CN207776458U - A kind of built-in fitting lifting accurate-location device - Google Patents
A kind of built-in fitting lifting accurate-location device Download PDFInfo
- Publication number
- CN207776458U CN207776458U CN201820037764.1U CN201820037764U CN207776458U CN 207776458 U CN207776458 U CN 207776458U CN 201820037764 U CN201820037764 U CN 201820037764U CN 207776458 U CN207776458 U CN 207776458U
- Authority
- CN
- China
- Prior art keywords
- built
- fitting
- location device
- accurate
- holders
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 claims abstract description 18
- 230000003014 reinforcing effect Effects 0.000 claims description 7
- 239000004744 fabric Substances 0.000 claims 1
- 229910000831 Steel Inorganic materials 0.000 description 12
- 239000010959 steel Substances 0.000 description 12
- 238000009434 installation Methods 0.000 description 11
- 238000000034 method Methods 0.000 description 10
- 230000006872 improvement Effects 0.000 description 8
- 238000007796 conventional method Methods 0.000 description 6
- 230000008569 process Effects 0.000 description 6
- 239000003795 chemical substances by application Substances 0.000 description 5
- 230000002787 reinforcement Effects 0.000 description 5
- 230000006378 damage Effects 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 230000008859 change Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 208000027418 Wounds and injury Diseases 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Built-in fitting provided by the utility model lifts accurate-location device, including holder, flexible connecting member and jack, opposite two holders set up are connected to construction agent structure, and flexible connecting member is connected between two holders, and flexible connecting member is formed with the multiple lifting lugs hooked for jack.Two holders of the utility model are as upending frame, flexible connecting member connects two holders and coordinates jack lifting, lifting built-in fitting, multiple lifting lugs cooperation jack on flexible connecting member uses, and the position for adjusting built-in fitting precisely, safely can lift or install built-in fitting.
Description
Technical field
The utility model is related to building fields, and in particular to a kind of built-in fitting lifting accurate-location device.
Background technology
As environmentally protective theory deepens continuously to construction enterprises, green, energy-saving and environmental protection are constructed into for engineering construction
Theme.The quantities of some engineerings is big in reality, structure type is complicated, and installation of embedded parts quantity is more and a large amount of built-in fittings
Volume and weight are all very big, therefore, can not be touched or the unhandy position of building element complexity tower crane in tower crane, it is desirable to real
There are larger difficulties for the precise positioning of existing built-in fitting.But it according to traditional installation of embedded parts method, then has the following problems:
Conventional method 1:Built-in fitting is hoisted near installation site using tower crane, by being manually carried to installation site,
Then the mode that construction personnel carries manually realizes the fixation of built-in fitting.This method need in the construction process labor intensive compared with
More, manpower transport does not realize that built-in fitting precisely firmly fix by installation, and built-in fitting weight is larger there are unstability
When, there are security risks.
Conventional method 2:Using truck crane built-in fitting be hoisted to installation site position it is pre-buried.This method is being constructed
In the process since truck crane operation height is relatively high, built-in fitting easily waves, it is difficult to accomplish it is accurate pre-buried, in hoisting process
It is easy to damage steel reinforcement cage or completed building element.And increases fund input using truck crane, expend the time
It is longer.
Conventional method 3:Utilize the welded reinforcement holder dragging built-in fitting progress built-in fitting on banded good steel reinforcement cage
It positions pre-buried.This method needs to be subjected on steel reinforcement cage in the construction process, can cause major injury to reinforcing bar.
To sum up analysis conventional method is difficult to realize accurate, secured, the safe installation of built-in fitting, manually puts into larger, peace
Full hidden danger is big, and fund input is more, can cause to damage to having component.
Utility model content
In order to solve the problems, such as conventional method be difficult to it is accurate, secured, safely lift or install built-in fitting, the utility model
Provide a kind of built-in fitting lifting accurate-location device.
Built-in fitting provided by the utility model lifts accurate-location device, including holder, flexible connecting member and jack, relatively
Two holders set up are connected to construction agent structure, and the flexible connecting member is connected between two holders, institute
It states flexible connecting member and is formed with the multiple lifting lugs hooked for the jack.
Two holders of the utility model as upending frame, flexible connecting member connect two holders and coordinate jack lifting,
Built-in fitting is lifted, multiple lifting lugs cooperation jack on flexible connecting member uses, and the position for adjusting built-in fitting can accurate, peace
Lift or install entirely built-in fitting.
The utility model built-in fitting lift accurate-location device further improvement lies in that, the flexible connecting member be lock
Chain, the lifting lug are the latch closure of the chain.
The further improvement of the utility model built-in fitting lifting accurate-location device is that the holder is formed with handle
Hand, the both ends of the chain are connected to the handle of two holders.
The utility model built-in fitting lift accurate-location device further improvement lies in that, further include being connected to described in two
Stiffening plate between holder.The utility model reinforces the connection between two holders using stiffening plate, and improving the utility model makes
With stability in the process, and then improve the accuracy of lifting positioning.
The further improvement of the utility model built-in fitting lifting accurate-location device is that two stiffening plates are connected
After be connected to the holder.
The further improvement of the utility model built-in fitting lifting accurate-location device is, between two stiffening plates
It is connected by pin.
The utility model built-in fitting lifting accurate-location device it is further improve be, shape on each stiffening plate
At the multiple adjustment holes for thering is the confession pin to wear.The utility model coordinates stiffening plate using adjustment hole, can be according to two holders
The distance between and adjust two stiffening plates total length, be easy to use.
The further improvement of the utility model built-in fitting lifting accurate-location device is that multiple adjustment holes are uniform
It is distributed on the stiffening plate.
The further improvement of the utility model built-in fitting lifting accurate-location device is that the top of the holder is equipped with
The both ends of anchor bolt, the stiffening plate are each formed with anchor hole, and the anchor bolt is connected to the stiffening plate by the anchor hole.
The utility model built-in fitting lift accurate-location device further improvement lies in that, the holder be vertical tube, it is described
Vertical tube is sheathed on the reinforcing bar of the construction agent structure.
Description of the drawings
Fig. 1 is the main structure diagram for the preferred embodiment that the utility model built-in fitting lifts accurate-location device.
Fig. 2 is the overlooking structure diagram for the preferred embodiment that the utility model built-in fitting lifts accurate-location device.
Fig. 3 is the structural schematic diagram of holder.
Fig. 4 is the use state diagram for the preferred embodiment that the utility model built-in fitting lifts accurate-location device.
Fig. 5 is the use state side view signal for the preferred embodiment that the utility model built-in fitting lifts accurate-location device
Figure.
Specific implementation mode
In order to solve the problems, such as conventional method be difficult to it is accurate, secured, safely lift or install built-in fitting, the utility model
Provide a kind of built-in fitting lifting accurate-location device.
The utility model built-in fitting lifting accurate-location device is made furtherly in the following with reference to the drawings and specific embodiments
It is bright.Those skilled in the art can be understood other advantages and work(of the utility model easily by the content disclosed by this specification
Effect.
In conjunction with shown in Fig. 1, Fig. 2 and Fig. 4, the preferred embodiment of the utility model built-in fitting lifting accurate-location device includes
Holder 11, flexible connecting member 12 and jack 13, opposite two holders 11 set up are connected to construction agent structure, flexible connecting member
12 are connected between two holders 11, and flexible connecting member 12 is formed with the multiple lifting lugs hooked for jack 13.
Two holders 11 of the utility model are used as upending frame, flexible connecting member 12 to connect two holders 11 and coordinate jack
13 liftings lift built-in fitting 3, and multiple lifting lugs cooperation jack 13 on flexible connecting member 12 uses, the water for adjusting built-in fitting 3
Prosposition is set, and built-in fitting 3 can precisely, be safely positioned, lifts or install.Specifically, holder 11 is vertical tube, in the present embodiment preferably
For elongated square steel, square steel is sheathed on the reinforcing bar 21 of construction agent structure 2.
Further, in the present embodiment, flexible connecting member 12 is chain, and lifting lug is the latch closure of chain.Multiple latch closure phases
Buckle-shaped at chain, and jack 13 can be hooked on latch closure, adjust the position of jack 13 by selecting latch closure, and then adjust pre-buried
The accurate adjusting of 3 position of built-in fitting is convenient in the position (adjustable range is between two stands 11) of part 3.In other embodiments, soft
Property connector 12 can be steel wire rope.
In conjunction with shown in Fig. 2 and Fig. 3, further, holder 11 is formed with handle 14, and the both ends of chain are connected to two
The handle 14 of a holder 11.Chain is wrapped on handle 14 in the present embodiment, and handle 14 is preferably U-shaped handle, and U-shaped handle is opened
Therefore the pipe shaft that the side of mouth is connected to square steel is formed with closed region between U-shaped handle and holder 11 so that chain is not
It easily falls off from handle 14, connection is more secured.
Further include the stiffening plate 15 between being connected to two holders 11 further in conjunction with shown in Fig. 1 and Fig. 2.This practicality
It is novel that two holders 11 are connected as an entirety using stiffening plate 15, the connection between two holders 11 is strengthened, is prevented
During lifting built-in fitting 3, external constructing structure is deformed because stress is excessive, influences the accuracy of lifting.The utility model
Stiffening plate 15 be rigid member, select 500mm × 50mm × 15mm sheet metal, can be between two holders 11 of operative constraint
Horizontal distance, fixing bracket 11, to be conducive to improve hoisting process in stability, the essence of built-in fitting 3 both may be implemented
Quasi- handling and installation, and construction safety risk and artificial input can be reduced, while reducing the damage to reinforcing bar 21.
Further, two stiffening plates 15 are connected to holder 11 after being connected, and pass through pin 151 between two stiffening plates 15
Connection.
Further, square steel top is equipped with platform 111, is connected with anchor bolt 112 on platform 111, stiffening plate 15 is formed with
Anchor hole, anchor bolt 112 are connected to stiffening plate 15 by anchor hole.Specifically, the platform 111 in the present embodiment is square plate,
Each platform 111 is fixed there are two anchor bolt 112, and the first end of each stiffening plate 15 sets that there are two corresponding anchor holes, adjacent
The distance between two anchor holes be 50mm.Specifically, select the anchor bolt 112 of a diameter of 8mm, anchor hole it is a diameter of
10mm.Using 112 connecting bracket 11 of anchor bolt and stiffening plate 15, removes and have bad luck convenient for stiffening plate 15.In other embodiments, it mends
The quantity of strong plate is one, and the first end and second end of stiffening plate is respectively formed there are two anchor hole, the first end of stiffening plate and the
Two ends are connected to two holders.
Further, the multiple adjustment holes 152 worn for pin 151 are formed on each stiffening plate 15, preferably, more
A adjustment hole 152 is evenly distributed on stiffening plate 15.Specifically, in the present embodiment, along from the second end of stiffening plate 15 to reinforcement
The direction of the first end of plate 15 is stayed every 50mm and sets an adjustment hole 152, and the distance between adjustment hole 152 and anchor hole are minimum
For 50mm, a diameter of 8mm of adjustment hole 152.The utility model coordinates stiffening plate 15 using adjustment hole 152, can be according to two branch
The entire length of the distance between frame 11 and two stiffening plates 15 of adjusting is easy to use.
In conjunction with shown in Fig. 1, Fig. 4 and Fig. 5, when built-in fitting lifts the installation of accurate-location device 1, according to the design of built-in fitting 3
Embedding position penetrates two holders 11 on the reinforcing bar 21 of construction agent structure 2 bound;According between two holders 11
The entire length of distance two stiffening plates 15 of adjustment, and two stiffening plates 15 are connected between two holders 11;In two branch
Chain is connected between frame 11;Jack 13 is hooked on the latch closure of chain, 13 position of jack can move on chain (adjusts model
It is trapped among between two stands 11), it is convenient for the accurate adjusting of 3 position of built-in fitting.
Positioning built-in fitting 3 first wants inbuilt position 4 during use, is arranged on the reinforcing bar 21 of the both sides of position 4
Square steel, the overall distance of two stiffening plates 15 is adjusted according to the spacing between two square steel, and stiffening plate 15 is connected to two
Between square steel, then chain is connected to the U-shaped handle of square steel, ensures that chain is located at the surface of position 4.It is positioned according to position 4
Jack 13 is specifically tentatively hung on chain latch closure corresponding with position 4 by the latch closure to be hooked of jack 13, to fall
Chain 13 is that reference standard is compared with position 4, then replaces latch closure if any deviation, selects another latch closure.So cycle is straight
To the latch closure to align selected with position 4,13 hanging position of jack is made to be overlapped with position 4.
By adjusting bracket 11 and the position of jack 13, the precision of the lifting of built-in fitting 3 is effectively ensured.The utility model
The positions of two holders 11 can be needed to carry out free adjusting according to site operation;It the position of jack 13 can also be in two branch
It is freely adjusted between frame 11, realizes the fine tuning to 3 vertical lifting position of built-in fitting, it is ensured that the utility model can meet different positions
The accurate handling for the built-in fitting 3 set and installation;Stiffening plate 15 reinforces the connection between two holders 11 simultaneously, improves whole steady
Qualitative, safety and lifting accuracy.
The utility model not only can be used as the vertical hoisting tool of the built-in fitting 3 at the operation of no tower crane construction site, but also can answer
For tower crane can not handling complex region, contribute to construction personnel carry out built-in fitting 3 accurate fixation, avoid because of built-in fitting 3
Excessive or overweight and the security risk generated and a large amount of artificial consumings.The utility model built-in fitting lifts accurate-location device energy
Enough be used in turn, easy to carry, installation operation is simple, remove, have bad luck it is convenient.It is inconvenient in no tower crane or tower crane to solve
Built-in fitting 3 is difficult to the problem lifted at Hoisting Position, saves a large amount of manpower and materials, reduces construction safety risk, substantially increases
Construction operation efficiency.
The above is only the preferred embodiment of the present utility model, not does limit in any form to the utility model
System, although the utility model has been disclosed with preferred embodiment as above, is not limited to the utility model, any to be familiar with sheet
Technical professional, in the range of not departing from technical solutions of the utility model, when the technology contents using the disclosure above
It makes a little change or is modified to the equivalent embodiment of equivalent variations, as long as being without departing from technical solutions of the utility model
Hold, any simple modification, equivalent change and modification made by the above technical examples according to the technical essence of the present invention, still
It is within the scope of the technical solutions of the present invention.
It should be noted that structure, ratio, size etc. depicted in this specification institute accompanying drawings, only coordinating
The bright revealed content of book, so that those skilled in the art understands and reads, being not limited to the utility model can implement
Qualifications, therefore do not have technical essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size,
In the case where not influencing the effect of the utility model can be generated and the purpose that can reach, should all still fall disclosed in the utility model
Technology contents obtain and can cover in the range of.
Claims (10)
1. a kind of built-in fitting lifts accurate-location device, it is characterised in that:It is opposite to set including holder, flexible connecting member and jack
Two vertical holders are connected to construction agent structure, and the flexible connecting member is connected between two holders, described
Flexible connecting member is formed with the multiple lifting lugs hooked for the jack.
2. built-in fitting as described in claim 1 lifts accurate-location device, it is characterised in that:The flexible connecting member is lock
Chain, the lifting lug are the latch closure of the chain.
3. built-in fitting as claimed in claim 2 lifts accurate-location device, it is characterised in that:The holder is formed with handle,
The both ends of the chain are connected to the handle of two holders.
4. built-in fitting as described in claim 1 lifts accurate-location device, it is characterised in that:Further include being connected to described in two
Stiffening plate between holder.
5. built-in fitting as claimed in claim 4 lifts accurate-location device, it is characterised in that:After two stiffening plates are connected
It is connected to the holder.
6. built-in fitting as claimed in claim 5 lifts accurate-location device, it is characterised in that:Lead between two stiffening plates
Cross pin connection.
7. built-in fitting as claimed in claim 6 lifts accurate-location device, it is characterised in that:It is formed on each stiffening plate
There are the multiple adjustment holes worn for the pin.
8. built-in fitting as claimed in claim 7 lifts accurate-location device, it is characterised in that:Multiple adjustment holes uniformly divide
Cloth is on the stiffening plate.
9. built-in fitting as claimed in claim 4 lifts accurate-location device, it is characterised in that:The top of the holder is equipped with anchor
The both ends of bolt, the stiffening plate are each formed with anchor hole, and the anchor bolt is connected to the stiffening plate by the anchor hole.
10. built-in fitting as described in claim 1 lifts accurate-location device, it is characterised in that:The holder is vertical tube, described
Vertical tube is sheathed on the reinforcing bar of the construction agent structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820037764.1U CN207776458U (en) | 2018-01-10 | 2018-01-10 | A kind of built-in fitting lifting accurate-location device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820037764.1U CN207776458U (en) | 2018-01-10 | 2018-01-10 | A kind of built-in fitting lifting accurate-location device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207776458U true CN207776458U (en) | 2018-08-28 |
Family
ID=63223003
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820037764.1U Expired - Fee Related CN207776458U (en) | 2018-01-10 | 2018-01-10 | A kind of built-in fitting lifting accurate-location device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207776458U (en) |
-
2018
- 2018-01-10 CN CN201820037764.1U patent/CN207776458U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211004200U (en) | Multifunctional steel plate combined hoisting sling | |
CN207844890U (en) | A kind of hoisting fixture for building curtain wall | |
CN103692096B (en) | Single-unit crane arm production line balance method and flow line production device | |
CN108086697A (en) | A kind of built-in fitting lifting accurate-location device and lifting precise positioning method | |
CN210914960U (en) | Horizontal hoisting tool for blades of wind generating set | |
CN207776458U (en) | A kind of built-in fitting lifting accurate-location device | |
CN208197158U (en) | A kind of reinforcing bar tire suspender of precast segment box beam | |
CN204456908U (en) | A kind of heavy beam equipment | |
CN207030735U (en) | Prefabricated balcony lifts servicing unit | |
CN206359122U (en) | A kind of concrete pipe Automatic hook block | |
CN108516454A (en) | A kind of hanging apparatus of prefabricated components | |
CN110171766B (en) | Steel bar transportation lifting appliance | |
CN209353735U (en) | The hanging apparatus of truss element | |
CN204551442U (en) | A kind of reinforcing bar cage hoisting movable hook | |
CN209228083U (en) | The protective device of spool at hand hole is reserved when a kind of lifting for PC plate | |
CN208023970U (en) | Construction discharging platform | |
CN206051264U (en) | A kind of one side tilting steel structure hoisting instrument | |
CN208814490U (en) | A kind of novel drainage ditch cover plate hanging apparatus | |
CN207633773U (en) | A kind of glomeration building prefabricated construction reinforcing bar guiding tube dismounting system | |
CN215482358U (en) | Bridge high pier steel bar installation operation device | |
CN201980854U (en) | Semi-automatic brick-suspending clamp | |
CN206476686U (en) | A kind of gate-type hoisting bracket | |
CN213173755U (en) | Beam column type support steel-pipe pile pothook | |
CN202090338U (en) | Derrick rig for adjusting hoisting of reinforcing cage | |
CN206903178U (en) | Hoisting type elevator steel platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180828 |