CN101906778B - Construction site tubular pile muddredger and manufacturing method thereof - Google Patents

Construction site tubular pile muddredger and manufacturing method thereof Download PDF

Info

Publication number
CN101906778B
CN101906778B CN201010255215XA CN201010255215A CN101906778B CN 101906778 B CN101906778 B CN 101906778B CN 201010255215X A CN201010255215X A CN 201010255215XA CN 201010255215 A CN201010255215 A CN 201010255215A CN 101906778 B CN101906778 B CN 101906778B
Authority
CN
China
Prior art keywords
edge
muddredger
tubular pile
construction site
center
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201010255215XA
Other languages
Chinese (zh)
Other versions
CN101906778A (en
Inventor
郭云道
韩伟
徐华
何新伟
凌江
董伟忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU XINGYE CONSTRUCTION DEVELOPMENT Co Ltd
Suzhou No1 Construction Group Co Ltd
Original Assignee
SUZHOU XINGYE CONSTRUCTION DEVELOPMENT Co Ltd
Suzhou No1 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU XINGYE CONSTRUCTION DEVELOPMENT Co Ltd, Suzhou No1 Construction Group Co Ltd filed Critical SUZHOU XINGYE CONSTRUCTION DEVELOPMENT Co Ltd
Priority to CN201010255215XA priority Critical patent/CN101906778B/en
Publication of CN101906778A publication Critical patent/CN101906778A/en
Application granted granted Critical
Publication of CN101906778B publication Critical patent/CN101906778B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a construction site tubular pile muddredger and a manufacturing method thereof. The muddredger comprises a dredging body extending into a tubular pile hole, and a holding rod used for being held by an operator, wherein the holding rod passes through the center of the dredging body and is fixedly connected with the dredging body; and the dredging body is provided with a first edge and a second edge, wherein the second edge rotates upwards at a certain angle relatively to the first edge by taking the holding rod as center. The method comprises the steps of: arranging a central hole in the center of a metal piece body; cutting off radius, and generating the first edge and the second edge, forming height difference between the first edge and the second edge, and rotating the second edge upwards at a certain angle relatively to the first edge about the center line where the central hole is arranged; leading a slender rod piece to pass through the central hole, and fixing the slender rod piece; and welding a handle. The tubular pile muddredger improves the efficiency for cleaning mud, has simple and convenient operation, greatly improves the construction efficiency and saves the construction cost.

Description

Construction site tubular pile muddredger and manufacturing approach thereof
Technical field
The present invention relates to a kind of construction tool of job site, the method that particularly relates to a kind of pile tube mud dredger and make this mud dredger.
Background technology
At present, prestressed concrete pipe pile has characteristics such as pile quality is good, and vertical bearing capacity of single pile is high, and is strong to engineering geological conditions compliance, and speed of application is fast.Therefore, since the seventies in 20th century, in engineerings such as China's building, highway, railway, harbour, obtained using widely.Pile for prestressed pipe stake top links to each other with basic platform through filling out core concrete; For rich groundwater area stake case, pile-raft foundation and for highrise building that receives the overturning moment effect or tall and slender structure; The basis might be all or a side drawn, make to push up and fill out core concrete and receive the pulling capacity effect.In order to guarantee that pile for prestressed pipe stake top links to each other with basic platform through filling out core concrete, the soil that must will be pressed in the native pile for prestressed pipe is cleaned out.The stake core soil of pile for prestressed pipe generally needs cleaning to about 3 meters, have in addition also can be darker.In the process of removing earth, waste time and energy.In the prior art, for the following method of removing in the pile for prestressed pipe of the general employing of earth:
(1), through using the head of spade; Earth in the pile for prestressed pipe hole is dug out; But the general length of the head of spade is at 30~50 centimetres; Width is at 5~10 centimetres, and the pile for prestressed pipe aperture is generally also only at 40~50 centimetres, and spade can only dig out and locate 1~2 meter earth in the pile for prestressed pipe aperture like this;
(2), in pile for prestressed pipe, water entry, earth is diluted and softens, through using grafter, earth is dug out again, but owing in earth, added water, the quality of earth increases, like this to operating personnel's physical fitness requirement height very.
At the construction field (site), often exist tens even up to a hundred pile for prestressed pipe holes etc. for clearance, as according to the above-mentioned method operating efficiency end very, this has also just prolonged the construction period greatly, causes the raising of construction cost.
Summary of the invention
An object of the present invention is to provide a kind of construction site tubular pile muddredger.
For achieving the above object, the technical scheme that the present invention adopts is:
A kind of construction site tubular pile muddredger; Comprise be used to stretch in the hole of post dredge body be used for the holding rod that the operator grips; Described holding rod passes the center of the described body of dredging and is fixedly connected with it; The described body of dredging has first edge and second edge, and described relatively first edge, described second edge is that the center rotated up certain angle with described holding rod.
Preferably, be connected with the handle that is used to rotate described mud dredger on the described holding rod.
Further preferably, described handle is yi word pattern.
Preferably, the Breadth Maximum of the described body of dredging is less than 3~4 centimetres of hole of post diameters.
Another object of the present invention provides a kind of method of making this mud dredger.
For achieving the above object, the technical scheme that the present invention adopts is:
A kind of method of making this construction site tubular pile muddredger, carry out according to the following steps:
(1), select a circular metal lamellar body, offer centre bore at the center of described metal lamellar body;
(2), described metal lamellar body is cut off along its any radius; Have the first relative edge and second edge on the metal lamellar body after cutting off; Described first edge and the second edge in the vertical direction are separated down; Make both form difference in height, more described second edge is rotated up certain angle with described relatively first edge of center line that described centre bore belongs at vertical direction;
(3), a slender rod piece is passed described centre bore, and described slender rod piece and metal lamellar body are fixed;
(4), on described slender rod piece, weld handle.
Preferably, described slender rod piece and metal lamellar body are fixedly connected through welding.
Because the technique scheme utilization, the present invention compared with prior art has advantage and effect: the efficient of removing earth through pile tube mud dredger of the present invention is high, easy and simple to handle, can improve efficiency of construction greatly, practices thrift construction cost.
Description of drawings
Accompanying drawing 1 is a structural representation of the present invention;
Accompanying drawing 2 is the making sketch map one of the body of dredging;
Accompanying drawing 3 is the making sketch map two of the body of dredging;
Accompanying drawing 4 is the making sketch map three of the body of dredging.
Wherein: 1, the body of dredging; 2, holding rod; 3, handle; 4, first edge; 5, second edge.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the present invention is further described:
A kind of construction site tubular pile muddredger as shown in Figure 1, comprise be used to stretch in the pile for prestressed pipe hole dredge body 1 be used for the holding rod 2 that the operator grips, holding rod 2 passes the center of the body 1 of dredging and is fixedly connected with it.Wherein, the body 1 of dredging has first edge 4 and 5 relative first edges 4,5, the second edges, second edge are that the center rotated up certain angle with holding rod 2, makes between first edge 4 and second edge 5 and produces difference in height.
In the present embodiment, be connected with the handle 3 that is used for the Rotation Dredging device on the holding rod 2, this handle 3 is yi word pattern, and the center of handle 3 is welded on the end of holding rod 2.
In addition, because the body 1 of dredging need stretch in the pile for prestressed pipe hole, the external diameter of the body 1 of therefore dredging is littler 3~4 centimetres than the diameter in pile for prestressed pipe hole at least, in order to avoid can't stretch into.The mud dredger (being generally 1.5m, 2.4m, 3.4m) that different length can be set according to the different degree of depth in pile for prestressed pipe hole is made by the job site actual conditions, uses from being short to long operating personnel with convenient scene.
Below the concrete preparation method of present embodiment down of setting forth:
This method is carried out according to the following steps:
(1), select a circular metal lamellar body, offer centre bore at the center of metal lamellar body, as shown in Figure 2;
(2), the metal lamellar body is cut off along its any radius, have the first relative edge 4 and second edge 5 on the metal lamellar body after cutting off, as shown in Figure 3.First edge 4 and second edge, 5 in the vertical directions are separated down; Make both form difference in height at vertical direction; Again second edge 5 is rotated up certain angle with relative first edge 4 of center line that centre bore belongs to; Make between first edge 4 and second edge 5 and produce difference in height, as shown in Figure 4.Generally speaking the difference in height at first edge 4 and second edge 5 is decided according to the soft degree of earth, and soil property is harder, and both differences in height are generally at 4~6 centimetres; Soil property is softer, and both differences in height are generally at 6~10 centimetres;
(3), a slender rod piece is passed centre bore, and slender rod piece and metal lamellar body are welded mutually fixing, make that sheet metal is body formed to be the body 1 of dredging, slender rod piece is grip part 2;
(4), welding handle 3 on slender rod piece.
Below the concrete method of operating of present embodiment down of setting forth:
Operator grasps grip part 2 body 1 of will dredging stretches in the pile for prestressed pipe hole, and rotating handles 3 makes earth sweep from first edge 4, and is deposited on the body 1 of dredging, when earth accumulation during to suitable degree, within the scope that promptly operating personnel can lift.The body 1 of will dredging lifts out, can carry out next operation after emptying.Like this, can not only remove the earth of the dark section in pile for prestressed pipe hole, operate also easylier, can improve duration of construction, saving construction cost greatly.
The foregoing description only is explanation technical conceive of the present invention and characteristics, and its purpose is to let the personage who is familiar with this technology can understand content of the present invention and enforcement according to this, can not limit protection scope of the present invention with this.All equivalences that spirit is done according to the present invention change or modify, and all should be encompassed within protection scope of the present invention.

Claims (6)

1. construction site tubular pile muddredger; It is characterized in that: comprise be used to stretch in the hole of post dredge body be used for the holding rod that the operator grips; Described holding rod passes the center of the described body of dredging and is fixedly connected with it; The described body of dredging has first edge and second edge; Described relatively first edge, described second edge is that the center rotated up certain angle with described holding rod, and the difference in height at described first edge, second edge is 4~6 centimetres or 6~10 centimetres.
2. construction site tubular pile muddredger according to claim 1 is characterized in that: be connected with the handle that is used to rotate described mud dredger on the described holding rod.
3. construction site tubular pile muddredger according to claim 2 is characterized in that: described handle is yi word pattern.
4. construction site tubular pile muddredger according to claim 1 is characterized in that: the Breadth Maximum of the described body of dredging is less than 3~4 centimetres of hole of post diameters.
5. method of making construction site tubular pile muddredger as claimed in claim 1, it is characterized in that: its manufacturing approach is carried out according to the following steps:
(1), select a circular metal lamellar body, offer centre bore at the center of described metal lamellar body;
(2), described metal lamellar body is cut off along its any radius; Have the first relative edge and second edge on the metal lamellar body after cutting off; Described first edge and the second edge in the vertical direction are separated down; Make both form difference in height, more described second edge is rotated up certain angle with described relatively first edge of center line that described centre bore belongs at vertical direction;
(3), a slender rod piece is passed described centre bore, and described slender rod piece and metal lamellar body are fixed;
(4), on described slender rod piece, weld handle.
6. manufacturing approach according to claim 5 is characterized in that: described slender rod piece and metal lamellar body are fixedly connected through welding.
CN201010255215XA 2010-08-17 2010-08-17 Construction site tubular pile muddredger and manufacturing method thereof Active CN101906778B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010255215XA CN101906778B (en) 2010-08-17 2010-08-17 Construction site tubular pile muddredger and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010255215XA CN101906778B (en) 2010-08-17 2010-08-17 Construction site tubular pile muddredger and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN101906778A CN101906778A (en) 2010-12-08
CN101906778B true CN101906778B (en) 2012-07-25

Family

ID=43262352

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010255215XA Active CN101906778B (en) 2010-08-17 2010-08-17 Construction site tubular pile muddredger and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN101906778B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103255792A (en) * 2013-02-05 2013-08-21 江苏省电力公司扬州市江都供电公司 Electric pole dibble

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635116A (en) * 2012-05-10 2012-08-15 南通海洲建设集团有限公司 Hole cleaner
CN104314118B (en) * 2014-11-19 2017-07-18 国家电网公司 Dell earther taking apparatus

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201268857Y (en) * 2008-04-25 2009-07-08 王汉猷 Soil shovel
CN201771009U (en) * 2010-08-17 2011-03-23 苏州第一建筑集团有限公司 Construction site tubular pile dredger

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11303118A (en) * 1998-04-27 1999-11-02 Takeo Yamaguchi Surveying post hole drilling tool

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201268857Y (en) * 2008-04-25 2009-07-08 王汉猷 Soil shovel
CN201771009U (en) * 2010-08-17 2011-03-23 苏州第一建筑集团有限公司 Construction site tubular pile dredger

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103255792A (en) * 2013-02-05 2013-08-21 江苏省电力公司扬州市江都供电公司 Electric pole dibble
CN103255792B (en) * 2013-02-05 2015-12-02 江苏省电力公司扬州市江都供电公司 A kind of electric pole dibble

Also Published As

Publication number Publication date
CN101906778A (en) 2010-12-08

Similar Documents

Publication Publication Date Title
CN101736760B (en) Construction method of prestressed anti-floating anchor rod
CN103132908B (en) Device for drilling rock and embedding rock-socketed prestressed pipe pile by down-hole hammer and construction method of device
CN106522242A (en) Foundation pit supporting system for subsurface structure close to soft ground stratum and construction method of foundation pit supporting system
CN102108706A (en) Simple manual spiral earth fetching device for reinforcing pile core of pre-stressed pipe pile
CN101851922B (en) Method for eliminating underground anchor rope/rod by using all casing drill
CN202969389U (en) Spiral shovel for clearing soil of pile core
CN104746519A (en) Obstacle clearing construction method
CN101906778B (en) Construction site tubular pile muddredger and manufacturing method thereof
CN102383431A (en) Sinking device and novel sinking method of center dug prestressed centrifuge pipe pile (square pile)
CN202039368U (en) Simple hand-operated spiral soil borrowing device for reinforcement of prestressed tubular pile core
CN201074340Y (en) Pile-drawing machine
CN111005381A (en) Bottom-pocket type vibration hammer profile steel pile extractor and pile extracting method thereof
CN107964995A (en) A kind of pile foundation borehole device
CN102383428B (en) Middle pick reverse drawing method prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof
CN201771009U (en) Construction site tubular pile dredger
CN201635074U (en) Ground anchor
CN203583501U (en) Deep-layer shear resistant device capable of preventing rock sliding
CN206385549U (en) For soft stratum close to underground structure foundation pit supporting system
CN202064350U (en) Collapsible soil hole-forming pile tube
CN202157743U (en) Drop hammer type accurate position impact perforator
CN206457823U (en) A kind of device for clearing up Prefabricated hollow pile stake core
CN206681011U (en) Pile tube stake holes cleaning device for inner wall
CN209722982U (en) A kind of pair of bracing wire beam foundation pit supporting construction
CN106759377A (en) The construction method of recyclable building enclosure
CN201268857Y (en) Soil shovel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant