CN208009432U - A kind of prestressed concrete pipe pile stake core hole cleaning device - Google Patents
A kind of prestressed concrete pipe pile stake core hole cleaning device Download PDFInfo
- Publication number
- CN208009432U CN208009432U CN201820097167.8U CN201820097167U CN208009432U CN 208009432 U CN208009432 U CN 208009432U CN 201820097167 U CN201820097167 U CN 201820097167U CN 208009432 U CN208009432 U CN 208009432U
- Authority
- CN
- China
- Prior art keywords
- cleaning device
- main shaft
- core hole
- hole cleaning
- prestressed concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Cleaning In General (AREA)
Abstract
The utility model is specifically related to a kind of prestressed concrete pipe pile stake core hole cleaning device, mainly solves existing PHC pipe piles in-core and pours into the technical problems such as a large amount of soil is not easy to dig out, labor intensity is big, working efficiency is low, construction quality is poor, pollution environment, tube wall soil are not easily cleaned.The utility model includes turning handle, transmission rod, main shaft, casing, and two sector peace shaped steel wire brush have many advantages, such as easy to operate, simple in structure, easy making.
Description
Technical field
The utility model belongs to construction engineering technical field, and in particular to a kind of prestressed concrete pipe pile stake core borehole cleaning dress
It sets.
Background technology
The advantages that PHC pile piles are high, easy for construction due to bearing capacity of single pile, the application in engineering is more and more extensive.PHC is managed
Stake during piling construction and in rest period and digging process stake core inner can pour into a large amount of soil, after pile crown amputates,
The sundries such as soil, mud in stake holes need to be cleaned out, since stake holes aperture is smaller (aperture 20cm), draw and dig depth 3m, iron
Shovel hardly enters the deeper internal sundries of stake holes cleaning, and Luoyang Spade easily makes sundries sink, is not easy to dig out, using high pressure when clearing up mud
Water flushing is also easy to produce mud, causes the shortcomings of labor intensity is big, working efficiency is low, construction quality is poor, pollution environment, or even sometimes
Also leave hidden danger of quality.
Utility model content
The purpose of this utility model is to solve existing PHC pipe piles in-core and pour into a large amount of soil to be not easy to dig out, work by force
The technical problems such as degree is big, working efficiency is low, construction quality is poor, pollution environment, tube wall soil are not easily cleaned, provide a kind of prestressing force
Concrete tubular pile stake core hole cleaning device.
In order to solve the above technical problems, the technical solution adopted in the utility model is:
A kind of prestressed concrete pipe pile stake core hole cleaning device, including turning handle, transmission rod, main shaft, casing and two sectors
Blade is equipped with sawtooth at the fan-shaped edge of described two sectors, and the turning handle is located at the top of transmission rod, under transmission rod
End is connect with the upper end of main shaft, and the lower end of main shaft and the upper end of casing connect, and what two sectors docked is located under casing
End, and two sectors is made to mutually stagger, it is equipped with sawtooth, and two sector mistakes at the fan-shaped edge of two sectors
Certain angle is opened, the promotion that the present apparatus screws in soil layer and soil is conducive to.
Further, the prestressed concrete pipe pile stake core hole cleaning device further includes flat pattern wire brush, and flat pattern wire brush is set
On the top of main shaft, for clearing up pile pile inner wall.
Further, the angle that described two sectors mutually stagger is 30 °, using 30 ° of angle, is conducive to screw in
Soil layer.
Further, length scale is equipped on the transmission rod, to observe the depth that the present apparatus gos deep into soil layer.
Further, between the turning handle and transmission rod, between transmission rod and main shaft, between flat pattern wire brush and main shaft,
Using being threadedly coupled between main shaft and casing, facilitate length and the disassembly and assembly of the adjustment present apparatus.
The dimension data that above-mentioned pile for prestressed pipe hole cleaning device component part uses can be repaiied according to actual demands of engineering
Change, make.
The utility model use above-mentioned simple scheme, draw dig depth be 3m when, take special narrow bucket spade by pile crown first
Soil clears out in following 500mm depth bounds, and turning handle, transmission rod, flat pattern wire brush, main shaft are then assembled into the clear soil dresses of 1.5m
Set and stretch into stake holes internal pressure underground layer, rotate clockwise rotation turning handle, tool with number of revolutions into underground layer about 100mm, by power transmission
Bar rises to exposing pile crown vertically, clears up on blade and carries out lower step soil digging after soil, when at 1.2m, spreading passes under soil digging to stake holes
Power bar is to 2.2m long, and with being continuously increased for clear native depth, every time when clear soil, flat pattern wire brush carries out pile pile inner wall clear
Reason repeats the above flow, until soil is cleared up to designed elevation in stake holes, it is very convenient quick.Solve existing PHC pipe piles
In-core pours into that a large amount of soil is not easy to dig out, labor intensity is big, working efficiency is low, construction quality is poor, pollution environment, tube wall soil
The technical problems such as it is not easily cleaned.Therefore, compared with the background art, the utility model has easy to operate, simple in structure, is easy system
The advantages that making.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
Specific implementation mode
The utility model patent is further described below in conjunction with shown in attached drawing.
A kind of prestressed concrete pipe pile stake core hole cleaning device, including turning handle 1, transmission rod 2, main shaft 3, casing 5 and two
Sector 6 is equipped with length scale on the transmission rod, and sawtooth, institute are equipped at the fan-shaped edge of described two sectors 6
The top that turning handle 1 is located at transmission rod 2 is stated, the lower end of transmission rod 2 is connect with the upper end of main shaft 3, lower end and the casing 5 of main shaft 3
Upper end connects, the folder for being located at the lower end of casing 5, and two sectors 6 being made to mutually stagger 30 ° of two sectors 6 docking
Angle;The prestressed concrete pipe pile stake core hole cleaning device further includes flat pattern wire brush 4, and flat pattern wire brush 4 is located at the upper of main shaft 3
Portion.Between the turning handle 1 and transmission rod 2, between transmission rod 2 and main shaft 3, between flat pattern wire brush 4 and main shaft 3, main shaft 3 with set
Using threaded connection between pipe 5.
Claims (5)
1. a kind of prestressed concrete pipe pile stake core hole cleaning device, it is characterised in that:Including turning handle (1), transmission rod (2), main shaft
(3), casing (5) and two sectors (6) are equipped with sawtooth, the turning handle at the fan-shaped edge of described two sectors (6)
(1) it is located at the top of transmission rod (2), the lower end of transmission rod (2) is connect with the upper end of main shaft (3), the lower end of main shaft (3) and casing
(5) upper end connection, what two sectors (6) were docked is located at the lower end of casing (5), and keeps two sectors (6) mutual
It is staggered.
2. a kind of prestressed concrete pipe pile stake core hole cleaning device according to claim 1, it is characterised in that:It is described pre- to answer
Power concrete tubular pile stake core hole cleaning device further includes flat pattern wire brush (4), and flat pattern wire brush (4) is located at the top of main shaft (3).
3. a kind of prestressed concrete pipe pile stake core hole cleaning device according to claim 2, it is characterised in that:It is described two
The angle that sector (6) mutually staggers is 30 °.
4. a kind of prestressed concrete pipe pile stake core hole cleaning device according to claim 3, it is characterised in that:In the biography
Power bar (2) is equipped with length scale.
5. according to a kind of prestressed concrete pipe pile stake core hole cleaning device of claim 1-4 any one of them, it is characterised in that:
Between the turning handle (1) and transmission rod (2), between transmission rod (2) and main shaft (3), between flat pattern wire brush (4) and main shaft (3),
It uses and is threadedly coupled between main shaft (3) and casing (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820097167.8U CN208009432U (en) | 2018-01-19 | 2018-01-19 | A kind of prestressed concrete pipe pile stake core hole cleaning device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820097167.8U CN208009432U (en) | 2018-01-19 | 2018-01-19 | A kind of prestressed concrete pipe pile stake core hole cleaning device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208009432U true CN208009432U (en) | 2018-10-26 |
Family
ID=63884223
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820097167.8U Active CN208009432U (en) | 2018-01-19 | 2018-01-19 | A kind of prestressed concrete pipe pile stake core hole cleaning device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208009432U (en) |
-
2018
- 2018-01-19 CN CN201820097167.8U patent/CN208009432U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205714026U (en) | A kind of water injection type drilling machine drilling rod | |
CN206554077U (en) | A kind of stake holes cleaning equipment | |
CN202969389U (en) | Spiral shovel for clearing soil of pile core | |
CN103669349A (en) | Variable diameter stirring type anchor rod and construction method thereof | |
CN100494615C (en) | Non-excavation underground pipeline tunnel wall tension propulsion machine | |
CN108824471A (en) | A kind of deep water drift net multi-column pier foundation and its construction method | |
CN205171521U (en) | A device that is used for tubular pile stake core to clear up | |
CN108035353A (en) | A kind of prestressed concrete pipe pile stake core hole cleaning device | |
CN208009432U (en) | A kind of prestressed concrete pipe pile stake core hole cleaning device | |
CN105297732A (en) | Slagging promoting device for ultra-thick clay layer positive-cycle cast-in-place pile and construction method of slagging promoting device | |
CN206941588U (en) | A kind of simple positioning tool of steel-pipe pile spreading | |
CN113846664B (en) | Continuous soil-taking and sinking machine for non-drainage open caisson | |
CN101906778B (en) | Construction site tubular pile muddredger and manufacturing method thereof | |
CN205776226U (en) | Formula prefabricated tubular pile stake core soil sampler is dug in a kind of rotation | |
CN203948024U (en) | The latent horizontal square hole rig that revolves of formula | |
CN209040780U (en) | A kind of environmental-friendly circulation device of hardened place prospecting | |
CN206457823U (en) | A kind of device for clearing up Prefabricated hollow pile stake core | |
CN203049636U (en) | Concrete pole foundation excavation tool | |
CN201268857Y (en) | Soil shovel | |
CN221074195U (en) | Rotary drilling rig drill bit soil sampling device | |
CN206328757U (en) | A kind of pile hole construction instrument | |
CN216225626U (en) | Quick cleaning device of steel sheet pile | |
CN105421460B (en) | A kind of pile tube bottom grouting device and method | |
CN221523561U (en) | Clear geotechnical tool of prestressing force tubular pile | |
CN214301746U (en) | Novel clear hole of pile foundation construction device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |