CN219034067U - Closing-up net construction structure - Google Patents

Closing-up net construction structure Download PDF

Info

Publication number
CN219034067U
CN219034067U CN202320215343.4U CN202320215343U CN219034067U CN 219034067 U CN219034067 U CN 219034067U CN 202320215343 U CN202320215343 U CN 202320215343U CN 219034067 U CN219034067 U CN 219034067U
Authority
CN
China
Prior art keywords
net
closing
fixedly connected
bar
horizontal rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320215343.4U
Other languages
Chinese (zh)
Inventor
吴礼飞
赵伟
杨剑超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Third Navigation Bureau South Engineering Co ltd
Jiangsu Branch Of Cccc Shanghai Port Engineering Co ltd
Jiangmen Xinhui Aviation Construction Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
Cccc Third Navigation Bureau South Engineering Co ltd
Jiangsu Branch Of Cccc Shanghai Port Engineering Co ltd
Jiangmen Xinhui Aviation Construction Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Third Navigation Bureau South Engineering Co ltd, Jiangsu Branch Of Cccc Shanghai Port Engineering Co ltd, Jiangmen Xinhui Aviation Construction Engineering Co ltd, CCCC Third Harbor Engineering Co Ltd filed Critical Cccc Third Navigation Bureau South Engineering Co ltd
Priority to CN202320215343.4U priority Critical patent/CN219034067U/en
Application granted granted Critical
Publication of CN219034067U publication Critical patent/CN219034067U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a closing-up net construction structure which comprises a first horizontal rod, wherein a second horizontal rod is arranged at the bottom end of the first horizontal rod, vertical reinforcing rods are installed between the first horizontal rod and the second horizontal rod at equal intervals, one side of each vertical reinforcing rod is fixedly connected with a mounting plate, one side of each mounting plate is provided with a water stop belt, the outside of each vertical reinforcing rod is provided with a net surface main body, the top end of each second horizontal rod is fixedly connected with a first connecting plate, and one side of each vertical reinforcing rod is fixedly connected with a second connecting plate. This binding off net construction structures improves stability through the backup pad, and the inside reinforcement vaulting pole of binding off net has improved whole binding off net holistic supporting strength with the reinforcement montant, and the support and the fixed measure of location of binding off net both sides for the stability of binding off net improves greatly, has accelerated the installation progress of binding off net, has both guaranteed its installation quality, has also improved its efficiency of tearing open of ann, has solved the poor problem of stability.

Description

Closing-up net construction structure
Technical Field
The utility model relates to the technical field of building construction, in particular to a closing-in net construction structure.
Background
The closing-in net is also called as a disassembling-free template net and is fixed as a consumable template, in order to solve the problem of insufficient concrete supply capacity of a large-volume concrete pouring and mixing station, the bottom plate needs to be poured in sections, and the concrete connecting surface between the sections needs to meet the specification and has a sufficiently rough exposed concrete CJ surface, so that a closing-in net device needs to be used.
Through retrieval, according to the fast-easy-closing-up net with tight combination disclosed by application number CN202220258335.3, the utility model is provided with the convex body hollow in the inside, so that the slurry leakage phenomenon in the pouring process can be effectively avoided, and meanwhile, the stability of the fast-easy-closing-up net after pouring and the compactness of the concrete connection surfaces on two sides of the fast-easy-closing-up net during combination can be improved, thereby improving the construction quality.
What is needed is a closing-in net construction structure that overcomes the technical shortcomings set forth in the prior art.
Disclosure of Invention
The utility model aims to provide a closing-in net construction structure so as to solve the problem of poor stability in the background technology.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a binding off net construction structure, includes first horizon bar, the bottom of first horizon bar is provided with the second horizon bar, equidistant perpendicular reinforcing bar is installed between first horizon bar and the second horizon bar, one side fixedly connected with mounting panel of perpendicular reinforcing bar, the waterstop is installed to one side of mounting panel, the externally mounted of perpendicular reinforcing bar has the net face main part, the top fixedly connected with first connecting plate of second horizon bar, one side fixedly connected with second connecting plate of perpendicular reinforcing bar, fixedly connected with backup pad between first connecting plate and the second connecting plate, the bottom fixedly connected with second connecting seat of first horizon bar, the top fixedly connected with first connecting seat of second horizon bar, fixedly connected with two sets of reinforcement montants between first connecting seat and the second connecting seat, fixedly connected with consolidates the vaulting pole between the reinforcement montant, form the CJ face through pouring between first horizon bar and the perpendicular reinforcing bar.
Preferably, an A-shaped supporting structure is formed between the reinforcing vertical rods and the reinforcing supporting rods, and the supporting plates are distributed on two sides of the top of the second horizontal rod.
Preferably, the net surface main body is paved outside the vertical steel bar rod, the first horizontal rod and the second horizontal rod.
Preferably, the outside fixedly connected with installation fixture block of net face main part, the outside of perpendicular bar lever is provided with the installation draw-in groove, the inside of installation fixture block is provided with the mounting bolt.
Preferably, the installation clamping block is embedded in the installation clamping groove.
Preferably, one end of the mounting bolt penetrates through the mounting clamping block and is embedded in the mounting clamping groove.
Preferably, high-wood plugging concrete is arranged on the outer side of the second horizontal rod.
Compared with the prior art, the utility model has the beneficial effects that: the closing-in net construction structure not only realizes the improvement of the supporting stability and the function of better forming quality, but also realizes the function of convenient disassembly and assembly;
(1) The support plates, the reinforcing support rods and the reinforcing vertical rods are arranged, the support plates arranged in the closing-in net are arranged on the two sides of the inside of the closing-in net to improve stability, the reinforcing support rods and the reinforcing vertical rods in the inside of the closing-in net improve the integral support strength of the whole closing-in net, and the support and positioning fixing measures on the two sides of the closing-in net greatly improve the stability of the closing-in net, quicken the installation progress of the closing-in net, ensure the installation quality of the closing-in net and improve the installation and disassembly efficiency of the closing-in net;
(2) By arranging the CJ face, after the process is innovatively used, the molding quality of the CJ face is good, the process meets the standard requirements, the closing-up net face has no obvious slurry leakage, the cleaning workload of a bottom plate at the later stage is reduced, the plugging compactness of the construction section of the pump house is enhanced, the template installation difficulty is reduced, the problem of slurry leakage of the template at the section is avoided, and the template installation difficulty at the section is also simplified;
(3) Through being provided with mesh main part, installation draw-in groove, installation fixture block and mounting bolt, the mesh main part is installed in the outside of binding off net structure through the installation fixture block, and the installation fixture block inlays can use the mounting bolt after the installation draw-in groove is inside with it fixed can, only need during the dismantlement with the installation fixture block from the inside completion of taking out of installation draw-in groove, this structure has realized convenient to detach's function.
Drawings
FIG. 1 is a schematic cross-sectional elevation view of the present utility model;
FIG. 2 is a schematic view of the CJ face parting of the present utility model;
FIG. 3 is a schematic elevational view of the present utility model;
fig. 4 is an enlarged schematic view of the structure of fig. 3 a according to the present utility model.
In the figure: 1. a first horizontal bar; 2. a vertical bar; 3. a water stop; 4. a second horizontal bar; 5. a first connection plate; 6. a mounting plate; 7. a second connecting plate; 8. a support plate; 9. a first connection base; 10. reinforcing the stay bars; 11. reinforcing a vertical rod; 12. a second connecting seat; 13. CJ face; 14. a mesh body; 15. installing a clamping groove; 16. installing a clamping block; 17. and (5) installing a bolt.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Example 1: referring to fig. 1-4, the closing-up net construction structure comprises a first horizontal rod 1, a second horizontal rod 4 is arranged at the bottom end of the first horizontal rod 1, vertical steel bars 2 are installed between the first horizontal rod 1 and the second horizontal rod 4 at equal intervals, one side of each vertical steel bar 2 is fixedly connected with a mounting plate 6, a water stop belt 3 is installed at one side of each mounting plate 6, a net surface main body 14 is installed outside each vertical steel bar 2, a first connecting plate 5 is fixedly connected to the top end of each second horizontal rod 4, a second connecting plate 7 is fixedly connected to one side of each vertical steel bar 2, a supporting plate 8 is fixedly connected between each first connecting plate 5 and each second connecting plate 7, a second connecting seat 12 is fixedly connected to the bottom end of each first horizontal rod 1, a first connecting seat 9 is fixedly connected to the top end of each second horizontal rod 4, two groups of reinforcing vertical rods 11 are fixedly connected between each first connecting seat 9 and each second connecting seat 12, and reinforcing supporting rods 10 are fixedly connected between the reinforcing vertical rods 11;
an A-shaped supporting structure is formed between the reinforcing vertical rods 11 and the reinforcing supporting rods 10, and the supporting plates 8 are distributed on two sides of the top of the second horizontal rod 4;
specifically, as shown in fig. 1 and 2, the supporting plate 8 installed inside the closing-in net is made of a wood, the wood is installed on two sides inside the closing-in net at intervals of 0.5M, the reinforcing supporting rods 10 and the reinforcing vertical rods 11 inside the closing-in net form a stable supporting A shape, the supporting strength of the whole closing-in net is improved, and supporting and positioning fixing measures on two sides of the closing-in net are adopted, so that the stability of the closing-in net is greatly improved.
Example 2: the net surface main body 14 is paved outside the vertical steel bar 2, the first horizontal bar 1 and the second horizontal bar 4, high-wood plugging concrete is arranged on the outer side of the second horizontal bar 4, and a CJ surface 13 is formed between the first horizontal bar 1 and the vertical steel bar 2 through pouring;
specifically, as shown in fig. 1 and 3, the forming quality of the CJ face 13 is good, the standard requirement is met, the closing-up net face has no obvious slurry leakage, the cleaning workload of the bottom plate in the later stage is reduced, the plugging compactness of the pump house construction section is enhanced, and meanwhile, the template installation difficulty is reduced.
Example 3: the outside of the net surface main body 14 is fixedly connected with a mounting clamping block 16, the outside of the vertical steel bar 2 is provided with a mounting clamping groove 15, the inside of the mounting clamping block 16 is provided with a mounting bolt 17, the mounting clamping block 16 is embedded in the mounting clamping groove 15, and one end of the mounting bolt 17 penetrates through the mounting clamping block 16 and is embedded in the mounting clamping groove 15;
specifically, as shown in fig. 1 and fig. 4, the net surface main body 14 is laid outside the closing net structure, the installation clamping block 16 outside the net surface main body 14 is embedded inside the installation clamping groove 15 and then can be fixed by using the installation bolt 17, and when the net surface main body is detached, the installation clamping block 16 is taken out from the installation clamping block 16, and then the net surface main body is taken out from the installation clamping groove 15.
Working principle: when the concrete pouring device is used, according to a pump room pouring process, a pump room bottom plate is poured for three times, a pump truck and a ground pump are combined for pouring, a closing net is adopted for closing a joint of the bottom plate CJ and exposed steel bars of a wall body, the closing net is 0.4mm thick and is arranged in a double-layer mode, 5cm Gao Mufang is used for closing concrete on the bottom side of the bottom plate, a T25 vertical steel bar 2 is used for positioning at a distance of 300mm on the side of the post-pouring concrete, 3T 25 steel bars with a distance of 500mm are transversely and generally arranged for reinforcement, after the auxiliary steel bars are installed, a supporting plate 8 is used for supporting and reinforcing the bottom side of the closing net and a second transverse steel bar, when the steel bars are outwards extended, the closing net is disconnected, the closing net is supplemented in a gap, two water stops with a width of 250mm are transversely arranged on one side of the pre-pouring concrete, the height of each water stop is 400mm and 800mm away from the bottom tread, the other half of the water stop is tightly attached to the closing net on the side of the concrete, the other half of the water stop is tightly attached to the closing net through a mounting plate 6 for binding, after the concrete pouring is completed, the closing net, the wood and the bottom plate is removed and the bottom plate 13 and the auxiliary steel bars are generally arranged for supporting and reinforcing bars are required to be cleaned, accepted, and the qualified templates are installed.
It will be evident to those skilled in the art that the utility model is not limited to the details of the foregoing illustrative embodiments, and that the present utility model may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are, therefore, to be considered in all respects as illustrative and not restrictive, the scope of the utility model being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. Closing up net construction structures, including first horizon bar (1), its characterized in that: the bottom of first horizon bar (1) is provided with second horizon bar (4), equidistant perpendicular bar (2) are installed between first horizon bar (1) and second horizon bar (4), one side fixedly connected with mounting panel (6) of perpendicular bar (2), waterstop (3) are installed to one side of mounting panel (6), the externally mounted of perpendicular bar (2) has net face main part (14), the top fixedly connected with first connecting plate (5) of second horizon bar (4), one side fixedly connected with second connecting plate (7) of perpendicular bar (2), fixedly connected with backup pad (8) between first connecting plate (5) and second connecting plate (7), the bottom fixedly connected with second connecting seat (12) of first horizon bar (1), the top fixedly connected with first connecting seat (9) of second horizon bar (4), fixedly connected with consolidates (11) between first connecting seat (9) and the second connecting seat (12), consolidate (11) are pour between one side fixedly connected with second connecting plate (7), consolidate between bar (1) and the montant (13) through vertical bar (13).
2. The closing-in net construction structure according to claim 1, wherein: a' -shaped supporting structure is formed between the reinforcing vertical rods (11) and the reinforcing supporting rods (10), and the supporting plates (8) are distributed on two sides of the top of the second horizontal rod (4).
3. The closing-in net construction structure according to claim 1, wherein: the net surface main body (14) is paved outside the vertical steel bar rods (2), the first horizontal rods (1) and the second horizontal rods (4).
4. The closing-in net construction structure according to claim 1, wherein: the outside fixedly connected with installation fixture block (16) of net face main part (14), the outside of perpendicular bar reinforcement (2) is provided with installation draw-in groove (15), the inside of installation fixture block (16) is provided with mounting bolt (17).
5. The closing-in net construction structure according to claim 4, wherein: the installation clamping block (16) is embedded in the installation clamping groove (15).
6. The closing-in net construction structure according to claim 4, wherein: one end of the mounting bolt (17) penetrates through the mounting clamping block (16) and is embedded in the mounting clamping groove (15).
7. The closing-in net construction structure according to claim 1, wherein: the outer side of the second horizontal rod (4) is provided with high-wood plugging concrete.
CN202320215343.4U 2023-02-15 2023-02-15 Closing-up net construction structure Active CN219034067U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320215343.4U CN219034067U (en) 2023-02-15 2023-02-15 Closing-up net construction structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320215343.4U CN219034067U (en) 2023-02-15 2023-02-15 Closing-up net construction structure

Publications (1)

Publication Number Publication Date
CN219034067U true CN219034067U (en) 2023-05-16

Family

ID=86285742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320215343.4U Active CN219034067U (en) 2023-02-15 2023-02-15 Closing-up net construction structure

Country Status (1)

Country Link
CN (1) CN219034067U (en)

Similar Documents

Publication Publication Date Title
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN211517947U (en) Bridge case roof beam is prefabricated with shaped steel pedestal
CN109972655B (en) Prefabricated pipe gallery mechanical and hydraulic combined type integrally-installed and disassembled steel template and installation method
CN102677895B (en) Suspended formwork pouring method for concrete foundation steps
CN219034067U (en) Closing-up net construction structure
CN212001240U (en) Accurate positioner of street lamp basis and built-in fitting
CN211993513U (en) Steel bench for beam slab prefabricating field
CN211079799U (en) Reinforced structure of impaired concrete road surface panel
CN201972715U (en) Integrated ditch cable trough mould frame
CN218233146U (en) Supporting device for pouring drainage side ditch
CN111236314A (en) Assembled rectangle concrete slab for utility tunnel
CN214423395U (en) Assembled waterproof wall of leading
CN210916832U (en) Track disassembly structure for high-speed rail ballastless track
CN204357118U (en) Form removal bracing frame behind a kind of beam slab ater-casting
CN220267224U (en) Device for preventing mutual string pouring of concrete with different labels
CN216193749U (en) Assembly type road structure for construction site
CN215717204U (en) Building engineering frame post template reinforcing apparatus
CN219118754U (en) Post-cast strip pouring system
CN208917969U (en) A kind of monoblock type combined steel formwork
CN219137751U (en) Pipe gallery pouring template assembly and pipe gallery
CN219528170U (en) Non-standard-section split heads for pre-buried leveling of tower crane foundation
CN220365107U (en) Simple and easy escape canal of on-spot pin-connected panel
CN220704900U (en) Concrete prefabricated anti-threshold standard module and assembly type assembly
CN216195401U (en) Assembly type structure connected by UHPC
CN212688637U (en) Road surface water stable layer construction template

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant