CN204759883U - Test model for simulating impervious curtain between concrete and bedrock - Google Patents

Test model for simulating impervious curtain between concrete and bedrock Download PDF

Info

Publication number
CN204759883U
CN204759883U CN201520471602.5U CN201520471602U CN204759883U CN 204759883 U CN204759883 U CN 204759883U CN 201520471602 U CN201520471602 U CN 201520471602U CN 204759883 U CN204759883 U CN 204759883U
Authority
CN
China
Prior art keywords
basement rock
curtain
seepage
concrete
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520471602.5U
Other languages
Chinese (zh)
Inventor
饶承彪
张细和
郑克勋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201520471602.5U priority Critical patent/CN204759883U/en
Application granted granted Critical
Publication of CN204759883U publication Critical patent/CN204759883U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

The utility model discloses a simulation is experimental model of impervious curtain between concrete and basement rock, this experimental model include basement rock (</b >2</b >), and the basement rock one side is equipped with concrete layer (</b >1</b >), and it has high pressure water pipe (</b >3</b >) to pre-embed in basement rock and concrete layer's contact surface (</b >6</b >), is equipped with water pressure gauge (</b >4</b >) on the high pressure water pipe. The utility model discloses a test model can simulate out the prevention of seepage curtain geological body model between concrete and the bed rock that can actual operation in the laboratory. The seepage flow and seepage pressure change characteristics of the curtain and the damage relation between the seepage flow and the curtain can be obtained through tests, and the water quality can be analyzed through the water flow seeped out from the test model, SO that the contents of ions such as SO42-, (HCO 3-), (Ca 2 +), (Mg 2 +), (and the like) in the seepage-proof curtain body and the data such as pH value, conductivity, temperature field and the like can be obtained, SO that a data basis close to reality is provided for the formation and the change of the seepage-proof curtain. [ b ]

Description

The test model of seepage proof curtain between a kind of simulation concrete and basement rock
Technical field
the utility model relates to the test model of seepage proof curtain between a kind of simulation concrete and basement rock, belongs to seepage control of dam curtain technique field.
Background technology
the most large medium-size station of China and reservoir have run and have exceeded Two decades years, also have more project go into operation successively and be completed in recent years.Seepage proof curtain is the crucial component of reservoir dam impervious leakage-stopping, and under seepage proof curtain is in the effect of high-pressure osmosis current for a long time, hydro-geochemical environment is complicated, and seepage proof curtain is corroded continuing and aging decay.To non-karst area, seepage of dam is based on fissurity seepage; To karst area, seepage field is more complicated, has karst and fissurity seepage feature concurrently.
grout curtain its essence is the process of cement grout in High Pressure retrofilling karst or crack.Actual geologic body is huge, material the Nomenclature Composition and Structure of Complexes complex.Because the geologic body of reality is huge, only have theoretical analysis and practical application at present, also there is no the formation about seepage proof curtain and change procedure simulated data, affect the Essential Analysis foundation to seepage proof curtain.
Utility model content
the purpose of this utility model is, the test model of seepage proof curtain between a kind of simulation concrete and basement rock is provided, for the formation of seepage proof curtain and change provide the data foundation close to reality between laboratory simulation concrete and basement rock, thus overcome the deficiencies in the prior art.
the technical solution of the utility model is achieved in that
between a kind of simulation concrete of the present utility model and basement rock, the test model of seepage proof curtain is that this test model comprises basement rock, and basement rock one side is provided with concrete layer, and be embedded with high-pressure water pipe at the surface of contact of basement rock and concrete layer, high-pressure water pipe is provided with water pressure gauge.
in aforesaid experimental model, described high-pressure water pipe one end is provided with Plastic cap, and one end that high-pressure water pipe is provided with Plastic cap is positioned at the central authorities of basement rock and concrete layer surface of contact, and Plastic cap is provided with rear bundle hole.
in aforesaid experimental model, described basement rock and concrete layer surface of contact are that hair side contacts.
owing to have employed technique scheme, compared with prior art, the utility model can simulate in laboratory can seepage proof curtain model of geological structure body between the concrete of practical operation and basement rock for the utility model.By testing the seepage flow and seepage pressure variation characteristic and the injuring relation with curtain thereof that can draw curtain, also can by the current oozed out in test model, analyze water quality, draw the data such as the isoionic content of SO42-, HCO3-, Ca2+, Mg2+ and pH value, conductivity, temperature field in seepage proof curtain body, for the formation of seepage proof curtain and change provide the data foundation close to reality.For between laboratory simulation concrete and basement rock, the formation of seepage proof curtain and change provide the data foundation close to reality.
Accompanying drawing explanation
fig. 1 is structural representation of the present utility model.
mark in accompanying drawing: 1-concrete layer; 2-basement rock; 3-high-pressure water pipe; 4-water pressure gauge; 5-Plastic cap; The surface of contact of 6-basement rock and concrete layer; Hole is pricked after 7-.
Embodiment
below in conjunction with drawings and Examples, the utility model is described in further detail, but not as to any restriction of the present utility model.
the utility model is constructed by the test method of seepage proof curtain between following a kind of simulation concrete and basement rock, as shown in Figure 1, the method is that curtain contacts with basement rock in seepage proof curtain whole process simulation is when testing, look for the basement rock 2 that a piece comparatively upright in advance, to wherein one side dabbing, high-pressure water pipe 3 with Plastic cap 5 is placed on the position in the middle of basement rock roughened surface, then the concrete layer 1 of mix is cast on the basement rock 2 of dabbing, and high-pressure water pipe is covered completely, when normal concrete does not condense, stretch in high-pressure water pipe 3 with elongated reinforcing bar and the Plastic cap 5 of high-pressure water pipe 3 other end is broken, form one and prick hole 7 afterwards, water is enable to enter the surface of contact 6 of basement rock and concrete layer from rear bundle hole 7, after normal concrete condensation, high-pressure water pipe 3 is connected high-pressure hydraulic pump, the data of observing on water pressure gauge 4 regulate required hydraulic pressure, the osmotic value of current in curtain when so namely showing that in seepage proof curtain, curtain contacts with basement rock by the mode of this simulation test, and the seepage flow of curtain and seepage pressure variation characteristic and the injuring relation with curtain thereof can be drawn.
the test model of seepage proof curtain between the of the present utility model a kind of simulation concrete built according to said method and basement rock, as shown in Figure 1, this test model comprises basement rock 2, basement rock one side is provided with concrete layer 1, be embedded with high-pressure water pipe 3 at the surface of contact 6 of basement rock and concrete layer, high-pressure water pipe is provided with water pressure gauge 4.High-pressure water pipe 3 one end is provided with Plastic cap 5, and one end that high-pressure water pipe is provided with Plastic cap is positioned at the central authorities of basement rock 2 and concrete layer 1 surface of contact, and Plastic cap is provided with rear bundle hole 7.Basement rock with concrete layer surface of contact 6 for hair side contacts.
Embodiment
this can simulate the whole process that in seepage proof curtain, curtain contacts with basement rock such as shown in Fig. 1.Look for the basement rock 2 that a piece comparatively upright, to wherein one side dabbing, high-pressure water pipe 3 with Plastic cap 5 is placed on the position in the middle of basement rock roughened surface, then the concrete layer 1 of mix is cast on the basement rock 2 of dabbing, and high-pressure water pipe is covered completely, when normal concrete does not condense, stretch in high-pressure water pipe 3 with elongated reinforcing bar and the Plastic cap 5 of high-pressure water pipe 3 other end is broken, form one and prick hole 7 afterwards, enable water enter the surface of contact 6 of basement rock and concrete layer from rear bundle hole.The effect of Plastic cap 5 is that when preventing casting concrete, concrete enters high-pressure water pipe and blocked by the mouth of pipe, again by pricking a hole after elongated reinforcing bar after only building.After normal concrete condensation, after maintenance a period of time, high-pressure water pipe 3 is connected high-pressure hydraulic pump, the data of observing on water pressure gauge 4 regulate required hydraulic pressure, thus draw the osmotic value of current in curtain.The water flowed out can carry out physics and chemistry analysis, draws the primary evaluation factors such as the content of SO42-, HCO3-, Ca2+, Mg2+ and pH value, conductivity, temperature field.

Claims (3)

1. the test model of a seepage proof curtain between simulation concrete and basement rock, it is characterized in that: comprise basement rock (2), basement rock one side is provided with concrete layer (1), and be embedded with high-pressure water pipe (3) at the surface of contact (6) of basement rock and concrete layer, high-pressure water pipe is provided with water pressure gauge (4).
2. the test model of seepage proof curtain between simulation concrete and basement rock according to claim 1, it is characterized in that: described high-pressure water pipe (3) one end is provided with Plastic cap (5), one end that high-pressure water pipe is provided with Plastic cap is positioned at the central authorities of basement rock (2) and concrete layer (1) surface of contact, and Plastic cap is provided with rear bundle hole (7).
3. the test model of seepage proof curtain between simulation concrete and basement rock according to claim 1, is characterized in that: described basement rock with concrete layer surface of contact (6) for hair side contacts.
CN201520471602.5U 2015-07-03 2015-07-03 Test model for simulating impervious curtain between concrete and bedrock Expired - Fee Related CN204759883U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520471602.5U CN204759883U (en) 2015-07-03 2015-07-03 Test model for simulating impervious curtain between concrete and bedrock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520471602.5U CN204759883U (en) 2015-07-03 2015-07-03 Test model for simulating impervious curtain between concrete and bedrock

Publications (1)

Publication Number Publication Date
CN204759883U true CN204759883U (en) 2015-11-11

Family

ID=54474566

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520471602.5U Expired - Fee Related CN204759883U (en) 2015-07-03 2015-07-03 Test model for simulating impervious curtain between concrete and bedrock

Country Status (1)

Country Link
CN (1) CN204759883U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105118363A (en) * 2015-07-03 2015-12-02 中国电建集团贵阳勘测设计研究院有限公司 Test method and model for simulating impervious curtain between concrete and bedrock
CN105464041A (en) * 2015-12-31 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Method and model for simulating impervious curtain of reservoir dam
CN107102124A (en) * 2017-04-19 2017-08-29 中国电建集团贵阳勘测设计研究院有限公司 Method for evaluating dissolution type erosion calcium precipitation amount of hydraulic and hydroelectric engineering
CN109831836A (en) * 2018-12-20 2019-05-31 成都理工大学 A kind of stratiform physical model and preparation method thereof based on flat heating element
CN112942250A (en) * 2021-02-04 2021-06-11 中国水利水电建设工程咨询渤海有限公司 Construction method of concrete anchoring structure with geomembrane penetration detection function

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105118363A (en) * 2015-07-03 2015-12-02 中国电建集团贵阳勘测设计研究院有限公司 Test method and model for simulating impervious curtain between concrete and bedrock
CN105118363B (en) * 2015-07-03 2017-09-26 中国电建集团贵阳勘测设计研究院有限公司 Test method and model for simulating impervious curtain between concrete and bedrock
CN105464041A (en) * 2015-12-31 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Method and model for simulating impervious curtain of reservoir dam
CN107102124A (en) * 2017-04-19 2017-08-29 中国电建集团贵阳勘测设计研究院有限公司 Method for evaluating dissolution type erosion calcium precipitation amount of hydraulic and hydroelectric engineering
CN107102124B (en) * 2017-04-19 2019-12-03 中国电建集团贵阳勘测设计研究院有限公司 Method for evaluating dissolution type erosion calcium precipitation amount of hydraulic and hydroelectric engineering
CN109831836A (en) * 2018-12-20 2019-05-31 成都理工大学 A kind of stratiform physical model and preparation method thereof based on flat heating element
CN112942250A (en) * 2021-02-04 2021-06-11 中国水利水电建设工程咨询渤海有限公司 Construction method of concrete anchoring structure with geomembrane penetration detection function
CN112942250B (en) * 2021-02-04 2022-05-31 中国水利水电建设工程咨询渤海有限公司 Construction method of concrete anchoring structure with geomembrane penetration detection function

Similar Documents

Publication Publication Date Title
CN204759883U (en) Test model for simulating impervious curtain between concrete and bedrock
CN105118363A (en) Test method and model for simulating impervious curtain between concrete and bedrock
CN204990969U (en) Test model for simulating impervious curtain of reservoir dam
CN101915721B (en) Test method for simulating variation of permeability coefficient of foundation pit precipitation
CN206292074U (en) A kind of piston drawing-in type ground water fixed depth harvester
CN105089589A (en) Visual experiment device for realizing combined injection and layered injection of polymer flooding agent and working method thereof
CN106088174A (en) A kind of soft clay area diaphram wall seepage detection system
CN103837385A (en) Coarse-grained soil polymer slip casting triaxial test sample kit and using method thereof
CN102608011A (en) Method for determining and building bound water for crack-pore (hole) type reservoir core
CN105096718A (en) Test method and model for simulating impervious curtain of reservoir dam
CN106198890A (en) A kind of indoor grouting simulation test device and using method thereof
CN104264719A (en) Vacuum preloading indoor model testing apparatus
CN204827402U (en) Experimental model for researching deep profile control and flooding oil displacement mechanism of water flooding sandstone reservoir
CN106932555A (en) In-situ ionic rare earth soaks the computational methods of the ore deposit single hole fluid injection radius of influence
CN203824878U (en) Test device for simulating seepage prevention of embankment foundation engineering soil
CN205003029U (en) A muddy water splitting pressure test device for shield tunnel
CN110672488A (en) Experimental device for influence of seepage pressure on rock-soil strength and ground stress on rock-soil permeability
CN204389350U (en) A kind of test unit studying curtain surface of contact soil particle migration rule
CN106368165A (en) Testing device for simulating seepage failure of dam with upper part defects and construction method thereof
CN204152479U (en) Fractured reservoir Weak Gels profile control performance evaluation visual experimental apparatus
CN205808885U (en) Device for seepage-proof curtain simulation test
CN201915970U (en) Draining type segment lining model test box
CN105466836A (en) Method for simulating impervious curtain of reservoir dam and test structure model adopted by method
CN204703203U (en) Pit accident bath scaled model experimental device
CN205301134U (en) Test structure model for simulating impervious curtain of reservoir dam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151111

Termination date: 20180703

CF01 Termination of patent right due to non-payment of annual fee