CN107443548A - A kind of production method of water channel gool prefabricated component - Google Patents

A kind of production method of water channel gool prefabricated component Download PDF

Info

Publication number
CN107443548A
CN107443548A CN201710726692.1A CN201710726692A CN107443548A CN 107443548 A CN107443548 A CN 107443548A CN 201710726692 A CN201710726692 A CN 201710726692A CN 107443548 A CN107443548 A CN 107443548A
Authority
CN
China
Prior art keywords
prefabricated component
water channel
mould
concrete
die cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710726692.1A
Other languages
Chinese (zh)
Inventor
潘春光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710726692.1A priority Critical patent/CN107443548A/en
Publication of CN107443548A publication Critical patent/CN107443548A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/22Moulds for making units for prefabricated buildings, i.e. units each comprising an important section of at least two limiting planes of a room or space, e.g. cells; Moulds for making prefabricated stair units
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/093Producing shaped prefabricated articles from the material by vibrating or jolting by means directly acting on the material, e.g. by cores wholly or partly immersed in the material or elements acting on the upper surface of the material
    • B28B1/0935Producing shaped prefabricated articles from the material by vibrating or jolting by means directly acting on the material, e.g. by cores wholly or partly immersed in the material or elements acting on the upper surface of the material using only elements wholly or partly immersed in the material, e.g. cores
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/38Treating surfaces of moulds, cores, or mandrels to prevent sticking

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of production method of water channel gool prefabricated component, comprise the following steps:(1)Make and be inverted and put with the mould needed for water channel prefabricated component same shape, mould, mold bottom is upward;(2)On die inside on even application mould oil or pad on plastic sheeting;(3)The framework of steel reinforcement made is inserted in and poured in mould, and adjusts the protective layer of concrete;(4)Field fabrication pours required concrete;Concrete is poured among mold bottom, uniformly divided to both ends, then is vibrated 1~3 minute with vibrator, then to mould upper surface troweling;Closed die cover plate;(5)Water channel prefabricated component after casting concrete conserves at the scene, and temperature tears side mould open after being more than 500h DEG C during maintenance, form removal chamber after temperature is more than 1500h DEG C during watering maintenance, and prefabricated component concentrates stacking after form removal chamber, during maintenance temperature up to more than 2000h DEG C when dispatch from the factory use.The features such as efficiency of construction can be greatly improved in the present invention.

Description

A kind of production method of water channel gool prefabricated component
Technical field
The present invention relates to a kind of hydraulic engineering field, and in particular to a kind of production method of water channel gool prefabricated component.
Background technology
Water channel is the main tool of the filling such as irrigation and water conservancy, traffic, municipal administration, sewage, rainy day draining row's engineering, and concrete The U-shaped gool mould of soil is one of main tool for producing gool.
With greatly developing for China's modern agriculture and water resource infrastructure, country and place are built to agricultural and water conservancy basis If scale of investment it is increasing.China is one to the relatively backward country of agricultural technology, vast in territory, water resource assignment ten Divide inequality, it is particularly very in short supply to west area, the water resource of drug in some provinces.At the same time, due to filling row's mode and material It is unreasonable, great lot of water resources is not utilized and protected well, is had become in China's agriculture project and water conservancy construction The poorly efficient serious problems utilized of water resource.Over more than 20 years, precast concrete gool(Referred to as U-shaped gool)It is special in China each province and city It is not popularization and application in western water resources regional agricultural water conservancy project in short supply, it is agriculture abundant with hydraulic department has obtained various regions Certainly, significant economic benefit and social benefit are achieved.
Also there is many through retrieving the Chinese patent literature about water channel gool prefabricated component, it is as follows:
1st, Chinese patent<Application number> 200620034095.X<Utility model title>Concrete prefabricated groove<Applicant>Fan Yun It is clever<Address>Development zone Pingshan, Deyang City the Yellow River, Sichuan Province Jie Bei sections(In the bureau of agriculture of Jingyang District)<Summary>It the utility model is related to A kind of concrete prefabricated groove for farmland water channel, the groove by a pair of shape of cross sections be " L " shape prefabricated components it is opposite Arrangement combinations form a "u"-shaped groove, and the different bottom plate of width, structure can be set up between the mating surface of the component of two " L " shapes The groove water channel different into various circulatioies, there is positioning spigot in the mating surface of each component.
2nd, Chinese patent<Application number> 201520717706.X<Utility model title>A kind of new prefabricated water channel<Application People>Deng Zenghua<Address>Ganzhou City of Jiangxi Province Shicheng County agricultural development office<Summary>A kind of new prefabricated water channel, is related to one Kind rural water conservancy transformation facility, especially a kind of new prefabricated water channel, including U-lag, the upper edge of U-lag are provided with road deck;Its It is characterized in:Often save U-lag end and be provided with water stopping trough, two save U-lag junction bar connectings, then in the water stopping trough at U-lag end With novel water-stop rubber filling, sealing effect is played.
3rd, Chinese patent<Application number> 201020113216.6<Utility model title>Anti-deformation combined penstock<Application People>Tian Shucheng<Address>7 buildings west gates of house west wing Unit 1 in Samples, Huadian, Jilin Province city three<Summary>It the utility model is related to water conservancy work Journey technical field, be it is a kind of be widely used in that agricultural irrigation, traffic municipal administration be defeated, Anti-deformation combined penstock of drainage system, it is special Putting is:It includes some blocks of canal plates, and the joint of adjacent canal plate is connected by sealing connecting strip with sealant sealing, canal plate with Convex edge is equipped with below the canal plate of canal plate joint, the joint of vertical or horizontal canal plate is in contact by the convex edge of its joint Flat recess consolidate block and the connecting screw that is placed in sealing connecting strip is connected;The joint of vertical and horizontal canal plate is right by its The connecting screw that the cross recess that the convex edge at the place of connecing is in contact consolidates block and is placed in sealing connecting strip is connected.
4th, Chinese patent<Application number> 201520000756.6<Utility model title>A kind of prefabricated drainage ditch pours into Pattern has<Applicant>Jiangxi technical college<Address>Nanchang City, Jiangxi Province Qingshanhu District precious jade lake garden in university<Summary>It is practical new Type discloses a kind of casting mold of prefabricated drainage ditch, including dolly, external mold and die cavity, and external mold is in matrix, and die cavity is in U Type, drainage ditch are taken shape in the cavity between external mold and die cavity.
The shortcomings of the prior art has:1st, the process of construction cycle is long, cost is high, needs artificial more, the construction period Between easily influenceed, it is necessary to excavate larger construction place, to be more easily damaged, not easy care, it is impossible to reuse, tear open by weather Except fairly cumbersome, original Land Environment of destructible etc.;2nd, water channel gool is easily by earth pressure crimp or damage, both pole The big service life for influenceing beam groove, and a larger increase cost input, waste of resource;3rd, during water channel gool installation docking, joint Sealing is poor, easy leak, causes water source to access maximum utilization;4th, it is more to make water channel gool prefabricated component process, It is too cumbersome during modulus, labour and working time are greatly wasted, work efficiency is low.
Applicant it is hereby stated that:We are an enterprises for researching and producing water conservancy irrigation canals and ditches cement prefab, are in the past few years being ground To study carefully and be made that many products in terms of developing water conservancy irrigation canals and ditches cement prefab, the product having at present has already passed through experiment and examined, Will put goods on the market, the several patent application documents that have applied on the same day are all our own scientific achievements, the present invention with《It is a kind of The production method of retaining wall prefabricated component》、《A kind of water channel engineering system and construction method》、《A kind of water channel is passed by one's way the life of prefabricated component Production method》、《A kind of water channel gool side leads to the production method of prefabricated component》、《A kind of production method of water channel threeway prefabricated component》、《One The production method of kind water channel corner prefabricated component》Process structure have similar part, but be our series of products, apply for a patent Purpose be for our series of products of protection, rather than for other purposes.
The content of the invention
The purpose of the present invention is the defects of being directed to prior art, there is provided one kind can meet mechanized construction, can be greatly improved Efficiency of construction, the larger shortening engineering construction duration, firm in structure, anti-extrusion deformation is strong, convenient disassembly, can reuse, right Good airproof performance is connect, appearance is neat, and streamline is attractive in appearance, and installation is quick, removes the production method of convenient water channel gool prefabricated component.
In order to realize the invention described above purpose, the technical scheme used for:
A kind of production method of water channel gool prefabricated component, described method comprise the following steps:
(1)Make and be inverted and put with the mould needed for water channel prefabricated component same shape, mould, mold bottom upward, pours from bottom Build concrete;
(2)On die inside on even application mould oil or pad on plastic sheeting;
(3)The framework of steel reinforcement made is inserted in and poured in mould, and adjusts the protective layer of concrete, described framework of steel reinforcement Trough rim by inside and outside stressing conditions configuration principal rod, bottom land is by upper and lower stressing conditions configuration principal rod, by the reinforcing bar of configuration point Then solution is welded into unit member, several unit members is welded to connect with longitudinal reinforcement to be formed into the shape that can be processed The framework of steel reinforcement of gool, the both ends distribution unit component on framework of steel reinforcement is closeer, and intermediate distribution unit member is sparse and uniform;
(4)Field fabrication pours required concrete;Concrete is poured among mold bottom, uniformly divided to both ends, then Vibrated, vibrated 1~3 minute using direct insertion vibrator, discharged the bubble in concrete, combine concrete compaction, then to mould Have notch upper surface and carry out troweling;Closed die cover plate;
(5)Water channel prefabricated component after casting concrete conserves at the scene, removable side mould after temperature is more than 500h DEG C during maintenance, As remove drive end bearing bracket, upper cover plate, rear end cap and sidewall paneling;Removable die cavity after temperature is more than 1500h DEG C during watering maintenance, tears open Prefabricated component, which is concentrated, after die cavity stacks, during maintenance temperature up to more than 2000h DEG C when can dispatch from the factory use.
Temperature is time × outdoor temperature when above-described, and the chronomere is hour, and time numerical value takes >=16 Positive integer, i.e. time add up and value >=16, time numerical value can use the numerical value such as 16,17,18,19,20,21,22,23,24;It is described Outdoor temperature unit for degree Celsius, outdoor temperature >=20 DEG C;Outdoor temperature is monitored in real time, it is every to carry out once every other hour Calculate, then all values are added up, in maintenance processes, the value of temperature is cumulative more than 500h DEG C when will be all, so that it may tears open Die cap plate, side wall mould, the end cap mould of mould;In maintenance processes of sprinkling water, the value of temperature is cumulative when will be all is more than 1500h DEG C, so that it may remove die cavity, prefabricated component concentrates stacking after form removal chamber;Continue to conserve, the value of temperature is tired out when will be all Value added to reach 2000h DEG C, prefabricated component can is dispatched from the factory use, during calculating, the numerical value in each stage, is not counted in the numerical value of next stage It is interior.
Above-described mould includes drive end bearing bracket, upper cover plate, die cavity, rear end cap, sidewall paneling and framework of steel reinforcement;Before described End cap, rear end cap correspond to the front and rear end for being installed on die cavity respectively, and are fixed using bolt;Framework of steel reinforcement, mould are cased with die cavity Chamber both sides are provided with symmetrical two pieces of sidewall panelings, and are fixed using bolt;The inclined angle of sidewall paneling corresponds to the inclination of die cavity Angle, and sidewall paneling is fixed on die cavity using bolt;Upper cover plate is placed on die cavity;The framework of steel reinforcement includes second layer structure Make reinforcing bar, first layer distributing bar, reinforcement distributing bar and longitudinal reinforcement, the second layer distributing bar, first layer construction steel Muscle connects and composes unit member, first layer distributing bar and reinforcement distributing bar by second layer distributing bar with reinforcement distributing bar Centre is sandwiched in, several unit members connect into framework of steel reinforcement by longitudinal reinforcement.
Above-described die cavity is using steel plate bending or is stamped to form, and its internal and edge is propped up using angle steel or channel-section steel Support.
Two symmetrical chamferings are provided with the top of above-described die cavity so that water channel gool prefabricated component groove madial wall and bottom Chamfering is formed, is easy to remove mud.
Above-described drive end bearing bracket, rear end cap are provided with boss, and described boss is the model of docking groove.
Above-described die cavity is provided with two pieces of symmetrical side walls, and the angle of described side wall and vertical plane is 5 °~8 °;Mould Chamber is provided with corresponding through hole with sidewall paneling, two through holes using cylinder connect, when pour, form removal after, cylinder institute It is lifting hole(eyelet) to locate the straight-through through hole that position is formed.
Above-described concrete includes the raw material of following parts by weight:60~70 parts of coarse-fine aggregate, 425~525 silicic acid 10~20 parts of salt cement, 5~10 parts of flyash, 5~10 parts of Iron-ore Slag micro mist, 1~3 part of high efficiency water reducing agent, described efficiently subtracts Aqua is that alcohol effluent dry powder adds the weight ratio of sulfoacid calcium water reducer to be 1:1.
Above-described coarse-fine aggregate is river sand and the mixture of limestone or granite particle, river sand and limestone or flower The weight ratio of hilllock rock particle is 1:1~1.5;The modulus of fineness of the river sand is 2.2~3.0, and the limestone or granite are broken Material diameter is 5~15mm.
It by sulfite liquor is raw material that above-described sulfoacid calcium water reducer preparation method, which is, adds sodium hydroxide PH value is adjusted to 8~10, is passed through after air reacts 10~12h at 70~80 DEG C and adds potassium sulfate, reacted at 70~80 DEG C 40~50min, filtering, sulfoacid calcium water reducer is produced after drying.
The product that the production method of above-described water channel gool prefabricated component obtains water conservancy construction, municipal drainage system or Purposes in terms of highway bridge and culvert.
The protrusion substantive distinguishing features and significant progress that the present invention has relative to prior art:
1st, the present invention can meet mechanized construction, efficiency of construction can be greatly improved, the larger shortening engineering construction duration, structure is hard Gu anti-extrusion deformation is strong, convenient disassembly, it can reuse, Butt sealing is good, and appearance is neat, and streamline is attractive in appearance, and installation is fast Speed, it is convenient to remove.
2nd, the water channel gool prefabricated component appearance that the present invention produces is neat, forms water channel, can cause water channel entirety appearance Neatly, carefully and neatly done attractive in appearance, when mounted, work efficiency improves more than 7 times than common construction method, and the construction period shorten to 80~90%.
3rd, materials needed for present invention production are few, can save cast-in-place concrete investment 12~35%, larger to reduce cost throwing Enter, great economic interests can be produced.
4th, the mould of production and application of the present invention, its making is simple and convenient, and assembling is quick, and process simplifies, and modulus, is convenient in demoulding Quickly;And reinforcement component is cased with a mold, it is firm so to build the beam groove preform structure being molded as, resistance to compression and tensile capacity By force;Reinforcement frame is made up of two-layer structure reinforcing bar, reinforcement distributing bar and lateral stressed reinforcing bar, overall uniform force, power conduction Property is good.
5th, the present invention reduces cement consumption, it is pre- to increase substantially concrete gool using Iron-ore Slag micro mist as admixture The intensity of product, effectively suppress the alkali-aggregate reaction of concrete, significantly improve the alkali resistant aggregate reaction performance of concrete, improve canal The durability of groove prefabricated component;The bleeding quantity of concrete is reduced, improves the workability of concrete;Improve the compactness of concrete, show Write the impermeability for improving gool prefabricated component.
6th, the sulfoacid calcium water reducer that uses of the present invention can reduce water consumption more than 10%, compression strength averagely improve 15% with On, the significant workability for improving concrete, the durability of concrete is greatly enhanced, at the beginning of significantly reducing hydrated cementitious The heat of hydration of phase.
7th, prefabricated component of the present invention has docking groove in joint, and concrete is filled up in docking groove, can greatly reduce water The loss of flow, substantially increases water use efficiency;Because joint has docking groove, there is gap between the prefabricated component of two docking, All connect as one, this gap be prefabricated component because expanded by heating or pre- cold events generation variable provide space, Protect prefabricated component.
8th, framework of steel reinforcement design of the present invention is special, can ensure that water channel prefabricated component is sturdy and durable, pre- compared with existing water channel Parts quality improves more than several times, can be through under pressure indeformable.
9th, the water channel prefabricated component after casting concrete of the present invention conserves at the scene, after temperature is more than 500h DEG C during maintenance Removable side mould, removable die cavity after temperature is more than 1500h DEG C during watering maintenance, prefabricated component, which is concentrated, after form removal chamber stacks, and conserves Can dispatch from the factory use during more than Shi Wenda 2000h DEG C;This kind of maintenance method is taken, can reach accurate to water channel prefabricated component Maintenance, the quality of water channel prefabricated component is improved, strengthen the resistance to compression of water channel prefabricated component and tensile capacity;It can also save unnecessary artificial Input, the unnecessary waste of water is also avoided that, reduces production cost.
Brief description of the drawings
Fig. 1 is a kind of dimensional structure diagram of water channel gool prefabricated-member mould of the present invention.
Fig. 2 is the dimensional structure diagram of die cavity.
Fig. 3 is the main structure diagram of beam groove.
Fig. 4 is the structural representation of gool prefabricated component.
Fig. 5 is the structural representation of reinforcement constitution.
Fig. 6 is the dimensional structure diagram of forward and backward end cap.
Fig. 7 is the main structure diagram of reinforcement constitution.
Element title and serial number in figure:Drive end bearing bracket 1, cover plate 2, die cavity 3, rear end cap 4, sidewall paneling 5, lifting hole(eyelet) 6, bolt 7, Docking groove 8, second layer distributing bar 9, first layer distributing bar 10, reinforcement distributing bar 11, longitudinal reinforcement 12, boss 13, spiral shell Keyhole 14.
Reinforcement constitution is not put in Fig. 1 on die cavity, in order to cheaply observe inside combination rear mold, therefore not by reinforcement constitution set On.
Embodiment
With reference to embodiments of the invention, the present invention is described in more detail.
Embodiment 1:
Referring to shown in Fig. 1 to 7, a kind of production method of water channel gool prefabricated component, described method comprises the following steps:
(1)Make and be inverted and put with the mould needed for water channel prefabricated component same shape, mould, mold bottom upward, pours from bottom Build concrete;
(2)On die inside on even application mould oil or pad on plastic sheeting;
(3)The framework of steel reinforcement made is inserted in and poured in mould, and adjusts the protective layer of concrete, described reinforcement constitution Trough rim by inside and outside stressing conditions configuration principal rod, bottom land is by upper and lower stressing conditions configuration principal rod, by the reinforcing bar of configuration point Then solution is welded into unit member, several unit members is welded to connect with longitudinal reinforcement to be formed into the shape that can be processed The reinforcement constitution of gool, the both ends distribution unit component on reinforcement constitution is closeer, and intermediate distribution unit member is sparse and uniform;
(4)Field fabrication pours required concrete;Concrete is poured among mold bottom, uniformly divided to both ends, then Vibrated, vibrated 1~3 minute using direct insertion vibrator, discharged the bubble in concrete, combine concrete compaction, then to mould Have notch upper surface and carry out troweling;Closed die cover plate;
(5)Water channel prefabricated component after casting concrete conserves at the scene, removable side mould after temperature is more than 500h DEG C during maintenance, Removable die cavity after temperature is more than 1500h DEG C during watering maintenance, prefabricated component concentrates stacking after form removal chamber, Wen Da during maintenance Can dispatch from the factory use at more than 2000h DEG C.
After cast in situs terminates, so that it may pair when be included in curing time, it is 9 points of morning to pour end, i.e., since 9 points of morning Timing;Take that 9 points of morning, totally 12 hours, outdoor temperature were 30 DEG C to 21 points at night the period, when temperature for 12 × 30= 360h·℃;21 points to 9 points of morning next day at night, totally 12 hours, when temperature be 12 × 28=336h DEG C;Two periods Numerical value is added, and as 360+336=696h DEG C is more than 500h DEG C, can remove the die cap plate, side wall mould, end cap mould of mould.
Watering maintenance, from 10 points of morning to 21 points at night, outdoor temperature is 30 DEG C, when temperature be 11 × 30=330h DEG C; 21 points to 9 points of morning at night, and outdoor temperature is 28 DEG C, when temperature be 12 × 28=336h DEG C;9 points to 21 points of morning, outdoor temp Spend for 32 DEG C, when temperature be 12 × 32=384h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 30 DEG C, when temperature be 12 ×30=360h·℃;9 points to 14 points of morning, outdoor temperature be 31 DEG C, when temperature be 5 × 31=155h DEG C;By the stage Numerical value adds up, and as 330+336+384+360+155=1565 are more than 1500h DEG C, you can removes die cavity, prefabricated component is hung Die cavity, carry out stacking maintenance.
Continuing to conserve, the value accumulated value of temperature reaches 2000h DEG C when will be all, from 14 points to 21 points at night of afternoon, Outdoor temperature be 31 DEG C, when temperature be 7 × 31=217h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 29 DEG C, Shi Wen For 12 × 29=348h DEG C;9 points to 21 points of morning, outdoor temperature be 32 DEG C, when temperature be 12 × 32=384h DEG C;At night 21 For point to 9 points of morning, outdoor temperature is 30 DEG C, when temperature be 12 × 30=360h DEG C;9 points to 21 points of morning, outdoor temperature 33 DEG C, when temperature be 12 × 33=396h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 30 DEG C, when temperature for 12 × 30= 360h·℃;The numerical value in the stage is added up, as 217+348+384+360+396+360=2065 reach 2000h DEG CWith On, illustrate the standard for having met maintenance, can dispatch from the factory use.
Described mould includes drive end bearing bracket 1, upper cover plate 2, die cavity 3, rear end cap 4, sidewall paneling 5 and reinforcement constitution;Described Drive end bearing bracket 1, rear end cap 4 correspond to the front and rear end for being installed on die cavity 3 respectively, and are fixed using bolt 7;Reinforcing bar is cased with die cavity 3 Construction, the both sides of die cavity 3 are provided with symmetrical two pieces of sidewall panelings 5, and are fixed using bolt 7;5 inclined angle of sidewall paneling corresponds to The angle of inclination of die cavity 3, its bottom are fixed using bolt 7;Upper cover plate 2 is placed on die cavity 3;The reinforcement constitution includes the second layer Distributing bar 9, first layer distributing bar 10, reinforcement distributing bar 11 and longitudinal reinforcement 12, the second layer distributing bar 9, One layer of distributing bar 10 connects and composes unit member, first layer distributing bar 10 and reinforcement distributing bar with reinforcement distributing bar 11 Second layer distributing bar 9 is sandwiched in centre by 11, and several unit members connect into reinforcement constitution by longitudinal reinforcement 12.
Described die cavity 3 is provided with two pieces of symmetrical side walls, and the angle of described side wall and vertical plane is 5 °;Die cavity 3 and side Wallboard 5 is provided with corresponding through hole, two through holes using cylinder connect, when pour, form removal after, cylinder present position The straight-through through hole formed is lifting hole(eyelet) 6.
Described concrete includes the raw material of following parts by weight:60 parts of coarse-fine aggregate, 10 parts of 425 portland cement, powder 5 parts of coal ash, 5 parts of Iron-ore Slag micro mist, 1 part of high efficiency water reducing agent, described high efficiency water reducing agent are that alcohol effluent dry powder adds sulfoacid calcium to subtract The weight ratio of aqua is 1:1.
Described coarse-fine aggregate is river sand and the mixture of limestone or granite particle, river sand and limestone or granite The weight ratio of particle is 1:1~1.5;The modulus of fineness of the river sand is 2.2~3.0, limestone or granite the particle footpath For 5~15mm.
It by sulfite liquor is raw material that described sulfoacid calcium water reducer preparation method, which is, adds sodium hydroxide regulation PH value is passed through after air reacts 12h at 80 DEG C to 10 and adds potassium sulfate, 50min is reacted at 80 DEG C, filter, after drying i.e. Obtain sulfoacid calcium water reducer.
Embodiment 2:
Referring to shown in Fig. 1 to 7, a kind of production method of water channel gool prefabricated component, described method comprises the following steps:
(1)Make and be inverted and put with the mould needed for water channel prefabricated component same shape, mould, mold bottom upward, pours from bottom Build concrete;
(2)On die inside on even application mould oil or pad on plastic sheeting;
(3)The framework of steel reinforcement made is inserted in and poured in mould, and adjusts the protective layer of concrete, described reinforcement constitution Trough rim by inside and outside stressing conditions configuration principal rod, bottom land is by upper and lower stressing conditions configuration principal rod, by the reinforcing bar of configuration point Then solution is welded into unit member, several unit members is welded to connect with longitudinal reinforcement to be formed into the shape that can be processed The reinforcement constitution of gool, the both ends distribution unit component on reinforcement constitution is closeer, and intermediate distribution unit member is sparse and uniform;
(4)Field fabrication pours required concrete;Concrete is poured among mold bottom, uniformly divided to both ends, then Vibrated, vibrated 1~3 minute using direct insertion vibrator, discharged the bubble in concrete, combine concrete compaction, then to mould Have notch upper surface and carry out troweling;Closed die cover plate;
(5)Water channel prefabricated component after casting concrete conserves at the scene, removable side mould after temperature is more than 500h DEG C during maintenance, Removable die cavity after temperature is more than 1500h DEG C during watering maintenance, prefabricated component concentrates stacking after form removal chamber, Wen Da during maintenance Can dispatch from the factory use at more than 2000h DEG C.
After cast in situs terminates, so that it may pair when be included in curing time, pour end be at 11 points at noon, i.e., opened for 11 points from noon Beginning timing;Period takes at 11 points at noon, and to 21 points at night, totally 10 hours, outdoor temperature are 30 DEG C, when temperature for 10 × 30= 300h·℃;21 points to 9 points of morning next day at night, totally 12 hours, when temperature be 12 × 28=336h DEG C;Two periods Numerical value is added, and as 300+336=636h DEG C is more than 500h DEG C, can remove the die cap plate, side wall mould, end cap mould of mould.
Watering maintenance, from 10 points of morning to 21 points at night, outdoor temperature is 30 DEG C, when temperature be 11 × 30=330h DEG C; 21 points to 9 points of morning at night, and outdoor temperature is 28 DEG C, when temperature be 12 × 28=336h DEG C;9 points to 21 points of morning, outdoor temp Spend for 32 DEG C, when temperature be 12 × 32=384h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 30 DEG C, when temperature be 12 ×30=360h·℃;9 points to 14 points of morning, outdoor temperature be 31 DEG C, when temperature be 5 × 31=155h DEG C;By the stage Numerical value adds up, and as 330+336+384+360+155=1565 are more than 1500h DEG C, you can removes die cavity, prefabricated component is hung Die cavity, carry out stacking maintenance.
Continuing to conserve, the value accumulated value of temperature reaches 2000h DEG C when will be all, from 14 points to 21 points at night of afternoon, Outdoor temperature be 31 DEG C, when temperature be 7 × 31=217h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 29 DEG C, Shi Wen For 12 × 29=348h DEG C;9 points to 21 points of morning, outdoor temperature be 32 DEG C, when temperature be 12 × 32=384h DEG C;At night 21 For point to 9 points of morning, outdoor temperature is 30 DEG C, when temperature be 12 × 30=360h DEG C;9 points to 21 points of morning, outdoor temperature 33 DEG C, when temperature be 12 × 33=396h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 30 DEG C, when temperature for 12 × 30= 360h·℃;The numerical value in the stage is added up, as 217+348+384+360+396+360=2065 reach 2000h DEG CWith On, illustrate the standard for having met maintenance, can dispatch from the factory use.
Described mould includes drive end bearing bracket 1, upper cover plate 2, die cavity 3, rear end cap 4, sidewall paneling 5 and reinforcement constitution;Described Drive end bearing bracket 1, rear end cap 4 correspond to the front and rear end for being installed on die cavity 3 respectively, and are fixed using bolt 7;Reinforcing bar is cased with die cavity 3 Construction, the both sides of die cavity 3 are provided with symmetrical two pieces of sidewall panelings 5, and are fixed using bolt 7;5 inclined angle of sidewall paneling corresponds to The angle of inclination of die cavity 3, its bottom are fixed using bolt 7;Upper cover plate 2 is placed on die cavity 3;The reinforcement constitution includes the second layer Distributing bar 9, first layer distributing bar 10, reinforcement distributing bar 11 and longitudinal reinforcement 12, the second layer distributing bar 9, One layer of distributing bar 10 connects and composes unit member, first layer distributing bar 10 and reinforcement distributing bar with reinforcement distributing bar 11 Second layer distributing bar 9 is sandwiched in centre by 11, and several unit members connect into reinforcement constitution by longitudinal reinforcement 12.
Described die cavity 3 is provided with two pieces of symmetrical side walls, and the angle of described side wall and vertical plane is 8 °;Die cavity 3 and side Wallboard 5 is provided with corresponding through hole, two through holes using cylinder connect, when pour, form removal after, cylinder present position The straight-through through hole formed is lifting hole(eyelet) 6.
Described concrete includes the raw material of following parts by weight:70 parts of coarse-fine aggregate, 20 parts of 525 portland cement, powder 10 parts of coal ash, 10 parts of Iron-ore Slag micro mist, 3 parts of high efficiency water reducing agent, described high efficiency water reducing agent are that alcohol effluent dry powder adds sulfoacid calcium The weight ratio of water reducer is 1:1.
Described coarse-fine aggregate is river sand and the mixture of limestone or granite particle, river sand and limestone or granite The weight ratio of particle is 1:1~1.5;The modulus of fineness of the river sand is 2.2~3.0, limestone or granite the particle footpath For 5~15mm.
It by sulfite liquor is raw material that described sulfoacid calcium water reducer preparation method, which is, adds sodium hydroxide regulation PH value is passed through after air reacts 10h at 70 DEG C to 8 and adds potassium sulfate, 40min is reacted at 70 DEG C, filter, after drying i.e. Obtain sulfoacid calcium water reducer.
Embodiment 3:
Referring to shown in Fig. 1 to 7, a kind of production method of water channel gool prefabricated component, described method comprises the following steps:
(1)Make and be inverted and put with the mould needed for water channel prefabricated component same shape, mould, mold bottom upward, pours from bottom Build concrete;
(2)On die inside on even application mould oil or pad on plastic sheeting;
(3)The framework of steel reinforcement made is inserted in and poured in mould, and adjusts the protective layer of concrete, described reinforcement constitution Trough rim by inside and outside stressing conditions configuration principal rod, bottom land is by upper and lower stressing conditions configuration principal rod, by the reinforcing bar of configuration point Then solution is welded into unit member, several unit members is welded to connect with longitudinal reinforcement to be formed into the shape that can be processed The reinforcement constitution of gool, the both ends distribution unit component on reinforcement constitution is closeer, and intermediate distribution unit member is sparse and uniform;
(4)Field fabrication pours required concrete;Concrete is poured among mold bottom, uniformly divided to both ends, then Vibrated, vibrated 1~3 minute using direct insertion vibrator, discharged the bubble in concrete, combine concrete compaction, then to mould Have notch upper surface and carry out troweling;Closed die cover plate;
(5)Water channel prefabricated component after casting concrete conserves at the scene, removable side mould after temperature is more than 500h DEG C during maintenance, Removable die cavity after temperature is more than 1500h DEG C during watering maintenance, prefabricated component concentrates stacking after form removal chamber, Wen Da during maintenance Can dispatch from the factory use at more than 2000h DEG C.
After cast in situs terminates, so that it may pair when be included in curing time, pour end be at 15 points in afternoon, i.e., opened for 15 points from afternoon Beginning timing;Period removes 15 points of noon to 21 points at night, and totally 6 hours, outdoor temperature are 30 DEG C, when temperature for 6 × 30= 180h·℃;21 points to 9 points of morning next day at night, totally 12 hours, when temperature be 12 × 28=336h DEG C;Two periods Numerical value is added, and as 180+336=516h DEG C is more than 500h DEG C, can remove the die cap plate, side wall mould, end cap mould of mould.
Watering maintenance, from 9 points of morning to 21 points at night, outdoor temperature is 30 DEG C, when temperature be 12 × 30=360h DEG C; 21 points to 9 points of morning at night, and outdoor temperature is 28 DEG C, when temperature be 12 × 28=336h DEG C;9 points to 21 points of morning, outdoor temp Spend for 32 DEG C, when temperature be 12 × 32=384h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 30 DEG C, when temperature be 12 ×30=360h·℃;9 points to 14 points of morning, outdoor temperature be 31 DEG C, when temperature be 5 × 31=155h DEG C;By the stage Numerical value adds up, and as 360+336+384+360+155=1595 are more than 1500h DEG C, you can removes die cavity, prefabricated component is hung Die cavity, carry out stacking maintenance.
Continuing to conserve, the value accumulated value of temperature reaches 2000h DEG C when will be all, from 14 points to 21 points at night of afternoon, Outdoor temperature be 31 DEG C, when temperature be 7 × 31=217h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 29 DEG C, Shi Wen For 12 × 29=348h DEG C;9 points to 21 points of morning, outdoor temperature be 32 DEG C, when temperature be 12 × 32=384h DEG C;At night 21 For point to 9 points of morning, outdoor temperature is 30 DEG C, when temperature be 12 × 30=360h DEG C;9 points to 21 points of morning, outdoor temperature 33 DEG C, when temperature be 12 × 33=396h DEG C;21 points to 9 points of morning at night, and outdoor temperature is 30 DEG C, when temperature for 12 × 30= 360h·℃;The numerical value in the stage is added up, as 217+348+384+360+396+360=2065 reach 2000h DEG CWith On, illustrate the standard for having met maintenance, can dispatch from the factory use.
Described mould includes drive end bearing bracket 1, upper cover plate 2, die cavity 3, rear end cap 4, sidewall paneling 5 and framework of steel reinforcement;Described Drive end bearing bracket 1, rear end cap 4 correspond to the front and rear end for being installed on die cavity 3 respectively, and are fixed using bolt 7;Reinforcing bar is cased with die cavity 3 Construction, the both sides of die cavity 3 are provided with symmetrical two pieces of sidewall panelings 5, and are fixed using bolt 7;5 inclined angle of sidewall paneling corresponds to The angle of inclination of die cavity 3, its bottom are fixed using bolt 7;Upper cover plate 2 is placed on die cavity 3;The reinforcement constitution includes the second layer Distributing bar 9, first layer distributing bar 10, reinforcement distributing bar 11 and longitudinal reinforcement 12, the second layer distributing bar 9, One layer of distributing bar 10 connects and composes unit member, first layer distributing bar 10 and reinforcement distributing bar with reinforcement distributing bar 11 Second layer distributing bar 9 is sandwiched in centre by 11, and several unit members connect into reinforcement constitution by longitudinal reinforcement 12.
Described die cavity 3 is provided with two pieces of symmetrical side walls, and the angle of described side wall and vertical plane is 6 °;Die cavity 3 and side Wallboard 5 is provided with corresponding through hole, two through holes using cylinder connect, when pour, form removal after, cylinder present position The straight-through through hole formed is lifting hole(eyelet) 6.
Described concrete includes the raw material of following parts by weight:65 parts of coarse-fine aggregate, 15 parts of 525 portland cement, powder 8 parts of coal ash, 8 parts of Iron-ore Slag micro mist, 2 parts of high efficiency water reducing agent, described high efficiency water reducing agent are that alcohol effluent dry powder adds sulfoacid calcium to subtract The weight ratio of aqua is 1:1.
Described coarse-fine aggregate is river sand and the mixture of limestone or granite particle, river sand and limestone or granite The weight ratio of particle is 1:1~1.5;The modulus of fineness of the river sand is 2.2~3.0, limestone or granite the particle footpath For 5~15mm.
It by sulfite liquor is raw material that described sulfoacid calcium water reducer preparation method, which is, adds sodium hydroxide regulation PH value is passed through after air reacts 11h at 75 DEG C to 9 and adds potassium sulfate, 45min is reacted at 75 DEG C, filter, after drying i.e. Obtain sulfoacid calcium water reducer.
The present invention takes construction method to comprise the following steps:
(1)Clear base unwrapping wire:The width that the Breadth Maximum taken more than prefabricated component is 20~30cm is as clear baseline, using pulverized limestone mark Know line;
(2)Excavated using excavator or manually in the region of pulverized limestone identification scribe, the rational stacking earthwork, and it is manually levelling Bottom, it is determined that the sideline of installation and Bottom Altitude;
(3)The prefabricated component of job site will be transported to, be lifted with excavator, the prefabricated component sling is put into foundation trench, is directed at side Line and Bottom Altitude is leveled up, then, remove suspension hook;
(4)After installation terminates, the site error of prefabricated component has been installed in amendment, reaches design requirement, and reinforcing prevents from deforming;
(5)With the U-shaped docking groove of cement fine sand slurry filling prefabricated component joint, the weight ratio of cement and fine sand is 1:4~5, sand Slurry with hold it is agglomerating preferably;
(6)After mortar joint condenses, the space on backfill prefabricated component both sides, compacting, remaining earth material etc. is transported out of.

Claims (10)

  1. A kind of 1. production method of water channel gool prefabricated component, it is characterised in that:Described method comprises the following steps:
    (1)Make and be inverted and put with the mould needed for water channel prefabricated component same shape, mould, mold bottom upward, pours from bottom Build concrete;
    (2)On die inside on even application mould oil or pad on plastic sheeting;
    (3)The framework of steel reinforcement made is inserted in and poured in mould, and adjusts the protective layer of concrete, described reinforcement constitution Trough rim by inside and outside stressing conditions configuration principal rod, bottom land is by upper and lower stressing conditions configuration principal rod, by the reinforcing bar of configuration point Then solution is welded into unit member, several unit members is welded to connect with longitudinal reinforcement to be formed into the shape that can be processed The reinforcement constitution of gool, the both ends distribution unit component on reinforcement constitution is closeer, and intermediate distribution unit member is sparse and uniform;
    (4)Field fabrication pours required concrete;Concrete is poured among mold bottom, uniformly divided to both ends, then Vibrated, vibrated 1~3 minute using direct insertion vibrator, discharged the bubble in concrete, combine concrete compaction, then to mould Have notch upper surface and carry out troweling;Closed die cover plate;
    (5)Water channel prefabricated component after casting concrete conserves at the scene, removable side mould after temperature is more than 500h DEG C during maintenance, Removable die cavity after temperature is more than 1500h DEG C during watering maintenance, prefabricated component concentrates stacking after form removal chamber, Wen Da during maintenance Can dispatch from the factory use at more than 2000h DEG C.
  2. The production method of prefabricated component 2. water channel according to claim 1 is passed by one's way, it is characterised in that:When described when temperature is Between × outdoor temperature, the chronomere is hour, and time numerical value takes >=16 positive integer, and the outdoor temperature unit is Celsius Degree, outdoor temperature >=20 DEG C, the outdoor temperature take positive integer.
  3. 3. the production method of water channel gool prefabricated component according to claim 1, it is characterised in that:Before described mould includes End cap(1), upper cover plate(2), die cavity(3), rear end cap(4), sidewall paneling(5)And reinforcement constitution;Described drive end bearing bracket(1), rear end Lid(4)Correspond to respectively and be installed on die cavity(3)Front and rear end, and use bolt(7)It is fixed;The die cavity(3)On be cased with reinforcing bar Skeleton, the die cavity(3)Both sides are provided with symmetrical two pieces of sidewall panelings(5), and use bolt(7)It is fixed;The sidewall paneling(5) Inclined angle corresponds to die cavity(3)Side wall on angle of inclination, its bottom uses bolt(7)It is fixed;Upper cover plate(2)It is placed on Die cavity(3)On;The reinforcement constitution includes second layer distributing bar(9), first layer distributing bar(10), reinforcement distributing bar (11)And longitudinal reinforcement(12), the second layer distributing bar(9), first layer distributing bar(10)With reinforcement distributing bar(11) Connect and compose unit member, first layer distributing bar(10)With reinforcement distributing bar(11)By second layer distributing bar(9)It is sandwiched in Centre, several unit members pass through longitudinal reinforcement(12)Connect into reinforcement constitution.
  4. 4. the production method of water channel gool prefabricated component according to claim 3, it is characterised in that:Described die cavity(3)Adopt With steel plate bending or it is stamped to form, its internal and edge is supported using angle steel or channel-section steel.
  5. 5. the production method of water channel gool prefabricated component according to claim 3, it is characterised in that:Described die cavity(3)Top Portion is provided with two symmetrical chamferings so that water channel gool prefabricated component groove madial wall forms chamfering with bottom, is easy to remove mud.
  6. 6. the production method of water channel gool prefabricated component according to claim 3, it is characterised in that:Described drive end bearing bracket(1)、 Rear end cap(4)It is provided with boss(13), described boss(13)Docking groove(8)Model.
  7. 7. the production method of water channel gool prefabricated component according to claim 3, it is characterised in that:Described die cavity(3)If There are two pieces of symmetrical side walls, the angle of described side wall and vertical plane is 5 °~8 °;Die cavity(3)With sidewall paneling(5)It is provided with phase Corresponding through hole, two through holes using cylinder connect, when pour, form removal after, cylinder present position formed it is straight-through Through hole is lifting hole(eyelet)(6).
  8. 8. the production method of water channel gool prefabricated component according to claim 1, it is characterised in that:Described concrete includes The raw material of following parts by weight:60~70 parts of coarse-fine aggregate, 10~20 parts of 425~525 portland cement, 5~10 parts of flyash, 5~10 parts of Iron-ore Slag micro mist, 1~3 part of high efficiency water reducing agent, described high efficiency water reducing agent are that alcohol effluent dry powder adds sulfoacid calcium diminishing The weight ratio of agent is 1:1.
  9. 9. the production method of water channel gool prefabricated component according to claim 8, it is characterised in that:Described coarse-fine aggregate is The weight of the mixture of river sand and limestone or granite particle, river sand and limestone or granite particle ratio is 1:1~1.5; The modulus of fineness of the river sand is 2.2~3.0, and limestone or granite the particle footpath is 5~15mm.
  10. 10. the production method of water channel gool prefabricated component according to claim 8, it is characterised in that:Described sulfoacid calcium subtracts It by sulfite liquor is raw material that aqua preparation method, which is, adds sodium hydroxide and adjusts pH value to 8~10, is passed through air and exists Potassium sulfate is added after reacting 10~12h at 70~80 DEG C, 40~50min is reacted at 70~80 DEG C, filtering, is produced after drying Sulfoacid calcium water reducer.
CN201710726692.1A 2017-08-22 2017-08-22 A kind of production method of water channel gool prefabricated component Pending CN107443548A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710726692.1A CN107443548A (en) 2017-08-22 2017-08-22 A kind of production method of water channel gool prefabricated component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710726692.1A CN107443548A (en) 2017-08-22 2017-08-22 A kind of production method of water channel gool prefabricated component

Publications (1)

Publication Number Publication Date
CN107443548A true CN107443548A (en) 2017-12-08

Family

ID=60493754

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710726692.1A Pending CN107443548A (en) 2017-08-22 2017-08-22 A kind of production method of water channel gool prefabricated component

Country Status (1)

Country Link
CN (1) CN107443548A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112761115A (en) * 2020-12-30 2021-05-07 陈栋 Closed channel prefabricated part for municipal engineering and manufacturing method thereof
CN113463571A (en) * 2021-07-31 2021-10-01 周张宁 Reinforced concrete stop block with water flow hole

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EA200101065A1 (en) * 2001-08-07 2002-06-27 Александр Юрьевич Баскаков FORM FOR CASTING OF FIGURED PRODUCTS FROM A CONCRETE MIXTURE AND A METHOD OF MANUFACTURING ELEMENTS OF A DRAINAGE SYSTEM WITH ITS USE
CN1802335A (en) * 2003-01-15 2006-07-12 联邦科学和工业研究组织 Cement products
CN103770203A (en) * 2014-02-21 2014-05-07 黑龙江省水利科学研究院 U-shaped sink machining mould
CN103874671A (en) * 2011-10-13 2014-06-18 电气化学工业株式会社 Method for manufacturing rapid-hardening agent and concrete product
CN104020046A (en) * 2014-06-04 2014-09-03 王卫仑 Method for estimating compressive strength of concrete in early stage
CN204109125U (en) * 2014-09-22 2015-01-21 广西壮族自治区水利科学研究院 The shaped device of channel concrete prefabricated component
CN204566339U (en) * 2015-04-14 2015-08-19 山西省水利水电科学研究院 The U-shaped canal mould of prefabricated reinforced concrete
CN205343391U (en) * 2016-01-18 2016-06-29 郑志忠 Pre -tensioning system prestressed concrete U template stake mould
CN105818266A (en) * 2015-01-09 2016-08-03 四川华西绿舍建材有限公司 Channel plate mold and method for manufacturing channel plate by means of channel plate mold
CN106007593A (en) * 2016-05-25 2016-10-12 象州县科学技术局 Method for producing concrete channel prefabricated part from mineral slag
CN106794596A (en) * 2014-08-12 2017-05-31 胡贝特·拉佩斯托费尔 Reinforcing element and the method for manufacturing reinforcing element

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EA200101065A1 (en) * 2001-08-07 2002-06-27 Александр Юрьевич Баскаков FORM FOR CASTING OF FIGURED PRODUCTS FROM A CONCRETE MIXTURE AND A METHOD OF MANUFACTURING ELEMENTS OF A DRAINAGE SYSTEM WITH ITS USE
CN1802335A (en) * 2003-01-15 2006-07-12 联邦科学和工业研究组织 Cement products
CN103874671A (en) * 2011-10-13 2014-06-18 电气化学工业株式会社 Method for manufacturing rapid-hardening agent and concrete product
CN103770203A (en) * 2014-02-21 2014-05-07 黑龙江省水利科学研究院 U-shaped sink machining mould
CN104020046A (en) * 2014-06-04 2014-09-03 王卫仑 Method for estimating compressive strength of concrete in early stage
CN106794596A (en) * 2014-08-12 2017-05-31 胡贝特·拉佩斯托费尔 Reinforcing element and the method for manufacturing reinforcing element
CN204109125U (en) * 2014-09-22 2015-01-21 广西壮族自治区水利科学研究院 The shaped device of channel concrete prefabricated component
CN105818266A (en) * 2015-01-09 2016-08-03 四川华西绿舍建材有限公司 Channel plate mold and method for manufacturing channel plate by means of channel plate mold
CN204566339U (en) * 2015-04-14 2015-08-19 山西省水利水电科学研究院 The U-shaped canal mould of prefabricated reinforced concrete
CN205343391U (en) * 2016-01-18 2016-06-29 郑志忠 Pre -tensioning system prestressed concrete U template stake mould
CN106007593A (en) * 2016-05-25 2016-10-12 象州县科学技术局 Method for producing concrete channel prefabricated part from mineral slag

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112761115A (en) * 2020-12-30 2021-05-07 陈栋 Closed channel prefabricated part for municipal engineering and manufacturing method thereof
CN113463571A (en) * 2021-07-31 2021-10-01 周张宁 Reinforced concrete stop block with water flow hole

Similar Documents

Publication Publication Date Title
CN107486940A (en) A kind of water channel is passed by one&#39;s way the production method of prefabricated component
CN103358387A (en) Production technology of anti-corrosion prefabricated reinforced concrete inspection well
CN109826084A (en) A kind of aqueduct method for repairing seepage
CN207327274U (en) A kind of water channel engineering system
CN107443548A (en) A kind of production method of water channel gool prefabricated component
CN107471404A (en) A kind of water channel gool side leads to the production method of prefabricated component
CN201162233Y (en) Rear irrigation zone structure with higher ground water level
CN107471425A (en) A kind of production method of water channel threeway prefabricated component
CN111908853A (en) Self-compacting soil, preparation method thereof and construction method for backfilling municipal cavity
CN106400838B (en) A kind of city integrated Pipe rack of prefabricated assembled concrete and construction method
CN112761158B (en) Green construction method of integral three-wall-in-one outer wall of reverse engineering steel concrete key pin meshed row pile
CN103572786B (en) A kind of pile crown node waterproof treating apparatus and construction method thereof
CN107471424A (en) A kind of water channel engineering system and construction method
CN206308707U (en) A kind of city integrated Pipe rack of prefabricated assembled concrete
CN111531702A (en) Preparation method of prestressed prefabricated part
CN101994328B (en) Method for making counterweight for excavator
CN211229151U (en) Concrete masonry module
CN207310188U (en) A kind of water channel gool prefabricated-member mould
CN107443567A (en) A kind of production method of retaining wall prefabricated component
CN111254965B (en) Grouting type recycled concrete precast pier foundation and manufacturing method thereof
CN107471426A (en) A kind of production method of water channel corner prefabricated component
CN212000674U (en) Novel reverse construction method assembly type non-pressure culvert
CN207310186U (en) A kind of water channel gool side leads to prefabricated-member mould
CN210288471U (en) Steel slag concrete retaining wall protective structure
CN208280156U (en) The non-fully pile foundation cushion cap under precipitation state inside a kind of foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171208