CN207243227U - A kind of shaped steel fast hoisting pine hook device - Google Patents
A kind of shaped steel fast hoisting pine hook device Download PDFInfo
- Publication number
- CN207243227U CN207243227U CN201720781424.5U CN201720781424U CN207243227U CN 207243227 U CN207243227 U CN 207243227U CN 201720781424 U CN201720781424 U CN 201720781424U CN 207243227 U CN207243227 U CN 207243227U
- Authority
- CN
- China
- Prior art keywords
- strong magnet
- supporting surface
- shaped steel
- hook device
- magnetic switch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Load-Engaging Elements For Cranes (AREA)
Abstract
The utility model discloses a kind of shaped steel fast hoisting pine hook device, the pine hook device includes supporting block, the supporting block includes the first supporting surface and the second supporting surface, the first strong magnet is equipped with first supporting surface, second supporting surface is equipped with the second strong magnet, the side of the supporting block is equipped with the first magnetic switch and the second magnetic switch, first magnetic switch controls the magnetic force of the first strong magnet, second magnetic switch controls the magnetic force of the second strong magnet, concave-arc part is equipped with the upper end side of the supporting block, lifting lug is equipped with the concave-arc part.The positioning of T rows and flat-bulb steel erection stage, easy to one man operation, realizes that one individually quickly finishes field operation when the utility model facilitates field operation, reduces the artificial use at scene, the labour cost of reduction, improves live work efficiency.
Description
Technical field
The utility model belongs to shipbuilding technical field, and in particular to a kind of shaped steel fast hoisting pine hook device.
Background technology
With the increase of ship business amount, the installation of shaped steel is increasing, causes the work during installation of field worker shaped steel
Make time increasing, the installation period of assembly line lengthens, and shaped steel installation has very big problem.
The operating type of shaped steel installation at the scene is following several:
(1), mainboard line both ends fixed with nut frock, fixing bracket is arranged on shaped steel;
(2), at shaped steel both ends be arranged fixing bracket, then supported with weight,
(3), to ensure the angle of section bar and mainboard, in the line later artificial angle of definite shaped steel and mainboard, then with
Support is fixed.
Above-mentioned installation method is respectively present following shortcoming:
First method manual operation amount is big, fixing bracket dismounting inconvenience;
Every piece of weight of second method is required for crane to be moved, and the utilization rate and scene for adding crane play heavy industry
Workload, and the time that stent is covered on shaped steel is longer, and work efficiency is low;
The third method increases the manual operation amount at scene, and the angle of shaped steel and mainboard does not ensure, installs accuracy
The bottom of compared with.
The content of the invention
For problems of the prior art, the utility model provides a kind of shaped steel fast hoisting pine hook device, Neng Goujie
The set-up time is saved, improves work efficiency.
To achieve the above object, the utility model uses following technical scheme:
A kind of shaped steel fast hoisting pine hook device, the pine hook device include supporting block, the supporting block include the first supporting surface and
Second supporting surface, is equipped with the first strong magnet on first supporting surface, and second supporting surface is equipped with the second strong magnet, institute
The side for stating supporting block is equipped with the first magnetic switch and the second magnetic switch, and first magnetic switch controls the first strong magnet
Magnetic force, second magnetic switch controls the magnetic force of the second strong magnet, concave-arc part is equipped with the upper end side of the supporting block,
Lifting lug is equipped with the concave-arc part.
Second supporting surface includes vertical plane and arcwall face, is mutually perpendicular to set between the vertical plane and the first supporting surface
Put.
The ratio that the area of first strong magnet accounts for the first supporting surface gross area is not less than 3/4;Second strong magnet
Area account for the vertical plane gross area ratio be not less than 3/4.
Compared with prior art, the technique effect of the utility model is as follows:
(1), since this frock has utilizing powerful magnet for adsorption mainboard in bottom, save scene with nut fix and shaped steel on cover
The time of stent;
(2), since this frock in the contact surface direction with shaped steel has magnet, save the time for adjusting shaped steel verticality;
(3)Since the application of this frock at the scene can reduce the usage time of live crane, making for live crane is improved
With rate.
Brief description of the drawings
Fig. 1 is the structure diagram of the utility model.
Fig. 2 is the front view of the utility model.
Fig. 3 is the usage state diagram of the utility model.
Embodiment
With reference to implementation example and attached drawing, the utility model is described in further detail, but it is new that this practicality should not be limited with this
The protection domain of type.
As depicted in figs. 1 and 2, the present embodiment shaped steel fast hoisting pine hook device, the pine hook device include supporting block 1, the branch
Bracer 1 includes the first supporting surface 11 and the second supporting surface, is equipped with the first strong magnet 2 on first supporting surface 11, and described
Two supporting surfaces are equipped with the second strong magnet 3, and the side of the supporting block 1 is equipped with the first magnetic switch 4 and the second magnetic switch
5, first magnetic switch 4 controls the magnetic force of the first strong magnet 2, and second magnetic switch 5 controls the magnetic of the second strong magnet 3
Power, is equipped with concave-arc part 6 in the upper end side of the supporting block 1, lifting lug 7 is equipped with the concave-arc part 6.
Preferably, the second supporting surface of the present embodiment includes vertical plane 12 and arcwall face 121, the vertical plane 12 and first
It is arranged in a mutually vertical manner between supporting surface 11.
As further preferred, the area of the first strong magnet of the present embodiment 2 accounts for the ratio of 11 gross area of the first supporting surface not
Less than 3/4;The ratio that the area of second strong magnet 3 accounts for 121 gross area of vertical plane is not less than 3/4.
The present embodiment select the first magnetic switch and the second magnetic switch be:Pai Diwei PT-CZ06 magnetic switch.
The magnetic attraction of the first strong magnet and the second strong magnet is 100Kg or so in the present embodiment, according to be applicable in shaped steel
Gross weight select the strong magnet of suitable number, to meet the needs of handling.
As shown in figure 3, the use process of the present embodiment is:
The first step, by the right angle of loose hook device in the present embodiment(The angle that 12 and first supporting surface 11 of vertical plane is formed)It is placed in type
Align at the line of steel mainboard 8 and with the right angle of shaped steel(The right angle of loose hook device is placed in the right angle of shaped steel mainboard formation), respectively
The first magnetic switch 4 and the second magnetic switch 5 are opened, the first strong magnet 2 and the second strong magnet 3 adsorb the mainboard in shaped steel respectively
On,(The shaped steel used in the present embodiment, section bar weight 500Kg or so, the need of shaped steel swing can be met using six loose hook devices
Will, each branch in two sides three), shaped steel carried out by lifting lug to be hoisted to installation site,
Second step, carries out shaped steel tack welding,
3rd step, closes the first magnetic switch and the second magnetic switch so that shaped steel is separated with loose hook device.
Although above-described embodiment makes the utility model specific descriptions, for those of ordinary skill in the art
For, it is understood that in disclosed in the utility model can be based within the spirit and scope for not departing from the utility model
Appearance is modified or improved, these modification and improvement are all within the spirit and scope of the utility model.
Claims (3)
1. a kind of shaped steel fast hoisting pine hook device, it is characterised in that loose hook device includes supporting block(1), the supporting block(1)Including
First supporting surface(11)With the second supporting surface, in first supporting surface(11)It is equipped with the first strong magnet(2), described second
Support face is equipped with the second strong magnet(3), the supporting block(1)Side be equipped with the first magnetic switch(4)Opened with the second magnetic force
Close(5), first magnetic switch(4)Control the first strong magnet(2)Magnetic force, second magnetic switch(5)Control second
Strong magnet(3)Magnetic force, in the supporting block(1)Upper end side be equipped with concave-arc part(6), in the concave-arc part(6)It is equipped with
Lifting lug(7).
2. shaped steel fast hoisting pine hook device according to claim 1, it is characterised in that second supporting surface includes vertical
Face(12)And arcwall face(121), the vertical plane(12)With the first supporting surface(11)Between be arranged in a mutually vertical manner.
3. shaped steel fast hoisting pine hook device according to claim 2, it is characterised in that first strong magnet(2)Face
Product accounts for the first supporting surface(11)The ratio of the gross area is not less than 3/4;Second strong magnet(3)Area account for vertical plane(12)Always
The ratio of area is not less than 3/4.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720781424.5U CN207243227U (en) | 2017-06-30 | 2017-06-30 | A kind of shaped steel fast hoisting pine hook device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720781424.5U CN207243227U (en) | 2017-06-30 | 2017-06-30 | A kind of shaped steel fast hoisting pine hook device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207243227U true CN207243227U (en) | 2018-04-17 |
Family
ID=61877234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720781424.5U Active CN207243227U (en) | 2017-06-30 | 2017-06-30 | A kind of shaped steel fast hoisting pine hook device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207243227U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113955040A (en) * | 2021-11-19 | 2022-01-21 | 沪东中华造船(集团)有限公司 | Ship section steel positioning and mounting auxiliary device and positioning and mounting method |
-
2017
- 2017-06-30 CN CN201720781424.5U patent/CN207243227U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113955040A (en) * | 2021-11-19 | 2022-01-21 | 沪东中华造船(集团)有限公司 | Ship section steel positioning and mounting auxiliary device and positioning and mounting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201980880U (en) | Hoisting device | |
CN103953200B (en) | Wallboard mounting machine | |
CN207243227U (en) | A kind of shaped steel fast hoisting pine hook device | |
CN204342297U (en) | A kind of transfer crane with jib structure | |
CN202729637U (en) | Mounting machinery of large span workpieces | |
CN201826262U (en) | Prestress tensioning trolley | |
CN209554640U (en) | A kind of novel pier front rack transporting device | |
CN201952153U (en) | Portable detachable hoisting equipment | |
CN207973403U (en) | Cover board suspender | |
CN203728448U (en) | Light mounting and dismounting frame for tower crane | |
CN202953690U (en) | Hoisting tool used for hoisting locomotive members | |
CN202240674U (en) | Turning device for turning wheel of francis hydraulic turbine | |
CN202988576U (en) | Simple and easy chain hoist lifting support | |
CN205387447U (en) | A device that equipment hoisted on was used for overhead power line pole and mounting tool thereof | |
CN204356638U (en) | Lifting device for steel box girders of bridge | |
CN203781617U (en) | Mounting tool for guide shoe on vertical hydro power generator | |
CN207645633U (en) | A kind of reversal hanger for Rectangular Tunnel combined type section of jurisdiction | |
CN202220329U (en) | Bridge installation positioning support | |
CN201660407U (en) | Simple rotary hanger for tile processing | |
CN205772813U (en) | For 40 tons of door machines built-in decelerator remove and install one suspender | |
CN201381196Y (en) | Light hanging bracket | |
CN105648920B (en) | A kind of construction method for hanging of bridge floor shoulder pole girder | |
CN204549893U (en) | A kind of tackling system of auxiliary hoist jib hinged-support bearing replacing | |
CN202829430U (en) | Movable type lifting appliance for comb plate expansion joint installation | |