CN207616874U - A kind of water channel corner prefabricated-member mould - Google Patents

A kind of water channel corner prefabricated-member mould Download PDF

Info

Publication number
CN207616874U
CN207616874U CN201721055018.7U CN201721055018U CN207616874U CN 207616874 U CN207616874 U CN 207616874U CN 201721055018 U CN201721055018 U CN 201721055018U CN 207616874 U CN207616874 U CN 207616874U
Authority
CN
China
Prior art keywords
die cavity
mould
reinforcement
side wall
water channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721055018.7U
Other languages
Chinese (zh)
Inventor
潘春光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201721055018.7U priority Critical patent/CN207616874U/en
Application granted granted Critical
Publication of CN207616874U publication Critical patent/CN207616874U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a kind of water channel corner prefabricated-member mould, the mold includes end cap mould, side wall mould, die cavity, reinforcement constitution and die cap plate;The side wall mould is secured by bolts on die cavity, and the inclined angle of side wall mould corresponds to the angle of inclination of die cavity side wall;Reinforcement constitution is cased on the die cavity, and the die cavity top surface is equipped with die cap plate, the both ends of the die cavity are fixed with end cap mould.The utility model can quickly produce prefabricated component in enormous quantities, and obtained preform structure is secured, and anti-extrusion ability is strong, and power conductibility is good, and construction efficiency can be greatly improved, and effectively shorten the construction period, install the features such as quick.

Description

A kind of water channel corner prefabricated-member mould
Technical field
The utility model is related to a kind of hydraulic engineering fields, and in particular to a kind of water channel corner prefabricated-member mould.
Background technology
Water channel is irrigation and water conservancy, traffic, municipal administration, sewage, the main tool of fillings row's engineering such as rainy day draining, and concrete The U-shaped gool mold of soil is one of the main tool for producing gool.
With greatly developing for China's modern agriculture and water resource infrastructure, agricultural and water conservancy basis are built in country and place If scale of investment it is increasing.China is one to the relatively backward country of agricultural technology, vast in territory, water resource assignment ten Divide unevenness, especially to west area, the water resource of drug in some provinces is very in short supply.At the same time, due to filling row's mode and material It is unreasonable, great lot of water resources is not utilized and is protected well, is had become in China's agriculture project and water conservancy construction The inefficient serious problems utilized of water resource.Over more than 20 years, precast concrete gool(Referred to as U-shaped gool)It is special in China each province and city It is promoted and applied in the agricultural water conservancy project for not being western water resources area in short supply, has obtained the abundant of various regions agricultural and hydraulic department Certainly, significant economic benefit and social benefit are achieved.
Through retrieve the Chinese patent literature in relation to water channel corner prefabricated component also there are many, it is as follows:
1, Chinese patent<Application number> 200620034095.X<Utility model title>Concrete prefabricated groove<Applicant> Fan Yuncong<Address>Jie Bei sections of development zone Pingshan, Deyang City the Yellow River, Sichuan Province(In the bureau of agriculture of Jingyang District)<Abstract>The utility model It is related to a kind of concrete prefabricated groove for farmland water channel, the groove is by the prefabricated components that a pair of of cross-sectional shape is " L " shape Opposite arrangement combinations form a "u"-shaped groove, and bottom of different size can be added between the mating surface of the component of two " L " shapes Plate constitutes the different groove water channel of various circulatioies, has positioning spigot in the mating surface of each component.
2, Chinese patent<Application number> 201520717706.X<Utility model title>A kind of novel prefabricated water channel<Application People>Deng Zenghua<Address>Ganzhou City of Jiangxi Province Shicheng County agricultural development office<Abstract>A kind of novel prefabricated water channel, is related to one Facility, especially a kind of novel prefabricated water channel, including U-lag is transformed in kind rural water conservancy, and the upper edge of U-lag is equipped with road deck;Its It is characterized in:Often section U-lag end is equipped with water stopping trough, and two save U-lag junction bar connectings, then in the water stopping trough at U-lag end With novel water-stop rubber filling, sealing effect is played.
3, Chinese patent<Application number> 201020113216.6<Utility model title>Anti-deformation combined penstock<Application People>Tian Shucheng<Address>7 buildings west gates of house west wing Unit 1 in Samples, Huadian, Jilin Province city three<Abstract>The utility model is related to water conservancy works Journey technical field, be it is a kind of be widely used in that agricultural irrigation, traffic municipal administration be defeated, Anti-deformation combined penstock of drainage system, it is special Putting is:It includes several blocks of canal plates, is tightly connected by sealing connecting strip and fluid sealant at the docking of adjacent canal plate, canal plate with It is equipped with convex edge below canal plate at canal plate docking, is in contact by the convex edge at its docking at the docking of vertical or horizontal canal plate Flat recess consolidate block and the connecting screw that is placed in sealing connecting strip is connected;It is right by its at the docking of vertical and horizontal canal plate The cross recess that the convex edge at the place of connecing is in contact consolidates block and the connecting screw being placed in sealing connecting strip is connected.
4, Chinese patent<Application number> 201520000756.6<Utility model title>A kind of prefabricated drainage ditch pours into Pattern has<Applicant>Jiangxi technical college<Address>Nanchang City, Jiangxi Province Qingshanhu District precious jade lake garden in university<Abstract>This practicality Novel to disclose a kind of casting mold of prefabricated drainage ditch, including trolley, external mold and internal model, external mold is in concave, and internal model is in U Type, drainage ditch take shape in the cavity between external mold and internal model.
The shortcomings of the prior art has:1, the process of construction period it is long, it is of high cost, need artificial more, the construction period Between easily influenced by weather, need to excavate larger construction place, be more easily damaged, not easy care, cannot reuse, tear open Except fairly cumbersome, original Land Environment of destructible etc.;2, water channel gool is easy by earth pressure crimp or damage, both pole The big service life for influencing beam slot, and a larger increase cost input, waste of resource;3, when water channel gool installation docking, at docking Poor sealing is easy leak, causes water source that could not access maximum utilization;4, it is more to make water channel corner prefabricated component process, It is too cumbersome when modulus, labour and working time are greatly wasted, work efficiency is low.
Invention content
The purpose of this utility model be in view of the drawbacks of the prior art, provide one kind can quickly it is large batch of production it is prefabricated Part, obtained prefabricated component can meet mechanized construction, and construction efficiency, larger shortening engineering construction duration, knot can be greatly improved Structure is firm, and anti-extrusion deformation is strong, convenient for disassembly and assembly, can reuse, and Butt sealing is good, and appearance is neat, and streamline is beautiful, installation Quickly, convenient water channel corner prefabricated-member mould is removed.
In order to realize aforementioned present invention purpose, the technical solution used for:
A kind of water channel corner prefabricated-member mould, the mold include end cap mould, side wall mould, die cavity, die cap plate and reinforcing bar Construction;The side wall mould is secured by bolts on die cavity, and the inclined angle of side wall mould corresponds to the inclination angle of die cavity side wall Degree;Reinforcement constitution is cased on the die cavity, and the die cavity top surface is equipped with die cap plate, the both ends of the die cavity are fixed with end Cover mold.
The reinforcement constitution includes second layer distributing bar, first layer distributing bar, reinforcement distributing bar and longitudinal reinforcement, The second layer distributing bar, first layer distributing bar and reinforcement distributing bar connect and compose unit member, first layer construction steel Second layer distributing bar is sandwiched in centre by muscle and reinforcement distributing bar, several unit members connect into reinforcing bar by longitudinal reinforcement Construction.
The die cavity is using steel plate bending or is stamped to form, and edge is supported using angle steel or channel steel.
It is set at the top of the die cavity there are two convenient for removing the symmetrical chamfering of mud, the chamfering is 45 ° or 60 °.
The die cavity is equipped with two pieces of symmetrical side walls, and the angle of the side wall and bottom surface is 95 ° -98 °;The side Lifting hole(eyelet) is additionally provided on wall.
The end cap mould is equipped with boss, and the boss forms docking groove with die cavity at the place of docking.
The substantive distinguishing features and progress that the utility model has compared with the existing technology:
1, the prefabricated component obtained by the utility model can meet mechanized construction, and construction efficiency, larger contracting can be greatly improved Casual labourer's journey construction period, firm in structure, anti-extrusion deformation is strong, convenient for disassembly and assembly, can reuse, and Butt sealing is good, appearance Neatly, streamline is beautiful, and installation is quick, and it is convenient to remove.
2, the water channel corner prefabricated component appearance that the utility model is produced is neat, forms water channel, can be so that water channel is whole Appearance is neat, carefully and neatly done beautiful, and when mounted, work efficiency improves 7 times or more than common construction method, and the construction period shorten to 80~ 90%。
3, materials needed for the utility model production are few, can save cast-in-place concrete investment 12~35%, larger to reduce cost Input, can generate great economic interests.
4, the mold that the utility model produces and uses, the production is simple and convenient, and assembling is quick, and process simplifies, modulus, demoulding Fast and easy;And it is cased with reinforcement component in a mold, it is firm to build the beam slot preform structure being molded as in this way, resistance to compression and tension energy Power is strong;Reinforcement frame is made of two-layer structure reinforcing bar, reinforcement distributing bar and lateral stressed reinforcing bar, whole uniform force, and power passes The property led is good.
5, the prefabricated component energy Fast Installation obtained by the utility model, changes the direction of a stream of water;Water is drained to different ground Side.
6, there is docking groove at the prefabricated component port obtained by the utility model, concrete is filled up in docking groove, it can pole The big loss for reducing water flow, substantially increases water use efficiency;Because there is docking groove at docking, between the prefabricated components of two docking There is gap, is not connected as one all, this gap is prefabricated component because the variable that expanded by heating or pre- cold events occur carries Space has been supplied, prefabricated component is protected.
7, reinforcement constitution described in the utility model includes second layer distributing bar, first layer distributing bar, reinforcement construction steel Muscle and longitudinal reinforcement, the second layer distributing bar, first layer distributing bar and reinforcement distributing bar connect and compose unit member, Second layer distributing bar is sandwiched in centre by first layer distributing bar and reinforcement distributing bar, several unit members pass through longitudinal steel Muscle connects into reinforcement constitution.This reinforcement constitution design is special, can ensure that water channel prefabricated component is sturdy and durable, compared with existing water Several times of canal Quality advance or more, can be through under pressure indeformable.
Description of the drawings
Fig. 1 is a kind of dimensional structure diagram of water channel corner prefabricated-member mould of the utility model.
Fig. 2 is the dimensional structure diagram of water channel corner prefabricated component.
Fig. 3 is the dimensional structure diagram of die cavity.
Fig. 4 is the structural schematic diagram of end cap mould.
Fig. 5 is the dimensional structure diagram of reinforcement constitution.
Fig. 6 is the cross section structure schematic diagram of reinforcement constitution.
Element title and serial number in figure:End cap mould 1, side wall mould 2, die cavity 3, die cap plate 4, bolt 5, docking groove 6, lifting hole(eyelet) 7, boss 8, bolt hole 9, reinforcement distributing bar 10, first layer distributing bar 11, second layer distributing bar 12, longitudinal reinforcement 13.
It does not put on reinforcement constitution in Fig. 1 on die cavity, in order to see the structure in mold after combining clearly, therefore first omits reinforcing bar structure It makes.
Specific implementation mode
The utility model is further described in conjunction with the embodiments of the present invention.
Embodiment 1:
Shown in Fig. 1 to 6, a kind of water channel corner prefabricated-member mould, the mold include end cap mould 1, side wall mould 2, Die cavity 3, die cap plate 4 and reinforcement constitution;The side wall mould 2 is secured by bolts on die cavity 3,2 inclined angle of side wall mould Corresponding to the angle of inclination of 3 side wall of die cavity;Reinforcement constitution is cased on the die cavity 3,3 top surface of die cavity is equipped with die cap plate 4, The both ends of the die cavity 3 are fixed with end cap mould 1.
The reinforcement constitution includes second layer distributing bar 12, first layer distributing bar 11, reinforcement distributing bar 10 and indulges To reinforcing bar 13, the second layer distributing bar 12, first layer distributing bar 11 and reinforcement distributing bar 10 connect and compose unit structure Second layer distributing bar 12 is sandwiched in centre by part, first layer distributing bar 11 with reinforcement distributing bar 10, several unit members Reinforcement constitution is connected by longitudinal reinforcement 13.
The die cavity 3 is using steel plate bending or is stamped to form, and edge is supported using angle steel or channel steel.
3 top of die cavity is set there are two convenient for removing the symmetrical chamfering of mud, and the chamfering is 45 °.
The die cavity 3 is equipped with two pieces of symmetrical side walls, and the angle of the side wall and bottom surface is 95 °;The side wall On be additionally provided with lifting hole(eyelet) 7;The lifting hole(eyelet) 7 can facilitate water channel corner prefabricated component to hang die cavity 3 and provided for Fast Installation good Good condition.
The end cap mould 1 is equipped with boss, and the boss forms docking groove 6,6 phase of docking groove with die cavity 3 at the place of docking It is low to the water flowing bottom of water channel beam slot corner prefabricated component;When two docking grooves 6 dock, abut each other smooth, and they Between again can be reserved with enough spaces for filling up concrete, the gap at docking is filled up using concrete, leakproofness Good, sound construction greatly reduces the loss of water, can make full use of water resource.
The processing step that the utility model produces water channel corner prefabricated component is as follows:
(1)Mold inversion is put in plane, and mold bottom upward, and is uniformly coated on die inside on mould oil or pad Plastic film;
(2)Die cavity is fixed, upper side wall mould is covered, the end cap mould at both ends is installed, is put into the reinforcing bar of enhancing water channel corner intensity Component, and reinforcement component is fixed, it is placed on die cavity;The reinforcement component is equipped with two layers of distribution bar in bottom, and uses Pulling force rib connection is integral, and the distribution bar of reinforcement component both ends distribution is closeer;Take two layers of arrangement reinforcing bar, Ji Nengzeng The structural capacity of strong reinforcement component, and the intensity and anti-pressure ability of water channel corner prefabricated component can be enhanced;
(3)Field fabrication pours required concrete;Concrete is poured among mold bottom toward both ends, stirring is equal It is even, and made firm by ramming using the vibrating head of vibrator, it makes firm by ramming 1-3 minutes, bubble is discharged, so that concrete compaction is combined, then to mould Have notch upper surface and carries out troweling;The die cap plate of closed die;
(4)Water channel corner prefabricated component scene maintenance after casting concrete, maintenance were collapsible die after 2~3 days, were then collected again In to carrying out watering maintenance 6-10 days on vacant lot.
Embodiment 2:
Shown in Fig. 1 to 6, a kind of water channel corner prefabricated-member mould, the mold include end cap mould 1, side wall mould 2, Die cavity 3, reinforcement constitution and die cap plate 4;The side wall mould 2 is secured by bolts on die cavity 3,2 inclined angle of side wall mould Corresponding to the angle of inclination of 3 side wall of die cavity;3 top surface of die cavity is equipped with die cap plate 4, and reinforcement constitution is cased on the die cavity 3, And the both ends of the die cavity 3 are fixed with end cap mould 1.
The reinforcement constitution includes second layer distributing bar 12, first layer distributing bar 11, reinforcement distributing bar 10 and indulges To reinforcing bar 13, the second layer distributing bar 12, first layer distributing bar 11 and reinforcement distributing bar 10 connect and compose unit structure Second layer distributing bar 12 is sandwiched in centre by part, first layer distributing bar 11 with reinforcement distributing bar 10, several unit members Reinforcement constitution is connected by longitudinal reinforcement 13.
The die cavity 3 is using steel plate bending or is stamped to form, and edge is supported using angle steel or channel steel.
3 top of die cavity is set there are two convenient for removing the symmetrical chamfering of mud, and the chamfering is 60 °.
The die cavity 3 is equipped with two pieces of symmetrical side walls, and the angle of the side wall and bottom surface is 96 °;The side wall On be additionally provided with lifting hole(eyelet) 7;The lifting hole(eyelet) 7 can facilitate water channel corner prefabricated component to hang die cavity 3 and provided for Fast Installation good Good condition.
The end cap mould 1 is equipped with boss, and the boss forms docking groove 6,6 phase of docking groove with die cavity 3 at the place of docking It is low to the water flowing bottom of water channel beam slot corner prefabricated component;When two docking grooves 6 dock, abut each other smooth, and they Between again can be reserved with enough spaces for filling up concrete, the gap at docking is filled up using concrete, leakproofness Good, sound construction greatly reduces the loss of water, can make full use of water resource.
The processing step that the utility model produces water channel corner prefabricated component is as follows:
(1)Mold inversion is put in plane, and mold bottom upward, and is uniformly coated on die inside on mould oil or pad Plastic film;
(2)Die cavity is fixed, upper side wall mould is covered, the end cap mould at both ends is installed, is put into the reinforcing bar of enhancing water channel corner intensity Component, and reinforcement component is fixed, it is placed on die cavity;The reinforcement component is equipped with two layers of distribution bar in bottom, and uses Pulling force rib connection is integral, and the distribution bar of reinforcement component both ends distribution is closeer;Take two layers of arrangement reinforcing bar, Ji Nengzeng The structural capacity of strong reinforcement component, and the intensity and anti-pressure ability of water channel corner prefabricated component can be enhanced;
(3)Field fabrication pours required concrete;Concrete is poured among mold bottom toward both ends, stirring is equal It is even, and made firm by ramming using the vibrating head of vibrator, it makes firm by ramming 1-3 minutes, bubble is discharged, so that concrete compaction is combined, then to mould Have notch upper surface and carries out troweling;The die cap plate of closed die;
(4)Water channel corner prefabricated component scene maintenance after casting concrete, maintenance were collapsible die after 2~3 days, were then collected again In to carrying out watering maintenance 6-10 days on vacant lot.
Embodiment 3:
Shown in Fig. 1 to 6, a kind of water channel corner prefabricated-member mould, the mold include end cap mould 1, side wall mould 2, Die cavity 3, reinforcement constitution and die cap plate 4;The side wall mould 2 is secured by bolts on die cavity 3,2 inclined angle of side wall mould Corresponding to the angle of inclination of 3 side wall of die cavity;Reinforcement constitution is cased on the die cavity 3, and 3 top surface of die cavity is equipped with die cap plate 4, the both ends of the die cavity 3 are fixed with end cap mould 1.
The reinforcement constitution includes second layer distributing bar 12, first layer distributing bar 11, reinforcement distributing bar 10 and indulges To reinforcing bar 13, the second layer distributing bar 12, first layer distributing bar 11 and reinforcement distributing bar 10 connect and compose unit structure Second layer distributing bar 12 is sandwiched in centre by part, first layer distributing bar 11 with reinforcement distributing bar 10, several unit members Reinforcement constitution is connected by longitudinal reinforcement 13.
The die cavity 3 is using steel plate bending or is stamped to form, and edge is supported using angle steel or channel steel.
3 top of die cavity is set there are two convenient for removing the symmetrical chamfering of mud, and the chamfering is 45 °.
The die cavity 3 is equipped with two pieces of symmetrical side walls, and the angle of the side wall and bottom surface is 98 °;The side wall On be additionally provided with lifting hole(eyelet) 7;The lifting hole(eyelet) 7 can facilitate water channel corner prefabricated component to hang die cavity 3 and provided for Fast Installation good Good condition.
The end cap mould 1 is equipped with boss, and the boss forms docking groove 6,6 phase of docking groove with die cavity 3 at the place of docking It is low to the water flowing bottom of water channel beam slot corner prefabricated component;When two docking grooves 6 dock, abut each other smooth, and they Between again can be reserved with enough spaces for filling up concrete, the gap at docking is filled up using concrete, leakproofness Good, sound construction greatly reduces the loss of water, can make full use of water resource.
The processing step that the utility model produces water channel corner prefabricated component is as follows:
(1)Mold inversion is put in plane, and mold bottom upward, and is uniformly coated on die inside on mould oil or pad Plastic film;
(2)Die cavity is fixed, upper side wall mould is covered, the end cap mould at both ends is installed, is put into enhancing water channel corner prefabricated component intensity Reinforcement constitution, and fix reinforcement constitution, be placed on die cavity;The reinforcement component is equipped with two layers of distribution bar in bottom, And the distribution bar that integral, described reinforcement component both ends distribution is connected using pulling force rib is closeer;Two layers of arrangement reinforcing bar is taken, Can reinforcing steel bar component structural capacity and enhance the intensity and anti-pressure ability of water channel corner prefabricated component;
(3)Field fabrication pours required concrete;Concrete is poured among mold bottom toward both ends, stirring is equal It is even, and made firm by ramming using the vibrating head of vibrator, it makes firm by ramming 1-3 minutes, bubble is discharged, so that concrete compaction is combined, then to mould Have notch upper surface and carries out troweling;The die cap plate of closed die;
(4)Water channel corner prefabricated component scene maintenance after casting concrete, maintenance were collapsible die after 2~3 days, were then collected again In to carrying out watering maintenance 6-10 days on vacant lot.

Claims (6)

1. a kind of water channel corner prefabricated-member mould, it is characterised in that:The mold includes end cap mould(1), side wall mould(2), mould Chamber(3), die cap plate(4)And reinforcement constitution;The side wall mould(2)Pass through bolt(5)It is fixed on die cavity(3)On, side wall mould(2) Inclined angle corresponds to die cavity(3)The angle of inclination of side wall;The die cavity(3)On be cased with reinforcement constitution, and the die cavity (3)Top surface is equipped with die cap plate(4), the die cavity(3)Both ends be fixed with end cap mould(1).
2. water channel corner prefabricated-member mould according to claim 1, it is characterised in that:The reinforcement constitution includes the second layer Distributing bar(12), first layer distributing bar(11), reinforcement distributing bar(10)And longitudinal reinforcement(13), the second layer construction Reinforcing bar(12), first layer distributing bar(11)With reinforcement distributing bar(10)Connect and compose unit member, first layer distributing bar (11)With reinforcement distributing bar(10)By second layer distributing bar(12)It is sandwiched in centre, several unit members pass through longitudinal reinforcement (13)Connect into reinforcement constitution.
3. water channel corner prefabricated-member mould according to claim 1, it is characterised in that:The die cavity(3)Using steel plate Bending is stamped to form, and edge is supported using angle steel or channel steel.
4. water channel corner prefabricated-member mould according to claim 1, it is characterised in that:The die cavity(3)Top is equipped with Two symmetrical chamferings convenient for removing mud, the chamfering are 45 ° or 60 °.
5. water channel corner prefabricated-member mould according to claim 1, it is characterised in that:The die cavity(3)Equipped with two pieces The angle of symmetrical side wall, the side wall and bottom surface is 95 ° -98 °;It is additionally provided with lifting hole(eyelet) on the side wall(7).
6. water channel corner prefabricated-member mould according to claim 1, it is characterised in that:The end cap mould(1)Equipped with convex Platform, the boss and die cavity(3)Docking groove is formed at docking(6).
CN201721055018.7U 2017-08-22 2017-08-22 A kind of water channel corner prefabricated-member mould Expired - Fee Related CN207616874U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721055018.7U CN207616874U (en) 2017-08-22 2017-08-22 A kind of water channel corner prefabricated-member mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721055018.7U CN207616874U (en) 2017-08-22 2017-08-22 A kind of water channel corner prefabricated-member mould

Publications (1)

Publication Number Publication Date
CN207616874U true CN207616874U (en) 2018-07-17

Family

ID=62818950

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721055018.7U Expired - Fee Related CN207616874U (en) 2017-08-22 2017-08-22 A kind of water channel corner prefabricated-member mould

Country Status (1)

Country Link
CN (1) CN207616874U (en)

Similar Documents

Publication Publication Date Title
CN109826084A (en) A kind of aqueduct method for repairing seepage
CN113136845A (en) Migration type ecological fishway and construction method
CN207327274U (en) A kind of water channel engineering system
CN113931035A (en) Assembly type curb rainwater collecting system and construction method thereof
CN107486940A (en) A kind of water channel is passed by one&#39;s way the production method of prefabricated component
CN207310188U (en) A kind of water channel gool prefabricated-member mould
CN207310186U (en) A kind of water channel gool side leads to prefabricated-member mould
CN207616874U (en) A kind of water channel corner prefabricated-member mould
CN107443548A (en) A kind of production method of water channel gool prefabricated component
CN107471424A (en) A kind of water channel engineering system and construction method
CN207327245U (en) A kind of water channel is passed by one&#39;s way prefabricated-member mould
CN107471404A (en) A kind of water channel gool side leads to the production method of prefabricated component
CN207616875U (en) A kind of retaining wall prefabricated-member mould
CN107471425A (en) A kind of production method of water channel threeway prefabricated component
CN113107007A (en) One-time pouring forming construction method for pipe gallery
CN207944436U (en) A kind of novel full assembled field culverts and water gates
CN110303576A (en) A kind of grout filling plastic mould inlet for stom water
CN207904936U (en) Hinge type ecological revetment block
CN107471426A (en) A kind of production method of water channel corner prefabricated component
CN205501994U (en) All steel sleeve pipe dado bored concrete pile of high bearing capacity
CN214061096U (en) Concrete water permeable brick with construction waste as aggregate
CN214497575U (en) Assembled river surge retaining wall
CN216295298U (en) Circular arc hexagonal prism filter core and mould of permeating water
CN107443567A (en) A kind of production method of retaining wall prefabricated component
CN220450801U (en) Farmland drainage concrete ditch structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180717