CN202729637U - Mounting machinery of large span workpieces - Google Patents

Mounting machinery of large span workpieces Download PDF

Info

Publication number
CN202729637U
CN202729637U CN 201220408497 CN201220408497U CN202729637U CN 202729637 U CN202729637 U CN 202729637U CN 201220408497 CN201220408497 CN 201220408497 CN 201220408497 U CN201220408497 U CN 201220408497U CN 202729637 U CN202729637 U CN 202729637U
Authority
CN
China
Prior art keywords
large span
dolly
machinery
guide rail
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220408497
Other languages
Chinese (zh)
Inventor
朱若兰
毕辉
杨凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai General Building Engineering Co ltd
Original Assignee
SHANGHAI GENERAL METAL STRUCTURE ENGINEERING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI GENERAL METAL STRUCTURE ENGINEERING CO LTD filed Critical SHANGHAI GENERAL METAL STRUCTURE ENGINEERING CO LTD
Priority to CN 201220408497 priority Critical patent/CN202729637U/en
Application granted granted Critical
Publication of CN202729637U publication Critical patent/CN202729637U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model reveals a mounting machinery of large span workpieces. The machinery comprises a main frame, a dolly, a lift, a sling, an operating platform and carts, wherein the main frame comprises a crossbeam which is laid with a guide rail on the top thereof and legs connected to both ends of the crossbeam; the dolly runs on the guide rail; the lift is mounted on the dolly and runs along the guide rail with the dolly; the sling is connected to a wire rope of the lift; the operating platform is mounted on the sling and the sling and the operating platform are lifted by the lift; the carts runs along the guide rail; and the legs are mounted on the carts. The mounting machinery of the large span workpieces provided by the utility model solves problems of low efficiency of construction, enables the mounting process to be simple, convenient, safe and reliable, ensures safety and quality of the construction, and meanwhile saves a lot of labor and ancillary costs, thereby being economic and rational.

Description

The installation machinery of large span workpiece
Technical field
The utility model relates to mechanical manufacturing field, relates in particular to a kind of installation machinery of large span workpiece.
Background technology
Aluminium alloy structure has from heavy and light, simple for structure, outward appearance is graceful, save cost, reduce energy consumption, enlarge usage space, exempt to safeguard in the future, the characteristics of zero seepage, begun to be widely used in recent years complex space curved surfaces and longspan structure for fields such as stadiums, chemical industry, aviations, wide as a kind of green building material development prospect of environmental protection and energy saving.Especially in longspan structure, aluminium alloy structure has unique preceence.It is with a slim and graceful figure, and reasonable stress is conducted oneself with dignity little, and the handing-over between rod member concerns simple and clear solution, can relatively fully play the lightweight of its material, high-strength and resistant to corrosion characteristic.
Yet, full hall scaffold and the artificial mounting processs of adopting in the common on-the-spot installation more, operating efficiency is low, and the cycle is long, and cost is high, and artificial aloft work is many, and potential safety hazard is many.
The utility model content
The utility model is intended to propose a kind of installation machinery of large span workpiece of the operating efficiency that can improve the large span workpiece.
According to an embodiment of the present utility model, a kind of installation machinery of large span workpiece is proposed, comprise main frame, dolly, elevator, suspender, job platform and cart.Main frame comprises crossbeam and the supporting leg that is connected to the crossbeam two ends, and the crossbeam top is equipped with guide rail.Dolly moves at guide rail.Elevator is installed on the dolly and moves along guide rail with dolly.Suspender is connected to the steel rope at elevator.Job platform is installed on the suspender, and suspender and job platform are hoisted by elevator.The cart orbiting, supporting leg is installed on the cart.
In one embodiment, cart comprises sliding type guide wheel and actuating device, and actuating device drives the sliding type guide wheel along rail moving.
In one embodiment, suspender comprises support and hitcher, and support is connected to the steel rope of elevator, and hitcher is fixed on the below of support.
In one embodiment, support has horizontally extending pole, and on pole, the level height of job platform is concordant with the hitcher bottom by steel cable suspended for job platform.
In one embodiment, the large span workpiece is Al alloy parts.
The installation machinery of the large span workpiece that the utility model proposes has solved the low problem of operating efficiency, makes installation process succinctly convenient, safe and reliable, has guaranteed engineering construction safety and quality.Saved simultaneously a large amount of artificial and supplementary costs, economical rationality.
Description of drawings
Fig. 1 has disclosed the Facad structure figure according to the installation machinery of the large span workpiece of an embodiment of the present utility model.
Fig. 2 has disclosed the construction profile according to the installation machinery of the large span workpiece of an embodiment of the present utility model.
The specific embodiment
With reference to illustrated in figures 1 and 2, Fig. 1 and Fig. 2 have disclosed the installation machinery according to the large span workpiece of an embodiment of utility model, and wherein Fig. 1 has disclosed its front view, and Fig. 2 has disclosed its lateral plan.
As shown in the figure, the installation machinery 100 of this large span workpiece comprises main frame 102, dolly 104, elevator 106, suspender 108, job platform 110 and cart 112.Main frame 102 comprises crossbeam 101 and the supporting leg 103 that is connected to the crossbeam two ends, and crossbeam 102 tops are equipped with guide rail 105.Dolly 104 is in guide rail 105 operations.Dolly 104 has actuating device, and this actuating device can be electrical motor, also can adopt structure of tow line, and driving dolly 104 is proven technique along guide rail 105 operations, is therefore no longer given unnecessary details herein.Elevator 106 is installed on the dolly 104 and moves along guide rail 105 with dolly.Elevator 106 has extended steel rope 107, and elevator 106 stretches out and shrink the realization elevating function by control steel rope 107.Suspender 108 is connected to the steel rope 107 at elevator 106, and steel rope 107 stretches out then suspender 108 reductions, and steel rope 107 shrinks then suspender 108 risings.As shown in the figure, suspender 108 comprises support 109 and hitcher 111, and support 109 is connected to the steel rope 107 of elevator 106, and hitcher 111 is fixed on the below of support 109.Job platform 110 is installed on the suspender 108, and job platform 110 and suspender 108 hoist with elevator 106 together or descend.Shown in being badly in need of with reference to the accompanying drawings, support 109 has horizontally extending pole 113, and job platform 110 is hung on the pole 113 by cable wire 114, and the level height of job platform 110 is concordant with the bottom of hitcher 111.Hitcher 111 is used for lifting large span workpiece to the position of appointment, and the workman of construction may stand on the job platform 110 the large span workpiece is constructed.Because the level height of job platform 110 is concordant with the bottom of hitcher 111, and hitcher 111 is the middle part that workpiece is placed its hook-shape structure in lifting large span workpiece, therefore the height of workpiece just in time with on job platform 110, be that workman's construction height is consistent just so that construction.Supporting leg 103 is installed on the cart 112, and cart is along track 115 operations.In one embodiment, cart 112 comprises sliding type guide wheel and actuating device, and actuating device drives the sliding type guide wheel and moves along track 115.Driving cart 112 also is a technology commonly used along track 115 operations, is therefore also no longer given unnecessary details herein.
The installation machinery of large span workpiece of the present utility model is particularly suitable for aluminum alloy large span workpiece is carried out constructing operation.The weight of aluminum alloy large span workpiece is lighter, thus the size of the parts such as elevator that adopt in the installation machinery of this large span workpiece and power can design smaller, be conducive to cost control.
The installation machinery of the large span workpiece that the utility model proposes has solved the low problem of operating efficiency, makes installation process succinctly convenient, safe and reliable, has guaranteed engineering construction safety and quality.Saved simultaneously a large amount of artificial and supplementary costs, economical rationality.

Claims (5)

1. the installation of large span workpiece machinery is characterized in that, comprising:
Main frame, main frame comprise crossbeam and the supporting leg that is connected to the crossbeam two ends, and the crossbeam top is equipped with guide rail;
Dolly, dolly moves at guide rail;
Elevator, elevator is installed on the dolly and moves along guide rail with dolly;
Suspender, suspender are connected to the steel rope at elevator;
Job platform, job platform are installed on the suspender, and suspender and job platform are hoisted by elevator;
Cart, the cart orbiting, supporting leg is installed on the cart.
2. the installation of large span workpiece as claimed in claim 1 machinery is characterized in that, described cart comprises sliding type guide wheel and actuating device, and actuating device drives the sliding type guide wheel along rail moving.
3. the installation of large span workpiece as claimed in claim 1 machinery is characterized in that, described suspender comprises support and hitcher, and support is connected to the steel rope of elevator, and hitcher is fixed on the below of support.
4. the installation of large span workpiece as claimed in claim 3 machinery is characterized in that, support has horizontally extending pole, and on pole, the level height of job platform is concordant with the hitcher bottom by steel cable suspended for described job platform.
5. the installation of large span workpiece as claimed in claim 1 machinery is characterized in that, described large span workpiece is Al alloy parts.
CN 201220408497 2012-08-17 2012-08-17 Mounting machinery of large span workpieces Expired - Lifetime CN202729637U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220408497 CN202729637U (en) 2012-08-17 2012-08-17 Mounting machinery of large span workpieces

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220408497 CN202729637U (en) 2012-08-17 2012-08-17 Mounting machinery of large span workpieces

Publications (1)

Publication Number Publication Date
CN202729637U true CN202729637U (en) 2013-02-13

Family

ID=47655359

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220408497 Expired - Lifetime CN202729637U (en) 2012-08-17 2012-08-17 Mounting machinery of large span workpieces

Country Status (1)

Country Link
CN (1) CN202729637U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104515929A (en) * 2014-10-27 2015-04-15 北京新能源汽车股份有限公司 Automatic testing arrangement of electric automobile high pressure control box high pressure connector continuity
CN106379814A (en) * 2015-12-14 2017-02-08 周韵贤 Crane pulley lifting grabbing device
CN107804782A (en) * 2015-12-14 2018-03-16 合肥龙精灵信息技术有限公司 A kind of permanent magnetic suck metal hoisting machine
CN111573580A (en) * 2020-06-03 2020-08-25 孟召阳 Device is built fast in dust-free workshop

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104515929A (en) * 2014-10-27 2015-04-15 北京新能源汽车股份有限公司 Automatic testing arrangement of electric automobile high pressure control box high pressure connector continuity
CN106379814A (en) * 2015-12-14 2017-02-08 周韵贤 Crane pulley lifting grabbing device
CN107804782A (en) * 2015-12-14 2018-03-16 合肥龙精灵信息技术有限公司 A kind of permanent magnetic suck metal hoisting machine
CN106379814B (en) * 2015-12-14 2018-06-01 黄成勇 A kind of gantry pulley lifts grabbing device
CN107804782B (en) * 2015-12-14 2019-05-24 日照泰东环保科技有限公司 A kind of permanent magnetic suck metal hoisting machine
CN111573580A (en) * 2020-06-03 2020-08-25 孟召阳 Device is built fast in dust-free workshop

Similar Documents

Publication Publication Date Title
CN202245820U (en) Small-sized electric sling cart
CN201183719Y (en) Revolving type mini single arm crane
CN202322177U (en) Portable carrier for heavy electrical equipment
CN201882763U (en) Special carrying pole type beam of double-machine lifting crane
CN202729637U (en) Mounting machinery of large span workpieces
CN102363512B (en) Portable heavy electrical equipment carrier
CN102587277A (en) Mobile equipment special for construction and maintenance of bridge barriers
CN201999647U (en) Ladle crane with structure of two trolleys and two main beams
CN202594654U (en) Moving rotary equipment mounting bracket
CN203312666U (en) Lift truck for replacing or overhauling disconnecting switch
CN201587828U (en) Gantry crane
CN201762035U (en) Simple crane movable arm
CN203159073U (en) Special multi-fulcrum overhang crane for maintaining hangar ceiling appliances
CN103010965A (en) Special tool of 110kVGW4-type for hoisting switch blades and porcelain bottles
CN201808587U (en) Electric worm forklift accessory system of trolley
CN202186847U (en) Movable hanger frame
CN202754704U (en) Hoisting device for heating surface module of heat recovery boiler
CN202380754U (en) Floor-type steel transfer trolley
CN205087828U (en) Simple and easy lifting device of 35kV circuit breaker
CN204714481U (en) A kind of slideable crow bar
CN2839219Y (en) Auxiliary exchanging block tray
CN202787930U (en) Hanging basket for high-place operations
CN208135763U (en) Assembled architecture equipment boom hoisting
CN203021243U (en) Safety vertical transportation tool of large glass
CN202465114U (en) Easily maintainable large-sized ship building gantry crane

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 200949 No. 8415 Hu Tai Road, Shanghai, Baoshan District

Patentee after: SHANGHAI GENERAL BUILDING ENGINEERING CO.,LTD.

Address before: 200949 No. 8415 Hu Tai Road, Shanghai, Baoshan District

Patentee before: Shanghai General Metal Structure Engineering Co.,Ltd.

CP01 Change in the name or title of a patent holder
CX01 Expiry of patent term

Granted publication date: 20130213

CX01 Expiry of patent term