CN207376762U - A kind of flood control electricity row station - Google Patents
A kind of flood control electricity row station Download PDFInfo
- Publication number
- CN207376762U CN207376762U CN201721469244.XU CN201721469244U CN207376762U CN 207376762 U CN207376762 U CN 207376762U CN 201721469244 U CN201721469244 U CN 201721469244U CN 207376762 U CN207376762 U CN 207376762U
- Authority
- CN
- China
- Prior art keywords
- water
- flood control
- flow channel
- water outlet
- flap valve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A20/00—Water conservation; Efficient water supply; Efficient water use
- Y02A20/20—Controlling water pollution; Waste water treatment
Landscapes
- Barrages (AREA)
Abstract
The utility model discloses a kind of flood control electricity row stations, it is intended to and when solving water pump operation or all standing, current repeated stock flap valve, the fixed screw for flap valve of controlling flood easily comes off, the situation that flood is caused to pour in down a chimney, its key points of the technical solution are that:It including water inlet flow channel, water outlet box culvert and is arranged between water inlet flow channel and water outlet box culvert for the water in water inlet flow channel to be evacuated to the water pump of water outlet box culvert, the water outlet of the water pump is provided with flood control flap valve, and the flood control flap valve front end is provided with emergency gate.A kind of flood control electricity row station of the utility model sets emergent emergency gate in flood control flap valve front end, has the advantages that prevent flood from pouring in down a chimney.
Description
Technical field
The utility model is related to hydraulic engineering field, more specifically, it relates to a kind of flood control electricity row station.
Background technology
Electricity row station is the water conservancy projects of water drainage of taking precautions against drought.It is laid in flat-bottomed land more, in rainy season, low-lying land is excluded by water pump
The ponding of band prevents the water conservancy projects of the generation of waterlogging.
The water outlet of water pump is usually provided with flood control flap valve, since the keying of flood control flap valve is by pump machine draining and outer river
Water pressure controls, and is instantaneous keying, and during water pump operation, current impact flap valve always, and the fixed screw for flap valve of controlling flood easily takes off
Fall, the situation that flood is caused to pour in down a chimney.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of flood control electricity row stations, controlling flood
Flap valve front end sets emergent emergency gate, has the advantages that prevent flood from pouring in down a chimney.
The above-mentioned technical purpose of the utility model technical scheme is that:A kind of flood control electricity row station,
Including water inlet flow channel, water outlet box culvert and it is arranged between water inlet flow channel and water outlet box culvert the water in water inlet flow channel being evacuated to
The water pump of water outlet box culvert, the water outlet of the water pump are provided with flood control flap valve, and the flood control flap valve front end is provided with emergency brake
Door.
By using above-mentioned technical proposal, when the water level on water inlet flow channel is higher than river level, water pump is by water inlet flow channel
Interior water is evacuated to water outlet box culvert, is then discharged at rivers and discharges, prevents urban waterlogging, during water pump operation, water impact flood control
Flap valve causes the fixed screw controlled flood on flap valve to come off, and then when so that the flood control flap valve is come off, closes the emergent of flood control flap valve front end
Gate prevents flood from pouring in down a chimney, while also is used as bulkhead gate when flood control flap valve overhauls.
The utility model is further arranged to:The emergency gate is controlled by hoist engine and lifted.
By using above-mentioned technical proposal, by hoist engine emergency gate is controlled to lift, can quickly control emergency brake
The keying of door.
The utility model is further arranged to:Vertical shaft venthole is provided at the pump outlet.
By using above-mentioned technical proposal, since water hammer pressure is larger at pump outlet, during water drainage, the gas that is generated between Shun
It presses larger, by the vertical shaft venthole of setting, air pressure is exported, reduce the influence to flood control flap valve and emergency gate.
The utility model is further arranged to:The pipelined channel bottom and water outlet box culvert bottom are provided with reinforcing layer,
The reinforcing layer includes reinforced concrete backplane level, concrete bed course and cement stone dust bed course successively.
By using above-mentioned technical proposal, in the reinforced concrete bottom plate that pipelined channel and water outlet box culvert bottom are set gradually
Layer, concrete bed course and cement stone dust bed course improve the fastness of bottom, reduce the percussion of flood.
The utility model is further arranged to:The water inlet of the water inlet flow channel sets bulkhead gate.
By using above-mentioned technical proposal, in the bulkhead gate that the water inlet of water inlet flow channel is set, facilitate water inlet flow channel
And the maintenance of water pump.
The utility model is further arranged to:The bulkhead gate front end sets trash rack.
By using above-mentioned technical proposal, the trash rack of setting reduces rubbish and enters in water inlet flow channel, rubbish is avoided to damage
Bad water pump.
The utility model is further arranged to:The water outlet box culvert outlet is connected with rivers, and the water outlet box culvert surrounding is equal
It is vertically arranged with water stop.
By using above-mentioned technical proposal, water outlet box culvert upper and lower surface is vertically arranged water stop, prevent fluviatic water from
It is flowed into the soil body in the soil body of water outlet box culvert upper and lower surface, improves the stability of water outlet box culvert.
In conclusion the utility model has the advantages that:
First, when the water level on water inlet flow channel is higher than river level, the water in water inlet flow channel is evacuated to water tank by water pump
Contain, be then discharged at rivers and discharge, prevent urban waterlogging, during water pump operation, water impact flood control flap valve causes flap valve of controlling flood
On fixed screw come off, and then when so that the flood control flap valve is come off, close the emergency gate of flood control flap valve front end, prevent flood from falling
It fills, while also is used as bulkhead gate when flood control flap valve overhauls;
Second, since water hammer pressure is larger at pump outlet, during water drainage, the air pressure generated between Shun is larger, passes through setting
Vertical shaft venthole, air pressure is exported, reduce to flood control flap valve and emergency gate influence.
Description of the drawings
Fig. 1 is the overall structure diagram of the present embodiment;
Fig. 2 is the structure diagram at electricity row station in the present embodiment;
Fig. 3 is the structure diagram that water outlet box culvert is connected with rivers in the present embodiment.
In figure:1st, water inlet flow channel;2nd, rivers;3rd, water outlet box culvert;4th, water pump;5th, flood control flap valve;6th, emergency gate;7th, elevator
Machine;8th, vertical shaft venthole;9th, mountain flour layer;10th, reinforced concrete backplane level;11st, concrete bed course;12nd, cement stone dust bed course;13rd, lock is overhauled
Door;14th, trash rack;15th, water stop.
Specific embodiment
With reference to the accompanying drawings and examples, the utility model is described in detail.
A kind of flood control electricity row station, as shown in Figure 1, including be connected with water-drawing channel water inlet flow channel 1, connect with rivers 2
It water outlet box culvert 3 and is arranged between water inlet flow channel 1 and water outlet box culvert 3 and is used to the flood in water inlet flow channel 1 being evacuated to water tank
Contain 3 water pump 4, the water outlet of water pump 4 is provided with flood control flap valve 5, and 5 front end of flood control flap valve is provided with emergency gate 6, emergency brake
Door 6 is controlled by QPK2 hoist engines 7 and lifted.
When the water level on water inlet flow channel 1 is higher than 2 water level of rivers, water pump 4 works is evacuated to water outlet by the water in water inlet flow channel 1
Box culvert 3 is then discharged at rivers 2 and discharges, and prevents urban waterlogging, and when water pump 4 is run, water impact flood control flap valve 5 causes to prevent
Fixed screw on big vast flap valve 5 comes off, and then when so that the flood control flap valve 5 is come off, closes the emergency gate 6 of 5 front end of flood control flap valve, prevent
Only flood pours in down a chimney, while also is used as the bulkhead gate 13 when flood control flap valve 5 overhauls.
As shown in Figures 2 and 3, vertical shaft venthole 8, water are provided at the top between 4 water outlet of water pump and emergency gate 6
4 water outlets are pumped since water hammer pressure is larger, during water drainage, the air pressure generated between Shun is larger, by the vertical shaft venthole 8 of setting,
Reduce the influence to flood control flap valve 5 and emergency gate 6.
Pipelined channel side wall and 3 bottom of water outlet box culvert at water pump 4 are enriched by backfilling mountain flour layer 9.
Pipelined channel bottom and 3 bottom of water outlet box culvert are provided with reinforcing layer, and reinforcing layer includes reinforced concrete backplane level successively from top to bottom
10th, concrete bed course 11 and cement stone dust bed course 12, and thickness is followed successively by 500mm, 100mm and 300mm.
The water inlet of water inlet flow channel 1 sets bulkhead gate 13, in the bulkhead gate that the water inlet of water inlet flow channel 1 is set
13, facilitate the maintenance of water inlet flow channel 1 and water pump 4.13 front end of bulkhead gate sets trash rack 14, and the trash rack 14 of setting subtracts
Few rubbish is entered in water inlet flow channel 1, and rubbish is avoided to damage water pump 4.
3 surrounding of water outlet box culvert is vertically arranged with water stop 15 at rivers 2, prevents the water in rivers 2 from the soil body
It is flowed into the soil body of 3 upper and lower surface of water outlet box culvert, improves the stability of water outlet box culvert 3.
The above is only the preferred embodiment of the utility model, and the scope of protection of the utility model is not limited merely to
Above-described embodiment, all technical solutions belonged under the utility model thinking belong to the scope of protection of the utility model.It should refer to
Go out, for those skilled in the art, several improvement under the premise of the utility model principle is not departed from and
Retouching, these improvements and modifications also should be regarded as the scope of protection of the utility model.
Claims (7)
1. a kind of flood control electricity row station, it is characterised in that:Including water inlet flow channel (1), water outlet box culvert (3) and it is arranged at water inlet flow channel
(1) it is used to the water in water inlet flow channel (1) being evacuated to the water pump (4) of water outlet box culvert (3), the water pump between water outlet box culvert (3)
(4) water outlet is provided with flood control flap valve (5), and described flood control flap valve (5) front end is provided with emergency gate (6).
2. a kind of flood control electricity row station according to claim 1, it is characterised in that:The emergency gate (6) passes through hoist engine
(7) control lifting.
3. a kind of flood control electricity row station according to claim 1, it is characterised in that:Water pump (4) water outlet is provided with
Vertical shaft venthole (8).
4. a kind of flood control electricity row station according to claim 1, it is characterised in that:Water inlet flow channel (1) bottom and go out
Water tank contains (3) bottom and is provided with reinforcing layer, and the reinforcing layer includes reinforced concrete backplane level (10), concrete bed course (11) and water successively
Mud stonework road cutting (12).
5. a kind of flood control electricity row station according to claim 1, it is characterised in that:The water inlet of the water inlet flow channel (1)
Bulkhead gate (13) is set.
6. a kind of flood control electricity row station according to claim 5, it is characterised in that:Bulkhead gate (13) front end sets and blocks
Dirty grid (14).
7. a kind of flood control electricity row station according to claim 1, it is characterised in that:Water outlet box culvert (3) outlet and rivers
(2) connect, water outlet box culvert (3) surrounding is vertically arranged with water stop (15).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721469244.XU CN207376762U (en) | 2017-11-06 | 2017-11-06 | A kind of flood control electricity row station |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721469244.XU CN207376762U (en) | 2017-11-06 | 2017-11-06 | A kind of flood control electricity row station |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207376762U true CN207376762U (en) | 2018-05-18 |
Family
ID=62334505
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721469244.XU Expired - Fee Related CN207376762U (en) | 2017-11-06 | 2017-11-06 | A kind of flood control electricity row station |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207376762U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111809711A (en) * | 2020-06-11 | 2020-10-23 | 上海市政工程设计研究总院(集团)有限公司 | Drainage box culvert maintenance well and method for maintaining drainage box culvert |
-
2017
- 2017-11-06 CN CN201721469244.XU patent/CN207376762U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111809711A (en) * | 2020-06-11 | 2020-10-23 | 上海市政工程设计研究总院(集团)有限公司 | Drainage box culvert maintenance well and method for maintaining drainage box culvert |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103541345B (en) | Aqueous vapor separate vacuum preloading and device | |
CN111236408A (en) | Joint construction structure of drainage pump station and regulation and storage tank and operation method thereof | |
CN210637109U (en) | Underground mine underground temporary drainage structure | |
CN207376762U (en) | A kind of flood control electricity row station | |
CN109339006B (en) | Efficient cone-type hydraulic power absorption well and construction method thereof | |
CN207092033U (en) | A kind of flood discharging tunnel | |
CN211873292U (en) | Drainage pumping station and regulation and storage tank jointly build structure | |
CN106498963A (en) | A kind of tube well dewatering system that is drawn water using air compressor machine and water pump concentration | |
CN209025056U (en) | A kind of Floater removing gate and scouring sluice integrated structure | |
CN207919510U (en) | Diversion tunnel blocks arrangement using lock under permanent plug first section joint gate | |
CN106759161A (en) | A kind of big cross section diversion tunnel plugging structure and construction method by stages | |
CN110847128A (en) | Water retaining dam and method for regulating and controlling water flow | |
CN212926150U (en) | Vertical post-cast strip structure of retaining wall | |
CN109763552A (en) | A kind of basis is dark to apply gravity type draining regeneration application system and its construction method | |
CN213038444U (en) | Temporary device for screening sludge in river channel culvert | |
CN107268547A (en) | Karst funnel reservoir and its flood releasing structure and construction method | |
CN201043475Y (en) | Drainage device for deep well in mine | |
CN107288106A (en) | A kind of flood discharging tunnel | |
CN210712774U (en) | Novel structure of built-in desilting basin of dam rolls | |
CN205954578U (en) | Stop log gate structure | |
CN206486900U (en) | A kind of use air compressor machine and water pump concentrate the tube well dewatering system drawn water | |
CN108951552B (en) | Pressureless tunnel overhauling channel with air vents | |
CN101264396B (en) | Ore dressing industry solid-liquid quick disconnect device | |
CN206110310U (en) | Bury intelligent sewage lifting pump station of formula integration | |
CN206655198U (en) | Big cross section diversion tunnel plugging structure by stages |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180518 Termination date: 20191106 |