- CN207714509U CN207714509U CN201721873563.7U CN201721873563U CN207714509U CN 207714509 U CN207714509 U CN 207714509U CN 201721873563 U CN201721873563 U CN 201721873563U CN 207714509 U CN207714509 U CN 207714509U
- Authority
- CN
- China
- Prior art keywords
- piping lane
- pedestal
- cover board
- sealing strip
- built
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 20
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 44
- 238000007789 sealing Methods 0.000 claims abstract description 35
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 20
- 239000010959 steel Substances 0.000 claims abstract description 20
- 238000009434 installation Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 235000017166 Bambusa arundinacea Nutrition 0.000 description 2
- 235000017491 Bambusa tulda Nutrition 0.000 description 2
- 241001330002 Bambuseae Species 0.000 description 2
- 235000015334 Phyllostachys viridis Nutrition 0.000 description 2
- 239000011425 bamboo Substances 0.000 description 2
- 239000011449 brick Substances 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Landscapes
- Building Environments (AREA)
Abstract
The utility model provides a kind of fast construction piping lane building, belong to building field, its scheme be include pedestal, be mounted on the base and center is in multiple the first piping lanes being vertically arranged on same circumference, first piping lane carries prefabricated doors and windows, multiple first piping lanes are evenly distributed with and surround a built-in space, one first cover board is set above first piping lane, the top of the open top and built-in space of first cover closure, first piping lane, what the pedestal was connect with the first piping lane offers first annular slot, the first sealing strip built in the first annular slot on one side;What first cover board was connect with the first piping lane opens up the second annular groove on one side, second sealing strip built in second annular groove, the first sealing strip, the second sealing strip are distinguished in the both ends of first piping lane, and the pedestal is fixed by L-type steel with the first piping lane, the first cover board and the first piping lane.Fast construction is realized by using piping lane to building field, while ensureing the leakproofness of building by sealing strip.
Description
Technical field
The utility model is related to building field, more particularly to fast construction piping lane is built.
Background technology
Current building construction mostly uses concreting or uses brick structure.Concrete construction or brick and tile building
The disadvantage is that weight is big, the production cycle is long.
To improve aforesaid way, has light steel house at present, structure such as notification number is similar disclosed in CN2599094Y.
The utility model proposes a kind of new schemes to realize fast construction.
Utility model content
The purpose of this utility model is to provide a kind of fast construction piping lane building, simple in structure.
The above-mentioned technical purpose of the utility model technical scheme is that:A kind of fast construction piping lane
Building, including pedestal, be mounted on the base and center be in multiple the first piping lanes being vertically arranged on same circumference, first manages
Corridor has a prefabricated doors and windows, and multiple first piping lanes are evenly distributed with and surround a built-in space, setting 1 the above first piping lane
One cover board, the top of the open top and built-in space of first piping lane of the first cover closure, the pedestal and the first piping lane
Connection offers first annular slot, the first sealing strip built in the first annular slot on one side;First cover board and the first pipe
Corridor connection opens up the second annular groove, the second sealing strip built in second annular groove, the both ends point of first piping lane on one side
Other first sealing strip, the second sealing strip, the pedestal are fixed by L-type steel with the first piping lane, the first cover board and the first piping lane.
First piping lane is bamboo winding piping lane, light-weight, facilitates lifting;First piping lane is inserted into first annular slot,
The first piping lane is fixed with pedestal by L-type steel, squeezing the first sealing strip by the gravity of the first piping lane realizes the first piping lane bottom
Sealing between portion and pedestal, later will in the first cover plate lid by the first cover board gravity make the second sealing strip be extruded to
It realizes the sealing between the first cover board at the top of the first piping lane, is fixed the first piping lane and the first cover board by L-type steel.
Further, the cross section of first piping lane is rectangle, and it is recessed that the bottom of the first annular slot opens up one first
Slot, the groove width of first groove are more than the thickness of the first piping lane, and first sealing strip is located in the first groove and both sides are prolonged
It extends in first annular slot, the first sealing strip upwardly extends to form first ring of abutting close to one end of first annular slot madial wall
The connecting section of shape slot madial wall, the connecting section are provided only on the adjacent madial wall of two of which of first annular slot.
In this way, when the first piping lane of installation, first the first piping lane is inserted into first annular slot so that the first piping lane is wherein
Two adjacent madial walls abut connecting section respectively, and the first sealing strip is located at first annular slot in straightened condition at first
It is interior, it is pressurized later so that the first sealing strip is absorbed in the first groove and both sides extend in first annular slot, due to the first groove
Groove width be more than the thickness of the first piping lane, therefore it can the dimensional fits that bring by mismachining tolerance of adjustment appropriate.This mode,
First ensure the leakproofness on the first piping lane wherein both sides, then the contact between the first sealing strip is increased by the first sealing strip indent
Area increases the leakproofness on other both sides, so that it is guaranteed that the leakproofness between the first piping lane bottom and pedestal.
Further, one end horizontal extension of the connecting section far from the first sealing strip is formed and the fixed connection of pedestal
Section.
In this way, due to the presence of linkage section, when the first piping lane declines, L-shaped sealing strip is abutted with slot inner side edge
It is not easy to be detached from pedestal on one side.
Further, two neighboring first piping lane is connected by connecting plate, and the both ends of connecting plate abut pedestal and the first lid
Plate, the connecting plate are connect by bolt with the first piping lane.
On the one hand connecting plate plays a part of to support the first cover board, on the other hand close the side of built-in space, inside empty
Between can be used as parlor.
Further, the support column of the first cover board of support is further fixed on the pedestal.
On the one hand support column can play a supporting role, on the other hand can also carve on the support columns etc. and to play decoration effect
Fruit.
Further, the second piping lane being vertically arranged, second piping lane and the first pipe are installed on first cover board
The axis of corridor is uniformly distributed on the same circumference.
In this way, being more uniformly stressed for the first cover board, is conducive to extend the first cover board service life.
Further, the caliber of first piping lane is more than the caliber of the second piping lane.
When transport, the first piping lane can be sleeved on outside the second piping lane, convenience in transport.
Further, it is fixed with column under the pedestal.
The setting of column is adapted to different landform, does not change original landforms.
In conclusion the utility model has the advantages that:1)The piping lane building of this programme design is suitable for various
Landform is built quickly, convenience in transport;2)It is assembled using produced piping lane, increases living space, increased space is mainly used as
Hall and garden;3)Using high-order ground(3.5 meters -5 meters)Mode is built, and can not change former land status, or be suitable for it
His complicated landform;4)Solar power generation and hot water apparatus can be installed at the top of second cover board;5)Bamboo trunk corridor building meets green ring
It protects, it is economical and practical, convenient requirement is built, it can be with standardized set at construction.
Description of the drawings
Fig. 1 is the structural schematic diagram of embodiment;
Fig. 2 is the structural schematic diagram hidden after the first cover board above section;
Fig. 3 is the first piping lane and pedestal, the connection structure sectional view of the first cover board;
Fig. 4 is the portions the A enlarged drawing of Fig. 3;
Fig. 5 is the portions the B enlarged drawing of Fig. 3;
Fig. 6 is the portions the C enlarged drawing of Fig. 3;
Fig. 7 is the distribution schematic diagram of support column in the first piping lane and the second piping lane in embodiment 2.
Reference numeral:1, pedestal;11, first annular slot;12, the first groove;13, the first sealing strip;14, connecting section;15、
Linkage section;2, the first piping lane;21, prefabricated doors and windows;3, column;4, built-in space;51, angle steel;52, connecting plate;53, mounting bar;
54, positioning column;6, the first cover board;61, the second annular groove;62, the second groove;63, the second sealing strip;7, L-type steel;81, second
Piping lane;82, the second cover board;9, support column.
Specific implementation mode
The utility model is described in further detail below in conjunction with attached drawing.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability
Field technique personnel can as needed make the present embodiment the modification of not creative contribution after reading this specification, but
As long as all being protected by Patent Law in the right of the utility model.
Embodiment 1:A kind of fast construction piping lane building, such as Fig. 1-2, including pedestal 1, be mounted on pedestal 1 and at center
It is rectangle in the cross section of the first piping lane 2 that four on same circumference are vertically arranged, the first piping lane 2 and carries prefabricated doors and windows
21.1 bottom of pedestal is fixed with multiple columns 3, and four the first piping lane 2 intervals surround a built-in space 4, each first piping lane 2
Both sides have been bolted angle steel 51, and the first adjacent piping lane 2 is sealed by connecting plate 52, and connecting plate 52 is same by bolt
When connect angle steel 51 on adjacent first piping lane 2, the bottom of connecting plate 52 abuts 1 upper surface of pedestal.It is welded on each connecting plate 52
It connects a mounting bar 53 and extends convergence one cross of formation to centre, a cylindrical positioning column 54 is fixed at the center of cross.
If the bottom of Fig. 4, the first piping lane 2 are connect by first annular slot 11 with pedestal 1, first annular slot 11 is opened in
On pedestal 1, the bottom of first annular slot 11 opens up one first groove 12, and the groove width of the first groove 12 is more than the thickness of the first piping lane 2
Degree, the first sealing strip 13 is located in the first groove 12 and both sides extend in first annular slot 11.Such as Fig. 5, the first sealing strip 13
The connecting section 14 to form first annular 11 madial wall of slot of an abutting is upwardly extended close to one end of 11 madial wall of first annular slot, is supported
It connects section 14 to be provided only on the adjacent madial wall of two of which of first annular slot 11, connecting section 14 is far from the first sealing strip 13
One end horizontal extension is formed and 1 fixed linkage section 15 of pedestal.
If the top of Fig. 6, the first piping lane 2 are connect by the second annular groove 61 with the first cover board 6, in the second annular groove 61
The second groove 62 is equally offered, the second annular groove 61 is built-in with the second sealing strip 63, and form is identical as the first sealing strip 13.
First cover board, 6 bottom opens up a location hole to match with positioning column 54, to facilitate the installation of the first cover board 6.
If the top of Fig. 1, the first piping lane 2 are fixed by L-type steel 7 and the first cover board 6, two spiral shells are at least fixed in L-type steel 7
Bolt is separately connected L-type steel 7 and the first cover board 6 and L-type steel 7 and 2 top of the first piping lane;The bottom of first piping lane 2 passes through L-type steel
7 fix with pedestal 1, and two bolts are at least fixed in L-type steel 7 and are separately connected L-type steel 7 and pedestal 1 and the pipe of L-type steel 7 and first
2 bottom of corridor.
Such as Fig. 1, the second piping lane 81 being vertically arranged, 81 outer diameter of the second piping lane and the first pipe are further fixed on the first cover board 6
2 internal diameter of corridor is identical, and the two structure is identical to carry prefabricated doors and windows 21.Second piping lane 81 is equally vertically arranged four and the second piping lane
81 and first piping lane 2 axis it is uniformly distributed on the same circumference, the second piping lane 81 is located at the top of connecting plate 52.Second piping lane 81 is same
Sample surrounds a built-in space 4, while the second piping lane 81 is connected also by connecting plate 52, and form is identical as the first piping lane 2.Second
Piping lane 81 is connect with the first piping lane 2 with the connection type of pedestal 1 with the first cover board 6;Second piping lane, 81 top is provided with the second lid
Plate 82, the second cover board 82 and the connection type of the second piping lane 81 and the first cover board 6 are identical as the connection type of the first piping lane 2.
As Fig. 1 is fixed with support column 9, the top of support column 9 to promote the compressive property of the first piping lane 2 on pedestal 1
It is abutted with 6 bottom of the first cover board, support column 9 is located at the edges and corners outside the first piping lane 2.
Pedestal 1, the first cover board 6, the peripheral of the second cover board 82 can install guardrail.The top of second cover board 82 can install too
Positive energy plate, water heater etc..Wherein L-shaped steel 7 is mounted on corner as far as possible when installation, facilitates opening for prefabricated doors and windows 21
If only illustrating in figure.
When installation, column 3, mounting seat 1 are first poured, then L-type steel 7 will be passed through in the lifting to pedestal 1 of the first piping lane 2
It is fixed, then the first cover board 6, the second piping lane 81 and the second cover board 82 are installed successively.
Embodiment 2:A kind of fast construction piping lane building, with embodiment 1 difference lies in:As shown in fig. 7, wherein X is bottom
Support column 9 between seat 1 and the first cover board 6, support columns 9 of the S between the first cover board 6 and the second cover board 82.
Claims (8)
1. a kind of fast construction piping lane building, it is characterised in that:Including pedestal (1), it is mounted on pedestal (1) and center is in same
Multiple the first piping lanes (2) being vertically arranged on one circumference, the first piping lane (2) carry prefabricated doors and windows (21), multiple described first
Piping lane (2) is uniformly distributed and surrounds a built-in space (4), one first cover board (6) of setting above first piping lane (2), and described first
Cover board (6) closes the top of the open top and built-in space (4) of the first piping lane (2), the pedestal (1) and the first piping lane (2)
Connection offers first annular slot (11), the first sealing strip (13) built in the first annular slot (11) on one side;Described first
What cover board (6) was connect with the first piping lane (2) opens up the second annular groove (61) on one side, and second is close built in second annular groove (61)
The first sealing strip (13), the second sealing strip (63) are distinguished in strip of paper used for sealing (63), the both ends of first piping lane (2), the pedestal (1) with
First piping lane (2), the first cover board (6) are fixed by L-type steel (7) with the first piping lane (2).
2. fast construction piping lane building according to claim 1, it is characterized in that:The cross section of first piping lane (2) is
Rectangle, the bottom of the first annular slot (11) open up one first groove (12), and the groove width of first groove (12) is more than the
The thickness of one piping lane (2), first sealing strip (13) is located in the first groove (12) and both sides extend to first annular slot
(11) in, the first sealing strip (13) upwardly extends that form an abutting first annular close to one end of first annular slot (11) madial wall
The connecting section (14) of slot (11) madial wall, the two of which that the connecting section (14) is provided only on first annular slot (11) are adjacent
On madial wall.
3. fast construction piping lane building according to claim 2, it is characterized in that:The connecting section (14) is far from the first sealing
One end horizontal extension of item (13) is formed and pedestal (1) fixed linkage section (15).
4. fast construction piping lane building according to claim 1, it is characterized in that:Two neighboring first piping lane (2) passes through company
Fishplate bar (52) connects, and the both ends of connecting plate (52) abut pedestal (1) and the first cover board (6), the connecting plate (52) pass through bolt
It is connect with the first piping lane (2).
5. fast construction piping lane building according to claim 1, it is characterized in that:It is further fixed on support on the pedestal (1)
The support column (9) of first cover board (6).
6. fast construction piping lane building according to claim 1, it is characterized in that:It is equipped on first cover board (6) perpendicular
The second piping lane (81) being directly arranged, second piping lane (81) and the axis of the first piping lane (2) are uniformly distributed on the same circumference.
7. fast construction piping lane building according to claim 6, it is characterized in that:The caliber of first piping lane (2) is more than
The caliber of second piping lane (81).
8. fast construction piping lane building according to claim 1, it is characterized in that:It is fixed with column under the pedestal (1)
(3)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721873563.7U CN207714509U (en) | 2017-12-27 | 2017-12-27 | Fast construction piping lane is built |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721873563.7U CN207714509U (en) | 2017-12-27 | 2017-12-27 | Fast construction piping lane is built |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207714509U true CN207714509U (en) | 2018-08-10 |
Family
ID=63050855
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721873563.7U Expired - Fee Related CN207714509U (en) | 2017-12-27 | 2017-12-27 | Fast construction piping lane is built |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207714509U (en) |
-
2017
- 2017-12-27 CN CN201721873563.7U patent/CN207714509U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2010043091A1 (en) | A container-type mobile house with a drainage system | |
CN204059594U (en) | A kind of hemispheric prefabricated house | |
CN106480977A (en) | Passive type house | |
TWM441686U (en) | Inter-connectably assembled pre-fabricated modular building | |
CN201474087U (en) | Improved arched house structure capable of repeatedly producing for nomadic people | |
CN207714509U (en) | Fast construction piping lane is built | |
CN104005474B (en) | A kind of method and die house of being constructed house by inflating die | |
CN103850439B (en) | A kind of modularized house construction method | |
CN104863392B (en) | A kind of Assembled type movable sentry box and its fast method for preparing | |
CN106912322A (en) | Half reassembling type rear wall of greenhouse | |
CN105696812A (en) | Thermal insulation fireproof removable house | |
CN203742233U (en) | Nondestructive roof communication tower | |
CN206245784U (en) | A kind of light-duty assembled island accommodation | |
CN215802536U (en) | Novel hyperboloid curtain skeleton | |
CN205776751U (en) | A kind of multi-functional dome room | |
CN214628480U (en) | Assembled heat preservation big-arch shelter | |
JP5054217B2 (en) | Concrete container house | |
CN203113514U (en) | Combined split-mounting-type house device | |
CN202787496U (en) | Mussel-like low greenhouse framework structure | |
CN205421533U (en) | Building energy conservation house framework | |
CN102823457B (en) | Clam-simulated pressure-resistant low-rise greenhouse framework and construction method | |
CN207829166U (en) | Piping lane is built | |
CN208763180U (en) | A kind of water scenery structure under limited loading condition | |
CN110206192B (en) | Rammed earth wall body entrance to a cave lintel | |
CN207549071U (en) | Winter and summer dual-purpose type curing means of roof beam district precast beam is deposited in construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180810 |