CN207844890U - A kind of hoisting fixture for building curtain wall - Google Patents

A kind of hoisting fixture for building curtain wall Download PDF

Info

Publication number
CN207844890U
CN207844890U CN201820087836.3U CN201820087836U CN207844890U CN 207844890 U CN207844890 U CN 207844890U CN 201820087836 U CN201820087836 U CN 201820087836U CN 207844890 U CN207844890 U CN 207844890U
Authority
CN
China
Prior art keywords
arm
fixed
hoisting fixture
wire rope
steel wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820087836.3U
Other languages
Chinese (zh)
Inventor
徐建平
李标
顾洪潮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Shunjiang Construction Engineering Group Co Ltd
Original Assignee
Zhejiang Shunjiang Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Shunjiang Construction Engineering Group Co Ltd filed Critical Zhejiang Shunjiang Construction Engineering Group Co Ltd
Priority to CN201820087836.3U priority Critical patent/CN207844890U/en
Application granted granted Critical
Publication of CN207844890U publication Critical patent/CN207844890U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a kind of hoisting fixture for building curtain wall, which includes that master chooses arm, walking track, oblique pull steel wire rope and electric block;The main rear end for choosing arm is fixed on by turning over girder steel on structure longitudinal beam, and the main front end for choosing arm is fixed by U-shaped anchor ear;Walking track is spliced in main choose on arm by several segmented tracks;One end of oblique pull steel wire rope is chosen arm with master and is connect, and the other end is fixed on positioned at the main steel wire rope fixed point for choosing arm last layer;Electric block is placed on walking track.Hoisting fixture scheme provided by the utility model can be good at being suitable for the lifting of inclined-plane cell cube, ensure construction efficiency and construction quality.

Description

A kind of hoisting fixture for building curtain wall
Technical field
The utility model is related to building curtain walls, and in particular to the Hoisting Program of building curtain wall.
Background technology
Building curtain wall refers to the exterior wall encirclement of building not load-bearing, usually by panel (glass, metallic plate, slabstone, ceramics Plate etc.) and subsequent supporting structure (aluminium cross beam and upright post, steel construction, Glass Rib etc.) composition.Specially can have one with respect to main body Determine displacement capacity or itself has certain deformability, do not undertake agent structure institute building external revetment the affected or decorative knot Structure.
Existing curtain wall construction tooling is all vertical surface generally directed to wall alien invasion, and can not well adapt to tilt outer Facade causes to tilt alien invasion curtain wall construction difficulty, influences construction speed and quality.
It can be seen that provide it is a kind of can be suitable for tilting the arrangement and method for construction of alien invasion curtain wall, with improve construction efficiency with The problem of quality is this field urgent need to resolve.
Utility model content
For the problems of existing curtain wall construction scheme, a kind of new curtain wall construction scheme is needed.
For this purpose, problem to be solved in the utility model is to provide a kind of hoisting fixture for building curtain wall, to overcome The problems of prior art.
To solve the above-mentioned problems, the hoisting fixture provided by the utility model for building curtain wall, the hoisting fixture Arm, walking track, oblique pull steel wire rope and electric block are chosen including main;
The rear end that the master chooses arm is fixed on by turning over girder steel on structure longitudinal beam, and the front end that the master chooses arm passes through U Type anchor ear is fixed;
The walking track is spliced in main choose on arm by several segmented tracks;
One end of the oblique pull steel wire rope is chosen arm with master and is connect, and the other end is fixed on positioned at the main steel wire rope for choosing arm last layer Fixed point;
The electric block is placed on walking track.
Further, the master chooses arm and is made of I-steel.
Further, it is described turn over girder steel use I-steel, arrange with structure longitudinal beam vertical direction and use anchor ear and Longitudinal beam is fixed.
Further, the walking track is made of I-steel.
Further, the U-shaped anchor ear is fixed by slot type embedded part and T-bolt.
Further, the U-shaped anchor ear is utilized and is fixed with structure to wearing bolt.
Further, the spacing that the master chooses arm and adjacent master chooses between arm is not more than 2 meters.
Further, the other end of the oblique pull steel wire rope is fixed on steel wire rope fixed point by U-shaped buckle.
Hoisting fixture scheme provided by the utility model can be good at being suitable for the lifting of inclined-plane cell cube, ensure construction effect Rate and construction quality.
Furthermore the simple and reliable property of this hoisting fixture scheme entirety composed structure, it is convenient to carry out.
Description of the drawings
The utility model is further illustrated below in conjunction with the drawings and specific embodiments.
Fig. 1 is the structural schematic diagram of hoisting fixture in this example;
Fig. 2 is the fixed structure schematic diagram that girder steel is turned in this example;
Fig. 3 is the fixed structure schematic diagram that arm front end is chosen in this example;
Fig. 4 is the fixed structure schematic diagram that arm rear end is chosen in this example;
Fig. 5 is the attachment structure schematic diagram that arm and track are chosen in this example.
Specific implementation mode
In order to make the technical means, creative features, achievement of purpose, and effectiveness of the utility model be easy to understand, under Face combines and is specifically illustrating, and the utility model is expanded on further.
For this example by taking a high-rise building as an example, three high building alien invasions of whole building are that stone material is modular and glass unit Formula cross occurrence, local location are pure glass unit body.
Accordingly, this example is lifted for vertical surface cell cube using roofing track;Room is utilized for inclined-plane cell cube The 5T hoist engines that face frame is set sling cell cube from ground lifting area, and the circular orbit by being erected at roofing hangs (5T) by unit Body level, which is operated to inclined-plane partial orbit, joins position, cell cube is changed to part-annular track hangs (5T) and carry out secondary water again Flat operating, operating to installation site carry out integral installation.
This example approach in the specific implementation, sets up part-annular track and hangs, as hoisting fixture, for inclined-plane unit Body is lifted.
Three tower local unit body ceiling mounted tracks can be divided into two kinds of forms in this example:A, structural facades are vertical, under plane It is upper small greatly;B, structural facades tilt, small big under plane.
Referring to Fig. 1, the part-annular track in this example hangs 100 and mainly chooses arm 110, walking track 120, oblique rollering steel by main Cord 130 and the corresponding cooperation of electric block 140 are constituted.
Wherein, the main rear end for choosing arm 110 is fixed on by turning over girder steel 150 on structure longitudinal beam, and before master chooses arm 110 End is fixed by U-shaped anchor ear 160;
Walking track 120 is spliced in main choose on arm by several segmented tracks;
One end of oblique pull steel wire rope 130 is connect with the main otic placode 111 for choosing arm front end, and the other end, which is fixed on, to be chosen positioned at master on arm One layer of steel wire rope fixed point 170.
Electric block 140 is placed on walking track 120.
In the specific implementation, the master during the part-annular track added is hung chooses the selection 20#a I-steel of arm 100, row to this programme It walks track 120 and selects 25#a I-steel, material Q235.Oblique pull steel wire rope 130 selects the steel wire rope of diameter 20.Electric block 140 select model HHBB05-02, the electric block of loading 5T (the unit plate weight of lifting is not more than 3T).
The track of such structure is installed by following erection sequence.
1) main to choose the processing of arm fracture:According to floor plan and live practical structures measurement result carry out blank, drilling and The welding of steel wire rope steel part is socketed, choosing arm to every and being numbered prevents wrongly installed position;
2) the fracture processing of track:It is moved back in successively based on structure and carries out cooperation lifting without tower crane, this example is by track root It is segmented according to structure type, every section of splicing position should avoid choosing arm stage casing at two and be spliced close to choosing arm position;
3) the main installation for choosing arm:
1. the arm of choosing processed is promoted to installation floor by roofing hoist engine, pass through hand-hydraulic handlebar in floor Master chooses arm and is transported to installation position;
2. referring to Fig. 2, this example is used as using 20#a I-steel and turns over girder steel 150, with structure longitudinal beam vertical direction cloth It sets and is fixed with longitudinal beam with anchor ear 151, for fixing main overhanging arm rear end.Here anchor ear by two groups of reinforcing bars with nut and Steel plate is constituted.
In addition, when structure longitudinal direction girder steel spacing is more than 6 meters, 25#a I-steel need to be used to be used as and turn over girder steel.
3. will socket 130 one end of steel wire rope by flower basket bolt and it is U-shaped buckle to be fixed on choose on arm otic placode 111, the other end is logical It crosses U-shaped button and is fixed on last layer steel wire rope fixed point.It is reversely pulled by bottle gouard moved by hands and master is chosen into arm pushing-out structure edge extremely Designed distance;
4. referring to Fig. 3, fixed point and structure fixation before arm 110, U-shaped armful of front end main will be chosen with the U-shaped anchor ear of arm 160 is chosen Hoop is fixed using slot type embedded part and T-bolt structure 161 as far as possible, and anchor ear is utilized to wearing if it can not utilize slot type embedded part Bolt is fixed with structure.
Referring to Fig. 4, the main rear end fixed point for choosing arm 110 is fixed on step, and 2. mounted 20#a is embraced on beam I-steel, main Choose 150 company of being fixed of 20#a I-steel that the rear end of arm 110 turns over girder steel by the steel plate connector 180 of 12mm thickness and being used as It connects.
5. step installs other and chooses arm using above-mentioned 1., 2., 3., 4..First use cushion block 190 by the pre- height in front end when choosing arm installation 20mm (referring to Fig. 3) takes out cushion block, to eliminate the elasticity of steel wire rope again after steel wire rope tension.The installation level for choosing arm is missed Difference is not more than ± 5mm, while it is also noted that choose distance and angle between arm, avoids not installing when track installation;It chooses arm and chooses Arm spacing is not more than 2 meters, and specific spacing is adjusted according to slot type embedded part lattice.It chooses arm and chooses structural edge inclined-plane and be up to 1.8 meters, vertical surface needs to be adjusted according to lifting, is not more than 1.8 meters.
4) installation of track
1. the track 120 of segmentation to be transported to the next layer for choosing arm installation floor by building hoist, and pass through manual liquid Delay unloading and is transported to installation position;
2. facing side operation when track installation for high-altitude, safety steel cable should be first set up, installation personnel ties up to safety belt It constructs again on safety steel cable.Track 120 is carried by being erected at the small-sized gun carriage for choosing arm floor and bottle gouard moved by hands cooperation It rises to and chooses arm position 110, fastened using anchor ear and bolt arrangement, easy to disassemble and recycling (as shown in Figure 5).
It by track and chooses arm paragraph by paragraph 3. repeating above-mentioned 1,2 steps and is attached completion;
4. splicing seams are corrected and are polished after the completion of track splicing, make stitching error control in the permission of walking dolly In range;Track both ends end carries out end socket processing using 12mm steel plates.
5. electric block is installed;
5) inspection and test running of track
1. inspection is each bolted whether position fastens, socket whether steel wire rope is tightened, the buckle of steel wire rope checks ring Whether in place;
2. the stitching portion bolt inspection of track, track with choose bolt that arm is connect and whether pressing plate secured;
3. carrying out zero load, static load, dynamic load test run to track, cell cube lifting is carried out after detecting track integral installation quality;
(2) part-annular track hangs dismounting
The dismounting mode of track is identical as mounting means, only carries out contrary operation,
1) electric block is removed;
2) track is removed by small-sized gun carriage and bottle gouard moved by hands paragraph by paragraph and transported to next position to be installed;
3) it loosens and chooses arm anchor ear, arm will be chosen by bottle gouard moved by hands be pulled in structure and remove and socket steel wire rope, be transported to roofing Hoist engine lifting position will choose arm and be promoted to next installation position;
4) track installation material is fully transferred to carry out track again according to track installation mode after next installation floor Secondary installation;
1) track has enough to meet the need mode:In order to ensure the unit construction period, select to install in same position difference floor in this example Two sets of tracks remove track after first set track crane installs unit, and second set of track is enabled after dismounting ensures cell cube It is smoothed out lifting, the material of first of track is installed to third road track position when not lifting this face cell cube.So Being used alternatingly can be reduced because track erection is influenced.
2) inspection of complete rotation track:There are many rapid wears to build when track installation, should be checked emphatically when having enough to meet the need installation, Especially fastening bolt, briquetting and steel wire rope etc., when purchasing track installation material more than a collection of acknowledgment copy of buying be replaced, really The installation quality of track and safety when protecting turnover installation.
Basic principles, main features, and advantages of the present invention has been shown and described above.One's own profession The technical staff of industry is it should be appreciated that the present utility model is not limited to the above embodiments, described in above embodiments and description Only illustrate the principles of the present invention, on the premise of not departing from the spirit and scope of the utility model, the utility model is also It will have various changes and improvements, these various changes and improvements fall within the scope of the claimed invention.The utility model Claimed range is defined by the appending claims and its equivalent thereof.

Claims (8)

1. the hoisting fixture for building curtain wall, which is characterized in that the hoisting fixture includes that master chooses arm, walking track, oblique pull Steel wire rope and electric block;
The rear end that the master chooses arm is fixed on by turning over girder steel on structure longitudinal beam, and the master chooses the front end of arm by U-shaped armful Hoop is fixed;
The walking track is spliced in main choose on arm by several segmented tracks;
One end of the oblique pull steel wire rope is chosen arm with master and is connect, and the other end is fixed on to be fixed positioned at the main steel wire rope for choosing arm last layer Point;
The electric block is placed on walking track.
2. hoisting fixture according to claim 1, which is characterized in that the master chooses arm and is made of I-steel.
3. hoisting fixture according to claim 1, which is characterized in that the girder steel that turns over uses I-steel, with structure Longitudinal beam vertical direction is arranged and is fixed with anchor ear and longitudinal beam.
4. hoisting fixture according to claim 1, which is characterized in that the walking track is made of I-steel.
5. hoisting fixture according to claim 1, which is characterized in that the U-shaped anchor ear passes through slot type embedded part and T-bolt It is fixed.
6. hoisting fixture according to claim 1, which is characterized in that the U-shaped anchor ear utilizes solid with structure to wearing bolt It is fixed.
7. hoisting fixture according to claim 1, which is characterized in that the master chooses arm and adjacent master chooses the spacing between arm No more than 2 meters.
8. hoisting fixture according to claim 1, which is characterized in that the other end of the oblique pull steel wire rope is buckled by U-shaped It is fixed on steel wire rope fixed point.
CN201820087836.3U 2018-01-18 2018-01-18 A kind of hoisting fixture for building curtain wall Expired - Fee Related CN207844890U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820087836.3U CN207844890U (en) 2018-01-18 2018-01-18 A kind of hoisting fixture for building curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820087836.3U CN207844890U (en) 2018-01-18 2018-01-18 A kind of hoisting fixture for building curtain wall

Publications (1)

Publication Number Publication Date
CN207844890U true CN207844890U (en) 2018-09-11

Family

ID=63415279

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820087836.3U Expired - Fee Related CN207844890U (en) 2018-01-18 2018-01-18 A kind of hoisting fixture for building curtain wall

Country Status (1)

Country Link
CN (1) CN207844890U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184055A (en) * 2018-10-24 2019-01-11 何容顺 Type unitized curtain wall mounting structure and method
CN111646364A (en) * 2020-04-27 2020-09-11 上海建工二建集团有限公司 Monorail crane attached to overhanging structural slab and application construction method thereof
CN113044709A (en) * 2021-03-09 2021-06-29 中电建建筑集团有限公司 Hoisting tool for glass curtain wall with special-shaped cornice structure
CN114057101A (en) * 2021-12-01 2022-02-18 中国十七冶集团有限公司 Horizontal transportation device and horizontal transportation method for curtain wall unit elements
CN114348864A (en) * 2021-04-21 2022-04-15 广东省第二建筑工程有限公司 Cantilever type double-rail double-column steel hanger for unitized curtain wall

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184055A (en) * 2018-10-24 2019-01-11 何容顺 Type unitized curtain wall mounting structure and method
CN111646364A (en) * 2020-04-27 2020-09-11 上海建工二建集团有限公司 Monorail crane attached to overhanging structural slab and application construction method thereof
CN111646364B (en) * 2020-04-27 2023-08-08 上海建工二建集团有限公司 Monorail crane attached to overhanging structural plate and application and construction method thereof
CN113044709A (en) * 2021-03-09 2021-06-29 中电建建筑集团有限公司 Hoisting tool for glass curtain wall with special-shaped cornice structure
CN114348864A (en) * 2021-04-21 2022-04-15 广东省第二建筑工程有限公司 Cantilever type double-rail double-column steel hanger for unitized curtain wall
CN114057101A (en) * 2021-12-01 2022-02-18 中国十七冶集团有限公司 Horizontal transportation device and horizontal transportation method for curtain wall unit elements

Similar Documents

Publication Publication Date Title
CN207844890U (en) A kind of hoisting fixture for building curtain wall
CN206053285U (en) A kind of modular assembly of high-altitude overlength is encorbelmented steel platform
CN107558723B (en) Method for manufacturing and installing hanging bracket of hanging basket for inclined roof
CN103086279B (en) Vertical transportation construction method for building construction
CN108915272A (en) A kind of inclined-plane cell cube hanging method
CN104032967B (en) Prefabricated assembled frame structure component construction method for hanging
CN102425261B (en) Large-span multiunit tensile membrane structure and installation construction method thereof
CN205772984U (en) A kind of hanging apparatus of monolithic steel truss
CN102337782B (en) Lift system for constructing truss platform on top of tall and large space
CN106760841A (en) A kind of construction method of buckling restrained brace structure
CN206616184U (en) Coke oven loss flue dust dust gathering arrester supporting construction
CN109881585A (en) A kind of assembly flow shop platform for high pier construction
CN110080794A (en) A kind of present low gas tunnel large-diameter shield fission is gone into the well construction method
CN116136122A (en) Integrated attached type inclined lifting climbing frame system and use method thereof
CN202214974U (en) 5.8 m ultrahigh external climbing frame
CN210828372U (en) Lifting and mounting integrated ALC partition board mounting machine
CN217028004U (en) Annular hanging basket suspension device for curtain wall construction of super high-rise building
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN108560510A (en) Surface low road movable overhaul platform in a kind of power station
CN109267500A (en) Bridge maintaining lift truss work platform
CN102182324A (en) Anti-falling safety net
CN205654127U (en) Portable operation protective platform of assembly type structure stairwell
CN109594697B (en) Construction method and structure of super high-rise built-in unit glass curtain wall
CN102733644B (en) Super-altitude roof super-long antenna hoisting construction method and system
CN113668401B (en) Hoisting process based on installation and transportation platform on long-span bridge pier

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180911

Termination date: 20220118