CN108412231A - Assembled is bolted reinforcing steel processing shed and its assemble method entirely - Google Patents

Assembled is bolted reinforcing steel processing shed and its assemble method entirely Download PDF

Info

Publication number
CN108412231A
CN108412231A CN201810043260.5A CN201810043260A CN108412231A CN 108412231 A CN108412231 A CN 108412231A CN 201810043260 A CN201810043260 A CN 201810043260A CN 108412231 A CN108412231 A CN 108412231A
Authority
CN
China
Prior art keywords
purlin
column
bolted
steel
processing shed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810043260.5A
Other languages
Chinese (zh)
Inventor
杨志坚
苏志华
李帼昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201810043260.5A priority Critical patent/CN108412231A/en
Publication of CN108412231A publication Critical patent/CN108412231A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/1205Small buildings erected in the open air
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2418Details of bolting
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2448Connections between open section profiles

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The present invention relates to a kind of assembleds to be bolted reinforcing steel processing shed and its assemble method entirely, including concrete foundation, at least two assembled rigid units, each assembled rigid unit includes two square steel tube columns and an i-shape steel beam, it is provided with cross support between two square steel tube columns, the outside of square steel tube column is connected by beam column diagonal brace with i-shape steel beam, column both ends are welded with end plate, the end plate of column top is connected by bolt with i-shape steel beam, the end plate of column bottom end is connected by bolt with concrete foundation, and the assembled rigid unit is arranged in parallel.Structure of the invention is safe and reliable, space is flexible, it is quick to be convenient to mount and dismount, can be recycled for multiple times.

Description

Assembled is bolted reinforcing steel processing shed and its assemble method entirely
Technical field
The present invention relates to a kind of one-shot job canopies of construction site, are bolted entirely more particularly, to a kind of assembled Reinforcing steel processing shed.
Background technology
Reinforcing steel processing shed is the place that construction site is processed steel, while being also to provide safe guarantor for worker The place of barrier.The reinforcing steel processing shed that current most of construction sites use is set up by fastener, steel pipe or by by welding The steel structure frame of composition, which does not only result in finished material and semi-finished product transport is inconvenient, and build with dismounting speed it is slow, Reuse rate is relatively low, safety is not high.Therefore, when building such one-shot job canopy, not only to consider safety, efficiency, also Guarantee to repeatedly use, quick for installation, energy conservation and environmental protection.
Invention content
The object of the present invention is to provide a kind of assembleds to be bolted reinforcing steel processing shed entirely, this kind of machining shed whole component by Prefabrication, structure safety, construction dismounting speed are fast, reusable, can be assembled at the construction field (site).
It is a further object to provide the assemble methods that a kind of assembled is bolted reinforcing steel processing shed entirely.
In order to solve the problems, such as that current construction site reinforcing steel processing shed exists, the technical solution adopted by the present invention is such as Under:
A kind of assembled is bolted reinforcing steel processing shed, including concrete foundation entirely, further includes at least two assembled rigid units, described Each assembled rigid unit include two square steel tube columns and an i-shape steel beam, be provided with friendship between two square steel tube columns Fork support, the outside of square steel tube column are connected by beam column diagonal brace with i-shape steel beam, and column both ends are welded with end plate, column top The end plate at end is connected by bolt with i-shape steel beam, and the end plate of column bottom end is connected by bolt with concrete foundation, described Assembled rigid unit is arranged in parallel.
It is welded with column on the side wall of the square steel tube column to pick up the ears plate, cross support is bolted on column and picks up the ears plate On.
The beam column diagonal brace is bolted on column and picks up the ears on plate.
The i-shape steel beam lower flange is disposed with lower layer's purlin, and color steel is arranged above lower layer's purlin.
The color steel is fixed on by tapping screw on lower layer's purlin.
It is provided with vertical purlin support above the i-shape steel beam, upper layer purlin, upper layer purlin are provided with above vertical purlin support Top is provided with scaffold board.
The vertical purlin support is welded in above i-shape steel beam.
It is bolted between the vertical purlin support and upper layer purlin.
It is welded with purlin otic placode, the i shaped steel on the outermost side on the upper and lower layer purlin on the outermost side Hole is equipped at lower flange of girder edge.
A kind of assembled is bolted the assemble method of reinforcing steel processing shed entirely, includes the following steps:
1. installing two square steel tube columns;
2. installing i-shape steel beam above two square steel tube columns;
3. cross support and beam column diagonal brace are installed,
4. the respective bolt holes position below two i-shape steel beams, the parallel lower layer's purlin of one row of setting, then in lower layer Color steel is fixed by tapping screw above purlin;
5. upper layer purlin is fixed in vertical purlin support by bolt, scaffold board is completely then spread in the top of upper layer purlin, is passed through Iron wire or hawser are fixed.
Advantage for present invention is with advantageous effect:
It is all prefabricated in advance in factory that a kind of assembled of the present invention is bolted component needed for reinforcing steel processing shed entirely, all logical at the scene It crosses and is bolted, without welding, assembling and dissembling speed is quick;And column is located at middle part, and the transport and processing of convenient material can be significantly Improve work task efficiency.The present invention is since there are one i-shape steel beam, two square steel tubes are vertical for setting in each assembled rigid unit Column, two beam column supports, two column braces, column are positioned in the middle part of i-shape steel beam, and surrounding volume is flexible, facilitates working apparatus The transport of tool and steel product, semi-finished product.For the present invention since a round is opened in i-shape steel beam lower flange both sides, side passes through spiral shell It tethers and connects lower layer's purlin, side hangs catch-phrase for enterprise's later stage and provides connecting portion.Since setting is anti-above the purlin of upper layer Structure is pounded, scaffold board, plank sheathing etc. can be placed.It can be used for waterproof since color steel is bolted above lower layer's purlin. Since the outermost side timber of levels is connected with otic placode, catch-phrase can be hung for enterprise's later stage, connecting portion is provided.
The present invention due to being provided with the double-deck roof boarding, upper layer disclosure satisfy that it is anti-pound requirement, lower layer can meet rain-proof requirement. And the superiority of i shaped steel self structure is taken full advantage of, rain-proof is arranged at lower flange, and anti-pound is arranged at top flange, right There is comfort cushioning effect in dropped object.Assembled rigid unit quantity can be freely set to meet requirement of engineering.Used in the present invention The all steel of component repeat and recycle, meet the green construction theory advocated in China, also agree with the sustainable development of country Exhibition strategy.The present invention can be applied not only to the reinforcing steel processing shed of construction site, it may also be used for carpenter's machining shed, escape way Deng.
Description of the drawings
The present invention is described in further details below in conjunction with the accompanying drawings:
Fig. 1 is the overall structure figure that a kind of assembled of the present invention is bolted reinforcing steel processing shed entirely;
Fig. 2 is the assembled rigid unit figure that a kind of assembled of the present invention is bolted reinforcing steel processing shed entirely;
Fig. 3 is the structure chart of the positions A cross support in Fig. 2;
Fig. 4 is the structure chart of the positions B beam column diagonal brace in Fig. 2;
Fig. 5 is the structure chart of the positions C bean column node in Fig. 2;
Fig. 6 is the structure chart of the positions D foot joint in Fig. 2;
Fig. 7 is the positions E lower layer's purlin and i-shape steel beam connection diagram in Fig. 1;
Fig. 8 is the positions F upper layer purlin and vertical purlin support connection diagram in Fig. 1.
Specific implementation mode
With reference to specific embodiment, the present invention will be described in further detail, but protection scope of the present invention is not had The embodiment of body is limited, and is subject to claims.In addition, with without prejudice under the premise of technical solution of the present invention, to this hair Any modifications or changes easy to implement of those of ordinary skill in the art made by bright fall within the claim model of the present invention Within enclosing.
As shown in figures 1-8, a kind of assembled of the present invention is bolted reinforcing steel processing shed, including concrete foundation entirely, at least Two assembled rigid units, the assembled rigid unit are arranged in parallel.Each assembled rigid unit includes two square steel tube columns 2 and an I-shaped Section steel beam 3 is provided with cross support 4 between two square steel tube columns, and the outside of square steel tube column passes through beam column diagonal brace 5 and I-shaped Section steel beam 3 is connected, and column both ends are welded with end plate 1, and the end plate of column top is connected by bolt 13 with i-shape steel beam 3, stands The end plate of column bottom end is connected by bolt with concrete foundation 14.
The i-shape steel beam lower flange is disposed with lower layer's purlin 6, and color steel 11 is arranged above lower layer's purlin.The coloured silk steel Plate is fixed on by tapping screw on lower layer's purlin.Vertical purlin support 7, vertical purlin support top are provided with above the i-shape steel beam It is provided with upper layer purlin 8, scaffold board 12 is provided with above the purlin of upper layer.The vertical purlin support is welded in above i-shape steel beam. It is bolted between the vertical purlin support and upper layer purlin 8.It is welded with purlin on the upper and lower layer purlin on the outermost side Otic placode 9 is equipped with hole at the i-shape steel beam lower flange on the outermost side, publicity mark can be arranged according to oneself requirement Language facilitates connection.
It is welded with column on the side wall of the square steel tube column to pick up the ears plate 10, cross support 4 is bolted on column side On otic placode.The beam column diagonal brace is bolted on column and picks up the ears on plate.
A kind of assembled of the present invention is bolted the assemble method of reinforcing steel processing shed entirely, includes the following steps:
1. installing two square steel tube columns 2;
2. installing i-shape steel beam 3 above two square steel tube columns 2;
3. cross support 4 and beam column diagonal brace 5 are installed,
4. the respective bolt holes position below two i-shape steel beams, the parallel lower layer's purlin 6 of one row of setting, then in lower layer 6 top of purlin fixes color steel 11 by tapping screw and is used for rain-proof, to meet waterproof requirement;
5. upper layer purlin 8 is fixed in vertical purlin support by bolt 13, then scaffold board 12 is completely spread in the top of upper layer purlin 8 Either plank sheathing is fixed by iron wire or hawser, prevents pounding requirement to meet.
The above is only presently preferred embodiments of the present invention, not does any type of limitation to the present invention, for For those skilled in the art, do not depart from technical solution of the present invention in the range of, when using the disclosure above Technology contents make it is a little be modified to the equivalent embodiment of equivalent variations, as long as being the content without departing from technical solution of the present invention, Any simple modification, equivalent change and modification made to the above embodiment also should be regarded as this hair according to the technical essence of the invention Bright protection domain.All undefined components in this embodiment can be implemented in the prior art.

Claims (10)

1. a kind of assembled is bolted reinforcing steel processing shed, including concrete foundation entirely, it is characterised in that:Further include at least two Assembled rigid unit, each assembled rigid unit include two square steel tube columns and an i-shape steel beam, and two square steel tubes are vertical Cross support is provided between column, the outside of square steel tube column is connected by beam column diagonal brace with i-shape steel beam, the weldering of column both ends It is connected to end plate, the end plate of column top is connected by bolt with i-shape steel beam, and the end plate of column bottom end passes through bolt and coagulation Earth foundation is connected, and the assembled rigid unit is arranged in parallel.
2. a kind of assembled according to claim 1 is bolted reinforcing steel processing shed entirely, it is characterised in that:The square steel It is welded with column on the side wall of tube column to pick up the ears plate, cross support is bolted on column and picks up the ears on plate.
3. a kind of assembled according to claim 1 is bolted reinforcing steel processing shed entirely, it is characterised in that:The beam column Diagonal brace is bolted on column and picks up the ears on plate.
4. a kind of assembled according to claim 1 is bolted reinforcing steel processing shed entirely, it is characterised in that:It is described I-shaped Girder steel lower flange is disposed with lower layer's purlin, and color steel is arranged above lower layer's purlin.
5. a kind of assembled according to claim 4 is bolted reinforcing steel processing shed entirely, it is characterised in that:The color steel It is fixed on lower layer's purlin by tapping screw.
6. a kind of assembled according to claim 4, is bolted reinforcing steel processing shed entirely, it is characterised in that:The I-shaped It is provided with vertical purlin support above section steel beam, upper layer purlin is provided with above vertical purlin support, scaffold board is provided with above the purlin of upper layer.
7. a kind of assembled according to claim 6, is bolted reinforcing steel processing shed entirely, it is characterised in that:It is described vertical Purlin support is welded in above i-shape steel beam.
8. a kind of assembled according to claim 6, is bolted reinforcing steel processing shed entirely, it is characterised in that:It is described vertical It is bolted between purlin support and upper layer purlin.
9. a kind of assembled according to claim 6, is bolted reinforcing steel processing shed entirely, it is characterised in that:It is described to be located at It is welded with purlin otic placode on outermost upper and lower layer purlin, hole is equipped at the i-shape steel beam lower flange on the outermost side Hole.
10. a kind of assembled according to claim 1 is bolted the assemble method of reinforcing steel processing shed entirely, it is characterised in that Include the following steps:
1. installing two square steel tube columns;
2. installing i-shape steel beam above two square steel tube columns;
3. cross support and beam column diagonal brace are installed,
4. the respective bolt holes position below two i-shape steel beams, the parallel lower layer's purlin of one row of setting, then in lower layer Color steel is fixed by tapping screw above purlin;
5. upper layer purlin is fixed in vertical purlin support by bolt, scaffold board is completely then spread in the top of upper layer purlin, is passed through Iron wire or hawser are fixed.
CN201810043260.5A 2018-01-17 2018-01-17 Assembled is bolted reinforcing steel processing shed and its assemble method entirely Pending CN108412231A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810043260.5A CN108412231A (en) 2018-01-17 2018-01-17 Assembled is bolted reinforcing steel processing shed and its assemble method entirely

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810043260.5A CN108412231A (en) 2018-01-17 2018-01-17 Assembled is bolted reinforcing steel processing shed and its assemble method entirely

Publications (1)

Publication Number Publication Date
CN108412231A true CN108412231A (en) 2018-08-17

Family

ID=63125852

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810043260.5A Pending CN108412231A (en) 2018-01-17 2018-01-17 Assembled is bolted reinforcing steel processing shed and its assemble method entirely

Country Status (1)

Country Link
CN (1) CN108412231A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537737A (en) * 2019-01-14 2019-03-29 浙江新盛建设集团有限公司 A kind of the totally detachable type machining shed and its assemble method of waterproof layer partition
CN110230414A (en) * 2019-07-12 2019-09-13 中铁建设集团有限公司 A kind of assembled platform canopy and its installation method
CN110485757A (en) * 2019-06-17 2019-11-22 天祥建设集团股份有限公司 A kind of steel bar meter field protection canopy

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201953070U (en) * 2010-12-20 2011-08-31 中国建筑一局(集团)有限公司 Reusable fabricated processing shed for construction site
WO2012110506A1 (en) * 2011-02-14 2012-08-23 Stefan Boettle Roof, in particular gas station roof
CN103741970A (en) * 2013-12-30 2014-04-23 广西建工集团第五建筑工程有限责任公司 Assembled machining shed for building construction and manufacture and installation method thereof
CN203594237U (en) * 2013-11-01 2014-05-14 中建三局建设工程股份有限公司 Multi-layer tool type recyclable crash-preventing shed
CN204676940U (en) * 2015-03-25 2015-09-30 马鞍山职业技术学院 Single column is outstanding draws Double Tops pin-connected panel reinforcing bar protection canopy
CN205840337U (en) * 2016-06-23 2016-12-28 合肥深安钢结构建筑系统工程有限公司 A kind of complete bolted reinforcing steel processing shed
CN207905389U (en) * 2018-01-17 2018-09-25 沈阳建筑大学 Assembled is bolted reinforcing steel processing shed entirely

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201953070U (en) * 2010-12-20 2011-08-31 中国建筑一局(集团)有限公司 Reusable fabricated processing shed for construction site
WO2012110506A1 (en) * 2011-02-14 2012-08-23 Stefan Boettle Roof, in particular gas station roof
CN203594237U (en) * 2013-11-01 2014-05-14 中建三局建设工程股份有限公司 Multi-layer tool type recyclable crash-preventing shed
CN103741970A (en) * 2013-12-30 2014-04-23 广西建工集团第五建筑工程有限责任公司 Assembled machining shed for building construction and manufacture and installation method thereof
CN204676940U (en) * 2015-03-25 2015-09-30 马鞍山职业技术学院 Single column is outstanding draws Double Tops pin-connected panel reinforcing bar protection canopy
CN205840337U (en) * 2016-06-23 2016-12-28 合肥深安钢结构建筑系统工程有限公司 A kind of complete bolted reinforcing steel processing shed
CN207905389U (en) * 2018-01-17 2018-09-25 沈阳建筑大学 Assembled is bolted reinforcing steel processing shed entirely

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537737A (en) * 2019-01-14 2019-03-29 浙江新盛建设集团有限公司 A kind of the totally detachable type machining shed and its assemble method of waterproof layer partition
CN110485757A (en) * 2019-06-17 2019-11-22 天祥建设集团股份有限公司 A kind of steel bar meter field protection canopy
CN110230414A (en) * 2019-07-12 2019-09-13 中铁建设集团有限公司 A kind of assembled platform canopy and its installation method
CN110230414B (en) * 2019-07-12 2023-10-03 中铁建设集团有限公司 Assembled platform canopy and installation method thereof

Similar Documents

Publication Publication Date Title
CN101886468B (en) Construction method of suspension type template support in high-position conjoined structure
CN101538896B (en) Construction method for jettied structure at high attitude of high-rise building
CN101397844B (en) Construction method of special section steel concrete composite structure inclined wall mould base engineering
CN106567458A (en) Assembly type steel-concrete combined beam column frame structure system
CN201762663U (en) Reinforced concrete superposed beam wing board support
CN108412231A (en) Assembled is bolted reinforcing steel processing shed and its assemble method entirely
CN108590242A (en) Assembling type steel structure one-shot job canopy and its installation method
CN207905389U (en) Assembled is bolted reinforcing steel processing shed entirely
CN108277977A (en) A kind of column mould reinforcement system and preparation method thereof
CN206917265U (en) A kind of adjustable small bore beam side reinforcement tools
CN208202657U (en) Assembled is bolted carpenter's machining shed entirely
CN105604183A (en) Construction method of rear welded joints of a truss
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN112227688A (en) Stiffening plate bearing type outer frame-free construction platform for residential building and construction method
CN108412230A (en) Assembled is bolted carpenter's machining shed and its assemble method entirely
CN107700840A (en) Formwork structure
CN204491837U (en) Suspension type high-strength steel bar lifting module
CN103628692A (en) Floor beam mounting bracket and use and construction method thereof
CN217975378U (en) Cast-in-place board template strutting arrangement of simple beam assembled
CN207332305U (en) Climbing frame in a kind of king-post construction
CN108149794A (en) The multi-functional sizing protection canopy of assembled and its assemble method
CN104831928A (en) Construction method for high-altitude large-span concrete connected structure formwork supporting steel platform
CN208534105U (en) Assembling type steel structure one-shot job canopy
CN104018586A (en) Connecting device for steel structure column and steel structure column
CN109577481A (en) Manufacturing method of flange bolt welding hybrid connection assembly type beam-column joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180817