Prior art keywords
construction
bridge
quick response
response code
terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720590108.XU
Other languages
Chinese (zh)
Inventor
刘继强
贾晓辉
陈登伟
蒋四礼
邱波
吴翔鲲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hanyang International Engineering Consulting Co., Ltd
China Railway Construction Investment Group Co Ltd
Original Assignee
SUN ENGINEERING CONSULTANTS INTERNATIONAL Inc
China Railway Construction Investment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUN ENGINEERING CONSULTANTS INTERNATIONAL Inc, China Railway Construction Investment Group Co Ltd filed Critical SUN ENGINEERING CONSULTANTS INTERNATIONAL Inc
Priority to CN201720590108.XU priority Critical patent/CN207264446U/en
Application granted granted Critical
Publication of CN207264446U publication Critical patent/CN207264446U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

It the utility model is related to Bridge construction monitoring system, including two-dimension code generator, server, expected construction information generation unit, the real-time collecting unit of construction information, construction site interactive terminal, construction monitoring management terminal and public access terminal;The Quick Response Code for the information generation different rights that two-dimension code generator is inputted according to expected construction information generation unit, the real-time collecting unit of construction information, server storage is output to by Quick Response Code;Server receives and stores bridge expection and realtime construction information, and expected and realtime construction information is associated with different rights Quick Response Code;Three Terminal Types access server to check bridge construction information by scanning Quick Response Code corresponding with its authority.The utility model come construction model of building bridge, while uses Quick Response Code hierarchy management technology using BIM technology, and the service of differentiation is presented after different rights personnel barcode scanning, improves bridge construction management efficiency, promotes bridge construction quality lifting.

Description

A kind of Bridge construction monitoring system
Technical field:
It the utility model is related to bridge construction implementation management field, and in particular to Bridge construction monitoring system.
Background technology:
Current BIM (Building Information Model) technologies have obtained more and more extensive attention and hair in China's engineering construction field Exhibition, it is integrated with the various relevant informations of engineering project in a manner of digitized, it includes the completeness of engineering information, uniformity And relevance is expected to fundamentally solve the letter between each stage application system such as project planning, design, construction and maintenance management Breath there are problems that tomography this, the lifecycle management of engineering project is realized, so as to greatly improve engineering construction and maintenance Efficiency and quality.
But at present due to all kinds of reasons (BIM typical problems, software limiting in itself, existing engineering system etc.), BIM Technology is especially also applied far away, used at this stage in engineering construction field on a large scale in the infrastructure such as bridge field Actual benefit caused by BIM technology yet reaches far away industry expection, especially live a line technology personnel and construction worker, Generally BIM technology is not known about, how important BIM information is effectively passed to them, helps their lifting construction quality, drops How about the BIM technology for containing immense value, is applied to the construction of actual science of bridge building by low operating risk under existence conditions During management, the level and benefit of science of bridge building sector application BIM are improved conscientiously, this is all pendulum in science of bridge building working people Member, a major issue especially in face of technical staff.
The content of the invention:
In order to solve the problems of prior art, the utility model provides a kind of Bridge construction monitoring system, this is System improves overall bridge construction quality and benefits, reduces construction risk, has easy for installation, easy to operate, economic height The characteristics of effect.
The utility model bridge construction management system adopts the following technical scheme that:A kind of Bridge construction monitoring system, including Two-dimension code generator, server, expected construction information generation unit, the real-time collecting unit of construction information, construction site interaction are eventually End, construction monitoring management terminal and public access terminal;Two-dimension code generator is single with server, expected construction information generation respectively The real-time collecting unit connection of member, construction information, it is defeated according to expected construction information generation unit, the real-time collecting unit institute of construction information The Quick Response Code of the information generation different rights entered, and the Quick Response Code generated is output in server and is stored;Server The bridge for receiving and storing expected construction information generation unit input is expected construction information, and the real-time collecting unit of construction information The bridge realtime construction information of input, and bridge is expected construction information, bridge realtime construction information and two-dimension code generator institute The Quick Response Code of the different rights of generation is associated;The Quick Response Code is using physical tag form or electronic tag form for construction Live interactive terminal, construction monitoring management terminal and public access terminal scanning, construction site interactive terminal, construction monitoring management Terminal and public access terminal access server to check bridge construction information by scanning Quick Response Code corresponding with its authority.
The construction site interactive terminal is mobile terminal or computer, and construction monitoring management terminal is mobile terminal or meter Calculation machine, public access terminal are mobile terminal.The mobile terminal is mobile phone or IPAD.
It is whole that the Quick Response Code of the different rights includes ordinary two dimensional code, interaction Quick Response Code and monitoring Quick Response Code, public access End accesses server by scanning ordinary two dimensional code, and construction site interactive terminal accesses server by scanning interaction Quick Response Code, Scanning monitoring Quick Response Code accesses server after construction monitoring management terminal input password.
As can be known from the above technical solutions, the utility model takes full advantage of BIM in terms of bridge is expected construction information generation Software is built bridge construction model, and carries out construction simulation so as to construction personnel's recognitive engineering weight difficult point and potential risk resource, then Carry out corresponding construction optimization;It is (such as bridge construction engineering weight difficult point, latent that bridge is expected construction information using planar bar code technology In risk source, important engineering information), the every terms of information of bridge construction process decomposed and encoded, generate respective two-dimensional code thing Label and electronic tag are managed, is stored in the own server or private clound/publicly-owned Cloud Server of bridge construction project, different rights After personnel's (being divided into the general public, a line technology personnel and construction worker, project manager) carry out barcode scanning, i.e., different visits Ask terminal, the BIM construction management informations of variantization can be read, built so that BIM technology preferably is served bridge And if administrative staff, the quality and benefits of bridge construction management is lifted with this, promotes the practical implementation of BIM technology, drop Low bridge beam construction risk.
Brief description of the drawings:
Fig. 1 is the Bridge construction monitoring system architecture diagram in the utility model embodiment;
Fig. 2 is the flow chart of the Bridge construction monitoring process in the utility model embodiment.
Embodiment:
The utility model is described in further detail with reference to embodiment and attached drawing, but the implementation of the utility model Mode not limited to this.
Embodiment
Such as Fig. 1, the present embodiment Bridge construction monitoring system includes two-dimension code generator, server, expected construction information life Into unit, the real-time collecting unit of construction information, construction site interactive terminal, construction monitoring management terminal and public access terminal. Two-dimension code generator is connected with server, expected construction information generation unit, the real-time collecting unit of construction information respectively, according to pre- The information that phase construction information generation unit, the real-time collecting unit of construction information are inputted generates corresponding Quick Response Code, wherein two dimension Code can use physical tag form, can also use electronic tag form, and the Quick Response Code generated is output to server In stored.The bridge that server receives and stores expected construction information generation unit input is expected construction information, Yi Jishi The bridge realtime construction information of work real time information sampling unit input, and bridge is expected construction information, bridge realtime construction letter Cease the respective two-dimensional code generated with two-dimension code generator to be associated, so that side of the user by terminal scanning Quick Response Code Formula, can check corresponding bridge construction information, you can check (the important construction of such as bridge construction engineering of expected construction information Process, construction point, potential risk resource, important engineering information, points for attention etc.), it can also check current construction information (such as Duration progress (normal, delay or advanced), people, machine, the service condition etc. of material).
It is expected that construction information generation unit is by establishing bridge construction model, to bridge construction organization scheme and main apply Work process is simulated, to obtain the expection construction information of bridge;The present embodiment establishes bridge construction mould using BIM technology Type, simulates bridge construction organization scheme and main working procedure.
The real-time collecting unit of construction information, for by the core construction information of main construction node time instance, such as the duration into Exhibition situation (normal, delay or advanced), people, machine, the service condition etc. of material are exported after collecting arrangement with word, diagrammatic form.Apply Work real time information sampling unit can use computer, or the mobile terminal such as mobile phone, IPAD to realize.
For the utility model fully by Quick Response Code hierarchy management technology, two-dimension code generator can accordingly generate 3 classes difference The Quick Response Code of authority, to improve differentiated service to different rights personnel:For public access terminal, ordinary two dimensional code is generated, Ordinary two dimensional code can be posted in the position (such as bridge construction scene entrance or enclose on wall) being easily seen, and the public is not required to Want password directly to access server by wechat or APP barcode scannings, obtain the bridges such as essential information and the time of completion of bridge The introductory information of beam, the public can also go out periphery traffic the noise appeared in bridge construction process, building waste, construction The problems such as capable influence, is fed back in server by ordinary two dimensional code;For construction site interactive terminal, interaction two dimension is generated Code, interaction Quick Response Code can be puted up at the construction field (site), and operating personnel equally accesses clothes without cryptoAPI by wechat or APP barcode scannings Business device, grasps the expection construction information and realtime construction information of bridge, such as important working procedure, Construction Points, pay attention to thing , potential construction operation is dangerous, current construction speed, materials situation etc., so as to be conducive to construction efficiency and construction quality Lifting;For construction monitoring management terminal, generation monitoring Quick Response Code, related bridge management personnel need password could barcode scanning access Server, browses to the core information of bridge construction project, such as engineering current construction situation, construction safety situation, duration, matter Amount, engineering funds service condition etc..
In the present embodiment, the main flow of Bridge construction monitoring process comprises the following steps referring to Fig. 2:
1st, according to Bridge Design data, bridge construction BIM models are established with reference to site operation requirement;
According to Bridge Design drawing, bridge construction BIM models are established with CATIA softwares.Since the center line of bridge is three Dimension curve, component also have many irregular shapes, and under Integrated comparative, CATIA softwares can preferably be competent at the work.Computer Hardware configuration recommend to select tetra- core above processors of I7, more than 16G memories, 2G or more independent display card.
2nd, bridge construction organization scheme and main working procedure are simulated and optimized using BIM softwares, obtain bridge Beam is expected construction information;
Of BIM models has just been divided when factor is in modeling according to the organization scheme, working procedure, construction machinery at scene Granularity, and working procedure simulation and optimization are carried out with up to the DELMIA softwares of Suo Pingtai, due to be with same platform, can be direct The BIM models established using step 1.
3rd, according to the bridge construction modeling scheme after optimization, main construction weight difficult point and important risk source are identified;
According to construction simulation scheme, manually the dangerous matter sources, emphasis and the difficult point that are likely to occur in work progress are identified, Arrangement and method for construction is adjusted at the same time, dangerous matter sources are identified, and is supplied to construction party, it is taken in the construction process suitable When safe precaution measure.
4th, bridge is expected construction information (the heavy difficult point and risk source of such as construction work) with word, figure using BIM technology The mode of table and video decomposes, stores and encode;By bridge realtime construction information, the core construction of such as main construction node time instance Information, such as duration progress (normal, delay or advanced), after people, machine, the service condition etc. of material collect arrangement, with word, The form output of chart;
It is difficult that the construction part that expresses clearly, working procedure make of BIM models and DELMIA softwares by engineering two dimension drawing The construction simulation video gone out is expressed, and corresponds to relevant Quick Response Code, allows site operation personnel can be by scanning two dimension Code reaches acquisition intuitively information, and such as site operation personnel can be more preferable equipped with the mobile equipment effects of IPAD.
5th, using two-dimension code generator, according to the content in step 4, the Quick Response Code of corresponding authority, i.e. ordinary two dimensional are generated Code, interaction Quick Response Code and monitoring Quick Response Code;
6th, the bridge of step 4 is expected construction information and bridge realtime construction information, and the Quick Response Code that step 5 is generated Store in server or the privately owned Cloud Server of public cloud that bridge construction project is had by oneself;
7th, all kinds of Quick Response Codes in server are carried out with Classification Management, relevant operation personnel can pass through server background two dimension Code system and corresponding terminal, realize Quick Response Code editor, logging template, user right, information inquiry, barcode scanning statistics, construction prison The functions such as control, it is specific as follows:
To the general public, by the data make comprising the introductory information of bridge into corresponding ordinary two dimensional code physical tag simultaneously Be affixed on above the fold, the public without password can by after wechat or Quick Response Code APP barcode scannings to the essential information of bridge and Time of completion etc. has a basic understanding and understanding, while the public also can be to the noise, airborne dust, building rubbish that occur in work progress During the problems such as rubbish is fed back and uploaded onto the server by corresponding Quick Response Code, correlation engineering responsible person can at any time browse and check The feedback opinion of the public;
For bridge technology personnel and a line construction worker, the intuitive of BIM technology, harmony and virtual will be given full play to The technical advantages such as property, the information such as the heavy difficult point in bridge construction process and risk source with BIM technology be fabricated to corresponding word, Chart and video content, and be converted into corresponding interactive Quick Response Code physical tag and be affixed on engineering site above the fold, operating personnel Important working procedure, Construction Points and note that equally can be by wechat or Quick Response Code APP barcode scannings to bridge without password Meaning item, potential construction operation danger etc. are well understood by and recognize, so as to be conducive to construction efficiency and construction quality Lifting;
For the violation operation appeared in construction or construction problem, related technical personnel and construction personnel can also lead to Cross barcode scanning to record site problems in a manner of chart, word and video and upload onto the server in time, server receiving Automatically corresponding monitoring Quick Response Code is fabricated to after upload information and related science of bridge building administrative staff hand is sent to type of alarm In machine, targetedly handled to do in time;
For leader and science of bridge building administrative staff, the monitoring two-dimensional code electronic label after server making is encrypted will The important bridge construction informations such as engineering current construction situation, construction safety situation, duration, quality, engineering funds service condition push away Leader and supervisor of construction's mobile phone terminal are sent to, and it is close to send in the form of short message or mail etc. corresponding Quick Response Code barcode scanning at the same time Code, only can just browse to the core information of bridge project after password is inputted.
The important value of BIM has been effectively passed to bridge construction and custodian by the utility model by way of Quick Response Code In member's hand, it is particularly advantageous to the understanding and application of a line technology personnel and construction worker to BIM, and a line engineers and technicians Operating efficiency and quality are directly related to the safety and quality of overall bridge, thus the utility model is advantageous to BIM technology Landing application in actual science of bridge building.
Above-described embodiment is the preferable embodiment of the utility model, but the embodiment of the utility model and from above-mentioned The limitation of embodiment, the change made under other any Spirit Essences and principle without departing from the utility model, modify, replace Generation, combination, simplify, and is included in other engineering construction fields (such as house, tunnel, station, roadbed, dam, harbour, airport) Used similar scheme, should be equivalent substitute mode, is included within the scope of protection of the utility model.

Claims (8)

1. a kind of Bridge construction monitoring system, it is characterised in that including two-dimension code generator, server, expected construction information life Into unit, the real-time collecting unit of construction information, construction site interactive terminal, construction monitoring management terminal and public access terminal; Two-dimension code generator is connected with server, expected construction information generation unit, the real-time collecting unit of construction information respectively, according to pre- The Quick Response Code for the information generation different rights that phase construction information generation unit, the real-time collecting unit of construction information are inputted, and will The Quick Response Code generated, which is output in server, to be stored;Server receives and stores expected construction information generation unit input Bridge be expected construction information, and the bridge realtime construction information of construction information real-time collecting unit input, it is and bridge is pre- The Quick Response Code for the different rights that phase construction information, bridge realtime construction information are generated with two-dimension code generator is associated;Institute State Quick Response Code and construction site interactive terminal, construction monitoring management terminal and public affairs are supplied using physical tag form or electronic tag form Crowd accesses terminal scanning, and construction site interactive terminal, construction monitoring management terminal and public access terminal are weighed by scanning with it Limit corresponding Quick Response Code and access server to check bridge construction information.
2. Bridge construction monitoring system according to claim 1, it is characterised in that the construction site interactive terminal is shifting Dynamic terminal or computer, construction monitoring management terminal are mobile terminal or computer, and public access terminal is mobile terminal.
3. Bridge construction monitoring system according to claim 2, it is characterised in that the mobile terminal for mobile phone or IPAD。
4. Bridge construction monitoring system according to claim 1, it is characterised in that the real-time collecting unit of construction information For the core construction information for node time instance of constructing to be carried out after collecting arrangement, exported with word, diagrammatic form.
5. the Bridge construction monitoring system according to claim 1 or 4, it is characterised in that the construction information gathers in real time Unit is realized using computer or mobile terminal.
6. Bridge construction monitoring system according to claim 1, it is characterised in that the Quick Response Code of the different rights includes Ordinary two dimensional code, interaction Quick Response Code and monitoring Quick Response Code, public access terminal access server by scanning ordinary two dimensional code, apply Work scene interactive terminal accesses server by scanning interaction Quick Response Code, and monitoring is scanned after construction monitoring management terminal input password Quick Response Code accesses server.
7. Bridge construction monitoring system according to claim 6, it is characterised in that the ordinary two dimensional code and interaction two dimension Code uses physical tag form, and ordinary two dimensional code is posted in bridge construction scene entrance or encloses on wall, interaction Quick Response Code Put up at the construction field (site).
8. Bridge construction monitoring system according to claim 1, it is characterised in that the server is bridge construction project Own server, privately owned Cloud Server or publicly-owned Cloud Server.
CN201720590108.XU 2017-05-24 2017-05-24 A kind of Bridge construction monitoring system Active CN207264446U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720590108.XU CN207264446U (en) 2017-05-24 2017-05-24 A kind of Bridge construction monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720590108.XU CN207264446U (en) 2017-05-24 2017-05-24 A kind of Bridge construction monitoring system

Publications (1)

Publication Number Publication Date
CN207264446U true CN207264446U (en) 2018-04-20

Family

ID=61915163

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720590108.XU Active CN207264446U (en) 2017-05-24 2017-05-24 A kind of Bridge construction monitoring system

Country Status (1)

Country Link
CN (1) CN207264446U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110243408A (en) * 2019-06-04 2019-09-17 中国神华能源股份有限公司神朔铁路分公司 Apparatus monitoring method, device, equipment and the storage medium of bridge monitoring system
CN110750688A (en) * 2019-10-25 2020-02-04 重庆交通大学 Bridge full life cycle BIM model information base construction method based on two-dimensional EBS coding
CN111866097A (en) * 2020-07-03 2020-10-30 熊猫智慧水务有限公司 Intelligent device-based scanned data aggregation method
CN115479594A (en) * 2022-10-13 2022-12-16 中交一公局第七工程有限公司 Bridge pier perpendicularity detection method and system based on BIM and three-dimensional scanning and application

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110243408A (en) * 2019-06-04 2019-09-17 中国神华能源股份有限公司神朔铁路分公司 Apparatus monitoring method, device, equipment and the storage medium of bridge monitoring system
CN110243408B (en) * 2019-06-04 2022-05-31 中国神华能源股份有限公司神朔铁路分公司 Equipment monitoring method, device, equipment and storage medium of bridge monitoring system
CN110750688A (en) * 2019-10-25 2020-02-04 重庆交通大学 Bridge full life cycle BIM model information base construction method based on two-dimensional EBS coding
CN111866097A (en) * 2020-07-03 2020-10-30 熊猫智慧水务有限公司 Intelligent device-based scanned data aggregation method
CN115479594A (en) * 2022-10-13 2022-12-16 中交一公局第七工程有限公司 Bridge pier perpendicularity detection method and system based on BIM and three-dimensional scanning and application
CN115479594B (en) * 2022-10-13 2023-09-19 中交一公局第七工程有限公司 BIM and three-dimensional scanning-based bridge pier perpendicularity detection method, system and application

Similar Documents

Publication Publication Date Title
CN107194588A (en) A kind of bridge construction management system and method based on Quick Response Code and BIM technology
CN207264446U (en) A kind of Bridge construction monitoring system
Ding et al. Using nD technology to develop an integrated construction management system for city rail transit construction
CN104835085B (en) Tourism runs supervision and safety emergency management interlinked command plateform system
Harrison et al. Foundations for smarter cities
CN105843182B (en) A kind of power scheduling accident prediction system and method based on OMS
CN203165006U (en) Engineering project management system
CN110083119A (en) A kind of the visual power system machine room monitoring system and method twin based on number
CN109447481A (en) A kind of live cost monitoring system and method based on threedimensional model
CN105023086A (en) Digital city management data sharing system based on cloud calculation
CN107798466A (en) A kind of Urban Operation administrative center system
CN105652830A (en) Bridge monitoring system based on BIM
CN107871204A (en) A kind of Urban Operation centric system architecture and engineering system
CN109460834A (en) Build operation management system and its management method
CN103136101A (en) Software automated testing unified operation platform
CN104134121A (en) Method for achieving visualization of power grid information system business data
CN113626914A (en) Engineering project management method, device and system based on digital twins
CN104008218A (en) Electric power engineering three-dimensional integrated design platform
CN109558412A (en) The data growing method and device of assembled architecture construct platform
CN109840684A (en) Management method, equipment, system and the storage medium of architecture information
CN109447390A (en) The task management system of airport emergency management and rescue
CN106452887A (en) Electric power communication system visual display system based on diagram-model-data integration
CN110019435A (en) Data processing method and system based on assembled architecture platform
CN113704567A (en) Internet of things data management method and device, Internet of things data resource pool and equipment
CN109559070A (en) The equipment production information management method and device of assembled architecture platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 518000, No. 3333, Central Road, Shenzhen, Guangdong, Nanshan District

Patentee after: CHINA RAILWAY CONSTRUCTION & INVESTMENT GROUP Co.,Ltd.

Patentee after: Hanyang International Engineering Consulting Co., Ltd

Address before: 518000, No. 3333, Central Road, Shenzhen, Guangdong, Nanshan District

Patentee before: CHINA RAILWAY CONSTRUCTION & INVESTMENT GROUP Co.,Ltd.

Patentee before: Guangzhou Hanyang Engineering Consulting Co.,Ltd.