Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721673094.4U
Other languages
Chinese (zh)
Inventor
沈志平
朱军
袁江文
孙洪
陈德茂
王鸿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Zhengye Engineering & Investment Inc Ltd
Original Assignee
Guizhou Zhengye Engineering & Investment Inc Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Zhengye Engineering & Investment Inc Ltd filed Critical Guizhou Zhengye Engineering & Investment Inc Ltd
Priority to CN201721673094.4U priority Critical patent/CN207567892U/en
Application granted granted Critical
Publication of CN207567892U publication Critical patent/CN207567892U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of large-scale karst depression flood drainage systems, and including Cut-off ditch and tidal channel, Cut-off ditch is arranged on depression side slope or slope top, and tidal channel is arranged on depression and is interconnected with Cut-off ditch, and tidal channel is communicated to the sinkhole on depression.The utility model sets interconnected Cut-off ditch and tidal channel in karst depression in mima type microrelief landforms, tidal channel drains into water in karst depression in leak hole, Cut-off ditch plays a part of to collect rainfall rainwash, tidal channel, which rises, to be collected, dredge the effect of flowing water, Karst Mountain rainfall can effectively be slowed down, soil erosion is caused to surface erosion, the effect that rainfall flowing water avoids occurring in karst depression waterlogging and Secondary Geological Hazards is dredged simultaneously, it is plentiful that the utility model is suitable for rainfall, and the large-scale karst depression of ground unit complexity, engineering-built is easy, cost is relatively low, it is easily managed maintenance.

Description

A kind of large size karst depression flood drainage system
Technical field
The utility model is related to a kind of large-scale karst depression flood drainage systems, belong in large-scale karst depression the technology neck that drains off floodwaters Domain.
Background technology
Karst depression is the common negative land form in the karst area formed under corrosion, by peak cluster positive form and funnel-form What negative land form common combination was formed.Radius scale can be also formed in the area that karst is developed by force to reach hundreds of meters or even have 1~2 The large-scale depression of kilometer.This kind of depression is typically under strong vertical circulation effect, caves in what is formed by cavern.In low-lying area Widely distributed in ground to have a large amount of molten Study on Rock that collapse, depression bottom then deposits thicker clay layer.Moreover, in large-scale karst low-lying area Also there is the rubble collapse deposit area formed recently and the high slope area being made of the peak cluster mountain ridge in ground.This causes in large size Extremely complex ground unit interface and different microreliefs are then constituted in karst depression.Under condition of raining, rainwater passes through Different ground units is pooled to depression bottom, and is drained by sinkhole to underground underground river system.Due to large-scale karst depression face The catchment area of the larger each ground unit of product is different, and the rainwash formed after rainfall is also different.Especially for the pine in depression It dissipates accumulation area and easily causes soil erosion under Rainfall simulator erosion.At present, drainning off floodwaters in face of this kind of large-scale karst depression complicated landform Preventing waterlogging, there has been no ripe technologies for disposal facility.
Invention content
The technical problems to be solved in the utility model is:A kind of large-scale karst depression flood drainage system is provided, it is existing to solve It is caused in soil erosion and depression in large-scale karst depression since rainfall causes in depression table soil to wash away present in technology Flooded problem.
The technical solution that the utility model is taken is:A kind of large size karst depression flood drainage system, including Cut-off ditch and drains off floodwaters Ditch, Cut-off ditch are arranged on depression side slope or incompact-deposit bodies top, and tidal channel is arranged on depression and is interconnected with Cut-off ditch, Tidal channel is communicated to the sinkhole on depression.
Preferably, above-mentioned Cut-off ditch section is trapezium structure.
Preferably, above-mentioned tidal channel is rectangular configuration.
Preferably, drop step is provided in above-mentioned tidal channel, to play energy dissipating flowing water, alleviates washing away for insulated stream Effect.
Preferably, tenon is provided in above-mentioned tidal channel, to play energy dissipating flowing water, alleviates the work washed away of insulated stream With.
Preferably, above-mentioned Cut-off ditch and tidal channel are built by laying bricks or stones using stone masonry, and outer surface is both provided with concrete plastering Layer.
The beneficial effects of the utility model:Compared with prior art, the effect of the utility model is as follows:
(1)The utility model sets interconnected Cut-off ditch and tidal channel in karst depression in mima type microrelief landforms, row Great Gulch drains into water in karst depression in leak hole, Cut-off ditch play a part of collect rainfall rainwash, tidal channel rise collect, The effect of flowing water is dredged, can effectively slow down Karst Mountain rainfall and soil erosion be caused to surface erosion, while dredge drop Rain flowing water avoids occurring in karst depression the effect of waterlogging and Secondary Geological Hazards, and the utility model is plentiful suitable for rainfall, and The large-scale karst depression of ground unit complexity, engineering-built is easy, and cost is relatively low, is easily managed maintenance.
Description of the drawings
Fig. 1 is the utility model embodiment planar structure schematic diagram;
Fig. 2 is the utility model embodiment karst depression block plan;
Fig. 3 is the utility model embodiment Cut-off ditch schematic diagram;
Fig. 4 is the utility model embodiment tidal channel schematic diagram;
Fig. 5 is the utility model embodiment tidal channel tenon schematic diagram;
Fig. 6 is the utility model embodiment tidal channel drop step schematic diagram.
Specific embodiment
Below in conjunction with the accompanying drawings and the utility model is described further in specific embodiment.
Embodiment 1:As shown in Fig. 1 ~ Fig. 6, a kind of large size karst depression flood drainage system, including Cut-off ditch 1 and tidal channel 2, Cut-off ditch 1 is arranged on depression side slope area or depression sloped region top, and tidal channel 2 is arranged on depression and is interconnected with 1 phase of Cut-off ditch Logical, tidal channel 2 is communicated to the sinkhole 3 on depression, and Cut-off ditch 1 plays a part of to collect rainfall rainwash, and tidal channel 2 plays remittance Collect, dredge the effect of flowing water.
Preferably, above-mentioned Cut-off ditch 1 sets at least eight, and section is trapezium structure, and width B is in 600~1300mm, height H is spent in 400~1000mm.
Preferably, above-mentioned tidal channel 2 sets at least four, and rectangular cross-section structure, width B is in 300~900mm, height H is spent in 300~900mm.
Preferably, drop step 4 is provided in above-mentioned tidal channel 2, drop 4 high 400~450mm of step, to play energy dissipating Flowing water alleviates the effect washed away of insulated stream.
Preferably, tenon 5, tenon 5 high 90~100mm, spacing 150mm, to play energy dissipating are provided in above-mentioned tidal channel 2 Flowing water alleviates the effect washed away of insulated stream.
Preferably, above-mentioned Cut-off ditch 1 and tidal channel 2 are built by laying bricks or stones using stone masonry, and outer surface is both provided with concrete and smears Face layer.
A kind of method of drainning off floodwaters of large size karst depression flood drainage system, this method include the following steps:
(1)It determines microgeomorphologyd in karst depression, depression can be divided into peak cluster side slope area, depression sloped region, depression Karst depression is divided into multiple charge for remittance cellular zones by gentle slope area according to hypsography and watershed in region is divided;
(2)According to the position of multiple charge for remittance cellular zone areas and mima type microrelief condition selection Cut-off ditch, select at depression peak Cong Bianpo areas and depression sloped region top setting Cut-off ditch, Cut-off ditch section are trapezoidal, Cut-off ditch cross-sectional width B1With height H1Root The computational methods suitable for small watershed crest discharge is used to calculate according to charge for remittance cellular zone catchment area where Cut-off ditch to obtain.According to The size of depression catchment area can increase and decrease the quantity of Cut-off ditch, and catchment area is less than 0.5km2One of Cut-off ditch, charge for remittance are set Area is in 1km2To 0.5km2Twice Cut-off ditch is set, and catchment area is more than 1km2Three Cut-off ditch are set;
(3)According to microrelief partitioning scenario in depression, the low-lying place in the sloped region of depression is laid perpendicular to depression bottom Tidal channel.Tidal channel one end is connected with Cut-off ditch, and one end is connect with sinkhole, and tidal channel rectangular cross-section, drain off floodwaters furrow width Spend B2With height H2It is obtained according to connected Cut-off ditch size, i.e., tidal channel area of section is twice of Cut-off ditch, to meet draining It needs;
(4)Tidal channel locates setting drop step or tenon more suddenly in the gradient;
(5)Expand the original sinkhole entrance in depression, tidal channel is connect with sinkhole.
The above, only specific embodiment of the present utility model, but the scope of protection of the utility model is not limited to In this, in the technical scope that any one skilled in the art discloses in the utility model, variation can be readily occurred in Or replace, it should be covered within the scope of the utility model, therefore, the scope of protection of the utility model should be with the power Subject to the protection domain of profit requirement.

Claims (6)

1. a kind of large size karst depression flood drainage system, it is characterised in that:Including Cut-off ditch(1)And tidal channel(2), Cut-off ditch(1) It is arranged on depression side slope or incompact-deposit bodies top, tidal channel(2)It is arranged on depression and and Cut-off ditch(1)It is interconnected, row Great Gulch(2)The sinkhole being communicated on depression(3).
2. a kind of large-scale karst depression flood drainage system according to claim 1, it is characterised in that:Cut-off ditch(1)Section is Trapezium structure.
3. a kind of large-scale karst depression flood drainage system according to claim 1, it is characterised in that:Tidal channel(2)For rectangle Structure.
4. a kind of large-scale karst depression flood drainage system according to claim 1, it is characterised in that:Tidal channel(2)Interior setting There is drop step(4).
5. a kind of large-scale karst depression flood drainage system according to claim 1, it is characterised in that:Tidal channel(2)Interior setting There is tenon(5).
6. a kind of large-scale karst depression flood drainage system according to claim 1, it is characterised in that:Cut-off ditch(1)With drain off floodwaters Ditch(2)It is built by laying bricks or stones using stone masonry, outer surface is both provided with concrete float coat.
CN201721673094.4U 2017-12-05 2017-12-05 A kind of large size karst depression flood drainage system Active CN207567892U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721673094.4U CN207567892U (en) 2017-12-05 2017-12-05 A kind of large size karst depression flood drainage system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721673094.4U CN207567892U (en) 2017-12-05 2017-12-05 A kind of large size karst depression flood drainage system

Publications (1)

Publication Number Publication Date
CN207567892U true CN207567892U (en) 2018-07-03

Family

ID=62690264

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721673094.4U Active CN207567892U (en) 2017-12-05 2017-12-05 A kind of large size karst depression flood drainage system

Country Status (1)

Country Link
CN (1) CN207567892U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109868878A (en) * 2019-03-29 2019-06-11 贵州正业工程技术投资有限公司 A kind of large size Karst depression hydrophobic structure and its construction method
CN110432083A (en) * 2019-08-30 2019-11-12 贵州正业工程技术投资有限公司 A kind of karst depression surface vegetation ecological restoration device and its restorative procedure
CN111947605A (en) * 2020-08-20 2020-11-17 上海同禾工程科技股份有限公司 Slope safety monitoring system and monitoring method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109868878A (en) * 2019-03-29 2019-06-11 贵州正业工程技术投资有限公司 A kind of large size Karst depression hydrophobic structure and its construction method
CN110432083A (en) * 2019-08-30 2019-11-12 贵州正业工程技术投资有限公司 A kind of karst depression surface vegetation ecological restoration device and its restorative procedure
CN110432083B (en) * 2019-08-30 2024-04-30 贵州正业工程技术投资有限公司 Karst depression ground surface vegetation ecological restoration device and restoration method thereof
CN111947605A (en) * 2020-08-20 2020-11-17 上海同禾工程科技股份有限公司 Slope safety monitoring system and monitoring method thereof
CN111947605B (en) * 2020-08-20 2023-05-09 上海同禾工程科技股份有限公司 Slope safety monitoring system and monitoring method thereof

Similar Documents

Publication Publication Date Title
CN207567892U (en) A kind of large size karst depression flood drainage system
CN107829482A (en) A kind of large-scale karst depression flood drainage system and its method of drainning off floodwaters
CN106801403B (en) A method of preventing mud-stone flow disaster and mudstone apoblema recycles
CN114319401A (en) Foundation pit slope drainage system
CN104846781A (en) Ecological interlocking block and ecological interlocking block type slope protection construction method
CN105297685A (en) Base concrete panel rock-fill dam and construction method thereof
CN103866774A (en) Ditch pipe network protection body for slope protection and collapsing hill drainage and soil fixation
CN102888849B (en) A kind of large outdoors colliery refuse dump, loess area micro-slope reconstruction method
CN103556672A (en) Rainwater harvesting and water storage system for field road and construction method thereof
CN202787282U (en) Step type wet masonry rock berm roadbed side slope
CN103266633A (en) Seepage-proof sewage discharging and floodwater draining method for tailing reservoir in wet metallurgy
CN107700523B (en) Drainage system of prefabricated upward inclined retaining wall and construction method
CN109440554A (en) A kind of assembled greening band structure and its construction method
CN203755322U (en) Channel pipe network guarded body used for slope protection and drainage and soil fixation of slope collapse
CN206581137U (en) A kind of drainage system device for Highway in Loess Area bridge
CN204898465U (en) Ecological drainage facility of permafrost region dish
CN104452704B (en) The prevention and controls of a kind of wave mode sloping upland soil erosion and device thereof
CN207469190U (en) A kind of infitration galleries structure of efficient draining
CN212427186U (en) Slide-resistant plate retaining wall for slope protection
CN105178133B (en) Permafrost region dish Demonstration for Ecological Sanitation facility and its construction process
CN203034335U (en) Silty soil section highway drainage system
KR20130140238A (en) Method of paving road using dyke
CN209323289U (en) A kind of assembled greening band structure
CN207537994U (en) The underground erosion control wall construction of trraning pole is set
CN207525575U (en) Novel brick structure permeates water

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant