CN105297685A - Base concrete panel rock-fill dam and construction method thereof - Google Patents

Base concrete panel rock-fill dam and construction method thereof Download PDF

Info

Publication number
CN105297685A
CN105297685A CN201510817066.4A CN201510817066A CN105297685A CN 105297685 A CN105297685 A CN 105297685A CN 201510817066 A CN201510817066 A CN 201510817066A CN 105297685 A CN105297685 A CN 105297685A
Authority
CN
China
Prior art keywords
pedestal
district
antiseepage
rock
rockfill dam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510817066.4A
Other languages
Chinese (zh)
Other versions
CN105297685B (en
Inventor
杨家修
湛正刚
程瑞林
张合作
慕洪友
蔡大咏
王蒙
邱焕峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201510817066.4A priority Critical patent/CN105297685B/en
Publication of CN105297685A publication Critical patent/CN105297685A/en
Application granted granted Critical
Publication of CN105297685B publication Critical patent/CN105297685B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The invention discloses a base concrete face rockfill dam and a construction method thereof, belonging to the technical field of hydroelectric engineering. According to the technical scheme, the base is arranged below the concrete faced rockfill dam, the layered structure is adopted, the height of a rockfill body of the concrete faced rockfill dam and the length of a face plate are reduced fundamentally, and the deformation of the concrete faced rockfill dam and the face plate is reduced on the premise of not reducing the elevation of the top of the dam, so that the face rockfill dam with higher design, construction and operation can meet the technical requirements more easily, the deformation is controlled in a controllable range, and the limitation that the height concrete faced rockfill dam cannot be higher than 250m level because the height concrete faced rockfill dam is greatly deformed is broken through.

Description

A kind of pedestal Concrete Face Rockfill Dam and construction method thereof
Technical field
The invention belongs to hydroelectric project technical field, relate to a kind of new dam type being suitable for more than 70m rock, especially relate to a kind of pedestal Concrete Face Rockfill Dam and construction method thereof.
Background technology
Make a general survey of rock development course, cross the 180m levels such as rock (height of dam 179.5m) develop into water cloth a strip of land between hills rock (height of dam 233m) from Tianshengqiao-I rock (height of dam 178m), big vast family, height of dam development maximum span reaches 53m; At present, built most high CFRD water cloth a strip of land between hills rock operational excellence, illustrates that China has possessed design, builds, the ability of operation and management 200m level rock.But several 200m level high CFRD of short-term construction are obtaining successfully and while invaluable experience, part engineering also occurs that dam deformation is bigger than normal than predicted value, the problems such as extruding is damaged, leakage is larger occur panel.If height of dam continues to be increased to more than 250m, compared with water cloth a strip of land between hills rock of the highest built 233m, comparatively large with spline span, will larger design be brought and build difficulty.Therefore, in current technical foundation, success builds 250m level or higher rock, and those skilled in the art there is no pure assurance.
Due to the characteristic of dam material, the distortion of runtime is inevitable in CFRD Embankment process and after retaining, but is out of shape and excessively will causes face slab rupture, joint seal destroys, thus increase leakage, even cause seepage stability destruction etc., threaten dam resistance to overturning.In addition, conventional panels loose rock dam height of dam increases, and panel chord length increases, and behind reservoir filling position, under effect of water pressure, deck deflection distortion increases, and is out of shape the excessive panel that may cause and fractures, and makes panel lose antiseepage function.Facts have proved, identical material source, grating and when filling index, height of dam is higher, and panel chord length is longer, dam deformation and deck deflection distortion larger.Existing result of study shows, one of key technology of restriction rock height of dam is exactly the Deformation control of panel and dam body stockpile.
Summary of the invention
In order to solve the problem, the invention provides a kind of pedestal Concrete Face Rockfill Dam and construction method thereof, thus reach reduction dam body rockfill height, reduce panel chord length, thus reduce the effect of dam deformation value, make distortion within controlled range, make upper panel loose rock dam height meet the design of current rock, construction, operation, administrative skill level.
The present invention is achieved by following technical solution.
A kind of pedestal Concrete Face Rockfill Dam, comprise rock, panel, bed course district and transition region a, described transition region a, bed course district and panel are covered on the upstream face of rock successively, described rock has pedestal, is provided with transition region b between described pedestal and rock.
Described pedestal comprises the pedestal antiseepage district of upstream side and the pedestal supporting region in downstream.
Described pedestal antiseepage district is provided with toe board district, pedestal top.
Inside, described pedestal antiseepage district is provided with pedestal irrigation gallery.
Seepage proof curtain is provided with below described pedestal antiseepage district.
Pedestal antiseepage district transverse joint is provided with in described pedestal antiseepage district.
Described panel is provided with panel vertical lap seam.
Described rock two ends are provided with toe board.
A construction method for pedestal Concrete Face Rockfill Dam, comprises the steps:
A. pedestal is built: remove dam foundation covering layer, by the degree of depth that dam foundation excavation to bearing capacity meets the demands, and system peace reinforcing bar in excavation region, under pedestal antiseepage district, preset seepage proof curtain, reserved pedestal irrigation gallery, jumps and builds pedestal concrete soon, take Temperature Control Measures simultaneously, prevent crack; Pedestal supporting region then according to material behavior determination on-deck size, and takes Temperature Control Measures;
B. pedestal Anti-seeping technology: carry out Anti-seeping technology to pedestal antiseepage district and pedestal supporting region interface, establishes pedestal antiseepage district transverse joint in pedestal antiseepage district, the position of pedestal antiseepage district transverse joint is corresponding with the position of panel vertical lap seam;
C. pedestal joint face process: fill Transition Materials at pedestal top, the filling material and the indices that form transition region b, transition region b are identical with transition region a;
D. CFRD Embankment: fill rock, transition region a, bed course district, panel successively, panel arranges panel vertical lap seam, with pedestal antiseepage district transverse joint position one_to_one corresponding, completes construction.
In described step a, when pedestal antiseepage district builds, reserved upstream thickness 1 ~ 5m, toe board district together builds with pedestal top, and carries out the concreting of bank slope toe board simultaneously.
The invention has the beneficial effects as follows:
A kind of pedestal Concrete Face Rockfill Dam of the present invention and construction method thereof, by arranging pedestal under rock, its effect is: 1. have employed hierarchy, fundamentally reduce height and the panel length of rock rockfill, under the prerequisite not reducing crest elevation, reduce the distortion of rock and panel, make design, build and run higher rock to be more prone to reach technical requirements, by Deformation control in controlled range, breach because high CFRD can not higher than the limitation of 250m level by distortion is comparatively large, 2. first construct before rock construction complete, completion can be passed the flood period by dash, avoids the destruction that flood season, bed course temporary water dash may cause dam body temporary section, shortens the time of bed course provisional protection, reduce the maintenance cost of bed course provisional protection, also reduce the investment to construction diversion simultaneously.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the partial enlarged drawing at A place in the present invention;
Fig. 3 is the elevation of pedestal upstream face in the present invention.
In figure: 1-pedestal, 2-rock, 3-panel, 4-bed course district, 5-transition region a, 6-transition region b, 7-pedestal supporting region, 8-pedestal antiseepage district, toe board district, 9-pedestal top, 10-pedestal antiseepage district transverse joint, 11-pedestal irrigation gallery, 12-seepage proof curtain, 13-toe board, 14-panel vertical lap seam.
Detailed description of the invention
Technical scheme of the present invention is further described below in conjunction with accompanying drawing, but described in claimed scope is not limited to.
As shown in Figure 1, Figure 2, Figure 3 shows, a kind of pedestal Concrete Face Rockfill Dam of the present invention, comprise rock 2, panel 3, bed course district 4 and transition region a5, described transition region a5, bed course district 4 and panel 3 are covered on the upstream face of rock 2 successively, described rock 2 has pedestal 1, transition region b6 is provided with, as filling Transition Materials between described pedestal 1 and rock 2.
Described pedestal 1 comprises the pedestal antiseepage district 8 of upstream side and the pedestal supporting region 7 in downstream, pedestal 1 is highly less than 100m, pedestal supporting region 7 can be built up by one or more batch mixings in the rigid materials such as normal concrete, roller compacted concrete, cement sand and gravel, rock-fill concrete, and after building up, its rigidity is suitable with the dam foundation; Pedestal antiseepage district 8 is built up by normal concrete; Described pedestal antiseepage district 8 is provided with toe board district, pedestal top 9, and inside is provided with pedestal irrigation gallery 11, and below is provided with seepage proof curtain 12, carries out antiseepage to multiple position, reaches good anti-seepage effect.
Described panel 3 is provided with panel vertical lap seam 14, makes panel 3 can bear certain deflection; Be provided with some pedestal antiseepage districts transverse joint 10 along river vertical direction in described pedestal antiseepage district 8, the position of each pedestal antiseepage district transverse joint 10 is corresponding with panel vertical lap seam 14, establishes Copper water stop in seam.
Described rock 2 is conventional rock, rock 2 and panel 3, bed course 4, transition region a5 are all based on pedestal 1, and the upper surface of pedestal 1 is greater than the length of rock 2 bottom surface along direction, river course along the length in direction, river course, the step surface that pedestal 1 upstream side extends out, namely top, pedestal antiseepage district 8 is provided with toe board district, pedestal top 9, wide 8 ~ the 15m in toe board district, pedestal top 9, thick 1 ~ 2m, adopt more than C30 concreting; Pedestal 1 two ends are then provided with toe board 13, and toe board structure can avoid rock 2 be subject to current scour with the crossover position of pedestal 1 and seepage occurs.
Described pedestal 1 along the river to length L be the H that 15 ~ 100m adds 2.9 ~ 3.2 times, wherein H is the height of rock 2; Pedestal 1 puts slope respectively to upstream and downstream, and slope is than determining according to actual conditions.
During construction, take following steps:
A. pedestal is built: remove dam foundation covering layer, by the degree of depth that dam foundation excavation to bearing capacity meets the demands, and system peace reinforcing bar in excavation region, determine position, pedestal antiseepage district 8, in pedestal antiseepage district, 8 times default seepage proof curtains 12, then build pedestal concrete, reserve pedestal irrigation gallery 11 when building.When building, can first build pedestal supporting region 7, also can build rising with pedestal supporting region 7 in pedestal antiseepage district 8 simultaneously, and Anti-seeping technology is carried out to pedestal antiseepage district 8 and pedestal supporting region 7 interface; When pedestal antiseepage district 8 builds, adopt C20 or more than C20 normal concrete to jump and build soon, take Temperature Control Measures simultaneously, prevent crack; Reserved upstream thickness 1 ~ 5m, together builds with toe board district, pedestal top 9, and carry out the concreting of bank slope toe board 13 while building pedestal 1, and corresponding based process; Building then according to material behavior determination on-deck size of pedestal supporting region 7, guarantees the intensity reaching rock, and takes suitable Temperature Control Measures when building.
B. pedestal Anti-seeping technology: carry out Anti-seeping technology to pedestal antiseepage district 8 and pedestal supporting region 7 interface, establishes pedestal antiseepage district transverse joint 10 in pedestal antiseepage district 8, the position of pedestal antiseepage district transverse joint 10 is corresponding with the design attitude of panel vertical lap seam 14.
C. pedestal joint face process: fill Transition Materials at pedestal 1 top, the filling material and the indices that form transition region b6, transition region b6 are identical with the design objective of transition region a5, and filling-up thickness is then determined according to actual conditions;
D. CFRD Embankment: fill rock 2, transition region a5, bed course district 4, panel 3 successively, panel 3 arranges panel vertical lap seam 14, with transverse joint 10 position, pedestal antiseepage district one_to_one corresponding, panel 3 construction can carry out stage construction according to height of dam, realizes impoundment ahead generating.

Claims (10)

1. a pedestal Concrete Face Rockfill Dam, comprise rock (2), panel (3), bed course district (4) and transition region a (5), described transition region a (5), bed course district (4) and panel (3) are covered on the upstream face of rock (2) successively, it is characterized in that: described rock (2) has pedestal (1), between described pedestal (1) and rock (2), be provided with transition region b (6).
2. a kind of pedestal Concrete Face Rockfill Dam according to claim 1, is characterized in that: described pedestal (1) comprises the pedestal antiseepage district (8) of upstream side and the pedestal supporting region (7) in downstream.
3. a kind of pedestal Concrete Face Rockfill Dam according to claim 2, is characterized in that: described pedestal antiseepage district (8) is provided with toe board district, pedestal top (9).
4. a kind of pedestal Concrete Face Rockfill Dam according to claim 2, is characterized in that: described pedestal antiseepage district (8) inside is provided with pedestal irrigation gallery (11).
5. a kind of pedestal Concrete Face Rockfill Dam according to claim 2, is characterized in that: described pedestal antiseepage district (8) below is provided with seepage proof curtain (12).
6. a kind of pedestal Concrete Face Rockfill Dam according to claim 2, is characterized in that: be provided with pedestal antiseepage district transverse joint (10) in described pedestal antiseepage district (8).
7. a kind of pedestal Concrete Face Rockfill Dam according to claim 1, is characterized in that: described panel (3) is provided with panel vertical lap seam (14).
8. a kind of pedestal Concrete Face Rockfill Dam according to claim 1, is characterized in that: described rock (2) two ends are provided with toe board (13).
9. a construction method for pedestal Concrete Face Rockfill Dam, is characterized in that: comprise the steps:
A. pedestal is built: remove dam foundation covering layer, by the degree of depth that dam foundation excavation to bearing capacity meets the demands, system peace reinforcing bar in excavation region, 8 times default seepage proof curtains 12 in pedestal antiseepage district, reserved pedestal irrigation gallery 11, jump and build pedestal concrete soon, take Temperature Control Measures simultaneously, prevent crack; Building then according to material behavior determination on-deck size of pedestal supporting region 7, and take Temperature Control Measures when building;
B. pedestal Anti-seeping technology: carry out Anti-seeping technology to pedestal antiseepage district 8 and pedestal supporting region 7 interface, establishes pedestal antiseepage district transverse joint 10 in pedestal antiseepage district 8, the position of pedestal antiseepage district transverse joint 10 is corresponding with the position of panel vertical lap seam 14;
C. pedestal joint face process: fill Transition Materials at pedestal 1 top, the filling material and the indices that form transition region b6, transition region b6 are identical with transition region a5;
D. CFRD Embankment: fill rock 2, transition region a5, bed course district 4, panel 3 successively, panel 3 arranges panel vertical lap seam 14, with transverse joint 10 position, pedestal antiseepage district one_to_one corresponding, completes construction.
10. the construction method of a kind of pedestal Concrete Face Rockfill Dam as claimed in claim 9, it is characterized in that: in described step a, when pedestal antiseepage district 8 builds, reserved upstream thickness 1 ~ 5m, together build with toe board district, pedestal top 9, and carry out the concreting of bank slope toe board 13 simultaneously.
CN201510817066.4A 2015-11-23 2015-11-23 Base concrete panel rock-fill dam and construction method thereof Active CN105297685B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510817066.4A CN105297685B (en) 2015-11-23 2015-11-23 Base concrete panel rock-fill dam and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510817066.4A CN105297685B (en) 2015-11-23 2015-11-23 Base concrete panel rock-fill dam and construction method thereof

Publications (2)

Publication Number Publication Date
CN105297685A true CN105297685A (en) 2016-02-03
CN105297685B CN105297685B (en) 2017-10-24

Family

ID=55195448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510817066.4A Active CN105297685B (en) 2015-11-23 2015-11-23 Base concrete panel rock-fill dam and construction method thereof

Country Status (1)

Country Link
CN (1) CN105297685B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672205A (en) * 2016-03-29 2016-06-15 中国电建集团中南勘测设计研究院有限公司 Seepage prevention structure of concrete face rockfill dam
CN106087880A (en) * 2016-07-19 2016-11-09 中国水利水电第十工程局有限公司 Dam that a kind of 300 meter levels are high and construction technology thereof
CN106192907A (en) * 2016-07-11 2016-12-07 中国水利水电第十工程局有限公司 Set up the construction method of 150m~the 300m level high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN106638487A (en) * 2017-01-19 2017-05-10 中国电力建设股份有限公司 Combined water retaining dam and construction method of combined water retaining dam
CN107587484A (en) * 2017-08-31 2018-01-16 贵州省水利水电勘测设计研究院 A kind of rock for exempting from toe board structure
CN108316250A (en) * 2018-05-02 2018-07-24 中国电建集团华东勘测设计研究院有限公司 Technology and construction method are cleared using the silt that stops for dynamically stopping silt storage capacity separation mud-rock flow
CN108547190A (en) * 2018-06-22 2018-09-18 中国电建集团贵阳勘测设计研究院有限公司 Ecological type water-soaking embankment treatment method
CN110042800A (en) * 2019-05-24 2019-07-23 中水北方勘测设计研究有限责任公司 Concrete face rockfill dam leakage preventing structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB715126A (en) * 1950-07-27 1954-09-08 Wilhelm Degen Water-tight seals for dams, etc
CN102900092A (en) * 2012-09-24 2013-01-30 长江勘测规划设计研究有限责任公司 Artificial composite foundation of concrete face rockfill dam built on deep and thick coverage layer and construction method of artificial composite foundation
CN103132488A (en) * 2011-11-25 2013-06-05 中国水电顾问集团贵阳勘测设计研究院 Reverse osmosis water processing method and reverse osmosis drainage system in construction period of concrete faced rockfill dam
CN104120686A (en) * 2014-07-28 2014-10-29 中国电建集团西北勘测设计研究院有限公司 High elastic die cushion type composite dam
CN204059294U (en) * 2014-07-07 2014-12-31 黄河勘测规划设计有限公司 Deeply covered layer face dam riverbed toe board, junction plate, panel parting arrangement
CN104480903A (en) * 2014-12-12 2015-04-01 中国电建集团贵阳勘测设计研究院有限公司 Concrete panel rock-fill dam panel parting structure and construction method thereof
CN205134283U (en) * 2015-11-20 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Base concrete panel rock-fill dam

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB715126A (en) * 1950-07-27 1954-09-08 Wilhelm Degen Water-tight seals for dams, etc
CN103132488A (en) * 2011-11-25 2013-06-05 中国水电顾问集团贵阳勘测设计研究院 Reverse osmosis water processing method and reverse osmosis drainage system in construction period of concrete faced rockfill dam
CN102900092A (en) * 2012-09-24 2013-01-30 长江勘测规划设计研究有限责任公司 Artificial composite foundation of concrete face rockfill dam built on deep and thick coverage layer and construction method of artificial composite foundation
CN204059294U (en) * 2014-07-07 2014-12-31 黄河勘测规划设计有限公司 Deeply covered layer face dam riverbed toe board, junction plate, panel parting arrangement
CN104120686A (en) * 2014-07-28 2014-10-29 中国电建集团西北勘测设计研究院有限公司 High elastic die cushion type composite dam
CN104480903A (en) * 2014-12-12 2015-04-01 中国电建集团贵阳勘测设计研究院有限公司 Concrete panel rock-fill dam panel parting structure and construction method thereof
CN205134283U (en) * 2015-11-20 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Base concrete panel rock-fill dam

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672205A (en) * 2016-03-29 2016-06-15 中国电建集团中南勘测设计研究院有限公司 Seepage prevention structure of concrete face rockfill dam
CN106192907A (en) * 2016-07-11 2016-12-07 中国水利水电第十工程局有限公司 Set up the construction method of 150m~the 300m level high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN106192907B (en) * 2016-07-11 2018-06-22 中国水利水电第十一工程局有限公司 Add the construction method of 150m~300m grade high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN106087880A (en) * 2016-07-19 2016-11-09 中国水利水电第十工程局有限公司 Dam that a kind of 300 meter levels are high and construction technology thereof
CN106087880B (en) * 2016-07-19 2018-10-19 中国水利水电第十一工程局有限公司 A kind of dam that 300 meter level is high and its construction technology
CN106638487A (en) * 2017-01-19 2017-05-10 中国电力建设股份有限公司 Combined water retaining dam and construction method of combined water retaining dam
CN106638487B (en) * 2017-01-19 2019-10-25 中国电力建设股份有限公司 A kind of construction method combining checkdam and the combined dam
CN107587484A (en) * 2017-08-31 2018-01-16 贵州省水利水电勘测设计研究院 A kind of rock for exempting from toe board structure
CN108316250A (en) * 2018-05-02 2018-07-24 中国电建集团华东勘测设计研究院有限公司 Technology and construction method are cleared using the silt that stops for dynamically stopping silt storage capacity separation mud-rock flow
CN108547190A (en) * 2018-06-22 2018-09-18 中国电建集团贵阳勘测设计研究院有限公司 Ecological type water-soaking embankment treatment method
CN110042800A (en) * 2019-05-24 2019-07-23 中水北方勘测设计研究有限责任公司 Concrete face rockfill dam leakage preventing structure

Also Published As

Publication number Publication date
CN105297685B (en) 2017-10-24

Similar Documents

Publication Publication Date Title
CN205134283U (en) Base concrete panel rock-fill dam
CN105297685A (en) Base concrete panel rock-fill dam and construction method thereof
CN104480974B (en) Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN101644041B (en) Face rockfill dam toe board structure constructed on completely weathered bed rock and construction method thereof
CN104120686B (en) A kind of high-elastic die-cushion A seating compound dam
CN204023501U (en) A remove dangerous and consolidate prevention of seepage processing structure for earth and rockfill dam
CN103233446B (en) Composite material face earth and rockfill dam and impervious body construction method thereof
CN205012288U (en) Embankment dam pitch core -wall base
CN104878783A (en) Super-long basement concrete base plate deformation joint leakage prevention and leakage treatment method
CN104846781A (en) Ecological interlocking block and ecological interlocking block type slope protection construction method
CN104099903A (en) High-base asphalt concrete core wall dam
CN203514256U (en) Sash type river bank revetment structure
CN107059878A (en) A kind of construction method for being applied to river course across Metro station excavation
CN204435430U (en) A kind of reverse row being applicable to upstream type Tailings Dam oozes system and upstream type Tailings Dam
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
CN207567892U (en) A kind of large size karst depression flood drainage system
CN103061351B (en) Prevent the device that basement bottom board swells, seeps water
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN106149640A (en) Improve method and the double-drainage body rock of rock infiltration security
CN102587329A (en) Arched combined faceplate for earth-rock dam and construction method thereof
CN105297679A (en) Seepage-proofing method and structure for upstream surface layer of rock-fill dam
CN206189430U (en) A escape canal for deep overburden ground
CN104929081A (en) Enrockment concrete permeable dike and construction method thereof
CN212896195U (en) Double-layer geomembrane core wall rock-fill dam structure
CN204551378U (en) Seepage-proofing structure of upstream surface layer of rock-fill dam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant