Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820239050.9U
Other languages
Chinese (zh)
Inventor
赵文彦
黄仰收
张明欣
崔兰
李海喜
汪伟
刘建海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Traffic Planning Survey Design Institute Co Ltd
Original Assignee
Shanxi Traffic Planning Survey Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Traffic Planning Survey Design Institute Co Ltd filed Critical Shanxi Traffic Planning Survey Design Institute Co Ltd
Priority to CN201820239050.9U priority Critical patent/CN207944366U/en
Application granted granted Critical
Publication of CN207944366U publication Critical patent/CN207944366U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model is related to subgrade engineering, specifically a kind of novel discharge culvert.The utility model solves the problems, such as that existing culvert takes up an area that range is big, difficulty of construction is high, project cost is high, big to eco-environmental impact when being set to excavation section.A kind of novel discharge culvert, including wall body, inverted arch lining cutting, inverted arch filling;Wall body includes preliminary bracing, secondary lining;Wherein, preliminary bracing is anchor spraying concrete layer;Secondary lining is form concrete layer, and the lateral surface of secondary lining and the medial surface of preliminary bracing are fixed as one;Inverted arch lining cutting is form concrete layer, and the consistency of thickness of the thickness of inverted arch lining cutting and secondary lining;The two sides of inverted arch lining cutting are fixed as one with the two sides of secondary lining respectively, and inverted arch lining cutting and secondary lining surround loop configuration jointly;Inverted arch is filled with cast-in-place concrete layer, and the lateral surface of inverted arch filling and the medial surface of inverted arch lining cutting are fixed as one.The utility model is suitable for excavation section subgrade drainage.

Description

A kind of novel discharge culvert
Technical field
The utility model is related to subgrade engineering, specifically a kind of novel discharge culvert.
Background technology
The effect of culvert is the rapid surface water for excluding Highways ', ensures roadbed safety.Under prior art conditions, contain Hole is broadly divided into slab culvert, arch culvert, box culvert etc..However practice have shown that, existing culvert is both needed to when being set to excavation section using bright Digging method is constructed, and thus causing it to take up an area, range is big, difficulty of construction is high, project cost is high, big to eco-environmental impact.It is based on This, it is necessary to a kind of completely new culvert is invented, takes up an area that range is big, difficulty of construction to solve existing culvert when being set to excavation section High, project cost height, the problem big to eco-environmental impact.
Invention content
The utility model takes up an area that range is big, difficulty of construction is high, engineering in order to solve existing culvert when being set to excavation section Cost height, the problem big to eco-environmental impact, provide a kind of novel discharge culvert.
The utility model adopts the following technical scheme that realization:
A kind of novel discharge culvert, including wall body, inverted arch lining cutting, inverted arch filling;Wall body includes preliminary bracing, secondary lining It builds;Wherein, preliminary bracing is anchor spraying concrete layer;Secondary lining be form concrete layer, and the lateral surface of secondary lining with just The medial surface of phase supporting is fixed as one;Inverted arch lining cutting is form concrete layer, and the thickness of inverted arch lining cutting and secondary lining Consistency of thickness;The two sides of inverted arch lining cutting are fixed as one with the two sides of secondary lining respectively, and inverted arch lining cutting and secondary lining Block surrounds loop configuration jointly;Inverted arch is filled with cast-in-place concrete layer, and the inside of the lateral surface and inverted arch lining cutting of inverted arch filling Face is fixed as one.
When work, the medial surface of inverted arch filling and the medial surface of secondary lining surround drainage channel jointly.With existing culvert It compares, a kind of novel discharge culvert described in the utility model is constructed when being set to excavation section without cut and cover method, And need to only be constructed using subsurface excavation method, therefore it takes up an area that range smaller, difficulty of construction is lower, project cost is lower, to ecology Environment influences smaller.In addition, a kind of novel discharge culvert described in the utility model is by using loop configuration(The loop configuration It is surrounded jointly by inverted arch lining cutting and secondary lining), effectively increase structural stability, therefore it is by settlement influence smaller, antidetonation Ability is stronger.
The utility model is reasonable for structure, ingenious in design, efficiently solves existing culvert and takes up an area model when being set to excavation section Big, difficulty of construction height, project cost height, the problem big to eco-environmental impact are enclosed, excavation section subgrade drainage is suitable for.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
In figure:1a- preliminary bracings, 1b- secondary linings, 2- inverted arch lining cutting, the filling of 3- inverted arch.
Specific implementation mode
A kind of novel discharge culvert, including wall body, inverted arch lining cutting 2, inverted arch filling 3;Wall body includes preliminary bracing 1a, secondary Lining cutting 1b;Wherein, preliminary bracing 1a is anchor spraying concrete layer;Secondary lining 1b is form concrete layer, and secondary lining 1b The medial surface of lateral surface and preliminary bracing 1a is fixed as one;Inverted arch lining cutting 2 is form concrete layer, and the thickness of inverted arch lining cutting 2 The consistency of thickness of degree and secondary lining 1b;Two sides of the two sides of inverted arch lining cutting 2 respectively with secondary lining 1b are fixed as one, And inverted arch lining cutting 2 and secondary lining 1b surround loop configuration jointly;Inverted arch filling 3 is cast-in-place concrete layer, and inverted arch fills 3 Lateral surface and the medial surface of inverted arch lining cutting 2 are fixed as one.
The distance between the lateral surface top of preliminary bracing 1a and the lateral surface top of inverted arch lining cutting 2 are 653cm;Initial stage branch The distance between lateral surface left end and the lateral surface right end for protecting 1a are 702cm.When work, above-mentioned size design makes culvert open Spoir amount is less during digging, is thus conducive to environmental protection.
Wall is as bent wall wall body, and the internal diameter of vault is 300cm, and the internal diameter of side curl wall is 600cm;Inverted arch serves as a contrast The internal diameter for building 2 is 679cm.When work, bent wall wall body can enhance the bearing load ability of culvert, thus further increase knot Structure stability.
The thickness of preliminary bracing 1a is 16cm;The thickness of secondary lining 1b, the thickness of inverted arch lining cutting 2 are 35cm;Inverted arch The maximum gauge of filling 3 is 48cm.
The concrete of preliminary bracing 1a, the concrete of secondary lining 1b, inverted arch lining cutting 2 concrete be C25 concrete; The concrete of inverted arch filling 3 is C20 piece stone concretes.

Claims (5)

1. a kind of novel discharge culvert, it is characterised in that:Including wall body, inverted arch lining cutting(2), inverted arch filling(3);Wall body includes just Phase supporting(1a), secondary lining(1b);Wherein, preliminary bracing(1a)For anchor spraying concrete layer;Secondary lining(1b)It is built for mould mixed Solidifying soil layer, and secondary lining(1b)Lateral surface and preliminary bracing(1a)Medial surface be fixed as one;Inverted arch lining cutting(2)For mould Build concrete layer, and inverted arch lining cutting(2)Thickness and secondary lining(1b)Consistency of thickness;Inverted arch lining cutting(2)Two sides point Not and secondary lining(1b)Two sides be fixed as one, and inverted arch lining cutting(2)And secondary lining(1b)Ring junction is surrounded jointly Structure;Inverted arch is filled(3)For cast-in-place concrete layer, and inverted arch is filled(3)Lateral surface and inverted arch lining cutting(2)Medial surface be fixed as One.
2. a kind of novel discharge culvert according to claim 1, it is characterised in that:Preliminary bracing(1a)Lateral surface top With inverted arch lining cutting(2)The distance between lateral surface top be 653cm;Preliminary bracing(1a)Lateral surface left end and lateral surface it is right The distance between end is 702cm.
3. a kind of novel discharge culvert according to claim 1, it is characterised in that:Wall is as bent wall wall body, vault Internal diameter be 300cm, the internal diameter of side curl wall is 600cm;Inverted arch lining cutting(2)Internal diameter be 679cm.
4. a kind of novel discharge culvert according to claim 1, it is characterised in that:Preliminary bracing(1a)Thickness be 16cm;Secondary lining(1b)Thickness, inverted arch lining cutting(2)Thickness be 35cm;Inverted arch is filled(3)Maximum gauge be 48cm。
5. a kind of novel discharge culvert according to claim 1, it is characterised in that:Preliminary bracing(1a)Concrete, two Secondary lining cutting(1b)Concrete, inverted arch lining cutting(2)Concrete be C25 concrete;Inverted arch is filled(3)Concrete be C20 Piece stone concrete.
CN201820239050.9U 2018-02-10 2018-02-10 A kind of novel discharge culvert Expired - Fee Related CN207944366U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820239050.9U CN207944366U (en) 2018-02-10 2018-02-10 A kind of novel discharge culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820239050.9U CN207944366U (en) 2018-02-10 2018-02-10 A kind of novel discharge culvert

Publications (1)

Publication Number Publication Date
CN207944366U true CN207944366U (en) 2018-10-09

Family

ID=63699897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820239050.9U Expired - Fee Related CN207944366U (en) 2018-02-10 2018-02-10 A kind of novel discharge culvert

Country Status (1)

Country Link
CN (1) CN207944366U (en)

Similar Documents

Publication Publication Date Title
CN101270582B (en) Method for setting bracing column in underground cavity
CN202718138U (en) Self-locking type ecological retaining wall structure
CN108468347A (en) Corrugated steel outer lining concrete structure for underground pipe gallery
CN208632890U (en) A kind of anti-lifting by frost structure of seasonal frozen ground subgrade stake arch brace
CN107805987A (en) The hassock layer Foam lightweight soil road structure and construction method in deep soft foundation section
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN105951712A (en) Underground diaphragm wall construction method for cutting through underground structure under ground limitation condition
CN109083096A (en) A kind of step-like ecological slope protection structure of reservoir area fluctuating zone and its implementation method
CN208472893U (en) Plain stage of slope double-layer drainage ditch structure
CN203834511U (en) Bolting-grouting retaining wall with specially-shaped section
CN107700299B (en) Overpass lower-layer ground road structure and construction method thereof
CN203834468U (en) Internal expansion type miniature concrete pile
CN101838957A (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN208981282U (en) A kind of high earthquake territory concrete face rockfill dam dam crest structure
CN208380578U (en) Precast construction in a kind of roads and tunnels
CN215052148U (en) A kind of guarantee that meets the rapid flood discharge requirement in the river course leads to the urinal
CN106836034B (en) High-fill cover plate culvert flexible load shedding system and construction method
CN207944366U (en) A kind of novel discharge culvert
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN106638509A (en) Tunnel structure capable of reducing side slope excavation and construction method thereof
CN208884292U (en) Soft soil roadbed and normal roadbed intersection anti-settling structure
CN207452609U (en) A kind of hassock layer Foam lightweight soil road structure in deep soft foundation section
CN104612174B (en) A kind of ultra-soft cob brick loose tool assists the construction method of suspended deck structure
CN203096697U (en) Ballast field structure at earth and rockfill dam toe
CN102587421A (en) Advanced water-stopping isolation structure of later poured band for basement

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181009

Termination date: 20190210