CN105118363A - Method and model for simulated testing antiseepage curtain between concrete and bedrock - Google Patents

Method and model for simulated testing antiseepage curtain between concrete and bedrock Download PDF

Info

Publication number
CN105118363A
CN105118363A CN201510384055.1A CN201510384055A CN105118363A CN 105118363 A CN105118363 A CN 105118363A CN 201510384055 A CN201510384055 A CN 201510384055A CN 105118363 A CN105118363 A CN 105118363A
Authority
CN
China
Prior art keywords
basement rock
curtain
water pipe
concrete
pressure water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510384055.1A
Other languages
Chinese (zh)
Other versions
CN105118363B (en
Inventor
饶承彪
张细和
郑克勋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201510384055.1A priority Critical patent/CN105118363B/en
Publication of CN105118363A publication Critical patent/CN105118363A/en
Application granted granted Critical
Publication of CN105118363B publication Critical patent/CN105118363B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a method and model for simulated testing an antiseepage curtain between concrete and a bedrock. A regularly-shaped bedrock is provided, and one side of the bedrock is chiseled to be rough. A high pressure water pipe with a plastic bulkhead is placed on the center of the rough surface of the bedrock, and a stirred concrete layer is poured on the rough side of the bedrock to totally cover the high pressure water pipe. An elongated steel bar is extended in the high pressure water pipe to poke the plastic bulkhead on the other end of the high pressure water pipe so as to form a hole when the concrete is not yet cured, so that water can seep into the contact surface between the bedrock and the concrete layer from the hole. After the concrete is normally cured, the high pressure water pipe is connected with a high pressure water pump. The water pressure needed is adjusted according to the data on a water pressure gauge. In this way, a penetration value of water flow in an antiseepage curtain when the curtain makes contact with a bedrock can be obtained through simulated testing means, and the relation between the seepage flow of the curtain and penetration pressure variation characteristic and the damage of the curtain can be obtained.

Description

The test method of seepage proof curtain and model between a kind of simulation concrete and basement rock
Technical field
the present invention relates to test method and the model of seepage proof curtain between a kind of simulation concrete and basement rock, belong to seepage control of dam curtain technique field.
Background technology
the most large medium-size station of China and reservoir have run and have exceeded Two decades years, also have more project go into operation successively and be completed in recent years.Seepage proof curtain is the crucial component of reservoir dam impervious leakage-stopping, and under seepage proof curtain is in the effect of high-pressure osmosis current for a long time, hydro-geochemical environment is complicated, and seepage proof curtain is corroded continuing and aging decay.To non-karst area, seepage of dam is based on fissurity seepage; To karst area, seepage field is more complicated, has karst and fissurity seepage feature concurrently.
grout curtain its essence is the process of cement grout in High Pressure retrofilling karst or crack.Actual geologic body is huge, material the Nomenclature Composition and Structure of Complexes complex.Because the geologic body of reality is huge, only have theoretical analysis and practical application at present, also there is no the formation about seepage proof curtain and change procedure simulated data, affect the Essential Analysis foundation to seepage proof curtain.
Summary of the invention
the object of the invention is to, test method and the model of seepage proof curtain between a kind of simulation concrete and basement rock are provided, for the formation of seepage proof curtain and change provide the data foundation close to reality between laboratory simulation concrete and basement rock, thus overcome the deficiencies in the prior art.
technical scheme of the present invention is achieved in that
between a kind of simulation concrete of the present invention and basement rock, the test method of seepage proof curtain is, when the whole process simulation that the method curtain in seepage proof curtain contacts with basement rock is tested, look for the basement rock that a piece comparatively upright in advance, to wherein one side dabbing, high-pressure water pipe with Plastic cap is placed on the position in the middle of basement rock roughened surface, then the concrete layer of mix is cast on the basement rock of dabbing, and high-pressure water pipe is covered completely, can simulate between concrete layer and basement rock like this and form seepage proof curtain; When normal concrete does not condense, stretch in high-pressure water pipe with elongated reinforcing bar and the Plastic cap of high-pressure water pipe other end is broken, after forming one, prick hole, enable water enter the surface of contact of basement rock and concrete layer from rear bundle hole; After normal concrete condensation, high-pressure water pipe is connected high-pressure hydraulic pump, the data of observing on water pressure gauge regulate required hydraulic pressure, the osmotic value of current in curtain when so namely showing that in seepage proof curtain, curtain contacts with basement rock by the mode of this simulation test, and the seepage flow of curtain and seepage pressure variation characteristic and the injuring relation with curtain thereof can be drawn.
between the of the present invention a kind of simulation concrete built according to said method and basement rock, the test model of seepage proof curtain is, this test model comprises basement rock, basement rock one side is provided with concrete layer, and be embedded with high-pressure water pipe at the surface of contact of basement rock and concrete layer, high-pressure water pipe is provided with water pressure gauge.
in aforesaid experimental model, described high-pressure water pipe one end is provided with Plastic cap, and one end that high-pressure water pipe is provided with Plastic cap is positioned at the central authorities of basement rock and concrete layer surface of contact, and Plastic cap is provided with rear bundle hole.
in aforesaid experimental model, described basement rock and concrete layer surface of contact are that hair side contacts.
owing to have employed technique scheme, compared with prior art, the present invention can simulate in laboratory can seepage proof curtain model of geological structure body between the concrete of practical operation and basement rock in the present invention.By testing the seepage flow and seepage pressure variation characteristic and the injuring relation with curtain thereof that can draw curtain, also can by the current oozed out in test model, analyze water quality, draw the data such as the isoionic content of SO42-, HCO3-, Ca2+, Mg2+ and pH value, conductivity, temperature field in seepage proof curtain body, for the formation of seepage proof curtain and change provide the data foundation close to reality.For between laboratory simulation concrete and basement rock, the formation of seepage proof curtain and change provide the data foundation close to reality.
Accompanying drawing explanation
fig. 1 is structural representation of the present invention.
mark in accompanying drawing: 1-concrete layer; 2-basement rock; 3-high-pressure water pipe; 4-water pressure gauge; 5-Plastic cap; The surface of contact of 6-basement rock and concrete layer; Hole is pricked after 7-.
Embodiment
below in conjunction with drawings and Examples, the present invention is described in further detail, but not as any limitation of the invention.
between a kind of simulation concrete of the present invention and basement rock, the test method of seepage proof curtain is, as shown in Figure 1, the method is that curtain contacts with basement rock in seepage proof curtain whole process simulation is when testing, look for the basement rock 2 that a piece comparatively upright in advance, to wherein one side dabbing, high-pressure water pipe 3 with Plastic cap 5 is placed on the position in the middle of basement rock roughened surface, then the concrete layer 1 of mix is cast on the basement rock 2 of dabbing, and high-pressure water pipe 3 is covered completely, can simulate between concrete layer 1 and basement rock 2 like this and form seepage proof curtain; When normal concrete does not condense, stretch in high-pressure water pipe 3 with elongated reinforcing bar and the Plastic cap 5 of high-pressure water pipe 3 other end is broken, form one and prick hole 7 afterwards, enable water enter the surface of contact 6 of basement rock and concrete layer from rear bundle hole 7; After normal concrete condensation, high-pressure water pipe 3 is connected high-pressure hydraulic pump, the data of observing on water pressure gauge 4 regulate required hydraulic pressure, the osmotic value of current in curtain when so namely showing that in seepage proof curtain, curtain contacts with basement rock by the mode of this simulation test, and the seepage flow of curtain and seepage pressure variation characteristic and the injuring relation with curtain thereof can be drawn.
the test model of seepage proof curtain between the of the present invention a kind of simulation concrete built according to said method and basement rock, as shown in Figure 1, this test model comprises basement rock 2, basement rock one side is provided with concrete layer 1, be embedded with high-pressure water pipe 3 at the surface of contact 6 of basement rock and concrete layer, high-pressure water pipe is provided with water pressure gauge 4.High-pressure water pipe 3 one end is provided with Plastic cap 5, and one end that high-pressure water pipe is provided with Plastic cap is positioned at the central authorities of basement rock 2 and concrete layer 1 surface of contact, and Plastic cap is provided with rear bundle hole 7.Basement rock with concrete layer surface of contact 6 for hair side contacts.
Embodiment
this can simulate the whole process that in seepage proof curtain, curtain contacts with basement rock such as shown in Fig. 1.Look for the basement rock 2 that a piece comparatively upright, to wherein one side dabbing, high-pressure water pipe 3 with Plastic cap 5 is placed on the position in the middle of basement rock roughened surface, then the concrete layer 1 of mix is cast on the basement rock 2 of dabbing, and high-pressure water pipe is covered completely, when normal concrete does not condense, stretch in high-pressure water pipe 3 with elongated reinforcing bar and the Plastic cap 5 of high-pressure water pipe 3 other end is broken, form one and prick hole 7 afterwards, enable water enter the surface of contact 6 of basement rock and concrete layer from rear bundle hole.The effect of Plastic cap 5 is that when preventing casting concrete, concrete enters high-pressure water pipe and blocked by the mouth of pipe, again by pricking a hole after elongated reinforcing bar after only building.After normal concrete condensation, after maintenance a period of time, high-pressure water pipe 3 is connected high-pressure hydraulic pump, the data of observing on water pressure gauge 4 regulate required hydraulic pressure, thus draw the osmotic value of current in curtain.The water flowed out can carry out physics and chemistry analysis, draws the primary evaluation factors such as the content of SO42-, HCO3-, Ca2+, Mg2+ and pH value, conductivity, temperature field.

Claims (4)

1. the test method of a seepage proof curtain between simulation concrete and basement rock, it is characterized in that: when the whole process simulation that curtain contacts with basement rock in seepage proof curtain is tested, look for the basement rock (2) that a piece comparatively upright in advance, to wherein one side dabbing, high-pressure water pipe (3) with Plastic cap (5) is placed on the position in the middle of basement rock roughened surface, then the concrete layer (1) of mix is cast on the basement rock (2) of dabbing, and high-pressure water pipe is covered completely, can simulate between concrete layer (1) and basement rock (2) like this and form seepage proof curtain; When normal concrete does not condense, stretch in high-pressure water pipe (3) with elongated reinforcing bar and the Plastic cap (5) of high-pressure water pipe (3) other end is broken, prick hole (7) after forming one, enable water enter the surface of contact (6) of basement rock and concrete layer from rear bundle hole (7); After normal concrete condensation, high-pressure water pipe (3) is connected high-pressure hydraulic pump, the data of observing on water pressure gauge (4) regulate required hydraulic pressure, the osmotic value of current in curtain when so namely showing that in seepage proof curtain, curtain contacts with basement rock by the mode of this simulation test, and the seepage flow of curtain and seepage pressure variation characteristic and the injuring relation with curtain thereof can be drawn.
2. the test model of a seepage proof curtain between simulation concrete and basement rock, it is characterized in that: comprise basement rock (2), basement rock one side is provided with concrete layer (1), and be embedded with high-pressure water pipe (3) at the surface of contact (6) of basement rock and concrete layer, high-pressure water pipe is provided with water pressure gauge (4).
3. the test model of seepage proof curtain between simulation concrete and basement rock according to claim 2, it is characterized in that: described high-pressure water pipe (3) one end is provided with Plastic cap (5), one end that high-pressure water pipe is provided with Plastic cap is positioned at the central authorities of basement rock (2) and concrete layer (1) surface of contact, and Plastic cap is provided with rear bundle hole (7).
4. the test model of seepage proof curtain between simulation concrete and basement rock according to claim 2, is characterized in that: described basement rock with concrete layer surface of contact (6) for hair side contacts.
CN201510384055.1A 2015-07-03 2015-07-03 The test method and model of seepage proof curtain between a kind of simulation concrete and basement rock Active CN105118363B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510384055.1A CN105118363B (en) 2015-07-03 2015-07-03 The test method and model of seepage proof curtain between a kind of simulation concrete and basement rock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510384055.1A CN105118363B (en) 2015-07-03 2015-07-03 The test method and model of seepage proof curtain between a kind of simulation concrete and basement rock

Publications (2)

Publication Number Publication Date
CN105118363A true CN105118363A (en) 2015-12-02
CN105118363B CN105118363B (en) 2017-09-26

Family

ID=54666327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510384055.1A Active CN105118363B (en) 2015-07-03 2015-07-03 The test method and model of seepage proof curtain between a kind of simulation concrete and basement rock

Country Status (1)

Country Link
CN (1) CN105118363B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464041A (en) * 2015-12-31 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Method and model for simulating impervious curtain of reservoir dam
CN105466836A (en) * 2015-12-31 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Method for simulating impervious curtain of reservoir dam and test structure model adopted by method
CN106092855A (en) * 2016-07-07 2016-11-09 中国电建集团贵阳勘测设计研究院有限公司 The device of a kind of seepage proof curtain simulation test and test method
CN112504938A (en) * 2020-12-13 2021-03-16 中国科学院武汉岩土力学研究所 Seepage simulation device, real triaxial rock permeability real-time measuring system and method
CN112782055A (en) * 2021-01-06 2021-05-11 中国建筑股份有限公司 Penetration test device
CN112834403A (en) * 2021-01-06 2021-05-25 中国建筑股份有限公司 Penetration test method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4552011A (en) * 1982-09-28 1985-11-12 Phillips Petroleum Company Establishing a differential pressure across a core sample or calibrating a differential pressure transducer
CN101561378A (en) * 2009-05-22 2009-10-21 清华大学 Tester for testing seepage and scour characteristics of contact surface of soil body and structure
CN102839628A (en) * 2012-09-06 2012-12-26 中国水利水电科学研究院 Large-scale high-pressure cylinder permeation simulation device and method
CN103091214A (en) * 2011-10-29 2013-05-08 成都理工大学 Under-dam seepage flow experiment apparatus
CN204759883U (en) * 2015-07-03 2015-11-11 中国电建集团贵阳勘测设计研究院有限公司 Impervious curtain's test model between simulation concrete and basement rock

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4552011A (en) * 1982-09-28 1985-11-12 Phillips Petroleum Company Establishing a differential pressure across a core sample or calibrating a differential pressure transducer
CN101561378A (en) * 2009-05-22 2009-10-21 清华大学 Tester for testing seepage and scour characteristics of contact surface of soil body and structure
CN103091214A (en) * 2011-10-29 2013-05-08 成都理工大学 Under-dam seepage flow experiment apparatus
CN102839628A (en) * 2012-09-06 2012-12-26 中国水利水电科学研究院 Large-scale high-pressure cylinder permeation simulation device and method
CN204759883U (en) * 2015-07-03 2015-11-11 中国电建集团贵阳勘测设计研究院有限公司 Impervious curtain's test model between simulation concrete and basement rock

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464041A (en) * 2015-12-31 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Method and model for simulating impervious curtain of reservoir dam
CN105466836A (en) * 2015-12-31 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Method for simulating impervious curtain of reservoir dam and test structure model adopted by method
CN106092855A (en) * 2016-07-07 2016-11-09 中国电建集团贵阳勘测设计研究院有限公司 The device of a kind of seepage proof curtain simulation test and test method
CN112504938A (en) * 2020-12-13 2021-03-16 中国科学院武汉岩土力学研究所 Seepage simulation device, real triaxial rock permeability real-time measuring system and method
CN112782055A (en) * 2021-01-06 2021-05-11 中国建筑股份有限公司 Penetration test device
CN112834403A (en) * 2021-01-06 2021-05-25 中国建筑股份有限公司 Penetration test method
CN112782055B (en) * 2021-01-06 2023-01-03 中国建筑股份有限公司 Penetration test device

Also Published As

Publication number Publication date
CN105118363B (en) 2017-09-26

Similar Documents

Publication Publication Date Title
CN105118363A (en) Method and model for simulated testing antiseepage curtain between concrete and bedrock
CN204759883U (en) Impervious curtain's test model between simulation concrete and basement rock
CN105203410B (en) A kind of experimental rig for being used to measure rock shearing creep properties
CN103954511B (en) A kind of Fracture Networks rock shearing-seepage flow coupling experiment method
CN104060637B (en) A kind of centrifuge model test method that gravel pile reinforcing is soft soil roadbed
CN105096718B (en) A kind of test method and model of simulation reservoir seepage control of dam curtain
CN104878739B (en) Drainage material assembly capable of being transversely connected with plastic drainage boards and method for constructing drainage material assembly
CN204990969U (en) Simulation reservoir dam impervious curtain's test model
CN106198890A (en) A kind of indoor grouting simulation test device and using method thereof
CN107014730B (en) A method of simulating true groundwater erosion Nuclear Waste Repository padded coaming
CN103091471B (en) A kind of model accelerating rinse fill consolidation and test method thereof
CN202899174U (en) Tubular pile fiber grating sensor testing system
CN106289614A (en) The model test apparatus of Indoor measurement Earth Pressure for Shield Tunnel Lining and method
CN103389260A (en) Laboratory simulation test method for researching underground water seepage obstruction caused by pile foundation
CN104264719A (en) Vacuum preloading indoor model testing apparatus
CN203824878U (en) Test device for simulating seepage prevention of embankment foundation engineering soil
CN205242462U (en) Research anti -floating pile resists test device that foundation ditch suddenly gushes failure mechanisms
CN103308393B (en) Formation fracturing resistance testing device and method
CN204112378U (en) A kind of two casing device of pile measurement with emulation buffer action
CN102561134B (en) Compaction method for embankment filling under high liquid limit red clay according to equilibrium moisture content
CN105466836A (en) Method for simulating impervious curtain of reservoir dam and test structure model adopted by method
CN106768153B (en) A kind of slurry consolidation cubical contraction test device and method of testing
CN204703203U (en) Pit accident bath scaled model experimental device
CN108343095A (en) The experimental rig and method of static pressure pile-sinking in the simulation saturation soil body
CN205157281U (en) Test and appraisal of crack infiltration self -healing ability are with concrete sample and test and appraisal device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant