CN207847066U - A kind of construction formwork for placing - Google Patents
A kind of construction formwork for placing Download PDFInfo
- Publication number
- CN207847066U CN207847066U CN201820082322.9U CN201820082322U CN207847066U CN 207847066 U CN207847066 U CN 207847066U CN 201820082322 U CN201820082322 U CN 201820082322U CN 207847066 U CN207847066 U CN 207847066U
- Authority
- CN
- China
- Prior art keywords
- template
- block
- fixedly connected
- spring
- iron sheet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model is related to technical field of building construction, and disclose a kind of construction formwork for placing, including the first template, the left side of first template is opened up there are two symmetrical cavity, the inner roof wall and inner bottom wall of two cavitys have been fixedly connected with limited block, the left side of first template is installed with the first iron sheet, the left side of first iron sheet is overlapped with the second template, the right side of second template is fixedly connected there are two symmetrical inserted block, two inserted blocks are plugged on the inside of two cavitys through the first iron sheet respectively, the top and bottom of the inserted block open up fluted, the inner roof wall and inner bottom wall of two grooves have been fixedly connected with the first spring.The utility model solves that installation is inconvenient, and working efficiency is low, it is difficult to demould, the short problem of service life, reach that service life is long, and easy for installation, demoulding is simple, saves the time of work, the effect improved work efficiency.
Description
Technical field
The utility model is related to technical field of building construction, specially a kind of construction formwork for placing.
Background technology
Concreting refers to concreting entering mould the process until plasticizing, coagulation in civil construction project
It is made predetermined body in the materials to mould such as soil, when concreting, the free height of concrete is no more than 2m, when more than 3m
When should take corresponding measure.
Currently, existing formwork for placing for building, when installation, needs fixing bracket to carry out the fixation to template, when mounted
It is very inconvenient, a large amount of time is wasted, the efficiency of work is low, and allows traditional template after being poured, and is easy to meet
Aqueous corrosion, when use easily together with concrete conglutination, it is difficult to demould, make troubles to construction, the service life of template is short.
Utility model content
(One)The technical issues of solution
In view of the deficiencies of the prior art, the utility model provides a kind of construction formwork for placing, solves installation
Inconvenience, working efficiency are low, it is difficult to demould, the short problem of service life.
(Two)Technical solution
To achieve the above object, the utility model provides the following technical solutions:A kind of construction formwork for placing, including
First template, the left side of first template are opened up there are two symmetrical cavity, the inner roof wall of two cavitys and interior
Bottom wall has been fixedly connected with limited block, and the left side of first template is installed with the first iron sheet, first iron sheet
Left side is overlapped with the second template, and the right side of second template is fixedly connected with that there are two symmetrical inserted blocks, described in two
Inserted block is plugged on the inside of two cavitys respectively through the first iron sheet, the top and bottom of the inserted block open up it is fluted, two
The inner roof wall and inner bottom wall of a groove have been fixedly connected with the first spring, inner roof wall of first spring far from groove and
One end of inner bottom wall is fixedly connected with block, and block is located at the right side of limited block, and the left side of second template offers
The left end of translot, the translot offers circular groove, and the right side of first template is fixedly connected with outer cover, the right side of the outer cover
The middle part movable sleeve of side is connected to pull rod, and the outer surface fixing sleeve of the pull rod is connected to slide plate, and the top and bottom of the slide plate are lived
Dynamic to be socketed on the inside of outer cover, the right side of the slide plate is fixedly connected with second spring, and the second spring is far from slide plate
One end be just fixedly connected on the left of outer cover inner wall, the left end of the pull rod sequentially passes through the first template, translot and circular groove simultaneously
It is fixedly connected with fixture block.
Preferably, the right side of first template and the second template and front are installed with reinforcing rib, and reinforce
The bottom of muscle and the bottom of the first template and the second template are flush.
Preferably, there are gaps between the both ends of the block and the both sides of groove inner wall, and block is far from the first spring
One end extend to the outside of groove.
Preferably, the right end of the pull rod is fixedly connected with pulling block, and the vertical length value of pull rod is less than the vertical of translot
Length value.
Preferably, the vertical length value of the fixture block is less than the laterally wide angle value of the diameter value and translot of circular groove, and fixture block
Vertical length value be more than translot vertical length value.
Preferably, the back side of second template is installed with the second iron sheet.
Operation principle:When mounted, the inserted block of the second template is plugged on to the inside of cavity, the work that block passes through limited block
With, the first spring contraction is pushed, is detached from limited block when the right end of limited block when block moves, the first spring reset, at this point, inserting
Block is fixed on the inside of cavity, and pull rod is moved to the left the inside of circular groove when by operating pulling block, and second spring is shunk, in up time
Needle rotates 90 degree, unclamps pulling block, and second spring resets, and fixture block is fixed on the inner wall of circular groove by the elastic force of second spring, into
Fixation of the row to the first template and the second template.
(Three)Advantageous effect
The utility model provides a kind of construction formwork for placing.Has following advantageous effect:
(1), by the cavity of setting, inserted block, groove, block and limited block, can be under the action of the first spring
The top and bottom of one template and the second template are fixed, and facilitate the positioning of staff couple the first template and the second template
And fixation, facilitate the installation of staff.
(2), can under the action of fixture block by the translot of setting, circular groove, outer cover, pull rod, slide plate and second spring
First template and the second template are effectively reinforced, what being detached from occurred in the first template and the second template when avoiding pouring shows
As ensure that the stability of the first template and the second template when pouring, passing through the first iron sheet and the second iron sheet of setting, Neng Goufang
Just the template after solidification is dismantled, improves the efficiency of work.
Description of the drawings
Fig. 1 is the sectional view of the utility model the first template front view;
Fig. 2 is the sectional view of the utility model the second template side view;
Fig. 3 is the enlarged structure schematic diagram at A in the utility model Fig. 1.
In figure:1 first template, 2 cavitys, 3 first iron sheets, 4 second templates, 5 inserted blocks, 6 grooves, 7 first springs, 8 blocks,
9 translots, 10 circular grooves, 11 outer covers, 12 pull rods, 13 slide plates, 14 second springs, 15 fixture blocks, 16 reinforcing ribs.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
The every other embodiment obtained, shall fall within the protection scope of the present invention.
As shown in Figs. 1-3, the utility model provides a kind of technical solution:A kind of construction formwork for placing, including the
One template 1, the left side of the first template 1 are opened up there are two symmetrical cavity 2, and the inner roof wall and inner bottom wall of two cavitys 2 are equal
It is fixedly connected with limited block, the left side of the first template 1 is installed with the first iron sheet 3, and the left side of the first iron sheet 3 is overlapped with
The back side of second template 4, the second template 4 is installed with the second iron sheet, and staff can be facilitated the later stage to remove template, carried
The high efficiency of work, the right side of the second template 4 are fixedly connected there are two symmetrical inserted block 5, and two inserted blocks 5 run through first
Iron sheet 3 is plugged on the inside of two cavitys 2 respectively, and the top and bottom of inserted block 5 open up fluted 6, the interior top of two grooves 6
Wall and inner bottom wall have been fixedly connected with the first spring 7, and the internal activity of the first spring 7 is socketed with telescopic rod, and the top of telescopic rod
Portion and bottom are fixedly connected between block 8 and the inner wall of groove 6 respectively, can be carried out to the first spring 7 and effectively be limited,
It ensure that the stabilization of the first spring 7, can more effectively carry out fixing the first template 1 and the second template 4, the first spring 7 is remote
One end of inner roof wall and inner bottom wall from groove 6 is fixedly connected with block 8, between the both sides of 6 inner wall of both ends and groove of block 8
There are gap, avoids block 8 and rub between the side of 6 inner wall of groove when upper and lower mobile, ensure that block 8 moves
Dynamic flexibility, and the one end of block 8 far from the first spring 7 extends to the outside of groove 6, when can effectively pass through limited block
Inserted block 5 is connected to the inside of cavity 2, ensures the fixation of the first template 1 and the second template 4, and block 8 is located at the right side of limited block
The left side of side, the second template 4 offers translot 9, and the left end of translot 9 offers circular groove 10, and the right side of the first template 1 is fixed
It is connected with outer cover 11, the middle part movable sleeve on the right side of outer cover 11 is connected to pull rod 12, and the right end of pull rod 12 is fixedly connected with pulling block, and
The vertical length value of pull rod 12 is less than the lateral length value of translot 9, ensure that fixture block 15 is effectively inserted into the inside of circular groove 10, draws
The outer surface fixing sleeve of bar 12 is connected to slide plate 13, and the top and bottom of slide plate 13 are actively socketed on the inside of outer cover 11, slide plate
13 right side is fixedly connected with second spring 14, the one end of second spring 14 far from slide plate 13 just left side with 11 inner wall of outer cover
It is fixedly connected, the left end of pull rod 12 sequentially passes through the first template 1, translot 9 and circular groove 10 and is fixedly connected with fixture block 15, fixture block 15
Vertical length value be less than circular groove 10 diameter value and translot 9 laterally wide angle value, and the vertical length value of fixture block 15 be more than cross
The vertical length value of slot 9, can facilitate fixture block 15 to be moved to the inside of circular groove 10, while ensure that the card of fixture block 15 and circular groove 10
Connect, the right side of the first template 1 and the second template 4 and front are installed with reinforcing rib 16, and the bottom of reinforcing rib 16 with
The bottom of first template 1 and the second template 4 is flush, and can effectively be supported to the first template 1 and the second template 4, into
The quantity of the supportive and stability that ensure that the first template 1 and the second template 4 of one step, the first template 1 and the second template 4 is equal
It it is two, and each template is both provided with iron sheet to opposite, the connection between each template and the first template 1 and the second mould
Connection type between plate 4 is identical.
Operation principle:When mounted, the 2nd 4 inserted block 5 is plugged on the inside of cavity 2, the work that block 8 passes through limited block
With, the contraction of the first spring 7 is pushed, is detached from limited block when the right end of limited block when block 8 moves, the first spring 7 resets, this
When, inserted block 5 is fixed on the inside of cavity 2, and pull rod 12 is moved to the left the inside of circular groove 10, second spring when by operating pulling block
14 shrink, and are rotating clockwise 90 degree, unclamp pulling block, and second spring 14 resets, and the elastic force of second spring 14 consolidates fixture block 15
It is scheduled on the inner wall of circular groove 10, carries out the fixation to the first template 1 and the second template 4.
It can to sum up obtain, by the cavity 2 of setting, inserted block 5, groove 6, block 8 and limited block, in the effect of the first spring 7
Under, the top and bottom of the first template 1 and the second template 4 can be fixed, facilitate 1 He of the first template of staff couple
The positioning and fixation of second template 4, facilitate the installation of staff, pass through the translot 9 of setting, circular groove 10, outer cover 11, pull rod
12, slide plate 13 and second spring 14 can carry out the first template 1 and the second template 4 effectively to add under the action of fixture block 15
Gu avoiding the phenomenon that the first template 1 and the second template 4 are detached from when pouring, the first template 1 and second when pouring ensure that
The stability of template 4 can be facilitated and be dismantled to the template after solidification, be carried by the first iron sheet 3 of setting and the second iron sheet
The high efficiency of work, solves that installation is inconvenient, and working efficiency is low, it is difficult to demould, the short problem of service life.
It should be noted that herein, relational terms such as first and second and the like are used merely to a reality
Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation
In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to
Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those
Element, but also include other elements that are not explicitly listed, or further include for this process, method, article or equipment
Intrinsic element.In the absence of more restrictions, the element limited by sentence " including a reference structure ", is not arranged
Except there is also other identical elements in the process, method, article or apparatus that includes the element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is appreciated that can these embodiments be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaiied
Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of construction formwork for placing, including the first template(1), it is characterised in that:First template(1)Left side
Face is opened up there are two symmetrical cavity(2), two cavitys(2)Inner roof wall and inner bottom wall be fixedly connected with limit
Block, first template(1)Left side be installed with the first iron sheet(3), first iron sheet(3)Left side be overlapped with
Second template(4), second template(4)Right side be fixedly connected there are two symmetrical inserted block(5), two inserted blocks
(5)Through the first iron sheet(3)It is plugged on two cavitys respectively(2)Inside, the inserted block(5)Top and bottom offer
Groove(6), two grooves(6)Inner roof wall and inner bottom wall be fixedly connected with the first spring(7), first spring
(7)Far from groove(6)Inner roof wall and one end of inner bottom wall be fixedly connected with block(8), and block(8)Positioned at the right side of limited block
Side, second template(4)Left side offer translot(9), the translot(9)Left end offer circular groove(10), described
First template(1)Right side be fixedly connected with outer cover(11), the outer cover(11)The middle part movable sleeve on right side be connected to pull rod
(12), the pull rod(12)Outer surface fixing sleeve be connected to slide plate(13), the slide plate(13)Top and bottom pivot bush unit
In outer cover(11)Inside on, the slide plate(13)Right side be fixedly connected with second spring(14), the second spring
(14)Far from slide plate(13)One end just and outer cover(11)It is fixedly connected on the left of inner wall, the pull rod(12)Left end pass through successively
Wear the first template(1), translot(9)And circular groove(10)And it is fixedly connected with fixture block(15).
2. a kind of construction formwork for placing according to claim 1, it is characterised in that:First template(1)With
Second template(4)Right side and front be installed with reinforcing rib(16), and reinforcing rib(16)Bottom and the first template
(1)With the second template(4)Bottom be flush.
3. a kind of construction formwork for placing according to claim 1, it is characterised in that:The block(8)Both ends
With groove(6)There are gap between the both sides of inner wall, and block(8)Far from the first spring(7)One end extend to groove(6)'s
It is external.
4. a kind of construction formwork for placing according to claim 1, it is characterised in that:The pull rod(12)Right end
It is fixedly connected with pulling block, and pull rod(12)Vertical length value be less than translot(9)Vertical length value.
5. a kind of construction formwork for placing according to claim 1, it is characterised in that:The fixture block(15)It is vertical
Length value is less than circular groove(10)Diameter value and translot(9)Laterally wide angle value, and fixture block(15)Vertical length value be more than cross
Slot(9)Vertical length value.
6. a kind of construction formwork for placing according to claim 1, it is characterised in that:Second template(4)'s
The back side is installed with the second iron sheet.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820082322.9U CN207847066U (en) | 2018-01-18 | 2018-01-18 | A kind of construction formwork for placing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820082322.9U CN207847066U (en) | 2018-01-18 | 2018-01-18 | A kind of construction formwork for placing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207847066U true CN207847066U (en) | 2018-09-11 |
Family
ID=63415203
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820082322.9U Expired - Fee Related CN207847066U (en) | 2018-01-18 | 2018-01-18 | A kind of construction formwork for placing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207847066U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109244639A (en) * | 2018-09-18 | 2019-01-18 | 张淼淼 | A kind of antenna vibrator for mobile communication base station |
CN112252558A (en) * | 2020-11-06 | 2021-01-22 | 绍兴宝城建筑工业化制造有限公司 | Node connection structure of prefabricated floor slab and construction method |
CN112627520A (en) * | 2020-12-01 | 2021-04-09 | 机械工业第九设计研究院有限公司 | Fixed template structure of pouring frame for civil construction engineering |
CN113756562A (en) * | 2021-09-09 | 2021-12-07 | 张永升 | Combined connection module of prefabricated building and combined plate body structure thereof |
CN115354766A (en) * | 2022-09-13 | 2022-11-18 | 谢正芳 | Assembled combination acoustic celotex board |
-
2018
- 2018-01-18 CN CN201820082322.9U patent/CN207847066U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109244639A (en) * | 2018-09-18 | 2019-01-18 | 张淼淼 | A kind of antenna vibrator for mobile communication base station |
CN109244639B (en) * | 2018-09-18 | 2020-07-24 | 广东盛路通信科技股份有限公司 | Antenna oscillator of mobile communication base station |
CN112252558A (en) * | 2020-11-06 | 2021-01-22 | 绍兴宝城建筑工业化制造有限公司 | Node connection structure of prefabricated floor slab and construction method |
CN112627520A (en) * | 2020-12-01 | 2021-04-09 | 机械工业第九设计研究院有限公司 | Fixed template structure of pouring frame for civil construction engineering |
CN113756562A (en) * | 2021-09-09 | 2021-12-07 | 张永升 | Combined connection module of prefabricated building and combined plate body structure thereof |
CN115354766A (en) * | 2022-09-13 | 2022-11-18 | 谢正芳 | Assembled combination acoustic celotex board |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207847066U (en) | A kind of construction formwork for placing | |
CN207347929U (en) | Crash barrier template structure and anticollision barrier casting system | |
CN206667764U (en) | Pour and use separating device | |
CN208346615U (en) | Box girder inner formwork | |
CN209261237U (en) | A kind of prefabricated panel clamping device | |
CN202787330U (en) | Post-cast strip template | |
CN202090932U (en) | Universal template device for tunnel construction | |
CN207048304U (en) | A kind of easy-to-mount construction moulding plate | |
CN204221941U (en) | A kind of combined type sycon cable duct mould | |
CN213952961U (en) | Green's waterproof anticorrosive template device | |
CN204679074U (en) | A kind of novel surface observation pier structure | |
CN209244257U (en) | A kind of removable superstructure formwork | |
CN210797894U (en) | Prefabricated built-in concrete structure's connected node | |
CN209742363U (en) | Floor opening formwork hanging device | |
CN109235709B (en) | Full cast-in-place outer wall structure of building | |
CN208633503U (en) | A kind of high intensity is exempted from nail plastic building template | |
CN207739656U (en) | A kind of hanging dry wall scene supporting apparatus in hole side | |
CN214739893U (en) | Assembled wall embodiment pouring hidden column template fixing device | |
CN215289706U (en) | Prefabricated bent cap template system of superelevation gradual change section | |
CN219034067U (en) | Closing-up net construction structure | |
CN215803203U (en) | Regularization constructional column pouring mold | |
CN203361191U (en) | Basement exterior wall structure | |
CN208917969U (en) | A kind of monoblock type combined steel formwork | |
CN207739155U (en) | A kind of bridge pier of overpass pours plate | |
CN209552030U (en) | A kind of prefabricated box girder inner formwork plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180911 Termination date: 20210118 |
|