CN207332305U - Climbing frame in a kind of king-post construction - Google Patents

Climbing frame in a kind of king-post construction Download PDF

Info

Publication number
CN207332305U
CN207332305U CN201721392563.5U CN201721392563U CN207332305U CN 207332305 U CN207332305 U CN 207332305U CN 201721392563 U CN201721392563 U CN 201721392563U CN 207332305 U CN207332305 U CN 207332305U
Authority
CN
China
Prior art keywords
construction
king
frame
post
climbing frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721392563.5U
Other languages
Chinese (zh)
Inventor
李德坤
万慧
李燕青
古宇鹏
周龙
杨大瑜
居敏
程琳刚
王福生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
8th Engineering Co Ltd of MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
8th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC, 8th Engineering Co Ltd of MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN201721392563.5U priority Critical patent/CN207332305U/en
Application granted granted Critical
Publication of CN207332305U publication Critical patent/CN207332305U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

本实用新型公开了一种塔柱施工内爬架,涉及塔柱施工技术领域,所述塔柱施工内爬架由上至下依次包括钢筋施工平台,钢筋施工架体,内模施工上架体,内模施工下架体和吊平台。采用本实用新型,每完成一节塔柱主筋安装后,通过起重设备提升塔柱施工内爬架施工至下一节段塔柱,施工工序少,耗时短。同时,内模施工上架体和内模施工下架体为内模安装时提供操作平台,同时兼做内模支撑,节省了内模支撑结构,施工效率高且节约钢材资源。

The utility model discloses an inner climbing frame for tower column construction, which relates to the technical field of tower column construction. The inner climbing frame for tower column construction includes a steel bar construction platform, a steel bar construction frame body, and an inner mold construction upper frame body in sequence from top to bottom. Internal mold construction lower frame body and hanging platform. With the utility model, after the installation of the main reinforcement of a section of the tower column is completed, the construction of the inner climbing frame for the construction of the tower column is lifted by the hoisting equipment to the next section of the tower column, so that the construction process is less and the time consumption is short. At the same time, the inner mold construction upper frame and the inner mold construction lower frame provide an operating platform for the inner mold installation, and also serve as inner mold support, saving the inner mold support structure, high construction efficiency and saving steel resources.

Description

一种塔柱施工内爬架An inner climbing frame for tower column construction

技术领域technical field

本实用新型涉及塔柱施工技术领域,具体涉及一种塔柱施工内爬架。The utility model relates to the technical field of tower column construction, in particular to an internal climbing frame for tower column construction.

背景技术Background technique

塔柱通常采用劲性骨架配合爬模施工,每节段塔柱施工完成后,接高劲性骨架,安装钢筋,然后合模浇筑混凝土,依此循环。劲性骨架设计为永久埋入混凝土,塔柱设计劲性骨架一般不作为主体加筋结构,仅作为施工辅助措施。一个塔柱劲性骨架重量达到数百甚至上千吨,采用该法施工,对钢材造成一定浪费。而且劲性骨架每节加工、接高均须消耗工时。The tower column is usually constructed with a stiff frame and climbing formwork. After the construction of each section of the tower column is completed, a high-strength frame is connected, steel bars are installed, and then the mold is closed to pour concrete, and the cycle is repeated. The stiff skeleton is designed to be permanently embedded in concrete, and the stiff skeleton designed for the tower column is generally not used as the main reinforcement structure, but only as an auxiliary construction measure. The weight of a rigid frame of a tower reaches hundreds or even thousands of tons, and construction using this method will cause a certain waste of steel. Moreover, the processing and height connection of each section of the rigid frame must consume man-hours.

实用新型内容Utility model content

针对现有技术中存在的缺陷,本实用新型的目的在于提供一种塔柱施工内爬架,施工工序少,耗时短且节约钢材资源。Aiming at the defects existing in the prior art, the purpose of this utility model is to provide an inner climbing frame for tower column construction, which has fewer construction procedures, less time-consuming and saves steel resources.

为达到以上目的,本实用新型采取的技术方案是:一种塔柱施工内爬架,所述塔柱施工内爬架由上至下依次包括钢筋施工平台,钢筋施工架体,内模施工上架体,内模施工下架体:In order to achieve the above purpose, the technical solution adopted by the utility model is: an inner climbing frame for tower column construction, the inner climbing frame for tower column construction includes a steel bar construction platform from top to bottom, a steel bar construction frame body, and an inner mold construction upper frame Body, lower frame body under internal mold construction:

所述钢筋施工平台包括水平设置的纵横梁体系和设于所述纵横梁体系上的主筋定位组件,所述主筋定位组件用于将塔柱主筋定位于所述纵横梁体系上;The reinforcement construction platform includes a horizontally arranged longitudinal and transverse beam system and a main reinforcement positioning component arranged on the longitudinal and transverse beam system, and the main reinforcement positioning component is used to position the main reinforcement of the tower column on the longitudinal and transverse beam system;

所述钢筋施工架体包括第一空间桁架体系;The steel construction frame body includes a first space truss system;

所述内模施工上架体包括第二空间桁架体系;The inner mold construction upper frame body includes the second space truss system;

所述内模施工下架体包括第三空间桁架体系以及挂座组件,所述挂座组件用于将所述内模施工下架体固定于已施工部分的所述塔柱上。The inner mold construction lower frame body includes a third space truss system and a hanger assembly, and the hanger assembly is used to fix the inner mold construction lower frame body on the tower column of the constructed part.

在上述技术方案的基础上,所述钢筋施工平台通过螺栓与所述钢筋施工架体连接。On the basis of the above technical solution, the steel bar construction platform is connected to the steel bar construction frame body through bolts.

在上述技术方案的基础上,所述塔柱施工内爬架还包括吊平台,所述吊平台设于所述内模施工下架体下方。On the basis of the above technical solution, the inner climbing frame for tower column construction also includes a hanging platform, and the hanging platform is arranged under the lower frame body of the inner mold construction.

在上述技术方案的基础上,所述第一空间桁架体系由角钢拼接而成。On the basis of the above technical solution, the first space truss system is spliced by angle steel.

在上述技术方案的基础上,所述第二空间桁架体系包括两桁片和设于两桁片之间的连接带,所述桁片由H型钢和万能杆件拼接而成。On the basis of the above-mentioned technical solution, the second space truss system includes two girders and a connecting belt arranged between the two girders, and the girders are spliced by H-shaped steel and universal rods.

在上述技术方案的基础上,所述第三空间桁架体系由H型钢和万能杆件拼接而成。On the basis of the above technical solution, the third space truss system is spliced by H-shaped steel and universal rods.

在上述技术方案的基础上,所述挂座组件包括挂座,挂座本体和爬锥,所述挂座用于与所述第三空间桁架体系固定连接并将所述第三空间桁架体系挂设于所述挂座本体上,所述爬锥用于与所述挂座本体固定连接并将所述挂座本体固定于已施工部分的所述塔柱上。On the basis of the above technical solution, the hanger assembly includes a hanger, a hanger body and a climbing cone, and the hanger is used for fixedly connecting with the third space truss system and hanging the third space truss system It is arranged on the hanging base body, and the climbing cone is used for fixedly connecting with the hanging base body and fixing the hanging base body on the tower column of the constructed part.

在上述技术方案的基础上,所述内模施工下架体还包括调节丝杆,所述调节丝杆用于限制所述内模施工下架体的转动。On the basis of the above technical solution, the inner mold construction lower frame body further includes an adjusting screw rod, and the adjustment screw rod is used to limit the rotation of the inner mold construction lower frame body.

在上述技术方案的基础上,所述内模施工下架体还包括附墙撑,所述附墙撑设于所述第三空间桁架体系已施工部分的所述塔柱之间。On the basis of the above technical solution, the lower frame under construction of the internal formwork further includes a wall brace, and the wall brace is installed between the tower columns of the constructed part of the third space truss system.

与现有技术相比,本实用新型的优点在于:Compared with the prior art, the utility model has the advantages of:

采用本实用新型,每完成一节塔柱主筋安装后,通过起重设备提升塔柱施工内爬架至下一节段塔柱,施工工序少,耗时短。With the utility model, after the installation of the main reinforcement of a section of the tower column is completed, the lifting equipment is used to lift the tower column to construct the inner climbing frame to the next section of the tower column, so that the construction process is less and the time consumption is short.

同时,内模施工上架体和内模施工下架体为内模安装时提供操作平台,同时兼做内模支撑,节省了内模支撑结构,施工效率高且节约钢材资源。At the same time, the inner mold construction upper frame and the inner mold construction lower frame provide an operating platform for the inner mold installation, and also serve as inner mold support, saving the inner mold support structure, high construction efficiency and saving steel resources.

附图说明Description of drawings

图1为本实用新型实施例中塔柱施工内爬架的结构示意图;Fig. 1 is the structural representation of climbing frame in tower column construction in the utility model embodiment;

图2为本实用新型实施例中塔柱施工内爬架的钢筋施工平台的结构示意图;Fig. 2 is the structural representation of the reinforced construction platform of climbing frame in tower column construction in the utility model embodiment;

图3为本实用新型实施例中塔柱施工内爬架的内模施工上架体的结构示意图;Fig. 3 is the structure schematic diagram of the upper frame body of the inner mold construction of the tower column construction inner climbing frame in the utility model embodiment;

图4为本实用新型实施例中塔柱施工内爬架的内模施工下架体的结构示意图;Fig. 4 is the structure schematic diagram of the lower frame body of the inner mold construction of the inner mold construction of the tower column construction in the utility model embodiment;

图5为本实用新型实施例中塔柱施工内爬架的挂座组件的结构示意图。Fig. 5 is a structural schematic diagram of the hanger assembly of the inner climbing frame in the construction of the tower column in the embodiment of the utility model.

图中:1-钢筋施工平台,11-纵横梁体系,12-主筋定位组件,2-钢筋施工架体,21-第一空间桁架体系,3-内模施工上架体,31-第二空间桁架体系,311-桁片,312-连接带,4-内模施工下架体,41-第三空间桁架体系,42-挂座组件,421-挂座,422-挂座本体,423-爬锥,43-调节丝杆,44-附墙撑,5-吊平台,6-塔柱,61-塔柱主筋。In the figure: 1-reinforcement construction platform, 11-longitudinal and horizontal beam system, 12-main reinforcement positioning component, 2-reinforcement construction frame, 21-first space truss system, 3-inner mold construction upper frame, 31-second space truss System, 311-truss piece, 312-connecting belt, 4-lower frame under internal mold construction, 41-third space truss system, 42-hanging seat component, 421-hanging seat, 422-hanging seat body, 423-climbing cone , 43-adjusting screw rod, 44-attached wall support, 5-hanging platform, 6-tower column, 61-tower column main reinforcement.

具体实施方式Detailed ways

以下结合附图及实施例对本实用新型作进一步详细说明。Below in conjunction with accompanying drawing and embodiment the utility model is described in further detail.

参见图1和图2所示,本实用新型实施例提供一种塔柱6施工内爬架,塔柱6施工内爬架由上至下依次包括钢筋施工平台1,钢筋施工架体2,内模施工上架体3,内模施工下架体4:Referring to Fig. 1 and Fig. 2, the utility model embodiment provides a kind of inner climbing frame of tower column 6 construction, and the inner climbing frame of tower column 6 construction comprises steel bar construction platform 1 successively from top to bottom, steel bar construction frame body 2, inner Upper frame body 3 for mold construction, lower frame body 4 for inner mold construction:

钢筋施工平台1包括水平设置的纵横梁体系11和设于纵横梁体系11上的主筋定位组件12,主筋定位组件12用于将塔柱6主筋定位于纵横梁体系11上;The reinforcement construction platform 1 includes a vertical and horizontal beam system 11 arranged horizontally and a main reinforcement positioning assembly 12 arranged on the longitudinal and horizontal beam system 11, and the main reinforcement positioning assembly 12 is used to locate the main reinforcement of the tower column 6 on the longitudinal and horizontal beam system 11;

钢筋施工架体2包括第一空间桁架体系21;钢筋施工平台1通过螺栓与钢筋施工架体2连接;The steel bar construction frame body 2 includes a first space truss system 21; the steel bar construction platform 1 is connected to the steel bar construction frame body 2 through bolts;

内模施工上架体3包括第二空间桁架体系31;The upper frame body 3 of the inner mold construction includes the second space truss system 31;

内模施工下架体4包括第三空间桁架体系31以及挂座组件32,挂座组件32用于将内模施工下架体4固定于已施工部分的塔柱6上。The inner mold construction lower frame body 4 includes a third space truss system 31 and a hanger assembly 32, and the hanger assembly 32 is used to fix the inner mold construction lower frame body 4 on the tower column 6 of the constructed part.

塔柱6施工内爬架还包括吊平台5,吊平台5设于内模施工下架体4下方。吊平台5用于为塔柱6施工提供防护平台。The climbing frame in the construction of the tower column 6 also includes a hanging platform 5, and the hanging platform 5 is located under the lower frame body 4 during the construction of the inner mold. Crane platform 5 is used for providing protection platform for tower column 6 construction.

参见图1所示,第一空间桁架体系21由角钢拼接而成。参见图3所示,第二空间桁架体系31包括两桁片311和设于两桁片311之间的连接带312,桁片311由H型钢和万能杆件拼接而成。参见图4所示,第三空间桁架体系31由H型钢和万能杆件拼接而成。Referring to Fig. 1, the first space truss system 21 is spliced by angle steel. Referring to FIG. 3 , the second space truss system 31 includes two girders 311 and a connecting belt 312 arranged between the two girders 311 , and the girders 311 are spliced by H-shaped steel and universal rods. Referring to Fig. 4, the third space truss system 31 is spliced by H-shaped steel and universal rods.

参见图5所示,挂座组件32包括挂座321,挂座本体322和爬锥323,挂座321用于与第三空间桁架体系31固定连接并将第三空间桁架体系31挂设于挂座本体322上,爬锥323用于与挂座本体322固定连接并将挂座本体322固定于已施工部分的塔柱6上。Referring to Fig. 5, the hanger assembly 32 includes a hanger 321, a hanger body 322 and a climbing cone 323, the hanger 321 is used to be fixedly connected with the third space truss system 31 and hang the third space truss system 31 on the hanger On the seat body 322 , the climbing cone 323 is used to be fixedly connected with the hanging seat body 322 and fix the hanging seat body 322 on the tower column 6 of the constructed part.

参见图5所示,内模施工下架体4还包括调节丝杆43,调节丝杆43用于限制内模施工下架体4的转动。内模施工下架体4还包括附墙撑44,附墙撑44设于所述第三空间桁架体系31已施工部分的塔柱6之间。附墙撑44用于限制内模施工下架体4的转动。As shown in FIG. 5 , the lower frame body 4 for inner mold construction also includes an adjustment screw 43 , and the adjustment screw rod 43 is used to limit the rotation of the lower frame body 4 for inner mold construction. The inner frame construction lower frame body 4 also includes a wall brace 44, which is arranged between the tower columns 6 of the constructed part of the third space truss system 31. The attached wall support 44 is used to limit the rotation of the frame body 4 under the construction of the inner mold.

本实用新型的操作方法如下:The operation method of the present utility model is as follows:

S1,待施工塔柱6节段塔柱6主筋安装前,将挂座组件32安装在已施工节段塔柱6的设计位置,安装塔柱6施工内爬架;S1, before the main reinforcement of the tower column 6 in the construction tower column 6 section is installed, the hanging seat assembly 32 is installed at the design position of the tower column 6 in the construction section, and the inner climbing frame of the tower column 6 is installed;

S2,将塔柱6主筋通过主筋定位组件12固定于钢筋施工平台1上;S2, fixing the main reinforcement of the tower column 6 on the reinforcement construction platform 1 through the main reinforcement positioning assembly 12;

S3,完成塔柱6主筋安装后,拆除钢筋施工平台1,提升塔柱6施工内爬架至下一塔柱6节段。钢筋施工平台1,钢筋施工架体2,内模施工上架体3,内模施工下架体4之间均采用螺栓连接,视起重设备吊装能力,可将各架体拆解、分开吊装后再组拼,也可以整体吊装架体。由于一般主塔截面每节段均不相同,主筋定位组件12与钢筋施工平台1采用点焊固定,每完成一节段塔柱6主筋安装后,割除焊缝,解除主筋定位组件12。S3, after the installation of the main reinforcement of the tower column 6 is completed, the reinforcement construction platform 1 is removed, and the construction inner climbing frame of the tower column 6 is lifted to the next tower column 6 section. Steel bar construction platform 1, steel bar construction frame body 2, inner mold construction upper frame body 3, and inner mold construction lower frame body 4 are all connected by bolts. Depending on the hoisting capacity of the lifting equipment, each frame body can be disassembled and hoisted separately Then assembled, the frame body can also be hoisted as a whole. Since the cross-section of the general main tower is different in each section, the main reinforcement positioning assembly 12 is fixed with the reinforcement construction platform 1 by spot welding. After each section of the tower column 6 main reinforcement installation is completed, the weld is cut off and the main reinforcement positioning assembly 12 is released.

S4,利用内模施工上架体3安装塔柱6内模;S4, using the inner mold to construct the upper frame body 3 and install the inner mold of the tower column 6;

S5,内膜安装完成后,进行待施工节段混凝土浇筑;S5, after the installation of the inner membrane is completed, the concrete pouring of the segment to be constructed is carried out;

S6,重新安装钢筋施工平台1,重复步骤S2~S6直至完成全部塔柱6节段的施工。S6, reinstall the reinforcement construction platform 1, and repeat steps S2-S6 until the construction of all 6 sections of the tower column is completed.

本实用新型不局限于上述实施方式,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也视为本实用新型的保护范围之内。本说明书中未作详细描述的内容属于本领域专业技术人员公知的现有技术。The utility model is not limited to the above-mentioned embodiments. For those of ordinary skill in the art, without departing from the principle of the utility model, some improvements and modifications can also be made. within the scope of the new protection. The content not described in detail in this specification belongs to the prior art known to those skilled in the art.

Claims (9)

1. climbing frame in a kind of king-post construction, it is characterised in that climbing frame is from top to bottom applied including reinforcing bar successively in the king-post construction Work platform (1), reinforcement construction frame body (2), internal model construction upper frame (3), internal model construction lower frame (4):
The reinforcement construction platform (1) includes the horizontally disposed system of beam body in length and breadth (11) and on the system of beam body in length and breadth (11) Main reinforcement positioning component (12), main ribs positioning component (12) is used to king-post main reinforcement (61) being positioned at the beam body system in length and breadth (11) on;
The reinforcement construction frame body (2) includes the first space truss system (21);
The internal model construction upper frame (3) includes second space girder system (31);
The internal model construction lower frame (4) includes the 3rd space truss system (41) and hanging seat component (42), the hanging seat group Part (42) is used for the king-post (6) that internal model construction lower frame (4) is fixed on to part of having constructed.
2. climbing frame in king-post construction as claimed in claim 1, it is characterised in that:The reinforcement construction platform (1) passes through bolt It is connected with the reinforcement construction frame body (2).
3. climbing frame in king-post construction as claimed in claim 1, it is characterised in that:In the king-post construction climbing frame further include hang it is flat Platform (5), the platform (5) that hangs is below internal model construction lower frame (4).
4. climbing frame in king-post construction as claimed in claim 1, it is characterised in that:The first space truss system (21) is by angle Steel is spliced.
5. climbing frame in king-post construction as claimed in claim 1, it is characterised in that:The second space girder system (31) includes Two purlin pieces (311) and the connect band (312) between two purlin pieces (311), the purlin piece (311) is by H profile steel and universal rod body It is spliced.
6. climbing frame in king-post construction as claimed in claim 1, it is characterised in that:The 3rd space truss system (41) is by H Shaped steel and universal rod body are spliced.
7. climbing frame in king-post construction as claimed in claim 1, it is characterised in that:The hanging seat component (42) includes hanging seat (421), hanging seat body (422) and cone (423) is climbed, the hanging seat (421) is used for solid with the 3rd space truss system (41) Fixed to connect and the 3rd space truss system (41) is hung on the hanging seat body (422), the cone (423) of climbing is used for It is fixedly connected with the hanging seat body (422) and the hanging seat body (422) is fixed on to the king-post (6) for part of having constructed On.
8. climbing frame in king-post construction as claimed in claim 1, it is characterised in that:The internal model construction lower frame (4) further includes Adjust screw (43), the rotation for adjusting screw (43) and being used to limit the internal model construction lower frame (4).
9. climbing frame in king-post construction as claimed in claim 1, it is characterised in that:The internal model construction lower frame (4) further includes Attached wall supports (44), and attached wall support (44) is arranged on the 3rd space truss system (41) and has constructed the king-post (6) of part Between.
CN201721392563.5U 2017-10-26 2017-10-26 Climbing frame in a kind of king-post construction Expired - Fee Related CN207332305U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721392563.5U CN207332305U (en) 2017-10-26 2017-10-26 Climbing frame in a kind of king-post construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721392563.5U CN207332305U (en) 2017-10-26 2017-10-26 Climbing frame in a kind of king-post construction

Publications (1)

Publication Number Publication Date
CN207332305U true CN207332305U (en) 2018-05-08

Family

ID=62363337

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721392563.5U Expired - Fee Related CN207332305U (en) 2017-10-26 2017-10-26 Climbing frame in a kind of king-post construction

Country Status (1)

Country Link
CN (1) CN207332305U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700819A (en) * 2017-10-26 2018-02-16 中铁大桥局集团第八工程有限公司 Climbing frame and the king-post construction method using climbing frame in king-post construction in king-post construction
CN110644376A (en) * 2019-10-14 2020-01-03 中交武汉港湾工程设计研究院有限公司 Automatic climbing device for inclined tower column internal mold support

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700819A (en) * 2017-10-26 2018-02-16 中铁大桥局集团第八工程有限公司 Climbing frame and the king-post construction method using climbing frame in king-post construction in king-post construction
CN110644376A (en) * 2019-10-14 2020-01-03 中交武汉港湾工程设计研究院有限公司 Automatic climbing device for inclined tower column internal mold support
CN110644376B (en) * 2019-10-14 2021-04-27 中交武汉港湾工程设计研究院有限公司 Automatic climbing device for inclined tower column internal mold support

Similar Documents

Publication Publication Date Title
CN101979791B (en) Construction method of ring beam and ring corbel column stiffness connecting joint
CN105586833B (en) Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method
CN212249204U (en) A revolvable triangular support frame for shallow round warehouse overhanging board support system
CN204676435U (en) The scalable operating platform of a kind of high pier concrete construction
CN105780922A (en) Construction method for segmental formwork hoisting system of large-span steel reinforced concrete transfer truss
CN103469735B (en) The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation
CN110878522A (en) Construction system and construction method of beam under main tower
CN108532968A (en) A kind of assembled support device of steel bar truss floor support plate composite floor system
CN107700819B (en) Internal climbing frame for tower column construction and tower column construction method using internal climbing frame for tower column construction
CN205653708U (en) Work platform that inclined plane climbed follows
CN111809528A (en) A construction method for a pier column vertical back cage platform channel and a back cage platform channel device
CN103255866B (en) Roof circular arc-shaped dome structure and manufacturing method
CN205636516U (en) Convertible template system of hollow concrete leaning tower
CN207332305U (en) Climbing frame in a kind of king-post construction
CN214090973U (en) Bottom formwork supporting steel frame for pouring reinforced concrete cylindrical bin top concrete
CN107299713A (en) A kind of circular cone roofing integrally-lifting steel truss and its construction
CN211775609U (en) Integrated form scaffold of independent post roof beam outer frame high-rise building
CN103485574A (en) Method for constructing reinforced concrete structure of tower top of prilling tower
CN106042173A (en) bridge production system
CN102691267A (en) High pier construction method for external whole operation platform
CN201891174U (en) Stiff connecting node for ring girder and ring-shaped bracket column
CN214737405U (en) Inner operating platform of thin-wall hollow high pier
CN207512610U (en) A kind of assembled bridge pier construction operation platform
CN106284977B (en) A kind of main stupefied and its construction method of arc shear wall shuttering supporting reinforcing
CN108797350B (en) Tower column inner and outer stiff skeleton device and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180508

CF01 Termination of patent right due to non-payment of annual fee