CN202090338U - Derrick rig for adjusting hoisting of reinforcing cage - Google Patents

Derrick rig for adjusting hoisting of reinforcing cage Download PDF

Info

Publication number
CN202090338U
CN202090338U CN 201120070183 CN201120070183U CN202090338U CN 202090338 U CN202090338 U CN 202090338U CN 201120070183 CN201120070183 CN 201120070183 CN 201120070183 U CN201120070183 U CN 201120070183U CN 202090338 U CN202090338 U CN 202090338U
Authority
CN
China
Prior art keywords
mobile jib
main rod
place
reinforcing bar
derrick rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120070183
Other languages
Chinese (zh)
Inventor
计少博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Beijing Railway Construction Co of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Beijing Railway Construction Co of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Beijing Railway Construction Co of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN 201120070183 priority Critical patent/CN202090338U/en
Application granted granted Critical
Publication of CN202090338U publication Critical patent/CN202090338U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model provides a derrick rig for adjusting the hoisting of a reinforcing cage. The derrick rig comprises a main rod, buckles and a dimension control panel, and is characterized in that the main rod is formed by connecting an upper main rod and a lower main rod integrally through the buckles; the dimension control panel is mounted on the upper main rod; and two parallel ellipse slots are welded to the lower end of the lower main rod. The utility model has the advantages as follows: firstly, the essential problem that the length of a derrick boom molded by welding can not be adjusted freely according to the on-the-spot actual elevation is solved, many inconvenient factors brought forth by the welding of the reinforced derrick boom are avoided, the number of the participant staff is reduced, and the process time is greatly shortened; and secondly, steel bars for hoisting are not needed to purchase, so that the construction cost is greatly saved.

Description

A kind of reinforcing bar cage hoisting derrick rig in place of regulating
Technical field
The utility model belongs to the drilling hole bored concrete pile technology field, particularly relates to a kind of borehole filling pile cage of reinforcement hoisted in position with regulating derrick rig.
Technical background
Bored pile is widely used in bridge, the room is built and other engineering field, reinforcing bar cage hoisting is in place to be the important technology step of bored pile pile, and traditional hanging method is that the different light circle of reinforcing cage symmetry both sides weld length that do not coexist according to on-the-spot Horizon absolute altitude hangs muscle.There is following problem in this construction technology: 1, needs are bought the plain bar that bears the reinforcing cage load separately; 2, need check the welding processing district and carry out weld job; 3, under plain bar, expect the various scale error that causes easily of welding sequence; 4, adjustability is poor, and blanking again is time-consuming in case welding finishes takes a lot of work and cause the waste of a large amount of reinforcing bars.Summary the problems referred to above are reached a conclusion: not only increased construction cost and also reduced efficiency of construction.
Summary of the invention
In order to address the above problem, it is a kind of simple in structure, easy to use that the purpose of this utility model is to provide, and save construction cost and can regulate derrick rig with the reinforcing bar cage hoisting usefulness in place of accelerating speed of application.
In order to achieve the above object, a kind of reinforcing bar cage hoisting derrick rig in place of regulating that the utility model provides, comprise main body bar, buckle, size Control plate, it is characterized in that described main body bar is to be connected as one through buckle by top mobile jib and bottom mobile jib to constitute; The size Control plate is installed on the mobile jib of top; Mobile jib lower end, bottom is welded with two parallel oval slots.
Described size Control plate scale numerical value is vertically arranged along the top mobile jib.
Mobile jib top, described top is processed with a circular handle, and described circular handle and described top mobile jib are one.
Spacing between described two parallel oval slots is less than or equal to 0.5 meter.
A kind of reinforcing bar cage hoisting system in place that regulates, it is characterized in that, comprise derrick rig and inserted link that described adjusting reinforcing bar cage hoisting is in place, described inserted link top has one to hold handle, and the position that upwards surpasses two parallel oval slots in the bottom is equipped with a locator card.
Described inserted link length is greater than 1 meter of described main body pole length.
After described top mobile jib and bottom mobile jib overlapped by described buckle, main body bar total length numerical value was certain when size Control plate reading was zero.Adjust the suspension rod entire length by regulating top mobile jib and the varying sized control panel reading of bottom mobile jib lap length.
The reinforcing bar cage hoisting that the utility model the provides adjustable apparatus of using in place, owing to can adjust the suspension rod entire length by regulating top mobile jib and the varying sized control panel reading of bottom mobile jib lap length, the welding fabrication suspension rod can not be according to the root problem of on-the-spot actual elevation situation free adjustment length of boom so solved, and avoided thus because the inconvenience factor that the welded reinforcement suspension rod brings, reduced participant's quantity and significantly compressed activity time, saved construction cost greatly with reinforcing bar so removed the buying lifting from.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Symbol description among the figure:
Top mobile jib-1, buckle-2, size Control plate-3, bottom mobile jib-4, inserted link-5, slot-6, locator card-7, top trunk handle-8, inserted link handle-9.
The specific embodiment
Below in conjunction with accompanying drawing 1 and specific embodiment the utility model is elaborated.
A kind of reinforcing bar cage hoisting derrick rig in place of regulating of providing of the utility model comprises main body bar, buckle 2, size Control plate 3 as shown in Figure 1, it is characterized in that described main body bar is to be connected as one through buckle 2 by top mobile jib 1 and bottom mobile jib 4 to constitute; Size Control plate 3 is installed on the top mobile jib 1; 4 ends are welded with two parallel oval slots 6 under the mobile jib of bottom.
Described size Control plate 3 scale numerical value are vertically arranged along top mobile jib 1.
Mobile jib 1 top, described top is processed with a circular handle, and described circular handle and described top mobile jib 1 are one.
Spacing between described two parallel oval slots 6 is less than or equal to 0.5 meter.
A kind of reinforcing bar cage hoisting system in place that regulates, it is characterized in that, comprise derrick rig and inserted link 5 that described adjusting reinforcing bar cage hoisting is in place, there is an inserted link handle 9 on described inserted link 5 tops, and the position that upwards surpasses 0.5 meter of two parallel oval slot 6 spacing in the bottom is equipped with a locator card 7.
Described inserted link 5 length are at least greater than 1 meter of described main body pole length.
After described top mobile jib 1 and bottom mobile jib 4 overlapped well by described buckle 2, main body bar total length numerical value was certain when size Control plate 3 readings were zero.Adjust main body bar entire length by regulating top mobile jib 1 with varying sized control panel 3 readings of bottom mobile jib 4 lap length.
The technician has calculated the main body pole length according to reinforcing cage suspension centre to surface distance in the reinforcing bar cage hoisting process, utilizing calculated value to deduct regular length institute value in the time can regulating suspension rod top mobile jib 1 and be zero with bottom mobile jib 4 overlap joint size Control plates 3 readings is and can regulates the required increase length of main body bar, size Control plate 3 required demonstration numerical value just, regulate top mobile jib 1 and bottom mobile jib 4 lap length, with top mobile jib 1 and bottom mobile jib 4 two parts overlap joint card jail, the main body pole length is regulated to be and is finished with buckle 2.
Block reinforcing cage suspension rod zequin with bottom mobile jib 4 horizontal slot 6, inserted link 5 inserts in the slot 6, like this, two in place placements with the adjusting device symmetry operation of reinforcing bar cage hoisting can reach lifting requirements, and why two in place placements with the adjusting device symmetry operation of reinforcing bar cage hoisting are in order to prevent reinforcing cage placement inclination.

Claims (4)

1. regulate reinforcing bar cage hoisting derrick rig in place for one kind, comprise main body bar, buckle, size Control plate, it is characterized in that, described main body bar is to be connected as one through buckle by top mobile jib and bottom mobile jib to constitute; The size Control plate is installed on the mobile jib of top; Mobile jib lower end, bottom is welded with two parallel oval slots.
2. a kind of reinforcing bar cage hoisting derrick rig in place of regulating as claimed in claim 1, described size Control plate scale numerical value is vertically arranged along the top mobile jib.
3. a kind of reinforcing bar cage hoisting derrick rig in place of regulating as claimed in claim 2, mobile jib top, described top is processed with a circular handle, and described circular handle and described top mobile jib are one.
4. as claim 2 or 3 described a kind of reinforcing bar cage hoisting derrick rigs in place of regulating, the spacing between described two parallel oval slots is less than or equal to 0.5 meter.
CN 201120070183 2011-03-17 2011-03-17 Derrick rig for adjusting hoisting of reinforcing cage Expired - Fee Related CN202090338U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120070183 CN202090338U (en) 2011-03-17 2011-03-17 Derrick rig for adjusting hoisting of reinforcing cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120070183 CN202090338U (en) 2011-03-17 2011-03-17 Derrick rig for adjusting hoisting of reinforcing cage

Publications (1)

Publication Number Publication Date
CN202090338U true CN202090338U (en) 2011-12-28

Family

ID=45365415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120070183 Expired - Fee Related CN202090338U (en) 2011-03-17 2011-03-17 Derrick rig for adjusting hoisting of reinforcing cage

Country Status (1)

Country Link
CN (1) CN202090338U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612135A (en) * 2015-01-13 2015-05-13 成都聚智工业设计有限公司 Steel bar adjusting device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612135A (en) * 2015-01-13 2015-05-13 成都聚智工业设计有限公司 Steel bar adjusting device
CN104612135B (en) * 2015-01-13 2016-07-06 四川省第十五建筑有限公司 Reinforcing bar regulates device

Similar Documents

Publication Publication Date Title
CN103362119B (en) Large-size rebar cage exempt from the method that is welded to connect and syndeton
CN202299464U (en) Steel column rapid hoisting and in-position correcting device
CN102433841A (en) Method for installing abnormal-shape curve steel box girder
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
CN207294093U (en) A kind of large span steel truss integral lifting apparatus
CN106315389B (en) A kind of large scale prefabricated plate posture adjustment suspension bracket and its method
CN104032967B (en) Prefabricated assembled frame structure component construction method for hanging
CN207361649U (en) Large-scale vestibule steel structure hoisting instrument
CN103835511A (en) Integral lifting method for ultra-long light thin giant steel tube truss
CN203546728U (en) Improved installation fixing device of top-down steel pipe column
CN108842954A (en) A kind of huge different section Honeycomb Beam structural system construction method of installation of aerofoil profile roofing
CN203343650U (en) Positioning steel board for connecting large-diameter steel reinforcement cage
CN202090338U (en) Derrick rig for adjusting hoisting of reinforcing cage
CN205777412U (en) Roof flower is set a roof beam in place and exterior wall finishing construction mobile operating platform
CN102926554A (en) Steel hanging seat template supports and construction method thereof
CN107587770A (en) Disjunctor storehouse synchronization slding form operation method
CN104563525B (en) A kind of box steel arch beam Integral horizontal type group is to method
CN107881914B (en) Wire-dividing tube type cable saddle back field assembly type positioning device and assembly method
CN102383613B (en) Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device
CN205476528U (en) Precast pile device of taking one's place fast
CN201826438U (en) Steel column convenient for constructing temporary operating platform
CN204689525U (en) A kind of equipment jacking apparatus being convenient to measure
CN204825655U (en) Arc case roof beam lifts by crane focus off -centre and installation leveling system that takes one's place
CN204531180U (en) Control the stiff skeleton of large-scale component reinforcing bar binding precision
CN207633330U (en) Filling pile cage of reinforcement absolute altitude and verticality control device under a kind of concrete water

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111228

Termination date: 20200317

CF01 Termination of patent right due to non-payment of annual fee