Box beam steel and wood composite template Download PDF

Info

Publication number
CN207362703U
CN207362703U CN201720526802.5U CN201720526802U CN207362703U CN 207362703 U CN207362703 U CN 207362703U CN 201720526802 U CN201720526802 U CN 201720526802U CN 207362703 U CN207362703 U CN 207362703U
Authority
CN
China
Prior art keywords
steel
wood
box beam
box
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720526802.5U
Other languages
Chinese (zh)
Inventor
顾乾岗
舒承效
曹海涛
庄国强
江鹏飞
梁建
傅珺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hongrun Construction Group Co Ltd
Original Assignee
Hongrun Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hongrun Construction Group Co Ltd filed Critical Hongrun Construction Group Co Ltd
Priority to CN201720526802.5U priority Critical patent/CN207362703U/en
Application granted granted Critical
Publication of CN207362703U publication Critical patent/CN207362703U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model provides a kind of box beam steel and wood composite template, including:The bed die of box beam uses bamboo splint wooden model, uses the lumps of wood, using Two bors d's oeuveres steel pipe as main stupefied wood, the stupefied wood of master to be held using the jacking of bowl buckle stent as time stupefied wood below bamboo splint.Box beam flange plate bed die and web external mold use combined type Overall Steel Formwork.Splice an angle steel in the bottom of combined type Overall Steel Formwork, the lumps of wood is shelved on angle steel below bottom die of box-beam bamboo splint, prevents bottom die of box-beam bamboo splint from sinking.Box beam bottom uses wooden model, can be light-weight with composite assembly, can facilitate formwork erection and form removal, whole Zhang Mumo plate suqares are big, and seam is few, and concrete is specious.Box beam flange plate bed die and web external mold use combined type Overall Steel Formwork, solve difficulty when box girder web bottom circular arc chamfering uses wooden model formwork erection, ensure the linear beauty after concreting.

Description

Box beam steel and wood composite template
Technical field
This patent is related to the important equipment used on municipal bridge and railroad bridge engineering, and suitable construction site is to coagulation Quality requirement is higher, beautiful after native molding component, while needs the die plate equipment of mass production concrete component.
Background technology
In science of bridge building, when pouring reinforcement concrete box beam concrete, need to use combined steel formwork or wooden model.Using group Box-like punching block, cost is big, and since steel form weight is big, form removal is difficult.During using wooden model, there is substantial amounts of split bolt hole to need to repair Mend, have an impact to the box beam concrete appearance after shaping, appearance is more and more beautiful during present Bridge Design, linear more and more multiple It is miscellaneous, while when concrete structure external form is irregular, formwork erection is difficult, can not ensure box beam concrete structure external form reach design will Ask, and it is unfavorable to environmental protection using wooden model, while substantial amounts of timber need to be wasted.
Utility model content
Technical problem to be solved in the utility model is:During box beam concrete formwork erection, without to drawing screw, not wasting wood Material, environmental protection, formwork erection and form removal are convenient, the presentation quality of concrete and linear reach design requirement.At the same time solve formwork erection and Form removal is convenient, and cost is low.
Technical solution is used by the utility model solves above-mentioned technical problem:The bed die of box beam is using bamboo splint wood Mould, using Two bors d's oeuveres Φ 48*3.5mm steel pipes as main stupefied wood, is adopted using the lumps of wood of 50*100mm as time stupefied wood below bamboo splint Main stupefied wood is held with the jacking of bowl buckle stent.Box beam flange plate bed die and web external mold use combined type Overall Steel Formwork.In group An angle steel is spliced in the bottom of box-like Overall Steel Formwork, and the lumps of wood of 50*100mm is shelved on angle steel below bottom die of box-beam bamboo splint On, prevent bottom die of box-beam bamboo splint sink so that prevent box beam concrete pour after box beam lower concrete produce grind one's teeth.
Compared with prior art, the utility model has the advantage of:Box beam bottom uses wooden model, can be with composite assembly, weight Amount is light, can facilitate formwork erection and form removal, whole Zhang Mumo plate suqares are big, and seam is few, and concrete is specious.Box beam flange plate bed die Combined type Overall Steel Formwork is used with web external mold, box girder web bottom circular arc chamfering is solved and uses being stranded during wooden model formwork erection Difficulty, ensures the linear beauty after concreting.Timber is not required, it is not necessary to, need to be few with template number to drawing screw, can be multiple It is used in turn, saves artificial.
Brief description of the drawings
The steel and wood composite template front elevation of Fig. 1 the utility model.
The steel and wood composite moulding plate node point diagram of Fig. 2 the utility model.
The steel form front elevation of Fig. 3 the utility model.
The steel form plan of Fig. 4 the utility model.
Pavement figure on the outside of the steel form of Fig. 5 the utility model.
The steel and wood composite template support bracket of Fig. 6 the utility model sets up instance graph.
Embodiment
The bed die of box beam uses bamboo splint wooden model, uses the lumps of wood of 50*100mm to be used as time stupefied wood below bamboo splint Two bors d's oeuveres Φ 48*3.5mm steel pipes hold main stupefied wood as main stupefied wood using the jacking of bowl buckle stent.Box beam flange plate bed die and abdomen Plate external mold uses combined type Overall Steel Formwork.Splice an angle steel, bottom die of box-beam bamboo folder in the bottom of combined type Overall Steel Formwork The lumps of wood of 50*100mm is shelved on angle steel below plate, prevents bottom die of box-beam bamboo splint from sinking, so as to prevent box beam concrete from pouring Box beam lower concrete is produced and ground one's teeth after building.
The utility model is described in further detail below in conjunction with drawing.
Fig. 1 is the steel and wood composite template front elevation of the utility model.The bed die of box beam uses bamboo splint wooden model (A), bamboo folder It is overall using combined type as time stupefied wood, box beam flange plate bed die and web external mold using the lumps of wood (B) of 50*100mm below plate Steel form.The lumps of wood of 50*100mm below a piece angle steel of the bottom of combined type Overall Steel Formwork splicing, bottom die of box-beam bamboo splint Be shelved on angle steel, prevent bottom die of box-beam bamboo splint sink so that prevent box beam concrete pour after box beam bottom coagulation Local products life is ground one's teeth.Below box beam bottom plate, the round steel of diameter 24mm is worn between the combined steel formwork Screw arbor with nut at both-ends supporting rack of left and right Screw arbor with nut at both-ends.Combined steel formwork has panel and following reinforcing rib to be welded, and is shape steel support below reinforcing rib.
Fig. 2 is the auspicious figure of steel and wood composite every template node of the utility model.Splice one in the bottom of combined type Overall Steel Formwork The equal leg angle (C) of root 110*10, is spliced between steel form and equal leg angle using bolt, and bolt uses the circle of diameter 12mm Steel, spacing about 300mm.The lumps of wood of bottom die of box-beam bamboo splint (A) 50*100mm below is shelved on angle steel, prevents bottom die of box-beam bamboo Clamping plate sink so that prevent box beam concrete pour after box beam lower concrete produce grind one's teeth.Below box beam bottom plate, The round steel Screw arbor with nut at both-ends of diameter 24mm is worn between left and right combined steel formwork Screw arbor with nut at both-ends supporting rack (D), when preventing casting concrete Combined steel formwork is moved.
Fig. 3 is the steel form front detail view of the utility model.Panel (E) uses 5mm plates;Reinforcing rib uses 8# channel steels;Branch Support (G) uses 12# channel steels;Flange (F) uses 12*80 band steels, and to be assembled convenient, flange is equipped with positioning pin, and steel are A3 steel.
Fig. 4 is the steel form detail side elevation of the utility model.Monolithic combined steel template length is 2400mm, steel form The equal leg angle (H) of 110*10mm is spliced in bottom, and the spacing between Screw arbor with nut at both-ends supporting rack be 900mm, on side two to drawing spiral shell Bar supporting rack is 300mm with a distance from form stop.
Fig. 5 is pavement figure on the outside of the steel form of the utility model.Pavement panel uses the checkered steel plate of 3mm thickness, It can be replaced with plank, 40mm equal leg angle ribs are welded below the checkered steel plate of 3mm thickness, are 8# channel steels below 40mm equal leg angle ribs Stent, in the steel pipe of one end of 8# channel steel stents welding Φ 48*3.5mm, this steel pipe is welded before combined steel formwork dispatches from the factory, arrives Construction team connects three vertical Φ 48*3.5mm horizontal steel tubes on the steel pipe of Φ 48*3.5mm with fastener behind construction site, this The guard rail when steel pipe of a little Φ 48*3.5mm is as construction, prevents construction personnel from being fallen down in operation from steel form top Come.Between pavement platform and combined steel formwork by the Screw arbor with nut at both-ends supporting rack of the support plate (I) of 5mm and combined steel formwork it Between be bolted, bolt uses diameter 12mm round steel.Splice two people's rows on the combined steel formwork of a block length 2400mm Road supporting rack.
Fig. 6 is that the steel and wood composite template support bracket of the utility model sets up instance graph.The bed die of box beam uses bamboo splint Wooden model, it is stupefied as master using Two bors d's oeuveres Φ 48*3.5mm steel pipes using the lumps of wood of 50*100mm as time stupefied wood below bamboo splint Wood, main stupefied wood is held using the jacking of bowl buckle stent.Box beam flange plate bed die and web external mold use combined type Overall Steel Formwork. The lumps of wood of 50*100mm is shelved on angle below a piece angle steel of the bottom of combined type Overall Steel Formwork splicing, bottom die of box-beam bamboo splint On steel, prevent bottom die of box-beam bamboo splint from sinking, thus prevent box beam concrete pour after box beam lower concrete produce it is wrong Tooth.The bottom of combined type Overall Steel Formwork is laid on the cross bar on bowl buckle holder jacking along bridge to the lumps of wood, the lumps of wood is laid with.Bowl buckle Stent erection method and requirement and basement process are carried out according to custom requirements.

Claims (4)

  1. A kind of 1. box beam steel and wood composite template, it is characterised in that:The bed die of box beam uses bamboo splint wooden model, is used below bamboo splint The lumps of wood of 50*100mm is as time stupefied wood, using Two bors d's oeuveres Φ 48*3.5mm steel pipes as main stupefied wood, using the jacking of bowl buckle stent Hold main stupefied wood;Box beam flange plate bed die and web external mold use Overall Steel Formwork, and an angle is spliced in the bottom of Overall Steel Formwork Steel, the lumps of wood below bottom die of box-beam bamboo splint are shelved on angle steel.
  2. 2. box beam steel and wood composite template according to claim 1, it is characterised in that:Below box beam bottom plate, left and right group The round steel Screw arbor with nut at both-ends of diameter 24mm is worn between conjunction steel form Screw arbor with nut at both-ends supporting rack.
  3. 3. box beam steel and wood composite template according to claim 1, it is characterised in that:The bottom splicing of composite entity steel form The equal leg angle of a piece 110*10, is spliced between steel form and equal leg angle using bolt, and bolt uses the round steel of diameter 12mm, Spacing 300mm.
  4. 4. box beam steel and wood composite template according to claim 1, it is characterised in that:The panel of composite entity steel form uses 5mm plates;Reinforcing rib uses 8# channel steels;Support uses 12# channel steels;Flange uses 12*80mm band steels, and steel are A3 steel.
CN201720526802.5U 2017-05-12 2017-05-12 Box beam steel and wood composite template Active CN207362703U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720526802.5U CN207362703U (en) 2017-05-12 2017-05-12 Box beam steel and wood composite template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720526802.5U CN207362703U (en) 2017-05-12 2017-05-12 Box beam steel and wood composite template

Publications (1)

Publication Number Publication Date
CN207362703U true CN207362703U (en) 2018-05-15

Family

ID=62424827

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720526802.5U Active CN207362703U (en) 2017-05-12 2017-05-12 Box beam steel and wood composite template

Country Status (1)

Country Link
CN (1) CN207362703U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629447A (en) * 2019-01-24 2019-04-16 中建新疆建工土木工程有限公司 Variable cross-section construction of cast-in-situ box-beam and concreting method
CN111395172A (en) * 2020-03-23 2020-07-10 中国五冶集团有限公司 Side mold and method for constructing special-shaped section of cast-in-place hollow type landscape arch bridge
CN112342929A (en) * 2020-11-27 2021-02-09 中铁七局集团第五工程有限公司 Continuous beam inclined web circular arc section construction method adopting steel-wood mixed template
CN113417218A (en) * 2021-07-29 2021-09-21 中建八局第四建设有限公司 Prestressed concrete half-inverted T-shaped invisible bent cap steel-wood combined template and construction method
CN114622487A (en) * 2022-02-15 2022-06-14 中铁十五局集团有限公司 Construction method of quick-release curve superposed beam flange plate formwork structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629447A (en) * 2019-01-24 2019-04-16 中建新疆建工土木工程有限公司 Variable cross-section construction of cast-in-situ box-beam and concreting method
CN111395172A (en) * 2020-03-23 2020-07-10 中国五冶集团有限公司 Side mold and method for constructing special-shaped section of cast-in-place hollow type landscape arch bridge
CN112342929A (en) * 2020-11-27 2021-02-09 中铁七局集团第五工程有限公司 Continuous beam inclined web circular arc section construction method adopting steel-wood mixed template
CN113417218A (en) * 2021-07-29 2021-09-21 中建八局第四建设有限公司 Prestressed concrete half-inverted T-shaped invisible bent cap steel-wood combined template and construction method
CN114622487A (en) * 2022-02-15 2022-06-14 中铁十五局集团有限公司 Construction method of quick-release curve superposed beam flange plate formwork structure

Similar Documents

Publication Publication Date Title
CN207362703U (en) Box beam steel and wood composite template
CN106677069B (en) A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN104294767B (en) A kind of semi girder cast-in-place construction spreading Hanging Basket and construction method thereof
CN107217839A (en) Cast-in-situ concrete beam plate form bracing system and its construction method
CN208949693U (en) A kind of typified form for construction of cement concrete road surface
CN104831932A (en) Construction technology for high-grade concrete column base
CN205804185U (en) A kind of quick support system of Cast-in-situ Beam rack construction
CN103603494B (en) A kind of ultra-thin steel truss sloping core construction method and formwork structure
CN104612697A (en) Construction method for subway station track upwind way
CN204983649U (en) Big inclination cylinder steel form
CN214144682U (en) Early structure of tearing open of floor template and building frame template structure
CN106381810B (en) With the cast-in-place outstanding method for filling beam of beam-column type bracket
CN204139075U (en) A kind of semi girder cast-in-place construction spreading Hanging Basket
CN209568450U (en) A kind of connection structure for foundation pit assembled inner bracing member and crown beam
CN112227218A (en) Stainless steel-wood combined template applied to bare concrete and manufacturing method thereof
CN108533283A (en) A kind of two lining trolley of self-control and its application in repairing impaired tunnel
CN215882010U (en) Adjustable concrete box girder internal mold device
CN208267342U (en) High-altitude overhanging concrete structure formwork scaffold
CN201614748U (en) Composite-material brace keel
CN110700112A (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam and construction method
CN213952981U (en) Steel pipe supporting base of stair platform
CN210916968U (en) Cast-in-place box girder supporting structure
CN204608615U (en) Case formwork support structure in a kind of bridge
CN108098978A (en) A kind of assembled underground pipe gallery epimere producing device and production method
CN109653088B (en) Construction method of cast-in-place reinforced concrete guardrail