620447151.6U patent/CN205617770U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106930518A (en) * | 2017-05-11 | 2017-07-07 | 中国建筑第二工程局有限公司 | Construction support and construction system |
CN110565930A (en) * | 2019-08-22 | 2019-12-13 | 中建四局第六建筑工程有限公司 | Telescopic movable operation platform for top construction of light well and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203487803U (en) | Safety protection structure for elevator shaft construction | |
CN204126230U (en) | Assembly scaffold unit | |
CN204781881U (en) | Elevartor shaft structure construction handling frame | |
CN102626850A (en) | Installation process for metal oil tank in cave storage | |
CN205617770U (en) | Overhanging movable type edge construction operation platform | |
CN204126240U (en) | Moving lift type is encorbelmented operating platform | |
CN109113306A (en) | A kind of modularization elevator shaft and its construction method | |
CN109404010A (en) | A kind of aluminum tunnel modular system and its operating method | |
CN207048345U (en) | Construction discharge platform device | |
CN205206284U (en) | Detachable assembly type elevator shaft operating platform | |
CN205654127U (en) | Portable operation protective platform of assembly type structure stairwell | |
CN204024104U (en) | Fast-assembling modularization winding staircase | |
CN204238537U (en) | A kind of elevated hoistway operation platform | |
CN107795185A (en) | Chimney reinforces pylon high-altitude installation node security construction method | |
CN207003970U (en) | A kind of building scaffold being easily installed | |
CN205422060U (en) | Interim storehouse in portable building site | |
CN203394032U (en) | Inside-cylinder climb-type operation frame | |
CN203361590U (en) | Folding scaffold special for electric power construction | |
CN206591818U (en) | Pier stud vertical stratification integrative protection template | |
CN206591443U (en) | Pier stud vertical stratification integrative protection template | |
CN110792267A (en) | Combined circulating jacking support and construction process thereof | |
CN205382718U (en) | Sparse passway for escaping of steel platform die carrier system | |
WO2019024290A1 (en) | Method for building scaffold device in hyperboloidal linear cabin | |
CN204199657U (en) | The construction operation platform of irregular ceiling | |
CN203319589U (en) | Hoisting machine for installing air hose |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |