CN207379889U - It is a kind of to hit real permeable test device - Google Patents

It is a kind of to hit real permeable test device Download PDF

Info

Publication number
CN207379889U
CN207379889U CN201721478724.2U CN201721478724U CN207379889U CN 207379889 U CN207379889 U CN 207379889U CN 201721478724 U CN201721478724 U CN 201721478724U CN 207379889 U CN207379889 U CN 207379889U
Authority
CN
China
Prior art keywords
cylinder
retainer ring
test device
funnel
compaction cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721478724.2U
Other languages
Chinese (zh)
Inventor
徐书东
鲁贺贺
蒋玮
袁东东
鹿蓉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201721478724.2U priority Critical patent/CN207379889U/en
Application granted granted Critical
Publication of CN207379889U publication Critical patent/CN207379889U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

Real permeable test device is hit the utility model discloses a kind of, including water butt, compaction cylinder, funnel, the first graduated cylinder and the second graduated cylinder, wherein, the outlet at bottom of water butt is connected with the top entry of compaction cylinder, the outlet at bottom of compaction cylinder is located on funnel, the outlet at bottom of funnel is connected with the second graduated cylinder, and the entrance of the first graduated cylinder is connected with the overflow port of compaction cylinder upper side, which can measure the water permeability of porous pavement after compacting.

Description

It is a kind of to hit real permeable test device
Technical field
The utility model is related to a kind of permeable test devices, and in particular to a kind of to hit real permeable test device.
Background technology
Porous pavement is using porous materials makings such as water-permeating pitch mixed material, water-permeable cement concrete, permeable pavement bricks Surface layer, be a kind of novel pavement form with connectivity gap.Porous pavement is excellent with its significant draining, noise reduction Antiskid, security performance and good ecological benefits China have good application prospect.For porous pavement, in order to increase Add rain penetration amount, permeable effect of the evaluation pavement structure after compacting, it is therefore desirable to using corresponding test equipment to compacting The permeable effect of porous pavement is measured afterwards.
The pervious function of porous pavement is mainly measured with infiltration coefficient to reflect, current experiment room road pavement water permeability Test is tested using the pavement structure before not being compacted, and road surface structure hole gap variation is to water permeability after not considering compacting It influences, test result cannot react the pervious function of the pavement structure completely.
Utility model content
The purpose of the utility model is to overcome the shortcomings that the above-mentioned prior art, provide a kind of to hit real permeable test Device, the device can measure the water permeability of porous pavement after compacting.
In order to achieve the above objectives, it is described in the utility model hit real permeable test device include water butt, compaction cylinder, Funnel, the first graduated cylinder and the second graduated cylinder, wherein, the outlet at bottom of water butt is connected with the top entry of compaction cylinder, compaction cylinder Outlet at bottom be located on funnel, the outlet at bottom of funnel is connected with the second graduated cylinder, on the entrance and compaction cylinder of the first graduated cylinder The overflow port of end side surface is connected.
Valve is provided between water butt and compaction cylinder.
Supporting rack is further included, wherein, compaction cylinder and funnel are arranged in supporting rack.
First graduated cylinder is connected by water pipe with the overflow port of compaction cylinder upper side.
The bottom of compaction cylinder is provided with the cushion block with hole.
The stent includes the first retainer ring, the second retainer ring and several montants, the first retainer ring and the second retainer ring position Between each montant, each montant is connected with the outer circumferential surface of the first retainer ring and the outer circumferential surface of the second retainer ring, the first retainer ring Positioned at the top of the second retainer ring, compaction cylinder is connected in the first retainer ring, and funnel is connected in the second retainer ring.
Water-level gauge is provided in compaction cylinder.
Water valve is provided between funnel and the second graduated cylinder.
The utility model has the advantages that:
It is described in the utility model to hit real permeable test device in concrete operations, first the road surface in compaction cylinder is tied Structure hit reality, then injects water into compaction cylinder by water butt, and the second graduated cylinder is entered through pavement structure in compaction cylinder In, the water permeability of porous pavement after the amount assessment compacting by observing water in the second graduated cylinder, in addition, extra water is then by overflowing Head piece is entered in the first graduated cylinder, simple in structure, easy to operate, and practicability is extremely strong.
Description of the drawings
Fig. 1 is the structure diagram of the utility model;
Fig. 2 is the structure diagram of supporting rack 3 in the utility model.
Wherein, 1 be water butt, 2 be valve, 3 be supporting rack, 4 be compaction cylinder, 5 be funnel, 6 be water valve, 7 be water-level gauge, 8 it is overflow port, 9 be cushion block, 10 be the second graduated cylinder, 11 be water pipe, 12 be the first graduated cylinder, 301 be the second retainer ring, 302 is One retainer ring.
Specific embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings:
With reference to figure 1 and Fig. 2, it is described in the utility model hit real permeable test device include water butt 1, compaction cylinder 4, Funnel 5, the first graduated cylinder 12 and the second graduated cylinder 10, wherein, the outlet at bottom of water butt 1 is connected with the top entry of compaction cylinder 4, The outlet at bottom of compaction cylinder 4 is located on funnel 5, and the outlet at bottom of funnel 5 is connected with the second graduated cylinder 10, and the first graduated cylinder 12 enters Mouth is connected with the overflow port 8 of 4 upper side of compaction cylinder.
Valve 2 is provided between water butt 1 and compaction cylinder 4.The utility model further includes supporting rack 3, wherein, compaction cylinder 4 And funnel 5 is arranged in supporting rack 3;First graduated cylinder 12 is connected by water pipe 11 with the overflow port 8 of 4 upper side of compaction cylinder; The bottom of compaction cylinder 4 is provided with the cushion block 9 with hole;The stent include the first retainer ring 302, the second retainer ring 301 and Several montants, the first retainer ring 302 and the second retainer ring 301 between each montant, each montant and the first retainer ring 302 it is outer Circumferential surface and the outer circumferential surface of the second retainer ring 301 are connected, and the first retainer ring 302 is located at the top of the second retainer ring 301, compaction cylinder 4 are connected in the first retainer ring 302, and funnel 5 is connected in the second retainer ring 301;Water-level gauge 7 is provided in compaction cylinder 4;Funnel 5 and second are provided with water valve 6 between graduated cylinder 10;A diameter of 152mm of compaction cylinder 4.
The specific operation process of the utility model is:
Cushion block 9 with hole is positioned in compaction cylinder 4, then places one layer of geotechnological woven fabric in compaction cylinder 4 to prevent carefully Gather materials loss, then place pavement structure to be measured in compaction cylinder 4 again, and be layered and carry out hitting reality;Compaction cylinder 4 is positioned over first In retainer ring 302, and Open valve 2, the amount of water in the second graduated cylinder 10 is recorded, road surface is assessed according to the amount of water in the second graduated cylinder 10 The water permeability of structure.During the test, the situation of change of water level in compaction cylinder 4 is observed by water-level gauge 7, is hit by changing The change in elevation of water level simulates the pervious function of pavement structure in the case of different rainfalls in real cylinder 4.Wherein, fail in the short time It is then entered by the water oozed under funnel 5 by overflow port 8 in the first graduated cylinder 12, you can pavement structure leads under simulation rainstorm weather Cross the amount of rainfall of gutter discharge.

Claims (8)

1. a kind of hit real permeable test device, which is characterized in that including water butt (1), compaction cylinder (4), funnel (5), One graduated cylinder (12) and the second graduated cylinder (10), wherein, the outlet at bottom of water butt (1) is connected with the top entry of compaction cylinder (4), The outlet at bottom of compaction cylinder (4) is located on funnel (5), and the outlet at bottom of funnel (5) is connected with the second graduated cylinder (10), the first amount The entrance of cylinder (12) is connected with the overflow port (8) of compaction cylinder (4) upper side.
2. according to claim 1 hit real permeable test device, which is characterized in that water butt (1) and compaction cylinder (4) Between be provided with valve (2).
3. according to claim 1 hit real permeable test device, which is characterized in that supporting rack (3) is further included, In, compaction cylinder (4) and funnel (5) are arranged in supporting rack (3).
4. according to claim 1 hit real permeable test device, which is characterized in that the first graduated cylinder (12) passes through water pipe (11) overflow port (8) with compaction cylinder (4) upper side is connected.
5. according to claim 1 hit real permeable test device, which is characterized in that the bottom of compaction cylinder (4) is set There is the cushion block (9) with hole.
6. according to claim 3 hit real permeable test device, which is characterized in that the stent, which includes first, to be fixed Ring (302), the second retainer ring (301) and several montants, the first retainer ring (302) and the second retainer ring (301) are located at each montant Between, each montant is connected with the outer circumferential surface of the first retainer ring (302) and the outer circumferential surface of the second retainer ring (301), and first fixes Ring (302) is located at the top of the second retainer ring (301), and compaction cylinder (4) is connected in the first retainer ring (302), funnel (5) clamping In the second retainer ring (301).
7. according to claim 1 hit real permeable test device, which is characterized in that is provided with water in compaction cylinder (4) Position meter (7).
8. according to claim 1 hit real permeable test device, which is characterized in that funnel (5) and the second graduated cylinder (10) water valve (6) is provided between.
CN201721478724.2U 2017-11-08 2017-11-08 It is a kind of to hit real permeable test device Expired - Fee Related CN207379889U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721478724.2U CN207379889U (en) 2017-11-08 2017-11-08 It is a kind of to hit real permeable test device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721478724.2U CN207379889U (en) 2017-11-08 2017-11-08 It is a kind of to hit real permeable test device

Publications (1)

Publication Number Publication Date
CN207379889U true CN207379889U (en) 2018-05-18

Family

ID=62334681

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721478724.2U Expired - Fee Related CN207379889U (en) 2017-11-08 2017-11-08 It is a kind of to hit real permeable test device

Country Status (1)

Country Link
CN (1) CN207379889U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111006986A (en) * 2019-12-25 2020-04-14 西安建筑科技大学 Device and method for testing rainwater retention capacity and peak delay effect of permeable pavement

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111006986A (en) * 2019-12-25 2020-04-14 西安建筑科技大学 Device and method for testing rainwater retention capacity and peak delay effect of permeable pavement

Similar Documents

Publication Publication Date Title
CN106769774B (en) Asphalt pavement water seepage detection device and method for constant-pressure variable water head capable of preventing side seepage
CN103837385B (en) Coarse-grained soil high polymer grouting triaxial test sample preparation device and using method thereof
CN106049557B (en) Using the test method of the laboratory testing rig of simulation grout pile end follow-up grouting
CN103439237B (en) Blocking test device and method for water-permeable concrete pile in piping soil foundation
CN108613914B (en) Constant head asphalt mixture multidirectional seepage testing device
CN102095674A (en) Permeability testing method of water-permeable paving material, and special tester thereof
CN108088982A (en) Simulate the Experimental Method in Laboratory of fine grained seepage inflow erosion inside deep aquifers sand
CN104655468A (en) Sample preparation device and sample preparation method for sand-soil contact surface test sample as well as osmotic coefficient determination method
CN203758882U (en) Coarse particle soil penetration test device eliminating boundary effect
CN105717023B (en) A kind of permeable structure performance detector and detection method
CN113884423A (en) Device for testing silting-up characteristic of drainage anti-liquefaction channel of gravel pile indoors
CN105118363A (en) Method and model for simulated testing antiseepage curtain between concrete and bedrock
CN207379889U (en) It is a kind of to hit real permeable test device
CN110296930A (en) A kind of device and test method of on-site measurement porous pavement infiltration coefficient
CN107957390B (en) Method for simulating and measuring influence of farmland soil surface cracks on preferential inflow infiltration
CN207066937U (en) The measure device of swelled ground cracking water content
CN205404352U (en) Structural performance detector permeates water
CN107727547A (en) A kind of pervious concrete space distributing homogeneity evaluation method
CN112710592A (en) Method for establishing relation between porosity and permeability coefficient of permeable pavement material
CN101819105B (en) Drainage test system by low-path embankment and method thereof
CN201955291U (en) Permeability testing instrument for water permeable paving material
CN104831674B (en) Contact scour testing apparatus for earth-rock joint part
CN201707328U (en) Low-path-embankment waterproof and drainage test device
CN206459928U (en) Fill the device for testing permeability coefficient that big particle diameter rubber lamellar body hits real soil
CN206146800U (en) Osmotic coefficient measuring device of soil

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180518

Termination date: 20181108

CF01 Termination of patent right due to non-payment of annual fee