CN207988409U - Basic ground assembly - Google Patents

Basic ground assembly Download PDF

Info

Publication number
CN207988409U
CN207988409U CN201721910250.4U CN201721910250U CN207988409U CN 207988409 U CN207988409 U CN 207988409U CN 201721910250 U CN201721910250 U CN 201721910250U CN 207988409 U CN207988409 U CN 207988409U
Authority
CN
China
Prior art keywords
levelling
bar
basic ground
supporting surface
support element
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721910250.4U
Other languages
Chinese (zh)
Inventor
周东珊
余文钊
步挺
武鹏
许伟
周雪萍
李梦珺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yasha Decoration Co Ltd
Original Assignee
Zhejiang Yasha Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Yasha Decoration Co Ltd filed Critical Zhejiang Yasha Decoration Co Ltd
Priority to CN201721910250.4U priority Critical patent/CN207988409U/en
Application granted granted Critical
Publication of CN207988409U publication Critical patent/CN207988409U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Floor Finish (AREA)

Abstract

The utility model discloses a kind of basic ground assemblies.Basic ground assembly includes basic ground, the first support element and the second support element, and the first support element includes the first supporting surface, and the second support element includes the second supporting surface:Each levelling component includes levelling bar and leveling bar, and each levelling bar includes levelling face;The distance between the second end of leveling bar and levelling face are adjustable;The both ends of each levelling bar are overlapped on the first supporting surface and the second supporting surface, and multiple levelling bars are arranged along the axially direction perpendicular to levelling bar;It is multiple to look for co-planar and be each perpendicular to plumb line.Basic ground assembly provided by the utility model reduces the difficulty of maintenance or the maintenance of floor heating pipeline, reduces the security risk of floor heating pipeline, reduces hand labor intensity, improve the flatness on ground, shorten construction period, is conducive to standardize rapid construction.

Description

Basic ground assembly
Technical field
The utility model is related to building decoration technology field more particularly to a kind of basic ground assemblies.
Background technology
Be required to indoors in exterior decoration, before installation floor to entire ground carry out it is levelling so that the ground after installation floor Face keeps flatness.
In the prior art, the bottom surface for being equipped with floor heating generally first uses cement mortar screeding, then the cement after levelling Floor heating pipeline is laid on mortar, then in floor heating pipeline upper cement mortar to realize cement mortar bedding residence heating coil line and make water Mud Self-leveling is levelling, finally on the cement mortar after levelling laying floor complete ground laying.Inventor is realizing invention During find, the ground paving mode of above-mentioned installation floor heating has the following disadvantages:The first, floor heating pipeline is once after installation It is difficult to safeguard or overhaul, leading to floor heating use, there are some potential safety problemss in the process;The second, after cement screeding needs manually Phase smoothes out ground, increases hand labor intensity;Third, for the larger ground of area, using cement screeding Often there is certain fluctuating in face, it is difficult to meet flatness requirement, and the time needed for the solidification of ground is longer, extend construction week Phase is unfavorable for standardizing rapid construction.
Therefore, it is necessary to solve above-mentioned technical problem.
Utility model content
The utility model provides a kind of basic ground assembly, to solve problems of the prior art, reduces floor heating pipe The difficulty of maintenance or the maintenance of line reduces the security risk of floor heating pipeline, reduces hand labor intensity, improves the smooth of ground Degree shortens construction period, is conducive to standardize rapid construction.
The utility model provides a kind of basic ground assembly, including basic ground, further includes:Positioned at the basic ground First support element and the second support element on the both sides being oppositely arranged, first support element include the first supporting surface, described second Support element includes the second supporting surface:Multiple levelling components, each levelling component include levelling bar and leveling bar, Mei Gesuo It includes levelling face to state levelling bar;The first end of each leveling bar is connected with the levelling bar, each leveling bar Second end be connected in the basic ground, the leveling bar backwards to the levelling face, the second end of the leveling bar with The distance between the levelling face is adjustable;The both ends of the levelling bar are overlapped on first supporting surface and second described respectively On support face, multiple levelling bars are arranged along the axially direction perpendicular to the levelling bar;Multiple levelling faces It is coplanar and be each perpendicular to plumb line.
Optionally, the level height of first supporting surface is equal to the level height of second supporting surface.
Optionally, the basic ground assembly further include be located in the basic ground and the first metope for being oppositely arranged and Second metope, first support element are fixed on first metope, and second support element is fixed on second metope On.
Optionally, the basic ground assembly further includes third metope, and first metope and second metope pass through The third metope is connected;Third support element is connected on the third metope, the third support element includes third support Face, the third supporting surface along the axially extending setting of the levelling bar, with described look for by the level height of the third supporting surface The level height of plane is identical.
Optionally, the levelling bar is connected with the leveling bar by connector, and the connector includes being sequentially connected The first limiting plate, bottom plate and the second limiting plate, first limiting plate is oppositely arranged with second limiting plate;It is described The first end of leveling bar is connected with the bottom plate, and the levelling bar is fed through first limiting plate, the bottom plate, Yi Jisuo State the limit space of the second limiting plate restriction.
Optionally, the leveling bar is screw rod, is offered with female adjustment hole, the leveling bar on the bottom plate First end be screwed onto in the adjustment hole.
Optionally, reinforcing prop is connected on the bottom plate, the adjustment hole adds along the reinforcing prop axially through described Qiang Zhu.
Optionally, the lift span for penetrating through the levelling bar is offered on the levelling bar, the reinforcing prop is worn into described In lift span.
Optionally, the end face of the first end of the leveling bar offers Hexagon hole, the Hexagon hole and the lifting Hole alignment setting.
Basic ground assembly provided by the utility model, levelling face is levelling by the realization of multiple leveling bars, in basic ground Multiple levelling components of upper setting and by multiple levelling face leveling, multiple levelling face upper berth installed floors after leveling simultaneously make multiplely Plate is full of basic ground, it is ensured that multiple floors are located in same level, simplify leveling procedures, and it is strong to reduce labour Degree, accelerates speed of application, ensure that the flatness of the basic ground of large area;And floor heating pipeline can be laid on leveling bar Between second end and levelling bar, it is not necessarily to casting cement, the construction period of maintenance cement is shortened, reduces floor heating pipeline and using The difficulty of maintenance, maintenance in the process.
Description of the drawings
Preferred embodiment in the utility model will be described in detail by attached drawing below, it will help understand the utility model Objects and advantages, wherein:
Fig. 1 is the structural schematic diagram for the basic ground assembly that the preferred embodiment in the utility model provides.
Fig. 2 is the structural schematic diagram for the basic ground that the preferred embodiment in the utility model provides.
Fig. 3 is the structural schematic diagram for the levelling component that the preferred embodiment in the utility model provides.
Fig. 4 is the partial enlarged view of A in Fig. 3.
Fig. 5 is the structural schematic diagram that the leveling bar that the preferred embodiment in the utility model provides is connected with connector.
Fig. 6 is the structural schematic diagram for the leveling bar that the preferred embodiment in the utility model provides.
Fig. 7 is the structural schematic diagram for the connector that the preferred embodiment in the utility model provides.
Fig. 8 is the front view of Fig. 7.
Fig. 9 is the positive structural schematic diagram on floor.
Figure 10 is the structural schematic diagram at the back side on floor.
Specific implementation mode
Up, down, left, right, before and after, front, the back side, top, the bottom etc. mentioned or may mentioned in the present specification Orientation term is defined relative to construction shown in each attached drawing, and word "inner" and "outside" refer respectively to direction or remote From the direction of geometric center of specific component, they are opposite concepts, and it is therefore possible to can be according to its residing different location, difference Use state and correspondingly changed.So also should not these or other orientation term be construed to restricted use Language.
Fig. 1 is the structural schematic diagram for the basic ground assembly that the preferred embodiment in the utility model provides, and Fig. 2 is that this practicality is new The structural schematic diagram for the basic ground that type preferred embodiment provides, Fig. 3 are levelling group that the preferred embodiment in the utility model provides The structural schematic diagram of part, Fig. 4 are the partial enlarged view of A in Fig. 3.
As shown in Figures 1 to 4, the utility model provides a kind of basic ground assembly, including basic ground 2, is located at institute State first support element 21 and the second support element and multiple levelling components on the both sides that basic ground 2 is oppositely arranged.
Please refer to Fig. 1 to Fig. 4, first support element 21 includes the first supporting surface 22, and second support element includes the Two supporting surfaces, each levelling component include levelling bar 7 and leveling bar 4, and each levelling bar 7 includes levelling face 71; The first end of each leveling bar 4 is connected with the levelling bar 7, and the second end of each leveling bar 4 is connected to In the basic ground 2, the leveling bar 4 is backwards to the levelling face 71, the second end of the leveling bar 4 and the levelling face 71 The distance between it is adjustable;The both ends of each levelling bar 7 are respectively overlapped on first supporting surface 22 and second described On support face, multiple levelling bars 7 are arranged along the axially direction perpendicular to the levelling bar 7;It is multiple described levelling Face 71 is coplanar and is each perpendicular to plumb line.By means of infrared surface level-meter, by adjust leveling bar 4 second end and levelling face 71 it Between distance, levelling face 71 may be implemented in the level height of setting perpendicular to perpendicular, reached 71 leveling of levelling face Purpose.After 71 leveling of levelling face, the second end of leveling bar 4 is fixed in basic ground 2, is laid in basic ground 2 multiple Levelling component, and the installation floor on levelling face 71, multiple floors be full of entire basic ground 2, ensure that rapid construction and Mat formation the flatness on ground behind floor.
It refers to adjusting it should be noted that the distance between the second end of the leveling bar 4 and the levelling face 71 are adjustable The length of flat bar 4 can be adjusted, and leveling bar 4 can be fixed on the length value regulated:If leveling bar 4 is scalable setting And the bar with self-locking function;Or the second end of leveling bar 4 and 7 bolt of levelling bar, the second end for passing through driving leveling bar 4 are revolved Into or screw out levelling bar 7, with the distance between second end and the levelling face 71 for adjusting leveling bar 4.
The basic ground assembly that the utility model alternative embodiment provides, levelling face 71 are looked for by the realization of multiple leveling bars 4 It is flat, multiple levelling components are set in basic ground 2 and by multiple 71 leveling of levelling face, on multiple levelling faces 71 after leveling Mat formation floor and make multiple floors be full of basic ground 2, it is ensured that multiple floors are located in same level, simplify levelling Process reduces labor intensity, accelerates speed of application, ensure that the flatness of the basic ground 2 of large area;And floor heating pipeline It can be laid between the second end of leveling bar 4 and levelling bar 7, be not necessarily to casting cement, shorten the construction period of maintenance cement, Reduce the difficulty of the maintenance in use of floor heating pipeline, maintenance.
Optionally, when basic ground assembly is installed, can the first supporting surface 22 and the first be determined according to ground design height The height of two supporting surfaces is subsequently mounted the first support element 21 and the second support element to ensure the first supporting surface 22 and the second supporting surface It is respectively positioned in preset height.The level height of first supporting surface 22 is equal to the level height of second supporting surface, has The levelling bar 7 being overlapped on respectively conducive to both ends on the first supporting surface 22 and the second supporting surface keeps levelness, reduces levelling face 71 levelling difficulty.
Further, the basic ground assembly further includes being located at the first wall in the basic ground 2 and being oppositely arranged Face 31 and the second metope 32, first support element 21 are fixed on first metope 31, and second support element is fixed on On second metope 32, when 2 assembly of basic ground is installed, first bullet can be carried out on the first metope 31 and the second metope 32 Line then installs the first support element 21 on the basis of the snap the line on the first metope 31, on the basis of the snap the line on the second metope 32 Second support element is installed, ensure that the level height of the first supporting surface 22 and the second supporting surface after installation meets the requirements, quickly It is convenient.
Optionally, the basic ground assembly further includes third metope 33, first metope 31 and second metope 32 are connected by the third metope 33;Third support element 25, the third support element are connected on the third metope 33 25 include third supporting surface 26, and the third supporting surface 26 is along the axially extending setting of the levelling bar 7, the third supporting surface 26 level height is identical as the level height in the levelling face 71.Third supporting surface 26 is the receipts being connected on third metope 33 Side floor provides effectively support, ensure that the planarization for receiving side floor.
Optionally, the first support element 21 includes fixed plate connected vertically and connecting plate, and fixed plate is to be spirally connected or be bonded Mode be bonded and be fixed on the first metope 31, the first supporting surface 22 is located on connecting plate, and the first supporting surface 22 is perpendicular to metope Setting.The structure of second support element and, third support identical as the first support element 21 as the fixed form of the second metope 32 The structure of part 25 and identical as the first support element 21 as the fixed form of third metope 33, details are not described herein again.
Preferably, the leveling bar 4 is square tube.Square tube is hollow structure, has the ability of good carrying and resistance to deformation, And material can be saved, reduce weight.
Optionally, when the distance between the first metope 31 and the second metope 32 are larger, levelling bar 7 generally passes through first point of bar 72 and second point of bar 73 be spliced, one end of first point of bar 72 and one end of second point of bar 73 are connected to each other by abaculus 74.Tool Body is:The first end of abaculus 74 is embedded in the inside of the one end being connected to each other with second point of bar 73 on first point of bar 72, institute The second end for stating abaculus 74 is embedded in the inside of the one end being connected to each other with first point of bar 72 on second point of bar 73.Abaculus 74 Can by after docking first point of bar 72 and the firm quickly connection of second point of bar 73, accelerate construction speed.
Further, the outer diameter of abaculus 74, the internal diameter of first point of bar 72, second point of bar 73 internal diameter all same can make abaculus 74 are fastened on the inside of first point of bar 72 and second point of bar 73.Further, it can also be hammered into from the outside of first point of bar 72 Wear simultaneously into the first screw 75 in first point of bar 72 and abaculus 74, with further increase by first point of bar 72 and abaculus 74 it Between the stability that connects;It can also hammer into while be worn into second point of bar 73 and abaculus 74 from the outside of second point of bar 73 Two screws 76, further to increase the stability connected between second point of bar 73 and abaculus 74.In Fig. 3 to Fig. 4, abaculus 74 is embedding It is located at the inside of first point of bar 72 and second point of bar 73, therefore is shown in broken lines.
Fig. 5 is the structural schematic diagram that the leveling bar that the preferred embodiment in the utility model provides is connected with connector, and Fig. 6 is The structural schematic diagram for the leveling bar that the preferred embodiment in the utility model provides, Fig. 7 are what the preferred embodiment in the utility model provided The structural schematic diagram of connector, Fig. 8 are the front view of Fig. 7.
Referring to Fig. 1 to Fig. 8, optionally, the levelling bar 7 is connected with the leveling bar 4 by connector 1, The connector 1 includes sequentially connected first limiting plate 11, bottom plate 12 and the second limiting plate 13, first limiting plate 11 are oppositely arranged with second limiting plate 13;The first end of the leveling bar 4 is connected with the bottom plate 12, the levelling bar 7 are fed through the limit space that first limiting plate 11, the bottom plate 12 and second limiting plate 13 limit.First limit Position plate 11 and the second limiting plate 13 can prevent levelling bar 7 from tumbling, and improve the stability that levelling bar 7 is connect with leveling bar 4.It is levelling Bar 7 is connected on bottom plate 12, and plate 12 plays a supporting role to levelling bar 7, is driven by the rising or decline of bottom plate 12 levelling Bar 7 shares movement, simple and convenient.
Optionally, the leveling bar 4 is screw rod, is offered with female adjustment hole 14 on the bottom plate 12, described The first end of leveling bar 4 is screwed onto in the adjustment hole 14.By driving the first end precession of leveling bar 4 or screwing out adjustment hole 14, with the distance between second end and the levelling face 71 for adjusting leveling bar 4.
Preferably, being connected with reinforcing prop 15 on the bottom plate 12, the adjustment hole 14 is passed through along the axial direction of the reinforcing prop 15 Lead to the reinforcing prop 15.Reinforcing prop 15 can increase contact area of the bottom plate 12 along the axial direction and leveling bar 4 of leveling bar 4, improve Leveling bar 4 is connected to the stability on bottom plate 12.Further, the axis of reinforcing prop 15 is perpendicular to bottom plate 12,4 edge of leveling bar It is extended into adjustment hole 14 perpendicular to the direction of bottom plate 12, the leveling procedures in levelling face 71 can be simplified.
Further, the reinforcing prop 15 is fed through the bottom plate 12, is located at the bottom plate 12 on the reinforcing prop 15 Multiple ribs 16 are connected between the axial plane of outer surface side and the bottom plate 12, ribs 16 improves reinforcing prop 15 and bottom The stability connected between plate 12.It should be noted that the outer surface of bottom plate 12 refers on bottom plate 12 backwards to levelling face 71 Face.Optionally, the quantity of ribs 16 is multiple, and multiple ribs 16 are uniformly distributed along the circumferential direction of reinforcing prop 15.
Optionally, the lift span 77 for penetrating through the levelling bar 7 is offered on the levelling bar 7, the reinforcing prop 15 is worn Into in the lift span 77.The open top of lift span 77 is located on levelling face 71, and the bottom opening of lift span 77 is positioned at levelling On bar 7 on the surface in levelling face 71.Lift span 77 is that reinforcing prop 15 provides accommodation space, ensure that and is carried on the back on levelling bar 7 It is connected on bottom plate 12 to the fitting of the surface in levelling face 71, increases bonding strength, and convenient for adjusting the angle in levelling face 71.
Further, the end face of the first end of the leveling bar 4 offers Hexagon hole 41, the Hexagon hole 41 and institute State the alignment setting of lift span 77.The Hexagon hole 41 is aligned setting with the lift span 77, refers to 41 direction of Hexagon hole Lift span 77 is located at the opening on the tube wall at 71 place of levelling face.Die nut can be from opening on the tube wall where levelling face 71 Mouth extends into Hexagon hole 41, and driving leveling bar 4 precession or back-out in adjustment hole 14 is high with the level for adjusting levelling face 71 Degree simplifies adjustment process.
Preferably, the second end of the leveling bar 4 is connected with support plate 5, the support plate 5 perpendicular to the leveling bar 4, Leveling bar 4 is connected to by support plate 5 in basic ground 2, and support plate 5 increases the contact between leveling bar 4 and basic ground 2 Area improves stability of the leveling bar 4 in basic ground 2.
Optionally, it is opened up in the support plate 5 with female mounting hole, the second end of the leveling bar 4 is screwed onto In the mounting hole, leveling bar 4 and 5 bolt of support plate, can after plant produced direct-assembling at the construction field (site), accelerate The construction efficiency at scene.
Further, be connected with support column 6 in the support plate 5, the mounting hole along the support column 6 axially through The support column 6, support column 6 can increase the area that is spirally connected between leveling bar 4 and support plate 5, and be played vertically to leveling bar 4 The effect of support improves the stability of leveling bar 4.Optionally, it is also associated with and adds between the outer surface of support column 6 and support plate 5 Strengthening tendons 61, multiple reinforcing ribs 61 are uniformly distributed along the circumferential direction of the support column 6.
Fig. 9 is the positive structural schematic diagram on floor, and Figure 10 is the structural schematic diagram at the back side on floor.
Fig. 1 to Figure 10 is please referred to, by the distance between second end and the levelling face 71 for adjusting multiple leveling bars 4, is realized Multiple levelling faces 71 are coplanar and after plumb line, and floor 8 is mounted on levelling face 71, magic is arranged on levelling face 71 Patch, the hair side of velcro is backwards to levelling face 71.Velcro is set at the back side on floor 8, the hook surface 81 of velcro is backwards to floor 8 The back side.Floor 8 is snapped onto on levelling face 71, the hook surface 81 of the hair side and velcro that make velcro is bonded correspondingly It realizes that floor 8 is mounted on the effect in levelling face 71, multiple floors 8 is mounted on correspondingly according to the method described above multiple levelling On face 71.At the position for receiving side, floor 8 is directly overlapped on towards the edge of third metope 33 on third supporting surface 26.
Fig. 1 to Figure 10 is please referred to, basic ground assembly provided by the utility model is installed by the following method:Including: The both sides being oppositely arranged in basic ground 2 are installed by the first support element 21 and the second support element respectively;Make in each levelling component The both ends of levelling bar 7 are overlapped on respectively on the first supporting surface 22 and the second supporting surface;The second end of each leveling bar 4 is supported It is connected in the basic ground 2;Multiple levelling components are installed in the basic ground 2, make multiple 7 edges of levelling bar Axially direction perpendicular to the levelling bar 7 is arranged;Adjust the second end of each leveling bar 4 and each levelling face The distance between 71, keep multiple levelling faces 71 coplanar and perpendicular to plumb line;The second end of each leveling bar 4 is equal It is fixed in the basic ground 2.
When basic ground 2 is located at interior, SI further includes first being oppositely arranged after levelling according to ground design height Then snap the line on two the first metopes 31 and the second metope 32 installs the first support element 21 and second respectively according to snap the line position Support member.S2 further includes according to the suitably levelling bar 7 of room width assembled length, so that the end face at the both ends of levelling bar 7 is supported respectively It is connected on the first metope 31 and the second metope 32, improves the stationarity of levelling bar 7.
The utility model alternative embodiment provides the method for installing basic ground assembly, and levelling face 71 passes through multiple tune Flat bar 4 is realized levelling, multiple levelling components is arranged in basic ground 2 and by multiple 71 leveling of levelling face, more after leveling 71 upper berth installed floor 8 of a levelling face simultaneously makes multiple floors 8 be full of basic ground 2, it is ensured that multiple floors 8 are located at same level On face, leveling procedures are simplified, reduce labor intensity, accelerate speed of application, ensure that the flat of the basic ground 2 of large area Whole degree;And floor heating pipeline can be laid between the second end of leveling bar 4 and levelling bar 7, be not necessarily to casting cement, shortened maintenance The construction period of cement reduces the difficulty of the maintenance in use of floor heating pipeline, maintenance.
Finally it should be noted that:Above example is only to illustrate the technical solution of the utility model, rather than its limitations; Although the utility model is described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: It still can be with technical scheme described in the above embodiments is modified, or is carried out to which part technical characteristic etc. With replacement;And these modifications or replacements, various embodiments of the utility model technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (9)

1. a kind of basic ground assembly, including basic ground, which is characterized in that further include:
Positioned at first support element on the both sides that the basic ground is oppositely arranged and the second support element, first support element includes First supporting surface, second support element include the second supporting surface:
Multiple levelling components, each levelling component include levelling bar and leveling bar, and each levelling bar includes levelling Face;The first end of each leveling bar is connected with the levelling bar, and the second end of each leveling bar is connected to In the basic ground, the leveling bar is between the levelling face, the second end of the leveling bar and the levelling face Apart from adjustable;
The both ends of the levelling bar are overlapped on respectively on first supporting surface and second supporting surface, multiple levelling bars It is arranged along the axially direction perpendicular to the levelling bar;It looks for co-planar described in multiple and is each perpendicular to plumb line.
2. basic ground assembly according to claim 1, which is characterized in that the level height of first supporting surface is equal to The level height of second supporting surface.
3. basic ground assembly according to claim 1, which is characterized in that the basic ground assembly further includes being located at institute The first metope and the second metope stated in basic ground and be oppositely arranged, first support element are fixed on first metope On, second support element is fixed on second metope.
4. basic ground assembly according to claim 3, which is characterized in that the basic ground assembly further includes third wall Face, first metope and second metope are connected by the third metope;It is connected with third on the third metope Support element, the third support element include third supporting surface, the third supporting surface along the levelling bar axially extending setting, The level height of the third supporting surface is identical as the level height in levelling face.
5. basic ground assembly according to any one of claims 1-4, which is characterized in that the levelling bar and the tune Flat bar is connected by connector, and the connector includes sequentially connected first limiting plate, bottom plate and the second limiting plate, First limiting plate is oppositely arranged with second limiting plate;The first end of the leveling bar is connected with the bottom plate, institute It states levelling bar and is fed through the limit space that first limiting plate, the bottom plate and second limiting plate limit.
6. basic ground assembly according to claim 5, which is characterized in that the leveling bar is screw rod, on the bottom plate It offers with female adjustment hole, the first end of the leveling bar is screwed onto in the adjustment hole.
7. basic ground assembly according to claim 6, which is characterized in that reinforcing prop is connected on the bottom plate, it is described Adjustment hole is along the reinforcing prop axially through the reinforcing prop.
8. basic ground assembly according to claim 7, which is characterized in that offer on the levelling bar and looked for described in perforation The lift span of flat bar, the reinforcing prop are worn into the lift span.
9. basic ground assembly according to claim 8, which is characterized in that the end face of the first end of the leveling bar opens up There are Hexagon hole, the Hexagon hole to be aligned setting with the lift span.
CN201721910250.4U 2017-12-30 2017-12-30 Basic ground assembly Active CN207988409U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721910250.4U CN207988409U (en) 2017-12-30 2017-12-30 Basic ground assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721910250.4U CN207988409U (en) 2017-12-30 2017-12-30 Basic ground assembly

Publications (1)

Publication Number Publication Date
CN207988409U true CN207988409U (en) 2018-10-19

Family

ID=63818538

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721910250.4U Active CN207988409U (en) 2017-12-30 2017-12-30 Basic ground assembly

Country Status (1)

Country Link
CN (1) CN207988409U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104401A (en) * 2017-12-30 2018-06-01 浙江亚厦装饰股份有限公司 Basic ground assembly and installation method
CN110242009A (en) * 2019-06-20 2019-09-17 金螳螂精装科技(苏州)有限公司 A kind of ground screed finish support device, facing mounting structure and installation method
CN110565899A (en) * 2019-09-17 2019-12-13 苏州金螳螂建筑装饰股份有限公司 leveling structure and leveling method for epoxy gold grindstone terrace base layer
CN111502177A (en) * 2020-05-06 2020-08-07 浙江亚厦装饰股份有限公司 Installation method of leveling substrate assembly
CN111927040A (en) * 2020-09-09 2020-11-13 金螳螂精装科技(苏州)有限公司 Assembled leveling structure on ground
CN112064982A (en) * 2020-09-27 2020-12-11 浙江亚厦装饰股份有限公司 Assembly type accessible elastic floor system and installation method thereof
CN112064974A (en) * 2020-09-27 2020-12-11 浙江亚厦装饰股份有限公司 But leveling elastic component suitable for floor system
CN112942732A (en) * 2021-02-06 2021-06-11 北京市燕通建筑构件有限公司 Floor system
CN112982677A (en) * 2021-02-06 2021-06-18 北京市燕通建筑构件有限公司 Integrated house assembling system

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104401A (en) * 2017-12-30 2018-06-01 浙江亚厦装饰股份有限公司 Basic ground assembly and installation method
CN110242009A (en) * 2019-06-20 2019-09-17 金螳螂精装科技(苏州)有限公司 A kind of ground screed finish support device, facing mounting structure and installation method
CN110565899A (en) * 2019-09-17 2019-12-13 苏州金螳螂建筑装饰股份有限公司 leveling structure and leveling method for epoxy gold grindstone terrace base layer
CN110565899B (en) * 2019-09-17 2024-04-12 苏州金螳螂建筑装饰股份有限公司 Epoxy gold grindstone terrace base leveling structure and leveling method
CN111502177A (en) * 2020-05-06 2020-08-07 浙江亚厦装饰股份有限公司 Installation method of leveling substrate assembly
CN111927040A (en) * 2020-09-09 2020-11-13 金螳螂精装科技(苏州)有限公司 Assembled leveling structure on ground
CN112064982A (en) * 2020-09-27 2020-12-11 浙江亚厦装饰股份有限公司 Assembly type accessible elastic floor system and installation method thereof
CN112064974A (en) * 2020-09-27 2020-12-11 浙江亚厦装饰股份有限公司 But leveling elastic component suitable for floor system
CN112942732A (en) * 2021-02-06 2021-06-11 北京市燕通建筑构件有限公司 Floor system
CN112982677A (en) * 2021-02-06 2021-06-18 北京市燕通建筑构件有限公司 Integrated house assembling system
CN112982677B (en) * 2021-02-06 2022-04-01 北京市燕通建筑构件有限公司 Integrated house assembling system
CN112942732B (en) * 2021-02-06 2022-07-08 北京市燕通建筑构件有限公司 Floor system

Similar Documents

Publication Publication Date Title
CN207988409U (en) Basic ground assembly
CN108104401A (en) Basic ground assembly and installation method
CN105178433B (en) Precast concrete shear wall structure and its construction method
CN207974446U (en) Floor is aerial to be laid with component
CN108104417A (en) Base's leveling component and leveling method
CN108316606A (en) A kind of ground overhead system and its installation method
US20180058082A1 (en) Ground anchor bracket for multiple wall braces
WO2020143222A1 (en) Fabricated suspended ceiling structure and installation method therefor
CN207974443U (en) Base's leveling component
CN108952075A (en) Assembled floor leveling structure and installation method
CN207988526U (en) The erecting by overhang of unit type curtain wall plate
CN111502308B (en) Bottom box adjusting device
CN206279630U (en) A kind of fastener inserts
CN110242003A (en) Load-bearing floor heating assembly and installation method
CN207974444U (en) Levelling foot and leveling component
CN207988413U (en) Ground leveling component
CN207620372U (en) A kind of built-in fitting blocks up sizing device and floor precast construction
CA2888544C (en) Primary and intermediate horizontal leveler
CN207999049U (en) Make somebody a mere figurehead leveling unit in floor
CN210316369U (en) Novel floor overhead support
CN108086657B (en) Floor overhead leveling device and leveling method
CN208918202U (en) Assembled floor leveling structure
CN208803681U (en) Piping shaft and building structure
CN110242002A (en) Floor heating assembly and installation method
CN110424740A (en) A kind of leveling unit and method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant