CN207944693U - A kind of removable construction operation platform - Google Patents

A kind of removable construction operation platform Download PDF

Info

Publication number
CN207944693U
CN207944693U CN201820274995.4U CN201820274995U CN207944693U CN 207944693 U CN207944693 U CN 207944693U CN 201820274995 U CN201820274995 U CN 201820274995U CN 207944693 U CN207944693 U CN 207944693U
Authority
CN
China
Prior art keywords
holder
platform
bracket base
operation platform
construction operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820274995.4U
Other languages
Chinese (zh)
Inventor
王继飞
张晓刚
李国民
李进军
高得力
李茜
朱俊杰
李欢
余涛
费悦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Original Assignee
China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Three Gorges Construction Engineering Co Ltd filed Critical China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Priority to CN201820274995.4U priority Critical patent/CN207944693U/en
Application granted granted Critical
Publication of CN207944693U publication Critical patent/CN207944693U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

A kind of removable construction operation platform, it includes the platform on top and the holder of lower part, the holder of lower part includes vertically arranged supporting rod, the stage casing of supporting rod is provided with lifting lug, the bottom of holder is provided with bracket base, the lateral of bracket base is equipped with opening, and groove is equipped with from opening to bracket base internal stretch.Purpose of the utility model is to solve existing scaffold operating platforms can be removed after use, it needs to build again again using the place of scaffold operating platform other, it is longer that this form of construction work occupies the construction period, and expend the technical issues of lot of materials is with manually, construction cost control is unfavorable for.

Description

A kind of removable construction operation platform
Technical field
The utility model belongs to construction equipment field, and in particular to a kind of removable construction operation platform.
Background technology
During high cut slope excavation supporting construction, it usually needs side slope excavation face carries out supporting construction, including spray shield Concrete construction and anchor bolt construction.Conventional construction method is to set up steel pipe scaffold conduct on excavating the side slope riding track formed Construction operation platform, construction personnel carry out the supporting construction of side slope on scaffold operating platform.
It generally needs to remove scaffold after use, on other ground needed using scaffold operating platform Side is built again again, and this form of construction work occupancy construction period is longer, and expends lot of materials with manually, is unfavorable for construction cost Control.
Invention content
Purpose of the utility model is to solve existing scaffold operating platforms can be removed after use, at it It needs to build again again using the place of scaffold operating platform, and this form of construction work occupancy construction period is longer, and expends The technical issues of lot of materials is with manually, construction cost control is unfavorable for.
Technical solution used by the utility model is:
A kind of removable construction operation platform, it includes the platform on top and the holder of lower part, and the holder of lower part includes Vertically arranged supporting rod, lifting lug is provided in the stage casing of supporting rod, and the bottom of holder is provided with bracket base, bracket base It is lateral be equipped with opening, groove is equipped with from opening to bracket base internal stretch.
Above-mentioned bracket base includes bottom frame rack-layer and supporting layer, and groove is formed between bottom frame rack-layer and supporting layer.
Above-mentioned platform is equipped with guardrail.
Above-mentioned holder is equipped with cat ladder.
It is coated with deep floor in the stage casing of supporting rod, lifting lug is arranged on deep floor.
Above-mentioned lifting lug is welded and fixed with deep floor.
Using the above structure, loading machine fast removal, conveniently moving, after being highly suitable as high cut slope excavation can be passed through Carry out the operating platform of supporting operation.
Description of the drawings
Fig. 1 is the structural schematic diagram of utility model;
Fig. 2 and Fig. 3 is the side view of the utility model;
Fig. 4 is the using renderings of the utility model.
Specific implementation mode
As shown in Figures 1 to 4, a kind of removable construction operation platform, it includes the platform 3 on top and the holder of lower part 1, the holder 1 of lower part includes vertically arranged supporting rod, and the stage casing of supporting rod is provided with lifting lug 7, is arranged in the bottom of holder 1 There are bracket base 2, the lateral of bracket base 2 to be equipped with opening, groove 6 is equipped with from opening to bracket base internal stretch.
The bracket base 2 includes bottom frame rack-layer and supporting layer, is formed between bottom frame rack-layer 10 and supporting layer 9 recessed Slot 6.
In use, can be used cooperatively the utility model and scraper bowl 12, scraper bowl 12 is equipped with hole for hoist 11, pull rod 13 One end is connect with lifting lug 7, and the other end is connect with hole for hoist 11.
12 times shovel bodies of the scraper bowl stretch into groove 6, specifically, processing welding operating platform holder 1, operation using channel steel 1 both ends column distance of platform support is suitable with the loading shovel length that will be used cooperatively, and is processed using channel steel and I-steel Pedestal 2 is welded, groove 6 is set, groove 6 processes welding fabrication, the bucket tooth phase of 6 size of groove and loading shovel using I-steel Matching enables the bucket tooth of loading shovel to stretch into groove 6 and carries operating platform.
Specifically, operating platform holder 1 and pedestal 2 are welded as a whole structure, in the 1 top installation of operating platform holder Platform 3, platform 3 are laid with decorative pattern checkered plates using angle steel processing welding.For ease of being carried out in the side slope face for having certain slope Supporting construction operation, 3 both ends of platform need to stretch out 1 range certain length of operating platform holder, and 3 both ends of platform are cantilevered structure.
The platform 3 is equipped with guardrail 4, and guardrail 4 is processed welding with angle steel and formed.
The holder 1 is equipped with cat ladder 5, and cat ladder 5 is processed welding with angle steel and formed, flat convenient for construction personnel's down operation Platform.
It is coated with deep floor 8 in the stage casing of supporting rod, lifting lug 7 is arranged on deep floor 8.
The lifting lug 7 is welded and fixed with deep floor 8.
Using this structure, during specific loading machine transports platform, will be grasped using compensation linkage 13 The lifting lug 7 made on 1 column of platform support is connected with the hole for hoist on loading shovel, plays fixed platform in transportational process Effect, compensation linkage 13 be finished product can purchase acquisition on the market, removed when platform stretches into groove 6 by loading shovel After moving up, the state for making operating platform be placed in horizontal stable is adjusted to compensation linkage 13, to ensure in transportational process In will not topple over.To ensure that the column channel steel of operating platform holder 1 in transportational process does not deform, in operating platform branch Close to 7 position welding steel of lifting lug as deep floor 8 on the inside of the channel steel of 1 column of frame.Wherein, movable operation platform is in place Before, the ground of construction part need to be carried out smooth, it is ensured that operating platform is in horizontal stable after being placed in position.Construction personnel is flat It need to fasten the safety belt when the construction operation of platform top and be connect with guardrail, to ensure construction safety.
To improve operating platform utilization rate, side slope needs to be propped up according to the timely side slope of situation of slagging tap in digging process Shield generally can carry out side slope supporting construction when height of slagging tap reaches the operable height of platform, complete in the altitude range supporting It carries out next layer of cycle at rear and slags tap and supporting.

Claims (6)

1. a kind of removable construction operation platform, it includes the platform on top(3)And the holder of lower part(1), it is characterised in that: The holder of the lower part(1)Including vertically arranged supporting rod, the stage casing of supporting rod is provided with lifting lug(7), in holder(1)'s Bottom is provided with bracket base(2), bracket base(2)It is lateral be equipped with opening, be equipped with from opening to bracket base internal stretch Groove(6).
2. removable construction operation platform according to claim 1, it is characterised in that:The bracket base(2)The bottom of including Portion's ccf layer and supporting layer, bottom frame rack-layer(10)With supporting layer(9)Between form groove(6).
3. removable construction operation platform according to claim 1 or 2, it is characterised in that:The platform(3)It is equipped with shield Column(4).
4. removable construction operation platform according to claim 1 or 2, it is characterised in that:The holder(1)It is equipped with and climbs Ladder(5).
5. removable construction operation platform according to claim 1 or 2, it is characterised in that:It is coated in the stage casing of supporting rod There is deep floor(8), lifting lug(7)It is arranged in deep floor(8)On.
6. removable construction operation platform according to claim 5, it is characterised in that:The lifting lug(7)With deep floor (8)It is welded and fixed.
CN201820274995.4U 2018-02-27 2018-02-27 A kind of removable construction operation platform Expired - Fee Related CN207944693U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820274995.4U CN207944693U (en) 2018-02-27 2018-02-27 A kind of removable construction operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820274995.4U CN207944693U (en) 2018-02-27 2018-02-27 A kind of removable construction operation platform

Publications (1)

Publication Number Publication Date
CN207944693U true CN207944693U (en) 2018-10-09

Family

ID=63700144

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820274995.4U Expired - Fee Related CN207944693U (en) 2018-02-27 2018-02-27 A kind of removable construction operation platform

Country Status (1)

Country Link
CN (1) CN207944693U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113982622A (en) * 2021-10-26 2022-01-28 中国十九冶集团有限公司 Tunnel construction machinery removes operation platform mounting structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113982622A (en) * 2021-10-26 2022-01-28 中国十九冶集团有限公司 Tunnel construction machinery removes operation platform mounting structure

Similar Documents

Publication Publication Date Title
CN102877637B (en) Method for implementing operating platform in bottom wall construction of cantilever beam
CN104878766A (en) Long side slope protection concrete continuous rapid pouring and form-drawing system and construction method
CN206616184U (en) Coke oven loss flue dust dust gathering arrester supporting construction
CN106499226B (en) A kind of method of main building construction in layer
CN110410109A (en) A kind of construction of hangar tunnel lining cutting arch shifting formwork trolley and construction method
CN207944693U (en) A kind of removable construction operation platform
CN110608057A (en) Device for removing duct piece in shield tunnel and using method thereof
CN207121164U (en) A kind of beam body mobile device
CN108396749A (en) The installation system and installation method of bracing members in a kind of foundation pit
CN208135764U (en) A kind of pipeline hanging device without spin
CN206616185U (en) The loss flue dust dust gathering arrester of coke oven installs chassis
CN212052362U (en) Bridge inner cavity lifting platform
CN108163582A (en) A kind of mobile dress ore deposit platform and its dress ore deposit method
CN107879261A (en) A kind of tilting arch trash rack hanging apparatus and hanging method
CN109779658B (en) Coal mine tunnel is with whitewashing device
CN109778806A (en) A kind of construction method of the Dun Qiang with connection beam whole slip
CN106088564A (en) Track climbing type monolithic architecture construction scaffolding
CN206128118U (en) Operation integration platform at bottom of cable pit ditch
CN202064621U (en) Conventionalized operation platform for construction of elevator shaft
CN202882930U (en) Vertical shaft bottom dredging rapid waste rock turning device
CN207795270U (en) A kind of portable cart
CN204728347U (en) High rock slope steel structure platform
CN206071598U (en) Self-propelled for tunnel excavation supporting bores quick-fried chassis
CN205242407U (en) A cluster pipe, chute combination system for deep basal pit concrete placement
CN221095137U (en) Novel spout anchor all-in-one of making level equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181009