CN208803681U - Piping shaft and building structure - Google Patents

Piping shaft and building structure Download PDF

Info

Publication number
CN208803681U
CN208803681U CN201821229392.9U CN201821229392U CN208803681U CN 208803681 U CN208803681 U CN 208803681U CN 201821229392 U CN201821229392 U CN 201821229392U CN 208803681 U CN208803681 U CN 208803681U
Authority
CN
China
Prior art keywords
piping shaft
piping
tube body
floor
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821229392.9U
Other languages
Chinese (zh)
Inventor
汤学东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tian Hua Architectural Design Corp Ltd
Original Assignee
Shanghai Tian Hua Architectural Design Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tian Hua Architectural Design Corp Ltd filed Critical Shanghai Tian Hua Architectural Design Corp Ltd
Priority to CN201821229392.9U priority Critical patent/CN208803681U/en
Application granted granted Critical
Publication of CN208803681U publication Critical patent/CN208803681U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of piping shaft and building structure, wherein piping shaft is prefabrication, versatility with height, assembling operation is only needed in construction site, greatly reduces original concrete cast-in-situ operation, to reduce manpower demand, reduce the construction time and reduce the pollution to environment.Further, piping shaft provided by the utility model is preferably provided with decorative layer, and building and finishing with integrated design and can construct, and finishing can be carried out with building main body construction is synchronous, reduces by a procedure, reduces human cost and construction time.

Description

Piping shaft and building structure
Technical field
The utility model relates to the realm of building construction, in particular to a kind of piping shaft and building structure.
Background technique
Current each building be unable to do without various piping shafts, such as water supply pipe well, power pipe well, hot water channels pipe well, But current piping shaft is formed by scene using concrete cast-in-situ mostly.It does so, not only pollutes environment, but also to construction personnel And the number demand of administrative staff is larger, human cost is high.In addition to this, because needing poured in place concrete, and without gauge Very little, so design and construction are more complex, construction cost is higher, and in addition construction period is also long, economic benefit is poor, does not meet state The requirement for the green building that family advocates energetically.
Therefore, it is necessary to design a kind of over-the-counter piping shaft prefabricated, versatility is good.
Utility model content
The purpose of this utility model is to provide a kind of piping shaft and building structure, to solve existing piping shaft design cost One or more of the problems such as height, long construction period, pollution environment and deficiency in economic performance.
In order to solve the above technical problems, the utility model provides a kind of piping shaft, the piping shaft is prefabrication and wraps Include hollow rectangular tube body and the spacing board for being set to the rectangular tube body both ends;Wherein, the rectangular tube body is extremely Pipe well door is offered in few one side wall.
Optionally, the rectangular tube body is equipped with interconnecting piece, and the interconnecting piece with the spacing board for connecting.
Optionally, the interconnecting piece is embedded bar, default one of step and pre-embedded bolt or multiple combinations.
Optionally, when the interconnecting piece be embedded bar when, the spacing board be also used to by cast-in-place concrete with it is described Interconnecting piece connection.
Optionally, the outer surface of the pipe well door and/or at least described rectangular tube body are equipped with the side wall of the pipe well door Outer surface be equipped with decorative layer.
Optionally, the height of architecture storey is the positive integer times of the piping shaft.
Optionally, the height of the piping shaft is 2200mm~4400mm.
In order to solve the above technical problems, the utility model additionally provides a kind of building structure, there is at least one floor, packet Include piping shaft as described in any one of the above embodiments;Wherein, the floor is equipped with through-hole, and the piping shaft is threaded through the through-hole In, while the spacing board is separately positioned on the both ends of the rectangular tube body.
Optionally, the floor and the piping shaft are multiple, and the through-hole on multiple floors is arranged same On straight line, and multiple piping shafts are threaded through in multiple through-holes and join end to end and connect.
Optionally, a spacing board is shared between piping shaft described in every two.
According to technical solution provided by the utility model, piping shaft provided by the utility model and building structure are with following The utility model has the advantages that
The first, piping shaft conveniently, reduces the operation work at scene in prefabricated outside the venue, the versatility with height, in-site installation Sequence reduces manpower demand, shortens the construction period, reduce construction cost, while reducing the pollution to environment;
The second, piping shaft provided by the utility model is preferably provided with decorative layer, and building and finishing can be with integrated designs And construct, finishing can be carried out with building main body construction is synchronous, reduced by a procedure, reduced human cost and construction time.
Detailed description of the invention
Fig. 1 is the perspective view of the piping shaft in the utility model first embodiment;
Fig. 2 is the assembling schematic diagram of spacing board on piping shaft shown in FIG. 1;
Fig. 3 is the perspective view of the piping shaft in the utility model second embodiment;
Fig. 4 is the assembling schematic diagram of spacing board on piping shaft shown in Fig. 3;
Fig. 5 is the perspective view that multiple piping shafts are superimposed in the utility model 3rd embodiment;
Fig. 6 is the perspective view of the building structure in the utility model fourth embodiment;
Fig. 7 is the plan view of the building structure in the preferred embodiment in the utility model.
In figure:
1- piping shaft;2- floor;10- side wall;11- interconnecting piece;20- spacing board;21- pipeline hole;30- pipe well door.
Specific embodiment
Below in conjunction with the drawings and specific embodiments to the utility model proposes piping shaft and building structure make further it is detailed It describes in detail bright.It should be noted that attached drawing is all made of very simplified form and using non-accurate ratio, only to convenient, bright The purpose of the utility model embodiment is aided in illustrating clearly.In addition, the structure that attached drawing is shown is often one of practical structures Point.Particularly, the emphasis that each attached drawing needs to show is different, uses different ratios sometimes.
Such as in the appended claims and used in the description, singular "a", "an" and "the" packet Plural reference is included, in addition in addition non-content explicitly points out.Such as in the appended claims and as used in this specification, art Language "or" be usually carried out with including the meaning of "and/or" using, in addition in addition non-content explicitly points out.
Please refer to figs. 1 to 4, and Fig. 1 is the perspective view of the piping shaft in the utility model first embodiment, and Fig. 2 is Fig. 1 institute The assembling schematic diagram of spacing board on the piping shaft shown, Fig. 3 are the perspective views of the piping shaft in the utility model second embodiment, figure 4 be the assembling schematic diagram of spacing board on piping shaft shown in Fig. 3.
As depicted in figs. 1 and 2, in the first embodiment, the utility model provides a kind of over-the-counter prefabricated piping shaft 1, It includes hollow rectangular tube body and the spacing board 20 for being set to the rectangular tube body both ends.Wherein, the rectangular tube body Pipe well door 30 is at least offered in one side wall 10, the pipe well door 30 can open or close.
Compared with prior art, piping shaft 1 provided by the utility model is prefabrication, according to the conventional tube of architectural design Size is arranged in road, according to substantially uniform length, width and height size, carries out modularized design, and the versatility with height is applied in building Work scene only needs assembling operation, greatly reduces original concrete cast-in-situ operation, thus reduce manpower demand, reduce the construction time with And pollution of the reduction to environment.
Further, the rectangular tube body is equipped with interconnecting piece 11, and the interconnecting piece 11 with the spacing board 20 for connecting. Preferably, the interconnecting piece 11 is embedded bar, default one of step or pre-embedded bolt or multiple combinations, when the connection When portion 11 is preferably embedded bar, the spacing board 20 is also used to connect by cast-in-place concrete with the interconnecting piece 11.Generally , the piping shaft of building needs to block at floor because of the reason of preventing fires, and therefore, the present embodiment uses prefabricated spacing board 20 As partition is blocked, meet the requirement of piping shaft fireproof blocking.In addition, interconnecting piece 11 is also when multiple piping shafts 1 connect from beginning to end The firmness of the connection between multiple piping shafts 1 can be further strengthened by the connection with spacing board 20.
Further, the pipeline hole 21 worn for pipeline is offered on the spacing board 20, which can be according to specific It needs to open up, and preferably opens up completion in prefabrication phase, worn directly to be used when subsequent assembling for pipeline, practical basis The number of pipe arrangement sets the quantity of pipeline hole 21.The required pipeline worn can be water supply pipe, power pipe etc., And the same piping shaft usually wears same kind of pipeline.
Further, the utility model is not specifically limited spacing board 20 and the connection type of interconnecting piece 11, such as can be The both ends embedded bar of side wall 10 forms the interconnecting piece 11, and then in construction site, convenient for the cast-in-place coagulation on interconnecting piece 11 Spacing board 20 is connected by soil with side wall 10.As shown in Fig. 2, end face of the size of the spacing board 20 preferably with rectangular tube body Matching, in such manner, it is possible to, convenient for placement spacing board 20, which reduces costs using the end of rectangular tube body as support, and Firm and reliable connection.
Further, as shown in Figure 3 and Figure 4, in a second embodiment, the interconnecting piece 11 can also be default step, It specifically is equipped with one of step in the one end of rectangular tube body, and the size of spacing board 20 is preferably matched with the step surface of step, this Sample facilitates one end that spacing board 20 is arranged in rectangular tube body.
In other embodiments, the interconnecting piece 11 can also be pre-embedded bolt, can will also be grown by screw bolt and nut Square tube body is fixedly connected with spacing board 20, and certain interconnecting piece 11 can be applied in combination with various ways, to further strengthen connection Firmness, the utility model is not construed as limiting this.
Further, the outer surface of the pipe well door 30 is equipped with decorative layer, alternatively, at least described rectangular tube body is equipped with institute The outer surface for stating the side wall 10 of pipe well door 30 is equipped with decorative layer, alternatively, simultaneously in the outer surface of pipe well door 30 and at least rectangular The outer surface that tube body is equipped with the side wall of pipe well door 30 is equipped with decorative layer.Since the pipeline being arranged in piping shaft 1 usually requires Maintenance, and at least one of piping shaft 1 be facing towards aisle, therefore, the present embodiment is at least at this towards offering on the face in aisle Pipe well door 30.And under construction, towards the surface in aisle, generally require decorations.And piping shaft provided by the utility model 1, the outer surface of side wall 10 and pipe well door 30 towards aisle can be according to the prefabricated decorative layer of Interior design of architecture, beauty warp Ji.For example, can be in prefabrication phase, using back-hand craft, the materials such as prefabricated ceramic tile, stone material, or molding rear surface sprayed coating Deng.The setting of the decorative layer may make building and finishing with integrated design and can construct, and design cost is low and design style is united One, and fit up and carried out with building main body construction is synchronous, it can reduce by a procedure, reduce human cost and construction time.
Further, the positive integer times of the highly preferred height H for the piping shaft 1 of architecture storey.In general, pipeline Well is generally a cube, and height is generally along the short transverse setting of building, i.e. perpendicularly to the direction on ground, the height H is spent according to the different set-up modes of aforementioned spacing board 20, there are two types of definition, when spacing board 20 is arranged outside rectangular pipe body, As shown in Figure 1, its height H is length the sum of of the thickness of a spacing board 20 with side wall 10 along short transverse.And spacing board 20 It is arranged in rectangular tubular body, as shown in Fig. 2, its height H is length of the side wall 10 along short transverse.In addition, building building The height of layer is the positive integer times of the piping shaft, then can make that positive integer pipe is only arranged in the altitude range of a floor Road well 1 avoids the height of piping shaft 1 and the unmatched situation of story height from occurring, is easily installed and connects.
Preferably, in the altitude range of a floor, a piping shaft 1 is only set, be more convenient for installing in this way and is connected It connects.Certainly one piping shaft 1 of only setting herein, refers to and a piping shaft 1 is only arranged in short transverse, when building needs are a variety of When the piping shaft 1 of function, it is mutually juxtaposed and is arranged in the same floor in the horizontal direction between multiple piping shafts 1, do not exist In this limitation.
It is furthermore preferred that the height H of the piping shaft 1 is in the range of 2200-4400mm.The layer of common buildings is a height of 2800-5400mm, some special buildings, such as indoor bicycle parking area etc., layer height may down to 2200mm, so, this is practical The height H of the piping shaft 1 of novel offer, single piping shaft 1 is chosen as 2200mm, to adapt to the building of different purposes.And it is another On the one hand, some layers of extra high building of height, such as some halls of Tong Gao or some offices, commercial building etc. up and down, can In such a way that a floor is spliced using two piping shafts 1 even more than piping shaft 1, carry out meet demand.So single pipeline The height H of well 1 is preferably lower than or equal to 4400mm, in this way, single piping shaft can be selected when layer height is less than or equal to 4400mm 1, and layer is tall and big when 4400mm, and multiple piping shafts 1 can be selected and splice.In addition, the height H of single piping shaft 1 is less than or equal to 4400mm can also make piping shaft 1 more convenient during production and transportation, and general general wagon can transport, and apply Working hour lifts also more convenient.
Preferably, piping shaft 1 provided by the utility model is prefabrication product.Prefabricated, work is carried out to piping shaft 1 by factory Factory can carry out digitlization and information-based management to the component of production, in turn, constitute the accuracy of each product members of piping shaft 1 It can be very high.And on the other hand, factorial construction can be by environment pollution control to reduced levels.In addition, modular production, Due to the phase same sex of product, template and equipment are reusable, and then can reduce production cost.Its modular production method Meet the requirement of green building.Certainly, piping shaft 1 provided by the utility model or construction site are prefabricated, are relatively suitble to In the little situation of construction scope, such as only two layers building, the dosage of piping shaft 1 is also little, can be at the construction field (site) It is prefabricated, transit link is saved, it is convenient directly to use.
Fig. 5 is please referred to Fig. 7, wherein Fig. 5 is the solid that multiple piping shafts are superimposed in the utility model 3rd embodiment Figure, Fig. 6 is the perspective view of the building structure in the utility model 3rd embodiment, and Fig. 7 is in the preferred embodiment in the utility model Building structure plan view.
As shown in Figure 5 and Figure 6, the 3rd embodiment of the utility model additionally provides a kind of building structure comprising as above The piping shaft 1;Wherein, the floor 2 is equipped with through-hole, and the piping shaft 1 wears in the through hole, at the same it is described between Partition 20 is separately positioned on the both ends of the rectangular tube body.
Preferably, the floor 2 and the piping shaft 1 are multiple, and the through-hole setting on multiple floors 2 exists On same straight line, and multiple piping shafts 1 are threaded through in multiple through-holes and join end to end and connect.Here through-hole, it is excellent It is selected in when floor 2 is constructed and reserves, facilitate wearing for subsequent pipeline well 1.It is preferably provided with built-in connection in the through-hole, in order to rear It is continuous to connect, such as embedded bar or pre-embedded bolt can be used with the piping shaft 1 etc., after the completion of the construction of floor 2, by pipeline When the lifting of well 1 is disposed therein, according to embedded bar, then only need to be attached embedded bar and pour a small amount of coagulation Piping shaft 1 and floor can be connected as an entirety by soil, so the workload that pours at scene subtracts significantly compared with prior art It is few.And connected according to pre-embedded bolt, then can even avoid scene completely pours work.Here floor 2, including building Floor plate or floorboard, particularly, when only one layer of building, floor 2 here only refers to floor plate, at this point, on the floor plate Through-hole is offered, pipeline is horizontally disposed along buried pipe wire casing or basement, until it is logical to be pierced by this upwards when the projected position of the through-hole Hole simultaneously enters piping shaft 1.In addition, piping shaft 1 provided in this embodiment, is equally applicable to basement, setting and superstructure It is similar, only its pipeline to penetrate direction different from superstructure, such as water pipe, usually since Underground pump station, along level Direction setting, until piping shaft 1 and the to the ground above laying are penetrated, so floor 2 at this time, can also refer to the top of basement Plate.In addition, if floor 2 can also refer to roof boarding, can open up on roof boarding at this time when there is part pipeline to need to lead to roofing Through-hole, so that piping shaft 1 is worn, for example, some buildings need to be arranged on roof between water tank, water pipe needs to be pierced by roofing Setting, can open up through-hole on roof boarding at this time, piping shaft 1 is arranged in wherein, so as to the laying of water pipe.
In general, piping shaft 1 is used for the short transverse setting along building, and pipeline is then arranged in inside it, a pipeline Well 1 is only used for the pipeline of special purpose, such as water pipe manhole, then the piping shaft is only used for setting water pipe system.So in piping shaft 1 for it is multiple when, successively stacked along short transverse.According to the height of floor, 1 mould of piping shaft is at least arranged in each floor Block.As shown in figure 5, L1, L2 and L3 in figure respectively refer to the flooring absolute altitude of floor 1, floor 2 and floor 3, by taking L1 and L2 as an example, It is respectively arranged a piping shaft 1, and the piping shaft 1 of L2 overlays on the piping shaft 1 of L1.Preferably, at this point, this two pipes A spacing board 20 can be shared between road well 1, as shown in Figure 5, naturally it is also possible to not share spacing board 20 and be provided separately.This Sample, according to the floor and height of building, multiple piping shafts 1 for stacking setting constitute a complete piping shaft system, are used for The pipeline of a certain purposes wears the height to the top of building or needs from construction bottom along the piping shaft system.
When the piping shaft system is multiple, the multiple piping shaft system is preferably set side by side in the horizontal direction, also The enabling direction of i.e. multiple piping shafts 1 is identical, and multiple piping shafts 1 are bordered by setting mutually with side, as shown in fig. 7, multiple pipelines Well system can flexibly and easily be applied in combination in the horizontal direction.In addition, in multiple piping shaft systems arranged side by side, if same The piping shaft of class can also be preferably connected to from each other, that is, connection hole is preset between the adjacent side wall 10, Pipeline is facilitated to interconnect setting.For example, cable bus is set in a piping shaft 1, setting in another adjacent piping shaft 1 The devices such as ammeter pass through the connection of connection hole between two piping shafts 1.In addition, the juxtaposition of multiple piping shaft systems, may be used also Think that setting or side are to modes such as the back sides back-to-back, the enabling of two piping shafts 1 of finger back-to-back here is contrary, together Sample, side refers to the enabling direction of two piping shafts 1 to the back side in 90 settings, and the utility model is to multiple piping shaft systems Juxtaposition is with no restriction.Certainly, multiple piping shaft systems can also be separated and are independently arranged, and the utility model is to multiple piping shafts The set-up mode of system is also with no restriction.
Foregoing description is only the description to the utility model preferred embodiment, not to any limit of the scope of the utility model Fixed, any change, the modification that those skilled in the art do according to the disclosure above content belong to the guarantor of claims Protect range.

Claims (10)

1. a kind of piping shaft, which is characterized in that for prefabrication and including hollow rectangular tube body and for being set to the length The spacing board at square tube body both ends;Wherein, pipe well door is offered in at least one side wall of the rectangular tube body.
2. piping shaft as described in claim 1, which is characterized in that the rectangular tube body is equipped with interconnecting piece, the interconnecting piece For being connect with the spacing board.
3. piping shaft as claimed in claim 2, which is characterized in that the interconnecting piece is embedded bar, default step and pre-buried One of bolt or multiple combinations.
4. piping shaft as claimed in claim 3, which is characterized in that when the interconnecting piece is embedded bar, the spacing board It is also used to connect by cast-in-place concrete with the interconnecting piece.
5. piping shaft as claimed in claim 1 or 2, which is characterized in that the outer surface of the pipe well door and/or at least described length The outer surface that square tube body is equipped with the side wall of the pipe well door is equipped with decorative layer.
6. piping shaft as claimed in claim 1 or 2, which is characterized in that the height of architecture storey is the just whole of the piping shaft Several times.
7. piping shaft as claimed in claim 6, which is characterized in that the height of the piping shaft is 2200mm~4400mm.
8. a kind of building structure has at least one floor, which is characterized in that the building structure includes such as claim 1 to 7 Any one of described in piping shaft;Wherein, the floor is equipped with through-hole, and the piping shaft is worn in the through hole, together Shi Suoshu spacing board is separately positioned on the both ends of the rectangular tube body.
9. building structure as claimed in claim 8, which is characterized in that the floor and the piping shaft be it is multiple, it is multiple The through-hole on the floor is arranged on same straight line, and multiple piping shafts are threaded through in multiple through-holes simultaneously It joins end to end and connects.
10. building structure as claimed in claim 9, which is characterized in that share an interval between piping shaft described in every two Plate.
CN201821229392.9U 2018-08-01 2018-08-01 Piping shaft and building structure Active CN208803681U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821229392.9U CN208803681U (en) 2018-08-01 2018-08-01 Piping shaft and building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821229392.9U CN208803681U (en) 2018-08-01 2018-08-01 Piping shaft and building structure

Publications (1)

Publication Number Publication Date
CN208803681U true CN208803681U (en) 2019-04-30

Family

ID=66229005

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821229392.9U Active CN208803681U (en) 2018-08-01 2018-08-01 Piping shaft and building structure

Country Status (1)

Country Link
CN (1) CN208803681U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409757A (en) * 2019-07-17 2019-11-05 阜阳市风雅颂生产力促进中心有限责任公司 A kind of full steel structure architectural shaft floor modules
CN110905165A (en) * 2019-11-04 2020-03-24 金点石(北京)建筑设计咨询服务有限责任公司 Piping shaft, building and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409757A (en) * 2019-07-17 2019-11-05 阜阳市风雅颂生产力促进中心有限责任公司 A kind of full steel structure architectural shaft floor modules
CN110905165A (en) * 2019-11-04 2020-03-24 金点石(北京)建筑设计咨询服务有限责任公司 Piping shaft, building and construction method

Similar Documents

Publication Publication Date Title
US10156073B2 (en) Modular building system
US8297002B2 (en) Constructive system
US6925761B1 (en) Modular buildings
DE212016000202U1 (en) Integrated composite building with steel structure
RU2712845C1 (en) Method of manufacturing large-sized finished three-dimensional module and method of building construction from large-size finished 3d modules
CN208803681U (en) Piping shaft and building structure
EP2175088B1 (en) Method of installation on site of a prefabricated semi-resistant module for construction
CN110612373A (en) Prefabricated pre-decorated volume construction of buildings
CN106193402B (en) Girder truss integrated form flooring module and its installation method
CN107060152A (en) Attachment means and method between a kind of prefabricated internal partition wall of transformer station and floor
CN110295624A (en) Crossroad underground pedestrian walk and pipe gallery build structure and its construction method jointly
US11885145B2 (en) Hybrid building system, building and method
CN204753834U (en) Partition plate of scissors stair and connection structure of floor roof beam
CN104499625A (en) Profiled steel sheet and composite floor
CN207453225U (en) A kind of superstructure unit and assembly concrete integrated floor
CN205171752U (en) Prefabricated light steel partition wall and mounting structure thereof
DE102014103852A1 (en) Multi-storey residential building
CN104652677B (en) template and floor
CN209308156U (en) A kind of prefabricated buildings that can be recycled
CN104878857B (en) A kind of lightweight prefabricated combined wall body
Oleinik et al. Optimization of parameters for the construction of prefabricated residential buildings
CN105888070A (en) Building method of modularized building
CN105888057A (en) Modularized building
WO2023222853A2 (en) Hybrid building system, building and method
CN113802743A (en) Assembled coincide floor

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant