CN110042800A - Concrete face rockfill dam leakage preventing structure - Google Patents

Concrete face rockfill dam leakage preventing structure Download PDF

Info

Publication number
CN110042800A
CN110042800A CN201910440994.1A CN201910440994A CN110042800A CN 110042800 A CN110042800 A CN 110042800A CN 201910440994 A CN201910440994 A CN 201910440994A CN 110042800 A CN110042800 A CN 110042800A
Authority
CN
China
Prior art keywords
concrete
geomembrane
strength
leakage preventing
preventing structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910440994.1A
Other languages
Chinese (zh)
Inventor
王立成
田新星
马妹英
李端阳
翟政
刘晶
孙亮科
宋慧
刘喜斌
付茂鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Water Resources Beifang Investigation Design and Research Co Ltd
Original Assignee
China Water Resources Beifang Investigation Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Water Resources Beifang Investigation Design and Research Co Ltd filed Critical China Water Resources Beifang Investigation Design and Research Co Ltd
Priority to CN201910440994.1A priority Critical patent/CN110042800A/en
Publication of CN110042800A publication Critical patent/CN110042800A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/06Earth-fill dams; Rock-fill dams

Abstract

The invention discloses a kind of concrete face rockfill dam antiseepage patterns, including high-strength geomembrane, concrete slab, grout curtain, rock ballast lid weight, Transition Materials, bed course area, main rockfill area, secondary rockfill area etc., conventional concrete panel top half is changed to the pattern of high-strength polyethylene film for earthwork, plays the role of antiseepage using the impermeability of geomembrane.Secondary rockfill area uses the biggish rockfill materials of deformation modulus, and geomembrane is adapted to the deformation of secondary rockfill area thereafter.This dam body pattern is simple, speed of application is very fast, lower to the building stones requirement of secondary rockfill area, easy for construction.

Description

Concrete face rockfill dam leakage preventing structure
Technical field
The present invention relates to concrete face rockfill dam, especially a kind of concrete face rockfill dam leakage preventing structure.
Background technique
Concrete face rockfill dam is a kind of common local material dam pattern.It is filled by stockpile layered rolling Dam body plays a supportive role, and armored concrete panel is arranged at its upstream as impervious body.
Typical concrete face rockfill dam is by upstream head weight body, panel, bed course area, transition region, main rockfill area, secondary enrockment The part such as area, downstream protection slope forms.Concrete face rockfill dam is excellent since its safety is good, adaptable, speed of application is fast etc. Point is become a kind of competitive dam type by the favor and attention of Ba Gongjie.
In the design and construction of concrete face rockfill dam, control deformation and crack are always that the core of engineering concern is asked Topic.The crack of concrete slab is broadly divided into two class of structural crack and non-structural crack.Structural crack is mainly in water Under load action, Rockfill Dam generates differential settlement deformation and displacement causes caused by panel and dam body come to nothing.Non- knot Structure crack is mainly concrete slab due to by complex boundary constraint condition, temperature, humidity environment variation, concrete surface board foot The influence of the factors such as very little, is easy to appear contraction fissure caused by non-loading cracks.The appearance of panel crack not only reduces its use Function, and the structure durability of dam body itself is influenced very big.For control critical eigenvalue, before panel concrete construction, dam body The pre- subsidence stage of general setting 4~6 months, influences the construction period to a certain extent.
Summary of the invention
The technical problem to be solved by the invention is to provide a kind of concrete face rockfill dam leakage preventing structures, by concrete Panel height reduces, and difficulty of construction reduces, and panel is located under water, and construction quality is guaranteed.On top using high-strength soil Work film replaces concrete slab antiseepage, can well adapt to the deformation of secondary rockfill area thereafter, effective to reduce top water pressure, Increase safety of dam body.
To solve the above-mentioned problems, the technical scheme adopted by the invention is that: a kind of concrete face rockfill dam antiseepage knot Structure, including concrete toe board, upstream rock ballast lid weight, upstream apron, downstream rock ballast lid weight, grout curtain, upstream bulwark, downstream Barricade, in upstream dam facing, using successively by Transition Materials, bed course area, concrete surface within the scope of from dam bottom to 1/2~2/3 times of height of dam Plate constitutes traditional concrete slab;Traditional concrete slab with up to dam crest use high-strength geomembrane anti-seepage pattern, Concrete protective plate is arranged in high-strength geomembrane top, and geomembrane bed course is arranged in lower part, and high-strength geomembrane lower end extends Concrete surface intralamellar part and fixation to lower part, high-strength geomembrane upper end extend to inside the bulwark of upstream side and fixed.
Traditional concrete slab be located at ordinary water level hereinafter, its material be armored concrete, strength grade >= C30, seepage-resistant grade >=W8.
The material of the high-strength geomembrane is high-intensitive reinforcement polyethylene film for earthwork, geomembrane nominal thickness >= 3.0mm, density >=0.94g/cm3, vertically and horizontally tensile yield strength >=40N/mm, vertically and horizontally tensile break strength >=60N/mm, Vertically and horizontally yield elongation rate >=11%, vertically and horizontally elongation at break >=600%, vertically and horizontally right-angle tearing load >=340N, anti-thorn Wear intensity >=720N, water vapor permeation coefficient≤1 × 10-13cm/s。
Built-in length >=0.5m of concrete surface intralamellar part is protruded into high-strength geomembrane lower end.
Built-in length >=0.5m inside the bulwark of upstream is protruded into high-strength geomembrane upper end.
Plate thickness >=0.2m of the concrete protective plate.
The geomembrane bed course has continuous grading, 80~100mm of maximum particle diameter, cushion thickness >=0.3m.
The concrete protective plate be armored concrete, concrete be normal silicate low-heat cement, concrete strength >= C25, plate thickness >=0.2m.
Corresponding behind traditional concrete slab is main rockfill area, right behind high-strength geomembrane anti-seepage pattern What is answered is time rockfill area.
Beneficial effects of the present invention: geomembrane has good ductility, and adaptive deformation ability is strong, can well adapt to secondary The deformation of rockfill area, and the dam type subregion is simple, speed of application is fast, needless to say dam body settlement completion can carry out geomembrane anti-seepage Construction.It can accelerate construction progress, shorten the period, engineering is made to play benefit in advance.
Detailed description of the invention
Fig. 1 is concrete face rockfill dam leakage preventing structure typical section figure of the invention.
Specific embodiment
Invention is further described in detail with reference to the accompanying drawings and detailed description:
As shown in Figure 1, concrete face rockfill dam leakage preventing structure of the invention, including concrete toe board 1, upstream rock ballast lid Weigh 10, upstream apron 11, downstream rock ballast lid weighs 12, grout curtain 13, upstream bulwark 14, downstream barricade 15, which is characterized in that In upstream dam facing, using successively by Transition Materials 6, bed course area 5, concrete slab 2 within the scope of from dam bottom to 1/2~2/3 times of height of dam Constitute traditional concrete slab;Traditional concrete slab is high to use high-strength geomembrane anti-seepage pattern up to dam crest Concrete protective plate 7 is arranged in strong 8 top of reinforced earth film, and geomembrane bed course 9 is arranged in lower part, and 8 lower end of high-strength geomembrane is prolonged It extends to 2 inside of concrete slab of lower part and fixes, 8 upper end of high-strength geomembrane extends to 14 inside of upstream side bulwark simultaneously It is fixed.
Traditional concrete slab 2 be located at ordinary water level hereinafter, its material be armored concrete, strength grade >= C30, seepage-resistant grade >=W8.
The material of the high-strength geomembrane 8 is high-intensitive reinforcement polyethylene film for earthwork, geomembrane nominal thickness >= 3.0mm, density >=0.94g/cm3, vertically and horizontally tensile yield strength >=40N/mm, vertically and horizontally tensile break strength >=60N/mm, Vertically and horizontally yield elongation rate >=11%, vertically and horizontally elongation at break >=600%, vertically and horizontally right-angle tearing load >=340N, anti-thorn Wear intensity >=720N, water vapor permeation coefficient≤1 × 10-13cm/s。
Built-in length >=0.5m inside concrete slab 2 is protruded into 8 lower end of high-strength geomembrane.
Built-in length >=0.5m inside upstream bulwark 14 is protruded into 8 upper end of high-strength geomembrane.
Plate thickness >=0.2m of the concrete protective plate 7.
The geomembrane bed course 9 has continuous grading, 80~100mm of maximum particle diameter, cushion thickness >=0.3m.
The concrete protective plate 7 be armored concrete, concrete be normal silicate low-heat cement, concrete strength >= C25, plate thickness >=0.2m.
Corresponding behind traditional concrete slab is main rockfill area 3, behind high-strength geomembrane anti-seepage pattern Corresponding is time rockfill area 4.
Specifically, concrete toe board 1 and 2 tail portion of concrete slab setting upstream rock ballast lid weigh 10 and upstream apron 11, Grout curtain 13 is arranged in toe board bottom.
Concrete slab height is reduced to the 1/2~2/3 of height of dam, is replaced at an upper portion thereof with high-strength geomembrane, soil Work film surface be arranged concrete slab carry out slope protection, play prevent geomembrane to be punctured, be anti-sun, age inhibiting effect, soil Work film rear portion uses thin layer bedding material.Geomembrane lower end is protruded into concrete slab, and built-in length >=0.5m, upstream is protruded into upper end It is inside the bulwark of side and fixed, built-in length >=0.5m.In toe board bottom, grout curtain is set.Geomembrane, panel, toe board, curtain Curtain grouting collectively constitutes the seepage prevention system of entire concrete face rockfill dam.Bed course area, transition are set gradually after concrete slab Area and main rockfill area, main rockfill area use the preferable grit material of gradation.Bed course area, secondary rockfill area are set gradually after geomembrane, it is secondary Rockfill area uses slightly soft dam material.
Be specifically described below, in the present embodiment, after the completion of dam foundation excavation, carry out first main 3 dam embankment of rockfill area, The construction of concrete slab 2, bed course area 5, Transition Materials 6 and concrete toe board 1, form of construction work and requirement and conventional concrete panel Rock-fill dam construction mode is identical.When within the scope of construction of concrete face slab to top 1m, start to carry out high-strength geomembrane 8 Construction guarantees that high-strength geomembrane 8 protrudes into concrete slab length not less than 0.5m, then begins to carry out time rockfill area 4 to apply The softer material that fills can be used in work, secondary rockfill area 4, and the sedimentation completely of main rockfill area 3 need not be waited to complete (to generally require 4~6 Month) time rockfill area 4 can be carried out fill.Then it is sequentially completed time rockfill area 4, geomembrane bed course 9, high-strength geomembrane 8, soil The construction of bulwark 15,14 at the top of work film concrete protective plate 7 and dam body, when construction, need to guarantee that high-strength geomembrane 8 is stretched Enter length >=0.5m in bulwark, thickness >=0.2m of concrete protective plate 7, geomembrane bed course thickness >=0.3m, in axis of dam side To if desired muti-piece geomembrane, using overlapping mode, the lap of splice >=1m.Finally, upstream is respectively set in dam body upstream slope foot Bedding 11 and upstream rock ballast lid weigh 10, and in downstream, slope foot setting downstream rock ballast lid weighs 12, and entire construction is completed.
Above-mentioned example is merely to illustrate technical idea and feature of the invention, and its object is to make technology in the art Personnel only cannot limit the scope of the patents of the invention with this example it will be appreciated that the contents of the present invention and implement accordingly, i.e., all Same changes or modifications made by disclosed spirit, still fall in the scope of the patents of the invention.

Claims (9)

1. a kind of concrete face rockfill dam leakage preventing structure, including concrete toe board (1), upstream rock ballast lid weight (10), upstream paving Cover (11), downstream rock ballast lid weight (12), grout curtain (13), upstream bulwark (14), downstream barricade (15), which is characterized in that In upstream dam facing, using successively by Transition Materials (6), bed course area (5), concrete surface within the scope of from dam bottom to 1/2~2/3 times of height of dam Plate (2) constitutes traditional concrete slab;Traditional concrete slab is to use high-strength geomembrane anti-seepage type up to dam crest Concrete protective plate (7) are arranged in formula, high-strength geomembrane (8) top, and geomembrane bed course (9) are arranged in lower part, high-strength soil The concrete slab (2) that work film (8) lower end extends to lower part is internal and fixed, and high-strength geomembrane (8) upper end extends to It is internal and fixed to swim side bulwark (14).
2. concrete face rockfill dam leakage preventing structure according to claim 1, which is characterized in that traditional concrete surface Plate (2) is located at ordinary water level hereinafter, its material is armored concrete, strength grade >=C30, seepage-resistant grade >=W8.
3. concrete face rockfill dam leakage preventing structure according to claim 1, which is characterized in that the high-strength geomembrane (8) material is high-intensitive reinforcement polyethylene film for earthwork, geomembrane nominal thickness >=3.0mm, density >=0.94g/cm3, in length and breadth To tensile yield strength >=40N/mm, vertically and horizontally tensile break strength >=60N/mm, vertically and horizontally yield elongation rate >=11%, in length and breadth To elongation at break >=600%, vertically and horizontally right-angle tearing load >=340N, anti-puncture intensity >=720N, water vapor permeation coefficient ≤1×10-13cm/s。
4. concrete face rockfill dam leakage preventing structure according to claim 1, which is characterized in that the high-strength geomembrane (8) the internal built-in length >=0.5m of concrete slab (2) is protruded into lower end.
5. concrete face rockfill dam leakage preventing structure according to claim 1, which is characterized in that the high-strength geomembrane (8) the internal built-in length >=0.5m of upstream bulwark (14) is protruded into upper end.
6. concrete face rockfill dam leakage preventing structure according to claim 1, which is characterized in that the concrete protective plate (7) plate thickness >=0.2m.
7. concrete face rockfill dam leakage preventing structure according to claim 1, which is characterized in that the geomembrane bed course (9) With continuous grading, 80~100mm of maximum particle diameter, cushion thickness >=0.3m.
8. concrete face rockfill dam leakage preventing structure according to claim 1, which is characterized in that the concrete protective plate It (7) is armored concrete, concrete is normal silicate low-heat cement, concrete strength >=C25, plate thickness >=0.2m.
9. any one of -8 concrete face rockfill dam leakage preventing structure according to claim 1, which is characterized in that described traditional Corresponding behind concrete slab is main rockfill area (3), and corresponding behind high-strength geomembrane anti-seepage pattern is time rockfill area (4)。
CN201910440994.1A 2019-05-24 2019-05-24 Concrete face rockfill dam leakage preventing structure Pending CN110042800A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910440994.1A CN110042800A (en) 2019-05-24 2019-05-24 Concrete face rockfill dam leakage preventing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910440994.1A CN110042800A (en) 2019-05-24 2019-05-24 Concrete face rockfill dam leakage preventing structure

Publications (1)

Publication Number Publication Date
CN110042800A true CN110042800A (en) 2019-07-23

Family

ID=67283529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910440994.1A Pending CN110042800A (en) 2019-05-24 2019-05-24 Concrete face rockfill dam leakage preventing structure

Country Status (1)

Country Link
CN (1) CN110042800A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110499743A (en) * 2019-07-29 2019-11-26 中电建十一局工程有限公司 A kind of overlay film cemented gravel dam and its method of construction
CN111395267A (en) * 2020-04-24 2020-07-10 中水北方勘测设计研究有限责任公司 Core wall rock-fill dam
CN113006006A (en) * 2021-03-11 2021-06-22 中国水电基础局有限公司 Novel panel structure of panel rock-fill dam and construction method thereof
CN114561914A (en) * 2022-03-04 2022-05-31 中国电建集团西北勘测设计研究院有限公司 Drainage structure in concrete panel rock-fill dam cushion zone in cold region

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6612779B1 (en) * 1998-12-10 2003-09-02 Capri Tech Italia S.R.L. Embankment dam and waterproofing method
CN103643656A (en) * 2013-11-22 2014-03-19 河海大学 High rock-fill dam membrane anti-seepage body on deep coverage layer and construction method of high rock-fill dam membrane anti-seepage body
CN105297685A (en) * 2015-11-23 2016-02-03 中国电建集团贵阳勘测设计研究院有限公司 Base concrete face rock fill dam and construction method thereof
CN205934862U (en) * 2016-08-17 2017-02-08 中国电建集团西北勘测设计研究院有限公司 Local high -modulus enrockment concrete -faced rockfill dam structure
CN108005031A (en) * 2017-12-31 2018-05-08 华北水利水电大学 Based on LINE-X flexible panel rock-fill dams
CN210395248U (en) * 2019-05-24 2020-04-24 中水北方勘测设计研究有限责任公司 Concrete face rockfill dam seepage prevention structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6612779B1 (en) * 1998-12-10 2003-09-02 Capri Tech Italia S.R.L. Embankment dam and waterproofing method
CN103643656A (en) * 2013-11-22 2014-03-19 河海大学 High rock-fill dam membrane anti-seepage body on deep coverage layer and construction method of high rock-fill dam membrane anti-seepage body
CN105297685A (en) * 2015-11-23 2016-02-03 中国电建集团贵阳勘测设计研究院有限公司 Base concrete face rock fill dam and construction method thereof
CN205934862U (en) * 2016-08-17 2017-02-08 中国电建集团西北勘测设计研究院有限公司 Local high -modulus enrockment concrete -faced rockfill dam structure
CN108005031A (en) * 2017-12-31 2018-05-08 华北水利水电大学 Based on LINE-X flexible panel rock-fill dams
CN210395248U (en) * 2019-05-24 2020-04-24 中水北方勘测设计研究有限责任公司 Concrete face rockfill dam seepage prevention structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110499743A (en) * 2019-07-29 2019-11-26 中电建十一局工程有限公司 A kind of overlay film cemented gravel dam and its method of construction
CN111395267A (en) * 2020-04-24 2020-07-10 中水北方勘测设计研究有限责任公司 Core wall rock-fill dam
CN113006006A (en) * 2021-03-11 2021-06-22 中国水电基础局有限公司 Novel panel structure of panel rock-fill dam and construction method thereof
CN114561914A (en) * 2022-03-04 2022-05-31 中国电建集团西北勘测设计研究院有限公司 Drainage structure in concrete panel rock-fill dam cushion zone in cold region
CN114561914B (en) * 2022-03-04 2024-01-19 中国电建集团西北勘测设计研究院有限公司 Drainage structure for bedding layer area of concrete face rockfill dam in cold area

Similar Documents

Publication Publication Date Title
CN110042800A (en) Concrete face rockfill dam leakage preventing structure
CN103643656B (en) High rock-fill dam membrane anti-seepage body on deep coverage layer and construction method of high rock-fill dam membrane anti-seepage body
CN111395267A (en) Core wall rock-fill dam
CN210395248U (en) Concrete face rockfill dam seepage prevention structure
CN108457249B (en) Structural design and construction method of composite panel gravel dam
CN108316251A (en) A method of Face Slab of Concrete of Rock-fill Dam is reinforced using superhigh tenacity cement-base composite material
CN110939104A (en) Mixed seepage-proofing dam
Ma et al. Key technical problems of extra-high concrete faced rock-fill dam
CN208981282U (en) A kind of high earthquake territory concrete face rockfill dam dam crest structure
CN106368176B (en) The high dam structure being built on earth material scarcity area deeply covered layer
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
CN110080282A (en) A kind of self-anchored type band tooth grid reinforced retaining wall structure and its reinforcement means
CN106087880A (en) Dam that a kind of 300 meter levels are high and construction technology thereof
CN110374060A (en) A kind of the reservoir seepage-proofing structure and construction method of rock-fill dams dam facing and earth and stone material backfill bottom storehouse
CN110158542A (en) The Lossless connection structure and construction method of cut-pff wall and nut cap concrete
CN113106931A (en) Core wall dam that can be under construction fast
CN211080254U (en) Structure for increasing backfill height of existing high-fill tunnel
CN107881987A (en) Deep covering layer top panel Rockfill Dam based moisture barrier structure
CN206736649U (en) A kind of light road bank structure
CN106120663B (en) A kind of concrete face rockfill dam
Emiroglu Influences on selection of the type of dam
CN212000904U (en) Mixed seepage-proofing dam
CN213204004U (en) Repair and reinforcement structure for canal slopes on two banks under downstream bridge of main canal river entering section
CN212223936U (en) A protective structure that is used for mountain area to adopt sand river course inner bridge pile foundation to expose disease
CN111021506A (en) Seepage-proofing intercepting drain structure capable of resisting foundation deformation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination