CN105113542A - Cantilever system and method for underground station construction - Google Patents
Cantilever system and method for underground station construction Download PDFInfo
- Publication number
- CN105113542A CN105113542A CN201510600528.7A CN201510600528A CN105113542A CN 105113542 A CN105113542 A CN 105113542A CN 201510600528 A CN201510600528 A CN 201510600528A CN 105113542 A CN105113542 A CN 105113542A
- Authority
- CN
- China
- Prior art keywords
- underground station
- formwork
- construction
- middle plate
- mid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑施工领域,具体而言,涉及一种地下车站施工用悬挑系统及地下车站施工方法。The invention relates to the field of building construction, in particular to a cantilever system for underground station construction and an underground station construction method.
背景技术Background technique
随着我国地下空间工程施工技术不断发展,地铁施工的规模将会越来越大,层数也会越来越多。而地铁中板梁及顶板施工时的支架、模板将是施工成本中很大一部分。With the continuous development of my country's underground space engineering construction technology, the scale of subway construction will become larger and the number of floors will also increase. The support and formwork during the construction of the subway mid-slab beam and roof will be a large part of the construction cost.
现有技术中的地下车站施工方式是先施工底板,再搭设下层中板梁支模架,浇筑完中板梁后,再搭设中板梁上支架,随后施工负一层中板梁。再搭设顶板下支架,再浇筑顶板混凝土,从下往上施工直至将车站主体结构施工完成。这一方法存在的问题是:由于中板梁明确规定荷载不大于800kg/m2。需最上层顶板施工完成后,再从上逐步拆除支模架工程。这显然导致最下层钢管支架、模板、方木等需在整个施工过程中保持不能拆除的状态,使材料和设备不能得到充分利用,也因此耽误工期,同时会大量增加钢管支架、模板的成本。The construction method of the underground station in the prior art is to construct the base plate first, then set up the formwork support for the lower middle plate beam, after pouring the middle plate beam, then erect the upper support of the middle plate beam, and then construct the negative layer middle plate beam. Then set up the lower support of the roof, and then pour the roof concrete, and construct from bottom to top until the construction of the main structure of the station is completed. The problem with this method is: since the plate girder clearly stipulates that the load is not greater than 800kg/m 2 . After the construction of the uppermost roof slab is completed, the formwork support project shall be gradually removed from above. This obviously leads to the need to keep the steel pipe support, formwork, and square timber at the bottom layer in a state that cannot be dismantled during the entire construction process, so that materials and equipment cannot be fully utilized, and the construction period is therefore delayed. At the same time, the cost of steel pipe support and formwork will be greatly increased.
发明内容Contents of the invention
本发明提供了一种地下车站施工用悬挑系统及地下车站施工方法,旨在改善上述技术问题。The invention provides a cantilever system for underground station construction and an underground station construction method, aiming at improving the above technical problems.
本发明是这样实现的:The present invention is achieved like this:
地下多层车站施工用悬挑系统,包括立柱和中板梁,所述中板梁横向设置,所述立柱竖向设置在底板上,所述立柱的上端支撑于所述中板梁的下表面;The cantilever system for the construction of underground multi-storey stations includes columns and mid-plate beams, the mid-plate beams are arranged horizontally, the columns are vertically arranged on the bottom plate, and the upper ends of the columns are supported on the lower surface of the mid-plate beams ;
所述中板梁上设置有固定件,所述固定件包括第一固定件和第二固定件,所述第一固定件的下端设置于所述中板梁的端部,上端固定设置有支架,所述支架横向设置,所述第二固定件的下端与所述立柱对应设置,上端与所述支架固定连接。The middle plate beam is provided with a fixing piece, the fixing piece includes a first fixing piece and a second fixing piece, the lower end of the first fixing piece is arranged at the end of the middle plate beam, and the upper end is fixedly provided with a bracket , the bracket is arranged transversely, the lower end of the second fixing member is arranged correspondingly to the column, and the upper end is fixedly connected to the bracket.
施工时,地下车站将基坑挖好后,先施工底板,然后在底板上搭建支模架和模板,中板梁在模板上施工,立柱的下端固定在底板上,上端顶住中板梁,中板梁施工完成后,中板梁由立柱进行承重,支模架和模板即可拆除循环使用,用于上方中板梁的施工。During construction, after the foundation pit is dug in the underground station, the base plate is constructed first, and then the formwork frame and formwork are built on the base plate. The middle plate beam is constructed on the formwork. After the construction of the mid-slab girder is completed, the mid-slab girder is loaded by the column, and the formwork frame and formwork can be removed and recycled for the construction of the mid-slab girder above.
中板梁上方设置固定件和支架,且固定件的位置是设置在与立柱对应的位置和中板梁的墙角处的,下方拆除的支模架重新设置在支架上,这样上方施工时的支模架重量以及上方施工中板梁时的重量经支架和固定件直接传到下方的立柱上,不会对已施工完成的中板梁造成影响,更不会发生中板梁断裂等情况。Fixtures and brackets are set above the mid-slab beam, and the position of the fixation piece is set at the position corresponding to the column and the corner of the mid-slab beam. The weight of the formwork and the weight of the mid-slab beam during construction above are directly transmitted to the lower column through the brackets and fixings, which will not affect the completed mid-slab beam, and will not cause the mid-slab beam to break.
通过本技术方案中的悬挑系统进行施工,相比于现有技术的施工支模方式,所需要的支模架和模板数量大量减少,可以节省大量成本。并且在最下层中板梁施工完成后,支模架便已拆除,更方便盾构机等施工设备进入车站开始施工。Construction is carried out through the cantilever system in the technical solution. Compared with the construction formwork support method in the prior art, the number of required formwork support frames and formwork is greatly reduced, which can save a lot of cost. And after the construction of the middle plate girder on the lowest floor is completed, the formwork support has been removed, making it easier for construction equipment such as shield machines to enter the station to start construction.
进一步地,所述立柱为两列,两列所述立柱间隔设置,且两列所述立柱沿所述中板梁的中轴线对称设置。Further, the upright columns are in two rows, the two rows of upright columns are arranged at intervals, and the two rows of upright columns are symmetrically arranged along the central axis of the middle plate beam.
立柱的设置方式对于整个悬挑系统的承重有重要影响,两列立柱是相互平行的,将两列立柱设置在中板梁下方呈对称的位置,两列立柱的承重量相当。The setting method of the columns has an important influence on the load-bearing of the entire cantilever system. The two columns are parallel to each other, and the two columns are arranged in a symmetrical position under the middle plate beam, and the load-bearing capacity of the two columns is equal.
进一步地,两列所述立柱间的间距等于所述中板梁的跨度的三分之一。Further, the distance between two columns of columns is equal to one-third of the span of the middle plate beam.
两列立柱分别位于中板梁跨度的三等分位置,这样中板梁的重量在立柱上的承重分布更加均匀。The two columns of uprights are respectively located at the three equal parts of the span of the mid-slab girder, so that the weight of the mid-slab girder is more evenly distributed on the uprights.
进一步地,所述固定件包括连接钢板和两块工字钢,两块所述工字钢竖向固定设置在所述中板梁上,所述连接钢板横向设置,所述连接钢板的两端分别连接两块所述工字钢的上端。Further, the fixing member includes a connecting steel plate and two pieces of I-shaped steel, the two pieces of I-shaped steel are vertically fixed on the middle plate beam, the connecting steel plate is arranged horizontally, and the two ends of the connecting steel plate The upper ends of the two I-beams are respectively connected.
第一固定件和第二固定件均采用同样的构造,均使用工字钢制成,连接钢板将工字钢的上表面连接起来,更方便支架设置。Both the first fixing part and the second fixing part adopt the same structure, and are both made of I-beams, and the connecting steel plates connect the upper surfaces of the I-beams, which is more convenient for bracket installation.
进一步地,所述支架由平铺在所述固定件上的多块钢材构成。Further, the bracket is composed of multiple pieces of steel laid flat on the fixing piece.
支架是设置在固定件上的,本技术方案中,支架同样由钢材制成,可以是工字钢也可以是其他形式的钢材。在固定件在平铺成一平面,方便设置支模架。The bracket is arranged on the fixing piece. In the technical solution, the bracket is also made of steel, which can be I-beam or other forms of steel. The fixing parts are tiled into a plane, which is convenient for setting the formwork frame.
需要说明的是,支架也可以采用枕木、方木等材料制成。It should be noted that the bracket can also be made of materials such as sleepers and square wood.
进一步地,所述立柱的下端设置有底座,所述底座沿其周向均匀设置有螺孔,所述螺孔内设置膨胀螺栓,所述膨胀螺栓将所述底座固定于地面。Further, the lower end of the column is provided with a base, and the base is uniformly provided with screw holes along its circumference, and expansion bolts are arranged in the screw holes, and the expansion bolts fix the base to the ground.
底座可以增大立柱与底板连接的受力面,减小对底板的压强,同时更方便分散立柱的压力。The base can increase the stress surface connecting the column and the bottom plate, reduce the pressure on the bottom plate, and at the same time, it is more convenient to disperse the pressure of the column.
进一步地,所述底座上设置有16个螺孔。Further, 16 screw holes are provided on the base.
一种地下车站施工方法,包括以下步骤:A kind of underground station construction method, comprises the following steps:
a、在最下层的底板上搭设支模架,安装模板,竖立立柱;a. Set up the formwork frame on the bottom floor of the lowest floor, install the formwork, and erect the column;
b、在模板上浇筑中板梁,养护使中板梁强度达到100%;b. Pour the mid-slab girder on the formwork, and maintain to make the mid-slab beam strength reach 100%;
c、拆除支模架和模板,在中板梁上依次设置固定件和支架;c. Remove the formwork frame and formwork, and set the fixing parts and brackets on the middle plate beam in turn;
d、在支架上重新设置支模架并安装模板,在中板梁或支架上再次竖立立柱,重复b、c步骤,直至按设计的地下车站层数将所有中板梁施工完成。d. Re-set the formwork frame on the bracket and install the formwork, erect the column again on the mid-slab beam or the bracket, repeat steps b and c, until the construction of all mid-slab beams is completed according to the designed number of floors of the underground station.
现有技术中,地下车站的层数逐渐增加,施工难度也逐渐增大,而通过本方法进行地下车站施工,从下至上逐层施工中板梁,当一层中板梁施工完成后,其下方的支模架即可拆除并用于上层的中板梁施工,避免了现有技术多层地下车站施工过程中需要使用大量的支模架和模板的情况。In the prior art, the number of floors of the underground station increases gradually, and the difficulty of construction also gradually increases. However, in the construction of the underground station by this method, the mid-slab girder is constructed layer by layer from bottom to top. The lower formwork support can be dismantled and used for the construction of the upper middle plate girder, which avoids the need to use a large number of formwork support and templates in the construction process of the multi-storey underground station in the prior art.
其中中板梁强度达到100%是指浇筑中板梁的混凝土强度达到设计值的100%,也就是完全达到设计强度。The strength of the mid-slab girder reaching 100% means that the concrete strength of the poured mid-slab girder reaches 100% of the design value, that is, the design strength is fully reached.
进一步地,步骤d中,上一层的立柱与下一层的立柱数量相同且位置对应。Further, in step d, the number of uprights on the upper floor and the number of uprights on the next floor are the same and their positions correspond.
施工过程中,每一层的立柱的位置均是与下一层的立柱位置对应的,这样上方中板梁以及支模架的重量能完全通过立柱逐层传递至底板,而并不会对已施工完成的中板梁造成损伤。During the construction process, the position of the column on each floor corresponds to the position of the column on the next floor, so that the weight of the upper middle plate beam and the formwork frame can be completely transferred to the bottom plate layer by layer through the column, without affecting the existing The completed mid-slab girder was damaged.
进一步地,待所有中板梁的强度均达到100%后,从最上层开始往下逐层拆除立柱。Further, after the strength of all the mid-plate girders reaches 100%, the columns are removed layer by layer starting from the uppermost layer.
本发明的有益效果是:本发明提供的地下车站施工用悬挑系统及地下车站施工方法采用悬挑式结构,在最下层的中板梁施工完成后,通过立柱承重,上方的中板梁施工时,通过固定件和支架将重力转移到下方的立柱上并传递至底板,最下层的支模架和模板即可拆除,这样可以大量节省地下车站施工时需要的支模架和模板数量,节约成本。The beneficial effects of the present invention are: the cantilever system for underground station construction and the construction method of the underground station provided by the present invention adopt a cantilever structure, and after the construction of the bottom girder is completed, the column bears the load, and the upper girder is constructed. At the same time, the gravity is transferred to the lower column and to the bottom plate through the fixing parts and brackets, and the lowermost formwork frame and formwork can be removed, which can greatly save the number of formwork frames and formwork required for underground station construction, saving cost.
附图说明Description of drawings
为了更清楚地说明本发明实施例的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本发明的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the accompanying drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present invention, and thus It should be regarded as a limitation on the scope, and those skilled in the art can also obtain other related drawings based on these drawings without creative work.
图1是本发明实施例提供的地下车站施工用悬挑系统的结构示意图;Fig. 1 is the structural representation of the cantilever system for underground station construction that the embodiment of the present invention provides;
图2是本发明实施例提供的地下车站施工用悬挑系统中立柱的结构示意图;Fig. 2 is a schematic structural view of the column in the cantilever system for underground station construction provided by the embodiment of the present invention;
图3是本发明实施例提供的地下车站施工用悬挑系统中固定件的结构示意图。Fig. 3 is a schematic structural view of the fixing parts in the cantilever system for underground station construction provided by the embodiment of the present invention.
图中标记分别为:The marks in the figure are:
底板101;中板梁102;第一固定件103;第二固定件104;支架105;连接钢板106;立柱110;底座111。Bottom plate 101 ; middle plate beam 102 ; first fixing piece 103 ; second fixing piece 104 ; bracket 105 ; connecting steel plate 106 ; upright column 110 ;
具体实施方式Detailed ways
随着我国地下空间工程施工技术不断发展,地铁施工的规模将会越来越大,层数也会越来越多。而地铁中板梁及顶板施工时的支架、模板将是施工成本中很大一部分。With the continuous development of my country's underground space engineering construction technology, the scale of subway construction will become larger and the number of floors will also increase. The support and formwork during the construction of the subway mid-slab beam and roof will be a large part of the construction cost.
现有技术中的地下车站施工方式是先施工底板,再搭设下层中板梁支模架,浇筑完中板梁后,再搭设中板梁上支架,随后施工负一层中板梁。再搭设顶板下支架,再浇筑顶板混凝土,从下往上施工直至将车站主体结构施工完成。这一方法存在的问题是:由于中板梁明确规定荷载不大于800kg/m2。需最上层顶板施工完成后,再从上逐步拆除支模架工程。这显然导致最下层钢管支架、模板、方木等需在整个施工过程中保持不能拆除的状态,使材料和设备不能得到充分利用,也因此耽误工期,同时会大量增加钢管支架、模板的成本。The construction method of the underground station in the prior art is to construct the base plate first, then set up the formwork frame for the lower middle plate beam, after pouring the middle plate beam, then erect the upper support of the middle plate beam, and then construct the negative layer middle plate beam. Then set up the lower support of the roof, and then pour the roof concrete, and construct from bottom to top until the construction of the main structure of the station is completed. The problem with this method is: since the plate girder clearly stipulates that the load is not greater than 800kg/m2. After the construction of the uppermost roof slab is completed, the formwork support project shall be gradually removed from above. This obviously leads to the need to keep the steel pipe support, formwork, and square timber at the bottom layer in a state that cannot be dismantled during the entire construction process, so that materials and equipment cannot be fully utilized, and the construction period is therefore delayed. At the same time, the cost of steel pipe support and formwork will be greatly increased.
本领域技术人员长期以来一直在寻求一种改善该问题的工具或方法。Those skilled in the art have been looking for a tool or method to improve this problem for a long time.
为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。因此,以下对在附图中提供的本发明的实施例的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments It is a part of embodiments of the present invention, but not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention. Accordingly, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.
应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步定义和解释。It should be noted that like numerals and letters denote similar items in the following figures, therefore, once an item is defined in one figure, it does not require further definition and explanation in subsequent figures.
在本发明的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该发明产品使用时惯常摆放的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”、“第三”等仅用于区分描述,而不能理解为指示或暗示相对重要性。In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" etc. The indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, or the orientation or positional relationship that is usually placed when the product of the invention is used, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying References to devices or elements must have a particular orientation, be constructed, and operate in a particular orientation and therefore should not be construed as limiting the invention. In addition, the terms "first", "second", "third", etc. are only used for distinguishing descriptions, and should not be construed as indicating or implying relative importance.
在本发明的描述中,还需要说明的是,除非另有明确的规定和限定,术语“设置”、“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should also be noted that, unless otherwise clearly specified and limited, the terms "installation", "installation", "connection" and "connection" should be understood in a broad sense, for example, it may be a fixed connection, It can also be a detachable connection or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediary, and it can be the internal communication of two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.
实施例,请参阅Examples, see
如图1至图3所示,本实施例提供了一种地下车站施工用悬挑系统,图1示出了该悬挑系统的结构,包括立柱110和中板梁102,所述中板梁102横向设置,所述立柱110竖向设置并支撑于底板101,所述立柱110的上端支撑于所述中板梁102的下表面。As shown in Figures 1 to 3, the present embodiment provides a cantilever system for construction of an underground station, and Figure 1 shows the structure of the cantilever system, including a column 110 and a mid-plate girder 102, and the mid-plate girder 102 is arranged horizontally, the column 110 is vertically arranged and supported on the bottom plate 101 , and the upper end of the column 110 is supported on the lower surface of the middle plate beam 102 .
如图2所示,立柱110采用加强的工字钢制成,其下端设置有底座111,底座111为圆盘状,底座111沿其周向均匀设置有16个螺孔,所述螺孔内设置膨胀螺栓,所述膨胀螺栓将所述底座111固定于地面。As shown in Figure 2, the column 110 is made of reinforced I-beam, and its lower end is provided with a base 111, the base 111 is disc-shaped, and the base 111 is evenly provided with 16 screw holes along its circumference. Expansion bolts are provided, and the expansion bolts fix the base 111 to the ground.
底座111可以增大立柱110与底板101连接的受力面,减小对底板101的压强,同时更方便分散立柱110的压力。The base 111 can increase the stress surface connecting the column 110 and the bottom plate 101 , reduce the pressure on the bottom plate 101 , and at the same time, disperse the pressure of the column 110 more conveniently.
立柱110为两组,立柱110的设置方式对于整个悬挑系统的承重有重要影响,两列立柱110是相互平行的,将两列立柱110设置在中板梁102下方呈对称的位置,两列立柱110的承重量相当。The columns 110 are divided into two groups, and the arrangement of the columns 110 has an important influence on the load-bearing of the entire suspension system. The two columns 110 are parallel to each other, and the two columns 110 are arranged in a symmetrical position under the middle plate beam 102. The two columns The load-bearing capacity of the column 110 is equivalent.
具体而言,本实施例中,两列立柱110分别位于中板梁102跨度的三等分位置,也就是说两列所述立柱110间的间距等于所述中板梁102的跨度的三分之一,这样中板梁102的重量在立柱110上的承重分布更加均匀。Specifically, in this embodiment, the two rows of columns 110 are respectively located at the positions of thirds of the span of the mid-plate beam 102, that is to say, the distance between the two rows of columns 110 is equal to one-third of the span of the mid-plate beam 102 One, the load-bearing distribution of the weight of the mid-slab girder 102 on the column 110 is more even.
中板梁102与底板101之间形成车站空间,中板梁102是通过浇筑施工进行设置的,其与车站内的竖梁或墙体连接固定。The space of the station is formed between the middle plate beam 102 and the bottom plate 101, and the middle plate beam 102 is set by pouring construction, and it is connected and fixed with the vertical beam or the wall in the station.
所述中板梁102上设置有固定件,所述固定件包括第一固定件103和第二固定件104,所述第一固定件103的下端设置于所述中板梁102的端部,具体而言,第一固定件103位于中板梁102与车站内墙体的犄角处。The middle plate beam 102 is provided with a fixing piece, the fixing piece includes a first fixing piece 103 and a second fixing piece 104, the lower end of the first fixing piece 103 is arranged at the end of the middle plate beam 102, Specifically, the first fixing member 103 is located at the corner of the middle plate girder 102 and the inner wall of the station.
所述第二固定件104的下端位置与所述立柱110的位置对应设置,如图1所示,两组第二固定件104的位置与下端立柱110的设置位置在竖向上重合,这样便于将上方的中板梁102、支模架等的重量直接转移到下方的立柱110上。The position of the lower end of the second fixing member 104 is set correspondingly to the position of the column 110. As shown in FIG. The weight of the upper middle plate beam 102 , formwork support, etc. is directly transferred to the lower column 110 .
第一固定件103和第二固定件104均采用同样的构造,均使用工字钢制成,具体而言,如图3所示,第一固定件103和第二固定件104均包括连接钢板106和两块工字钢,两块所述工字钢竖向固定设置,设置时,工字钢呈“工”字形支撑在中板梁102上,两块工字钢中间具有一定间隔,连接钢板106平铺,并且连接钢板106的两端连接在工字钢上。The first fixing part 103 and the second fixing part 104 all adopt the same structure, and are all made of I-shaped steel. Specifically, as shown in Figure 3, the first fixing part 103 and the second fixing part 104 both include connecting steel plates 106 and two pieces of I-beams, the two pieces of I-beams are fixed vertically. When setting, the I-beams are supported in the shape of "I" on the middle plate beam 102. There is a certain interval between the two pieces of I-beams. The steel plate 106 is laid flat, and the two ends of the connecting steel plate 106 are connected to the I-beam.
固定件的上端固定设置有支架105,所述支架105横向设置,所述支架105由平铺在所述固定件上的多块钢材构成,可以是工字钢也可以是其他形式的钢材。多块钢材平铺成一平面,方便设置支模架。A bracket 105 is fixedly arranged on the upper end of the fixing piece, and the bracket 105 is arranged horizontally. The bracket 105 is composed of a plurality of pieces of steel laid flat on the fixing piece, which may be I-beam or other forms of steel. Multiple pieces of steel are flattened into a plane, which is convenient for setting the formwork frame.
利用上述的悬挑系统,本实施例还提供一种地下车站的施工方法:Utilizing the above-mentioned cantilever system, this embodiment also provides a construction method for an underground station:
首先挖掘出地下车站施工用的基坑,并在基坑底部施工底101,其后在底板101上搭设支模架,然后在支模架上安装模板,并将立柱110竖立在底板101上,通过底盘将立柱110牢固的固定并保持立柱110呈竖直状态。First excavate the foundation pit for the construction of the underground station, and construct the bottom 101 at the bottom of the foundation pit, then set up the formwork frame on the base plate 101, then install the formwork on the formwork frame, and erect the column 110 on the base plate 101, The upright column 110 is fixed firmly by the chassis and the upright column 110 is kept in a vertical state.
本实施例中,支模架是由方木和枕木等材料搭建而成的,当支模架和模板搭建完成后,在模板上浇筑中板梁102,中板梁浇筑完成后,需要进行养护,等待中板梁102的强度达到100%。In this embodiment, the formwork frame is constructed of materials such as square wood and sleepers. After the formwork frame and formwork are built, the mid-slab beam 102 is poured on the formwork. After the mid-slab beam is poured, maintenance is required. , waiting for the strength of the plate girder 102 to reach 100%.
此时,便可将中板梁102下方的支模架和模板拆除,保持立柱110呈竖立状态并对中板梁102形成支撑,并在中板梁102上依次设置固定件和支架105,设置时,应尽量保证第二固定件104的位置是与立柱110的位置完全对齐的,而第一固定件103的位置则设置在中板梁102的上腋角处。At this point, the formwork frame and formwork below the mid-plate girder 102 can be removed to keep the upright column 110 in an upright state and support the mid-plate girder 102, and the fixing parts and brackets 105 are arranged successively on the mid-plate girder 102. , try to ensure that the position of the second fixing part 104 is completely aligned with the position of the column 110, while the position of the first fixing part 103 is set at the upper axillary corner of the middle plate beam 102.
支架105直接将钢材平铺在固定件上形成一平面即可。此时便可将下方拆下的支模架和模板重新在支架105上进行搭建,同时在支架105上再次设置立柱110,同样的,新设置的立柱110与下方的立柱110位置对应。The bracket 105 can directly spread the steel material on the fixing part to form a plane. At this point, the formwork frame and formwork removed below can be rebuilt on the support 105, and the column 110 is set again on the support 105 simultaneously. Similarly, the newly installed column 110 corresponds to the position of the column 110 below.
待支模架、模板和立柱110再次设置好后,再次浇筑地下倒数第二层的中板梁102。按同样的方法进行施工,直至将所有的中板梁102施工完成。施工完成后,根据设计选择是否将立柱110拆除。After the formwork frame, formwork and column 110 are set up again, the mid-plate girder 102 on the penultimate underground floor is poured again. Carry out construction by the same method, until all the middle plate girders 102 are constructed. After the construction is completed, choose whether to remove the column 110 according to the design.
更优选的实施方式是,在拆除立柱110时,从最上层开始往下逐层拆除立柱110,为保证安全,等所有的中板梁102的强度均达到100%后才能进行拆除。A more preferred embodiment is that when removing the uprights 110, the uprights 110 are removed layer by layer from the top floor down. To ensure safety, the removal can only be carried out after the strength of all the mid-plate beams 102 reaches 100%.
依照上述施工方法进行施工,不论地下车站需要建设多少层,均只需一套支模架和模板便可完成施工,这大大降低了支模架和模板的使用成本。According to the above construction method, no matter how many floors the underground station needs to build, only one set of formwork frames and formwork is required to complete the construction, which greatly reduces the cost of use of formwork frames and formwork.
本实施例提供的地下车站施工用悬挑系统及地下车站施工方法采用悬挑式结构,在最下层的中板梁102施工完成后,通过立柱110承重,上方的中板梁102施工时,通过固定件和支架105将重力转移到下方的立柱110上并传递至底板101,最下层的支模架和模板即可拆除,这样可以大量节省地下车站施工时需要的支模架和模板数量,同时,在最下层中板梁102施工完成后,支模架便已拆除,更方便盾构机等施工设备进入车站开始施工。The cantilever system and the construction method for the underground station provided in this embodiment adopt a cantilevered structure. After the construction of the bottom girder 102 is completed, the column 110 bears the load. During the construction of the upper girder 102, the Fixing parts and brackets 105 transfer the gravity to the column 110 below and transmit it to the base plate 101, and the lowermost formwork support and formwork can be removed, which can greatly save the formwork support and formwork quantity required during the construction of the underground station, and at the same time , after the construction of the lowermost middle plate girder 102 is completed, the formwork support has been removed, making it easier for construction equipment such as shield machines to enter the station and start construction.
以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included within the protection scope of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510600528.7A CN105113542B (en) | 2015-09-21 | 2015-09-21 | Underground station construction overhanging system and underground station construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510600528.7A CN105113542B (en) | 2015-09-21 | 2015-09-21 | Underground station construction overhanging system and underground station construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105113542A true CN105113542A (en) | 2015-12-02 |
| CN105113542B CN105113542B (en) | 2018-06-29 |
Family
ID=54661634
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510600528.7A Active CN105113542B (en) | 2015-09-21 | 2015-09-21 | Underground station construction overhanging system and underground station construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105113542B (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105525629A (en) * | 2016-01-20 | 2016-04-27 | 中铁上海工程局集团有限公司 | Construction method and device of subway station |
| CN111379438A (en) * | 2020-03-10 | 2020-07-07 | 中国铁路设计集团有限公司 | Vertical temporary supporting system for underground structure and using method |
| CN117403694A (en) * | 2023-10-30 | 2024-01-16 | 中铁大桥勘测设计院集团有限公司 | A method for dismantling the formwork for subway station structure construction using the multi-layer open-cut construction method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH11152761A (en) * | 1997-11-19 | 1999-06-08 | Kajima Corp | Underground structure and its construction method |
| CN101886468A (en) * | 2010-03-29 | 2010-11-17 | 南京大地建设集团有限责任公司 | Construction method of suspension type template support in high-position conjoined structure |
| CN102691411A (en) * | 2012-06-21 | 2012-09-26 | 中国建筑第五工程局有限公司 | Beam plate post-cast strip template support system and construction method thereof |
| CN203625872U (en) * | 2013-12-24 | 2014-06-04 | 葛洲坝集团第五工程有限公司 | Pile foundation construction platform |
| CN204919608U (en) * | 2015-09-21 | 2015-12-30 | 中铁上海工程局有限公司 | Underground station construction is with system of encorbelmenting |
-
2015
- 2015-09-21 CN CN201510600528.7A patent/CN105113542B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH11152761A (en) * | 1997-11-19 | 1999-06-08 | Kajima Corp | Underground structure and its construction method |
| CN101886468A (en) * | 2010-03-29 | 2010-11-17 | 南京大地建设集团有限责任公司 | Construction method of suspension type template support in high-position conjoined structure |
| CN102691411A (en) * | 2012-06-21 | 2012-09-26 | 中国建筑第五工程局有限公司 | Beam plate post-cast strip template support system and construction method thereof |
| CN203625872U (en) * | 2013-12-24 | 2014-06-04 | 葛洲坝集团第五工程有限公司 | Pile foundation construction platform |
| CN204919608U (en) * | 2015-09-21 | 2015-12-30 | 中铁上海工程局有限公司 | Underground station construction is with system of encorbelmenting |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105525629A (en) * | 2016-01-20 | 2016-04-27 | 中铁上海工程局集团有限公司 | Construction method and device of subway station |
| CN111379438A (en) * | 2020-03-10 | 2020-07-07 | 中国铁路设计集团有限公司 | Vertical temporary supporting system for underground structure and using method |
| CN117403694A (en) * | 2023-10-30 | 2024-01-16 | 中铁大桥勘测设计院集团有限公司 | A method for dismantling the formwork for subway station structure construction using the multi-layer open-cut construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105113542B (en) | 2018-06-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102587661B (en) | Method for constructing tall-section structural column of reinforced concrete frame | |
| CN210013462U (en) | An elevator shaft lifting construction operation platform | |
| CN105113542B (en) | Underground station construction overhanging system and underground station construction method | |
| CN103031892A (en) | Steel truss brace and manufacturing method for steel truss platform | |
| CN104831832B (en) | Assembly of shear wall structure and its installation method | |
| CN204282803U (en) | To encorbelment formwork structure for mounting platform | |
| CN103321406B (en) | A kind of support system of tall and big floor template | |
| CN206928642U (en) | A kind of safety and environmental protection movable formwork support | |
| CN204919608U (en) | Underground station construction is with system of encorbelmenting | |
| CN105525629A (en) | Construction method and device of subway station | |
| CN109989590B (en) | Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam | |
| CN202831628U (en) | Combined type bailey frame load-bearing shelving for pouring large span concrete beam | |
| CN103195232B (en) | Construction platform of elevator shaft and method for utilizing construction platform to construct elevator shaft | |
| CN206616843U (en) | A kind of support meanss of builder's jack | |
| CN106760500B (en) | Template supporting structure for construction of reserved hole top cover | |
| CN216920023U (en) | Support for large cantilever bent cap construction | |
| CN108331341A (en) | A kind of formwork support method and device of large size conversion beam | |
| CN204299144U (en) | Elevator internal mold operating platform | |
| CN204609297U (en) | Large-scale high-altitude load-bearing Cantilever Beams device | |
| CN211257760U (en) | A triangular support device for cantilevered scaffolding | |
| CN203890893U (en) | Supporting bracket for integral lifting of hollow slab girder | |
| CN204754164U (en) | Elevartor shaft construction derrick | |
| CN210002565U (en) | A column top anti-overturning device for a jack-up formwork system | |
| CN208267371U (en) | A kind of mould plate supporting device of large size conversion beam | |
| CN206530053U (en) | A kind of formwork support structure of hole to be provided top cover construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB02 | Change of applicant information |
Address after: 200436, No. 10, No. 272.278, No. 272.278, JIANGCHANG three, Shanghai Applicant after: Shanghai Civil Engineering Co., Ltd. of Crec Applicant after: THE FIRST CIVIL ENGINEERING CO., LTD. OF CREC SHANGHAI GROUP Address before: 200436, No. 10, No. 272.278, No. 272.278, JIANGCHANG three, Shanghai Applicant before: Shanghai Civil Engineering Co., Ltd. of CREC Applicant before: THE FIRST CIVIL ENGINEERING CO., LTD. OF CREC SHANGHAI GROUP |
|
| CB02 | Change of applicant information | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |