CN113982622A - Tunnel construction machinery removes operation platform mounting structure - Google Patents

Tunnel construction machinery removes operation platform mounting structure Download PDF

Info

Publication number
CN113982622A
CN113982622A CN202111245854.2A CN202111245854A CN113982622A CN 113982622 A CN113982622 A CN 113982622A CN 202111245854 A CN202111245854 A CN 202111245854A CN 113982622 A CN113982622 A CN 113982622A
Authority
CN
China
Prior art keywords
platform
operation platform
platform frame
tunnel construction
loader
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111245854.2A
Other languages
Chinese (zh)
Inventor
刘欢
曾梦川
黄学超
陈亚军
朱必东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Group Co ltd
Original Assignee
China 19th Metallurgical Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Group Co ltd filed Critical China 19th Metallurgical Group Co ltd
Priority to CN202111245854.2A priority Critical patent/CN113982622A/en
Publication of CN113982622A publication Critical patent/CN113982622A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • E21D9/122Working or loading platforms
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • E21D9/126Loading devices or installations

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to the field of tunnel construction machinery equipment, in particular to a mounting structure of a moving operation platform of tunnel construction machinery. The technical problem to be solved by the invention is to provide a movable operation platform installation structure of a tunnel construction machine, which utilizes the mobility of a loader to achieve the flexibility of the movement of an operation platform under the conditions of short steps and short step distance and narrow complex space of weak surrounding rocks. The technical scheme adopted by the invention for solving the technical problems is as follows: tunnel construction machinery removes operation platform mounting structure, including the loader, including the operation platform frame, operation platform frame bottom is provided with platform frame installation end, and wherein, platform frame installation end sets up on the loader scraper bowl of loader through scraper bowl fixing clip group. The invention is particularly suitable for the arrangement of the mobile operation platform under the conditions of short steps of weak surrounding rocks, short step distance and narrow complex space.

Description

Tunnel construction machinery removes operation platform mounting structure
Technical Field
The invention relates to the field of tunnel construction machinery equipment, in particular to a mounting structure of a moving operation platform of tunnel construction machinery.
Background
At present, tunnel excavation, particularly for weak surrounding rock excavation, has a large safety risk, is restricted by a construction operation space, and must consider the follow-up of an inverted arch and a secondary lining safety step distance and also consider the excavation speed. How safe convenient quick excavation tunnelling of tunnel weak country rock forms operation platform in narrow complicated space, improves work efficiency and urgently waits to solve. For example, the literature: CN201721438185.X the invention discloses a tunnel engineering excavation operation rack, which is used for blocking rocks above a support through a baffle when the rocks fall off, so that the service life of the baffle is prolonged, the rocks above the support are prevented from falling off to hurt construction operators on the tunnel excavation rack when the rocks are exploded during construction or surrounding rocks, and the safety during working is greatly improved. The invention discloses a liftable tunnel excavation rack, which can conveniently and flexibly adjust the height of an operation rack, ensure that an operator works at the most proper height, and is beneficial to improving the construction quality and ensuring the safety of the operator. However, the invention needs enough space for placing the excavation rack, is only suitable for tunnels with good surrounding rocks, and is basically not suitable for ultra-short step distance tunnels with weak surrounding rocks.
Disclosure of Invention
The technical problem to be solved by the invention is to provide a movable operation platform installation structure of a tunnel construction machine, which utilizes the mobility of a loader to achieve the flexibility of the movement of an operation platform under the conditions of short steps and short step distance and narrow complex space of weak surrounding rocks.
The technical scheme adopted by the invention for solving the technical problems is as follows: tunnel construction machinery removes operation platform mounting structure, including the loader, including the operation platform frame, operation platform frame bottom is provided with platform frame installation end, and wherein, platform frame installation end sets up on the loader scraper bowl of loader through scraper bowl fixing clip group.
Further, the platform frame mounting end is of a platform frame tiger-mouth structure.
Further, the platform frame mounting end comprises a support bracket and a support bracket bottom beam, and the support bracket bottom beam form a platform frame tiger-mouth structure.
Further, a bracket fixing bottom support steel bar beam is arranged at the bottom of the bottom beam of the bracket support.
Furthermore, the operating platform frame is composed of a platform frame center beam, platform frame side beams and a platform frame support reinforcing beam.
Further, the operation platform frame comprises a steel mesh platform.
Further, the operating platform frame comprises a protective railing.
Further, the bucket fixing clamp group comprises a spiral tightening type fixing connecting rod, a bucket fixing platform clamping group and a platform clamping group connecting piece matched with the bucket fixing platform clamping group.
The invention has the beneficial effects that: the invention mainly aims at short steps of weak surrounding rocks, narrow and complex space with short step distance and difficulty in forming a tunnel of an operation platform, so that the portable movable operation platform for excavation is formed by design innovation. When the platform frame is actually used, the mounting end of the platform frame is arranged on a loader bucket of a loader through the bucket fixing clamp group. When the operation platform frame needs to be moved, only the loader needs to be moved, and after the operation platform frame reaches a new operation position, the loader bucket of the loader can be adjusted to enable the operation platform frame to return to a horizontal state again, so that a new round of operation is performed. The invention is particularly suitable for the arrangement of the mobile operation platform under the conditions of short steps of weak surrounding rocks, short step distance and narrow complex space.
Drawings
Fig. 1 is a schematic view of a main body frame of the operation platform frame of the present invention.
Fig. 2 is a schematic structural diagram of the operating platform shelf of the present invention.
Fig. 3 is a schematic view of the present invention in actual use.
Fig. 4 is a schematic view of the present invention in actual use.
Labeled as: the platform comprises a platform frame middle beam 1, platform frame side beams 2, a platform frame support reinforcing beam 3, a platform frame mounting end 4, a support frame bottom beam 5, a support frame 6, a reinforcing mesh platform 7, a loader bucket 8, a loader 9, a support fixing bottom support steel bar beam 10, a protective railing 11, a spiral tightening type fixing connecting rod 12, a bucket fixing platform clamping group 13 and a platform clamping group connecting piece 14.
Detailed Description
The invention is further described below with reference to the accompanying drawings.
As shown in fig. 1, fig. 2, fig. 3, and fig. 4, the tunnel construction machine moving operation platform installation structure includes a loader 9, includes an operation platform frame, and a platform frame installation end 4 is provided at the bottom of the operation platform frame, wherein the platform frame installation end 4 is provided on a loader bucket 8 of the loader 9 through a bucket fixing clip set.
The structure endows the operating platform with flexibility in position space by means of the flexible maneuverability of the loader 9, forms a safe and stable platform for tunnel face operation, is convenient to operate, can quickly form an operating platform for workers working on the face particularly in weak surrounding rock sections, and provides great convenience for tunnel construction; meanwhile, the platform can move more conveniently and quickly by depending on a supporting system and a traveling system of the loader, the arriving position is comprehensive, particularly soft surrounding rock, small-space operation such as a core soil reservation method of annular excavation is adopted, and the position can be changed at any time to meet the problems of no operating space, no operating platform and the like in narrow space construction. The invention has simple manufacture, flexible application and wide range. The combined type mobile operation platform of the tunnel construction machinery can be flexibly applied to installation operation of tunnel excavation and other accessory facilities, particularly the tunnel excavation of weak surrounding rocks, the working efficiency is improved, the platform is simple in assembly operation, convenient to use and efficient in construction operation, the effects of shortening the construction period, reducing the cost and facilitating field civilized construction are achieved, the construction period is greatly shortened, and the cost is reduced.
In order to further simplify the platform frame mounting end 4, the platform frame mounting end 4 is preferably in a platform frame tiger-mouth structure. As shown in fig. 1, the platform mounting end 4 preferably comprises a bracket 6 and a bracket base beam 5, and the bracket 6 and the bracket base beam 5 form a platform frame tiger-mouth structure. The steel support platform bracket can be formed by splicing I18I-shaped steel. The platform part is spliced into a field-shaped framework by I-shaped steel, and a reinforcing mesh is laid on the framework to serve as a working platform surface; the bracket part is formed by splicing I-shaped steel to form a tiger-mouth-shaped bracket, the outer side of the bracket is wide, and the inner side of the bracket is narrow, so that the loader bucket can conveniently stretch into and be fixed.
In order to take into account the stability of the structure and facilitate the subsequent fixed mounting of the platform frame mounting end 4, such a scheme is preferred: the bottom of the bracket bottom beam 5 is provided with a bracket fixing bottom bracket steel bar beam 10.
In order to simplify the structure of the operating platform frame, the operating platform frame is preferably composed of a platform frame middle beam 1, a platform frame side beam 2 and a platform frame support reinforcing beam 3. In order to ensure that the operator is convenient to stand and to ensure safety, it is preferred that the operating platform frame comprises a mesh reinforcement platform 7. Simultaneously, in order to guarantee operating personnel's safety to and avoid the work platform on the article drop, it is preferred that the operation platform frame includes guard rail 11.
In the actual mounting of the platform frame on the loader bucket 8 of the loader 9, the following is preferred: the bucket fixing clamping set comprises a spiral tightening type fixing connecting rod 12, a bucket fixing platform clamping set 13 and a platform clamping set connecting piece 14 matched with the bucket fixing platform clamping set 13. As shown in fig. 3, the operation platform is mounted on the loader bucket 8 of the loader 9 by a screw-type fixed connecting rod 12, a bucket fixed platform fastener set 13 and a platform fastener set connecting piece 14 cooperating with the bucket fixed platform fastener set 13, so as to ensure that the operation platform can be adjusted along with the loader bucket 8 and is in a horizontal state. The bracket fixes the bottom support steel bar beam and fixes the front bottom end with the bucket through a spiral tightening type fixed connecting rod; and then the rear upper end of the platform is fixed by a bucket fixing platform buckle set. The platform is firmly combined with machinery through two layers of fixed connection. The loader bucket shovels into a tiger mouth of the bracket, the tiger mouth is wide in the front and narrow in the back, the bucket is lifted upwards slightly, the bracket and the bucket are fixed tightly through the self-weight of the tilting part at the front end of the bracket, the bracket platform is integrated with the bucket after the bracket and the bucket are fixed, and the loader travels through the bucket steering, so that a platform moving system is formed. Any space in the tunnel can be reached through the walking of the loader and the lifting of the bucket.
In actual manufacturing, such a scheme can be selected: firstly, determining the size of a platform according to the actual condition, and preparing a manufacturing material; splicing and welding the middle and side beams of the platform into a portal form, wherein the parallelism and the verticality between the middle and side beams are ensured during assembly, the gap between steel is reduced as much as possible, and the seam consistency of the template is ensured; welding the first web bracket to the platform frame, adjusting the mutual positions, and ensuring that the outer side of the bracket is wide and the inner side of the bracket is narrow and is vertical to the platform frame; welding and fixing the reinforcing mesh platform on the platform frame, and adjusting the density of the reinforcing mesh during manufacturing the reinforcing mesh to ensure that the phenomena of clamping feet and the like are avoided in the using process; and (3) trial assembly of the loader bucket, wherein the bucket extends into the tiger mouth end to lift the platform frame, so that whether the bucket is stable or not can be seen, the bucket ascends, descends and turns, and the mutual positions of all parts of the platform frame are corrected by adjusting again. After correction, the two fixed connecting assemblies at the front bottom end and the rear upper end are fastened to ensure firm connection.
Aiming at the weak surrounding rock short step, short step distance and narrow complex space, the invention is difficult to form the tunnel of the operation platform, and the portable movable operation platform for excavation is formed by design innovation. The platform is combined with the loader for construction in the tunnel, the flexibility of moving the operating platform is achieved by using the mobility of the loader, rapid excavation and tunneling are facilitated, the occupied space is small, the number of parts capable of being reached is large, and the problems that the construction space of weak surrounding rocks is narrow and the construction of operators is difficult are effectively solved. The method has the advantages of saving materials, being convenient for construction operation, improving the working efficiency and having better project period competition and cost competition advantages.

Claims (8)

1. Tunnel construction machinery removes operation platform mounting structure, including loader (9), its characterized in that: including the operation platform frame, operation platform frame bottom is provided with platform frame installation end (4), and wherein, platform frame installation end (4) set up on loader bucket (8) of loader (9) through the bucket fixing clip group.
2. The tunnel construction machine moving operation platform installation structure of claim 1, wherein: the platform frame mounting end (4) is of a platform frame tiger-mouth structure.
3. The tunnel construction machine moving operation platform installation structure of claim 2, wherein: the platform frame mounting end (4) comprises a support bracket (6) and a support bracket bottom beam (5), and the support bracket (6) and the support bracket bottom beam (5) form a platform frame tiger-mouth structure.
4. The tunnel construction machine moving operation platform installation structure of claim 3, wherein: the bottom of the bracket bottom beam (5) is provided with a bracket fixing bottom bracket steel bar beam (10).
5. The tunnel construction machine moving operation platform installation structure of claim 1, 2, 3 or 4, wherein: the operation platform frame is composed of a platform frame middle beam (1), platform frame side beams (2) and a platform frame support reinforcing beam (3).
6. The tunnel construction machine moving operation platform installation structure of claim 5, wherein: the operating platform frame comprises a reinforcing mesh platform (7).
7. The tunnel construction machine moving operation platform installation structure of claim 6, wherein: the operating platform frame comprises a protective railing (11).
8. The tunnel construction machine moving operation platform installation structure of claim 1, 2, 3 or 4, wherein: the bucket fixing clamping set comprises a spiral tightening type fixing connecting rod (12), a bucket fixing platform clamping set (13) and a platform clamping set connecting piece (14) matched with the bucket fixing platform clamping set (13).
CN202111245854.2A 2021-10-26 2021-10-26 Tunnel construction machinery removes operation platform mounting structure Pending CN113982622A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111245854.2A CN113982622A (en) 2021-10-26 2021-10-26 Tunnel construction machinery removes operation platform mounting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111245854.2A CN113982622A (en) 2021-10-26 2021-10-26 Tunnel construction machinery removes operation platform mounting structure

Publications (1)

Publication Number Publication Date
CN113982622A true CN113982622A (en) 2022-01-28

Family

ID=79741391

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111245854.2A Pending CN113982622A (en) 2021-10-26 2021-10-26 Tunnel construction machinery removes operation platform mounting structure

Country Status (1)

Country Link
CN (1) CN113982622A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2221271A2 (en) * 2009-02-18 2010-08-25 Boliden Mekaniska Verkstrad AB Work platform
CN207877197U (en) * 2017-12-05 2018-09-18 李元忠 A kind of maintenance platform
CN207944693U (en) * 2018-02-27 2018-10-09 中国葛洲坝集团三峡建设工程有限公司 A kind of removable construction operation platform
CN210418434U (en) * 2019-04-28 2020-04-28 中国石油天然气第一建设有限公司 Frock is laid fast to metallic steel tank bottom plate in restricted space
CN212054735U (en) * 2020-05-14 2020-12-01 中铁十八局集团有限公司 Rack device for tunnel construction
JP2021109738A (en) * 2020-01-10 2021-08-02 東日本電信電話株式会社 Work bench for aerial work platform vehicle

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2221271A2 (en) * 2009-02-18 2010-08-25 Boliden Mekaniska Verkstrad AB Work platform
CN207877197U (en) * 2017-12-05 2018-09-18 李元忠 A kind of maintenance platform
CN207944693U (en) * 2018-02-27 2018-10-09 中国葛洲坝集团三峡建设工程有限公司 A kind of removable construction operation platform
CN210418434U (en) * 2019-04-28 2020-04-28 中国石油天然气第一建设有限公司 Frock is laid fast to metallic steel tank bottom plate in restricted space
JP2021109738A (en) * 2020-01-10 2021-08-02 東日本電信電話株式会社 Work bench for aerial work platform vehicle
CN212054735U (en) * 2020-05-14 2020-12-01 中铁十八局集团有限公司 Rack device for tunnel construction

Similar Documents

Publication Publication Date Title
CN109236302B (en) Variable section excavation trolley in tunnel
CN202560245U (en) Multifunctional trolley with freely retractable arms
CN106150511A (en) Shield driving formula sky pushes through ground fissure bored tunnel construction method
CN217749999U (en) Major diameter former tubular column welding operation platform
CN106087698B (en) Portable construction operation platform of bored pile
CN113982622A (en) Tunnel construction machinery removes operation platform mounting structure
CN112012774B (en) Frame type drilling and anchoring robot
CN204492846U (en) Movable type with inverted arch lining device crosses car trestle
CN210081049U (en) Welding production line for main beam of rail crane
CN111121574A (en) Movable blasting protective cover plate
CN105696782A (en) Novel mobile operation platform
CN207828797U (en) A kind of continuous rigid frame PC track girders steel reinforcement cage binding clamping fixture
CN213672358U (en) Submerged arc welding operation platform capable of quickly adjusting height and horizontally moving
CN210509222U (en) Circular device with steel strip lining tunnel
CN206128627U (en) Movable floor top mounted putting of construction load can balance
CN214768614U (en) Jig frame for binding reinforcement cage of prefabricated concrete member
CN219570105U (en) Full car strutting arrangement that platform truck was used that tunnel construction was used
CN108104841B (en) A kind of highway long tunnel stops in emergency band lining trolley
CN110424749A (en) The rail mounted that high construction is connect for pier shaft reinforcing bar connects high rack device and its meets Gao Fangfa
CN217949798U (en) Auxiliary device for net rack embedding rod piece
CN217045266U (en) Auxiliary device for welding large-diameter pipeline
CN207701173U (en) A kind of tunnel Multifunctional mobile work operations platform
CN213413861U (en) Subway track laying machine becomes to stride jacking auxiliary device
CN113236351B (en) Continuous belt conveyor extension tunnel support mounting method and tool
CN221372255U (en) Tunnel reinforcing steel bar positioning trolley

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220128