CN207452600U - Post and track monoblock type constructing structure are cheated in subway inspection - Google Patents

Post and track monoblock type constructing structure are cheated in subway inspection Download PDF

Info

Publication number
CN207452600U
CN207452600U CN201721240992.0U CN201721240992U CN207452600U CN 207452600 U CN207452600 U CN 207452600U CN 201721240992 U CN201721240992 U CN 201721240992U CN 207452600 U CN207452600 U CN 207452600U
Authority
CN
China
Prior art keywords
track
bolt
post
connecting plate
monoblock type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721240992.0U
Other languages
Chinese (zh)
Inventor
施智亮
万广平
顾巍麟
陈睿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201721240992.0U priority Critical patent/CN207452600U/en
Application granted granted Critical
Publication of CN207452600U publication Critical patent/CN207452600U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The utility model provides a kind of subway inspection hole post and track monoblock type constructing structure,The structure includes setting up the track supporting rack of two parallel orbits,Bolt embedment sleeve,Connect bolt,Nut,Connecting plate,And embedded board,Subway inspection is equipped between two parallel orbits to cheat,The both sides of track are respectively equipped with the connecting plate of horizontal-extending a distance outward,The first bolt hole passed through for connection bolt is opened up on connecting plate,Embedded board is arranged at the lower section of track and two side connecting plates,Using connecting the first bolt hole of bolt drawing-in connecting plate and the second bolt hole of embedded board and the upper of bolt will be connected,Lower end is respectively adopted nut and is locked with bolt embedment sleeve,Bolt embedment sleeve is stretched into the post reinforcing bar,Utilize the reversed fixing bolt embedded sleeve barrel of track,Track laying is realized disposably to be installed in place,Ensure the precision that track is set up,Avoid the secondary adjustment of track,Civil engineering finished product can be protected again and can be saved the duration.

Description

Post and track monoblock type constructing structure are cheated in subway inspection
Technical field
The utility model is related to building field more particularly to a kind of subway inspection hole post and track monoblock type construction knots Structure.
Background technology
Railway traffic engineering is rapid in Shanghai Metallurgical Industry, and Subway Stop field parking and overhauling for subway.Wherein for ground Iron maintenance is column inspection hole, and column inspection hole is made of service pit, post and track.Passing construction is general first By civil engineering unit inspection of construction hole and post, rail is then set up on post by track unit, but on post The pre-buried positional precision of built-in fitting can not often meet the requirement that rail is laid with I precision, while rail is laid with easily to having completed Post cause some unfilled corners, breakage etc..
Therefore, how to provide a kind of formulate a set of can meet frame rail required precision and protect civil engineering finished product and can Save the subway inspection hole post of duration and track monoblock type constructing structure, it has also become construction circle need to further be improved excellent The technical issues of change.
Utility model content
The purpose of this utility model is to provide a kind of subway inspection hole post and track monoblock type constructing structures, can Meet frame rail required precision, and civil engineering finished product can be protected and can be saved the duration.
In order to solve the above technical problems, the utility model provides following technical solution:
A kind of subway inspection hole post and track monoblock type constructing structure, if including being used for two parallel orbits of erection Dry track supporting rack, several bolt embedment sleeves, several connection bolts, several nuts, several connecting plates and several pre-buried Plate is equipped with subway inspection between two parallel orbits and cheats, and is equipped at intervals with below the track several for pouring to be formed Check the post reinforcing bar of hole post, the both sides of the track are respectively equipped with the company of horizontal-extending a distance outward Fishplate bar, the first bolt hole passed through for the connection bolt is opened up on the connecting plate, and the embedded board is arranged at track and two The lower section of side connecting plate, the upward projected area of the embedded board cover track and two side connecting plates, are opened up on the embedded board It is described to connect bolt the first bolt hole of drawing-in and the second bolt hole successively, institute with corresponding second bolt hole of the first bolt hole The upper and lower end for stating connection bolt is locked respectively by nut and bolt embedment sleeve, and the bolt embedment sleeve extends downwardly into institute It states in post reinforcing bar.
Preferably, in above-mentioned subway inspection hole post and track monoblock type constructing structure, the track supporting rack Including cross bar, two hounds for being fixedly installed on cross bar both ends, two pieces of pedestals and the telescopic rod being arranged on pedestal, institute The upper end of telescopic rod and the cross bar detachable connection are stated, the parallel orbit is detachable to be arranged on the cross bar, institute It states parallel orbit and the cross bar is perpendicular.
Preferably, it is described to check that hole is small vertical in above-mentioned subway inspection hole post and track monoblock type constructing structure The cross section of column is square, and the connecting plate is rectangle, and the length of the connecting plate is less than the width of the square, institute The length for stating connecting plate is more than the width of the track, and the length direction of the connecting plate and the extending direction of the track mutually hang down Directly.
Preferably, in above-mentioned subway inspection hole post and track monoblock type constructing structure, two bolt hole dislocation It is arranged at the both sides of the track.
Preferably, in above-mentioned subway inspection hole post and track monoblock type constructing structure, the width of the track It is the 1/3-1/2 of the length of connecting plate.
Preferably, in above-mentioned subway inspection hole post and track monoblock type constructing structure, the track supporting rack It is set together every 3-5 meters.
Preferably, it is described to check that hole is small vertical in above-mentioned subway inspection hole post and track monoblock type constructing structure Column surrounding sets model of the column, and the model of the column is assembled by four pieces of wooden models by the way of withholding, the column mould of adjacent upright posts Plate is attached fixation using the lumps of wood.
Preferably, it is lateral in model of the column in above-mentioned subway inspection hole post and track monoblock type constructing structure Set up the bearing diagonal for preventing that model of the column from deforming.
From techniques disclosed above scheme, compared with prior art, the beneficial effects of the utility model are as follows:
First, subway inspection hole post and track monoblock type constructing structure provided by the utility model, utilize the connection Simultaneously spiral shell is respectively adopted in the upper and lower end for connecting bolt by the first bolt hole of bolt drawing-in connecting plate and the second bolt hole of embedded board Cap is locked with bolt embedment sleeve, and the bolt embedment sleeve is stretched into the post reinforcing bar, that is to say, that anti-using track To fixing bolt embedded sleeve barrel, substitution in the prior art bolt embedment sleeve first pour in recycled in post connection bolt with The way that track is fixedly connected by the connection of bolt embedment sleeve with post has accomplished that track laying is disposably installed in place, It ensures the precision that track is set up, avoids the secondary adjustment of track.
2nd, subway inspection hole post and track monoblock type constructing structure provided by the utility model, are first laid with track, after Pour post, without wait until post construction complete lay a railway track again, realize civil engineering i.e. post pour and track one Bodyization is constructed, and avoids the secondary adjustment of track, and the duration is greatly saved, improves construction efficiency.
3rd, subway inspection hole post and track monoblock type constructing structure, post and track provided by the utility model It is molded simultaneously, also avoids finished product protection problem of the post when subsequently laying a railway track in the prior art, therefore with very high society It can benefit.
Description of the drawings
Fig. 1 is that the facade knot of post and track monoblock type constructing structure is cheated in the subway inspection of one embodiment of the utility model Structure schematic diagram;
Fig. 2 is that the planar junction of post and track monoblock type constructing structure is cheated in the subway inspection of one embodiment of the utility model Structure schematic diagram;
Fig. 3 is the structure diagram when binding of post reinforcing bar is carried out in one embodiment of the utility model;
Fig. 4 is structure diagram when model of the column is installed in one embodiment of the utility model;
Fig. 5 be one embodiment of the utility model in post pour after the completion of structure diagram;
In figure:1- tracks, 2- tracks supporting rack, 21- cross bars, 22- hounds, 23- pedestals, 24- telescopic rod 3- bolts are pre- It is small vertical to bury sleeve, 4- connections bolt, 5- nuts, 6- connecting plates, the first bolts hole of 61-, 7- embedded boards, the second bolts hole of 71-, 8- Column, 80- upright post basics, 81- posts reinforcing bar, the 9- lumps of wood, 10- model of the column.
Specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.According to following explanation and The advantages of claims, the utility model and feature will become apparent from.It below will be by cited embodiment combination attached drawing, in detail Illustrate the technology contents and feature of the utility model.Need in addition it illustrate, attached drawing makes using very simplified form and With non-accurate ratio, only to purpose that is convenient, lucidly aiding in illustrating the utility model embodiment.For sake of convenience, under Described herein " on ", " under " the upper and lower direction with attached drawing is consistent, but this can't be the limit of technical solutions of the utility model System.
It please refers to Fig.1 to Fig. 5, present embodiment discloses a kind of subway inspection hole post and track monoblock type construction knots Structure, several track supporting racks 2, several bolt embedment sleeves 3, several connection bolts including being used to set up two parallel orbits 1 4th, several nuts 5, several connecting plates 6 and several embedded boards 7 are equipped with subway inspection between two parallel orbits 1 and cheat (not indicating), the lower section of the track 1 be equipped at intervals with it is several to form the post reinforcing bar 81 for checking hole post 8 for pouring, That is, post 8 is arranged at intervals at the both sides for checking hole, the both sides of the track 1 are respectively equipped with horizontal-extending outward The connecting plate 6 of a distance can be detachably connected between the connecting plate 6 and the track 1.On the connecting plate 6 The first bolt hole (not indicating) passed through for the connection bolt 4 is opened up, the embedded board 7 is arranged at track 1 and both sides connection The lower section of plate 6, upward projected area covering 1 and two side connecting plate 6 of track of the embedded board 7, open up on the embedded board 7 with Corresponding second bolt hole (not indicating) of first bolt hole is described to connect bolt 4 the first bolt hole of drawing-in and the second spiral shell successively Keyhole, the upper and lower end of the connection bolt 4 are locked respectively by nut 5 and bolt embedment sleeve 3, the bolt embedment sleeve 3 It extends downwardly into the post reinforcing bar 81.Subsequently on the premise of orbital position is adjusted, by pouring post reinforcing bar 81, What realization post 8 and rail 1 were laid with synchronously completes.
The subway inspection hole post and track monoblock type constructing structure of said structure utilize connection 4 drawing-in of bolt First bolt hole of connecting plate 6 and the second bolt hole of embedded board 7 and by connect bolt 4 upper and lower end be respectively adopted nut 5 with Bolt embedment sleeve 3 is locked, and so as to which bolt embedment sleeve 3 to be fixed on to the lower section of connecting plate 6, the bolt embedment sleeve 3 is stretched Enter in the post reinforcing bar 81, that is to say, that using 1 reversed fixing bolt embedded sleeve barrel 3 of track, substitute spiral shell in the prior art Bolt embedded sleeve barrel 3, which is first poured, stands track 1 with small in the interior recycling connection bolt 4 of post 8 and the connection of bolt embedment sleeve 3 The way that column 8 is attached so that the laying of track 1 can be disposably installed in place, it is ensured that the precision that track 1 is set up avoids 1 two adjustment of track, also, track 1 is first laid with, after-pouring post 8, without waiting until that the construction of post 8 is completed again to carry out It lays a railway track, the duration can be greatly saved, improve construction efficiency.In addition, post 8 and track 1 are molded simultaneously, also avoid existing There is the 8 finished product protection problem of post when subsequently laying a railway track in technology, therefore with very high economical, societal benefits.
Preferably, in above-mentioned subway inspection hole post and track monoblock type constructing structure, the track supporting rack 2 Including cross bar 21, it is fixedly installed on two hounds, 22, two pieces of pedestals 23 at 21 both ends of cross bar and is arranged on pedestal 23 Telescopic rod 24, the upper end of the telescopic rod 24 and 21 detachable connection of cross bar, the 1 detachable setting of parallel orbit In on the cross bar 21, the parallel orbit 1 and the cross bar 21 are perpendicular.It can be adjusted by the height of adjustable telescopic rod 24 The height of cross bar 21, and then adjust the height of the track 1.By adjusting the position of the hound 22, can adjust described The position of cross bar 21, and then adjust the laying direction for being arranged at track 1 on cross bar 21, so as to before post 8 pours, 1 location determination of track is good, then connection bolt 4 is poured and is laid in the high-precision in post 8, realizing track 1, is avoided existing There are the connection being embedded in advance in post 8 in technology bolt 4 and track 1 to connect difficulty and cause.
Preferably, it is described to check that hole is small vertical in above-mentioned subway inspection hole post and track monoblock type constructing structure The cross section of column 8 is square, and the connecting plate 6 is rectangle, and the length of the connecting plate 6 is less than the width of the square Degree, the length of the connecting plate 6 are more than the width of the track 1, the length direction of the connecting plate 6 and prolonging for the track 1 It is perpendicular to stretch direction, so that post 8 provides secure support to connecting plate 6.
Preferably, in above-mentioned subway inspection hole post and track monoblock type constructing structure, two the first bolts hole It shifts to install in the both sides of the track 1.Two the first bolts hole are shifted to install, can cause connecting plate 6 and post 8 it Between be more uniformly stressed, prevent stress concentration.
Preferably, in above-mentioned subway inspection hole post and track monoblock type constructing structure, the width of the track 1 It is the 1/3-1/2 of the length of connecting plate 6, can either be convenient for post 8 connecting connecting plate 6 by being connected bolt 4, and can be with So that reduce the floor space of connecting plate 6 and column on the premise of track 1 is subject to stablize and support, reduce the material of construction into This.
Preferably, in above-mentioned subway inspection hole post and track monoblock type constructing structure, the track supporting rack 2 It is set together every 3-5 meters.In this implementation, the track supporting rack 2 is set together every 4 meters.
Preferably, it is described to check that hole is small vertical in above-mentioned subway inspection hole post and track monoblock type constructing structure 8 surrounding of column sets model of the column 10, and the model of the column 10 is assembled by four pieces of wooden models by the way of withholding, using the side withheld Formula connects so that 10 convenient disassembly of model of the column, the model of the column of adjacent upright posts are attached fixation using the lumps of wood 9, can give The pouring construction of post 8 provides a stable support, improves the construction precision of post 8.
Preferably, it is lateral in model of the column in above-mentioned subway inspection hole post and track monoblock type constructing structure The bearing diagonal for preventing that model of the column from deforming is set up, further improves the construction precision of post 8.
Please continue to refer to Fig. 1 to 5, post and track monoblock type constructing structure are cheated in the subway inspection of the present embodiment, including Following steps:
Step 1 asks emphasis to carry out checking the reinforcing bar binding work for cheating post 8 refering to Fig. 3.
Step 2, please refers to Fig.1 and Fig. 2, sets up the track supporting rack 2 for setting up track 1, track supporting rack 2 is using work Word steel, track supporting rack 2 are set together every 3-5 meters.
Step 3 asks emphasis to carry out the erection of track 1 with continued reference to Fig. 1 and Fig. 2.
Step 4 asks emphasis that bolt embedment sleeve 3 is fixed on to the lower section of track 1, and is caused with continued reference to Fig. 1 and Fig. 2 Bolt embedment sleeve 3 is stretched into post reinforcing bar 81.That is, the position of bolt embedment sleeve 3 is reversely determined using track 1 It puts.
Step 5 asks emphasis refering to Fig. 4 and Fig. 5, after track 1 is set up, carries out the installation of model of the column 10 and small vertical The concreting of column 8.After the posts 8 such as follow-up reach intensity requirement, jury track supporting rack 2 can be removed.
Preferably, it is described in step 5 in above-mentioned subway inspection hole post and track monoblock type construction method Model of the column 10 is assembled by four pieces of wooden models by the way of withholding, and the model of the column 10 of adjacent upright posts is attached using the lumps of wood 9 It is fixed, the bearing diagonal (not shown) for preventing that model of the column 10 from deforming laterally is set up in model of the column 10, model of the column 10 has been fixed Cheng Hou, the physical dimension accurate adjustment that track 1 is carried out using the leg screw of track supporting rack 2 are worked, and adjust elevation and the side of track 1 To, after the completion of adjustment, casting concrete.
The subway inspection hole post and track monoblock type construction method of the present embodiment, first fix bolt embedment sleeve 3 It is poured behind the lower section of track 1, the position for adjusting track 1, then by bolt embedment sleeve 3 in post 8, compared to existing skill Bolt embedment sleeve 3, which is first poured, in art recycles the connection of connection bolt 4 and bolt embedment sleeve 3 in the post 8 by track 1 The way being fixedly connected with post 8 so that track 1, which is laid with, to be disposably installed in place, it is ensured that the precision that track 1 is set up is kept away Exempted from the adjustment of track 1 two times, also, be first laid with track 1, after-pouring post 8, without wait until the construction of post 8 complete again into Row is laid a railway track, and the duration is greatly saved, improves construction efficiency.In addition, post 8 and track 1 are molded simultaneously, also avoid existing Finished product protection problem of the post 8 when subsequently laying a railway track in technology, therefore with very high social benefit.
Foregoing description is only the description to the utility model preferred embodiment, not to any limit of the scope of the utility model Calmly, any change, the modification that the those of ordinary skill in the utility model field does according to the disclosure above content, belonging to right will Seek the protection domain of book.

Claims (8)

1. a kind of subway inspection hole post and track monoblock type constructing structure, which is characterized in that flat including being used for erection two Several track supporting racks of row track, several bolt embedment sleeves, several connection bolts, several nuts, several connecting plates and Several embedded boards are equipped with subway inspection between two parallel orbits and cheat, several be used for is equipped at intervals with below the track The post reinforcing bar to be formed and check hole post is poured, the both sides of the track are respectively equipped with horizontal-extending a distance outward The connecting plate, the first bolt hole passed through for the connection bolt is opened up on the connecting plate, the embedded board is arranged at The lower section of track and two side connecting plates, the upward projected area covering track of the embedded board and two side connecting plates, it is described pre-buried It is opened up on plate and corresponding second bolt hole of the first bolt hole, connection bolt the first bolt hole of drawing-in and second spiral shell successively Keyhole, the upper and lower end of the connection bolt are locked respectively by nut and bolt embedment sleeve, and the bolt embedment sleeve is downward It stretches into the post reinforcing bar.
2. subway inspection hole post as described in claim 1 and track monoblock type constructing structure, which is characterized in that the rail Road supporting rack includes cross bar, two hounds for being fixedly installed on cross bar both ends, two pieces of pedestals and is arranged at stretching on pedestal Contracting bar, the upper end of the telescopic rod and the cross bar detachable connection, the parallel orbit is detachable to be arranged at the horizontal stroke On bar, the parallel orbit and the cross bar are perpendicular.
3. subway inspection hole post as described in claim 1 and track monoblock type constructing structure, which is characterized in that the inspection Look into that the cross section of hole post is square, and the connecting plate is rectangle, the length of the connecting plate is less than the square Width, the length of the connecting plate is more than the width of the track, and the length direction of the connecting plate prolongs with the track It is perpendicular to stretch direction.
4. subway inspection hole post as described in claim 1 and track monoblock type constructing structure, which is characterized in that described two A bolt hole is shifted to install in the both sides of the track.
5. subway inspection hole post as claimed in claim 4 and track monoblock type constructing structure, which is characterized in that the rail The width in road is the 1/3-1/2 of the length of connecting plate.
6. subway inspection hole post as described in claim 1 and track monoblock type constructing structure, which is characterized in that the rail Road supporting rack is set together every 3-5 meters.
7. subway inspection hole post as described in claim 1 and track monoblock type constructing structure, which is characterized in that the inspection It looks into hole post surrounding and model of the column is set, the model of the column is assembled by four pieces of wooden models by the way of withholding, adjacent upright posts Model of the column fixation is attached using the lumps of wood.
8. subway inspection hole post as claimed in claim 7 and track monoblock type constructing structure, which is characterized in that in column Template laterally sets up the bearing diagonal for preventing that model of the column from deforming.
CN201721240992.0U 2017-09-26 2017-09-26 Post and track monoblock type constructing structure are cheated in subway inspection Active CN207452600U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721240992.0U CN207452600U (en) 2017-09-26 2017-09-26 Post and track monoblock type constructing structure are cheated in subway inspection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721240992.0U CN207452600U (en) 2017-09-26 2017-09-26 Post and track monoblock type constructing structure are cheated in subway inspection

Publications (1)

Publication Number Publication Date
CN207452600U true CN207452600U (en) 2018-06-05

Family

ID=62284260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721240992.0U Active CN207452600U (en) 2017-09-26 2017-09-26 Post and track monoblock type constructing structure are cheated in subway inspection

Country Status (1)

Country Link
CN (1) CN207452600U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558313A (en) * 2017-09-26 2018-01-09 上海建工五建集团有限公司 Post and track monoblock type constructing structure and method are cheated in subway inspection

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558313A (en) * 2017-09-26 2018-01-09 上海建工五建集团有限公司 Post and track monoblock type constructing structure and method are cheated in subway inspection

Similar Documents

Publication Publication Date Title
CN105113388B (en) Formwork and bracket combining structure of vase pier of viaduct and application method
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN207419520U (en) Piping lane construction template component
CN201535064U (en) Template for buildings
CN203021923U (en) Big cantilever bent cap steel truss construction platform
CN107558313A (en) Post and track monoblock type constructing structure and method are cheated in subway inspection
CN207452600U (en) Post and track monoblock type constructing structure are cheated in subway inspection
CN201428249Y (en) Building template supporting structure
CN103469735A (en) Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN205100119U (en) Steel form device in self -propelled
CN103866692A (en) Novel assembling method for bent cap bearing frame
CN205259603U (en) Centre form braced system
CN105019657A (en) Building construction system
CN210622816U (en) Movable adjustable novel grouting template
CN213682477U (en) Upper cover structure system applied to track operation line
CN204876579U (en) Building construction system
CN201144524Y (en) Reinforcement for detached wall stud
CN210713182U (en) A structure bracket that is used for C type stock ground tripper platform to be under construction
CN203213022U (en) Mobile temporary prestress tensioning anchor block
CN105113542A (en) Cantilever system and method for underground station construction
CN203475793U (en) Bracket type overhanging scaffold
CN112095780A (en) Upper cover structure system applied to track operation line and implementation method thereof
CN206607706U (en) A kind of drawing shore for shear wall construction
CN205822778U (en) A kind of huge post of stiffness is without screw aluminum alloy formwork system
CN104948004A (en) Revolving wall for on-site safety management

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant