High-altitude overhanging concrete structure formwork scaffold
Technical field
The utility model relates to a kind of formwork scaffolds, specifically high-altitude overhanging concrete structure formwork scaffold.
Background technique
It is serious to set up the waste of console mode support for shuttering labor and materials, also influences the duration, and because ultrastability is poor, frame body deformation is difficult
In control, certainly will the construction quality (bottom water Pingdu deviation is big) to flare beam slab have an adverse effect.
Summary of the invention
The utility model is intended to overcome the deficiencies of existing technologies, and provides a kind of high-altitude overhanging concrete structure branch support block hand
Frame solves high-altitude overhanging concrete structure formwork scaffold construction.
In order to solve the above-mentioned technical problem, the utility model is realized in this way:
A kind of high-altitude overhanging concrete structure formwork scaffold, it is characterised in that: it includes several I-steel, diagonal brace, steel
Muscle head fixing piece, upright bar, pressure ring and scaffold, several I-steel are arranged at intervals on overhang layer flooring and stretch out overhang layer
Flooring is overhanging part, which connect with diagonal brace upper end, and diagonal brace lower end is pre-buried with overhang layer lower layer
Steel plate connection, the scaffold are set to overhanging part I-steel top, if the I-steel top on the overhang layer flooring is equipped with
Dry steel bar end fixing piece, upright bar are inserted on fixing piece, and the I-steel top on overhang layer flooring is additionally provided with several pressure rings.
The high-altitude overhanging concrete structure formwork scaffold, it is characterised in that: diagonal brace upper end and I-steel bottom are cut with scissors
It connects, diagonal brace lower end and pre-embedded steel slab are welded to connect.
The high-altitude overhanging concrete structure formwork scaffold, it is characterised in that: the pressure ring at least four, wherein
Twice are set to the end on I-steel top on overhang layer flooring, and remaining twice are respectively arranged on I-steel top on overhang layer flooring
Middle part and front end, the spacing of end twice pressure ring are 200mm.
The high-altitude overhanging concrete structure formwork scaffold, it is characterised in that: the spacing of the I-steel is
1200mm, the spacing of diagonal brace are 1200mm or 2400mm.
The high-altitude overhanging concrete structure formwork scaffold, it is characterised in that: the horizontal spacing of the upright bar is
1200mm, longitudinal pitch are not more than 1200mm.
The beneficial effects of the utility model are: material is easily looked for, and it is easy for construction, it may be reused.Improve whole stress effect
Fruit and unloading effect keep frame body more stable, safer, and material can recycle, high recycling rate.
Detailed description of the invention
The utility model is described in further detail with embodiment with reference to the accompanying drawing:
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is I-steel enlarged diagram.
Fig. 3 is the connection schematic diagram of I-steel and pre-embedded steel slab.
Specific embodiment
It is as shown in Figs. 1-3: a kind of high-altitude overhanging concrete structure formwork scaffold, it include several I-steel 1, diagonal brace 2,
Steel bar end fixing piece 3, upright bar, pressure ring 4 and scaffold 5, several I-steel are arranged at intervals on overhang layer flooring and stretch out
Overhang layer flooring is overhanging part, and the overhanging part I-steel lower part and diagonal brace upper end are articulated and connected, and is taken for the creation of formwork frame body
If platform, the pre-embedded steel slab 6 of diagonal brace lower end and overhang layer lower layer is welded to connect, and pre-embedded steel slab is connected to outstanding by foundation bolt 7
Tiao Ceng lower layer;Pre-embedded steel slab specification is 400mm × 400mm × 10mm, and the spacing of the I-steel is 1200mm, the spacing of diagonal brace
For 1200mm or 2400mm;
The scaffold is set to overhanging part I-steel top, and the I-steel top on the overhang layer flooring is equipped with several
Steel bar end fixing piece, upright bar are inserted on fixing piece, to be linked together with falsework frame body upright bar;Between the transverse direction of the upright bar
Away from for 1200mm, longitudinal pitch is not more than 1200mm.
I-steel top on overhang layer flooring is additionally provided with four pressure rings, and pressure ring uses 16 round steel of Φ, and wherein twice are set to
The end on I-steel top on overhang layer flooring, remaining twice be respectively arranged on overhang layer flooring the middle part on I-steel top and before
End, the spacing of end twice pressure ring are 200mm.