CN207032468U - Assembled architecture - Google Patents

Assembled architecture Download PDF

Info

Publication number
CN207032468U
CN207032468U CN201720652798.7U CN201720652798U CN207032468U CN 207032468 U CN207032468 U CN 207032468U CN 201720652798 U CN201720652798 U CN 201720652798U CN 207032468 U CN207032468 U CN 207032468U
Authority
CN
China
Prior art keywords
assembled architecture
side fascia
steel
concrete
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720652798.7U
Other languages
Chinese (zh)
Inventor
吴青桦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720652798.7U priority Critical patent/CN207032468U/en
Application granted granted Critical
Publication of CN207032468U publication Critical patent/CN207032468U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Assembled architecture is the utility model is related to, including mainly has Side fascia, lining, superimposed sheet, balcony, air-conditioning plate, stair, steel joist, steel structure column, steel structure girder and prefabricated components to make and forms;Side fascia is provided with wall board connector and plate stitch handling member, prefabricated components are provided with machinery production concrete reinforcing steel cage, superimposed sheet installation support Side fascia, lining is installed on inside Side fascia, and multiple prefabricated constructions are installed by module, plate stitch processing and room node installation connect into assembled architecture;The building formed using prefabricated component in assemble in site, wall can be dismantled repeatedly, and can reuse will not produce building waste due to demolishing walls, and construction speed is fast, and climate conditionality is small, save labour and can improve construction quality.

Description

Assembled architecture
Technical field
Building construction technology field is the utility model is related to, more specifically refers to assembled architecture.
Background technology
Existing building construction is that accent is grown to tail steel construction, precast concrete, building cycle, builds site operation and pour mostly Note is complicated, and manual physical is heavy, many hidden dangers be present, and construction rubbish is more, and construction material construction is blown by weather Raining, it is big to influence, it is impossible to realizes quick prefabricated fabrication and installation.
Common building is by manually building, and balcony toilet parapet has many vertical and horizontal seams between having boiled water room, because at waterproof It is improper to manage, the easy leak in house.
Therefore, it is necessary to develop assembled architecture.
The content of the invention
The defects of the purpose of this utility model is to overcome prior art, there is provided assembled architecture, module installation and plate stitch Processing is linked and packed fast firmly, and to achieve the above object, the utility model uses following technical scheme:
This assembled architecture includes mainly having Side fascia, lining, superimposed sheet, balcony, air-conditioning plate, stair, steel joist, steel Structural column, steel structure girder and prefabricated components, which make, to be formed;The Side fascia is provided with wall board connector and plate stitch handling member, described pre- Component processed is provided with machinery production concrete reinforcing steel cage, the superimposed sheet installation support Side fascia, and lining is installed on Side fascia The inside, the multiple prefabricated construction is installed by module, plate stitch processing and room node installation connect into assembled architecture.
Preferably, the prefabricated components are had by concrete prefabricated components steel mould with different size and shape, are put into advance The good reinforcing bar of colligation, all kinds of built-in fittings, and prefabricated components are made in casting concrete.
Preferably, the module installation includes shear wall, column template, elevator hoistways inner template, form bracing and sets up, pacifies The box-like floor of folding and the bench installation of lifting staristep.
Preferably, the plate stitch, which is handled, includes floor piece cracking resistance reinforcement installation, preheating embedding line and surfacing steel bar in floor Colligation, floorslab concrete pouring connection and vertical and horizontal seam water-proofing treatment.
The vertical and horizontal water-proofing treatment uses outer stopper foamed polyethylene gluing, and inside uses hollow rubber waterstop.
The room node installation leads wall, or whole cast concrete walls and roofing including doing the high armored concrete of 200mm.
The beneficial effect of the utility model compared with prior art is:Built using prefabricated component what assemble in site formed Build, wall can be dismantled repeatedly, and can reuse will not produce building waste due to demolishing walls, and construction speed is fast, is bullied It is small to wait conditionality, saves labour and construction quality can be improved.
The utility model is further described with specific embodiment below in conjunction with the accompanying drawings.
Brief description of the drawings
Fig. 1 is the prefabricated buildings structural representation of the utility model specific embodiment;
Fig. 2 has node installation structural representation for the utility model embodiment;
Fig. 3 is the vertical and horizontal seam processing structure schematic diagram of the utility model embodiment.
Reference
1st, Side fascia;2nd, lining;3rd, superimposed sheet;4th, balcony;5th, air-conditioning plate;6th, stair;7th, steel joist;8th, steel construction Post;9th, steel structure girder;10th, prefabricated components;11st, wall is led;12nd, polyethylene foamed rod;13rd, hollow rubber waterstop.
Embodiment
In order to more fully understand technology contents of the present utility model, with reference to specific embodiment to skill of the present utility model Art scheme is further described and illustrated, but is not limited to this.
As Figure 1-3, including mainly there are Side fascia 1, lining 2, superimposed sheet 3, balcony 4, air-conditioning plate 5, stair 6, steel Keel 7, steel structure column 8, steel structure girder 9 and prefabricated components 10, which make, to be formed;Side fascia 1 is provided with wall board connector and plate stitch is handled Part, prefabricated components 10 are provided with machinery production concrete reinforcing steel cage, the installation support Side fascia 1 of superimposed sheet 3, and lining 2 is installed on The inside of Side fascia 1, multiple buildings of prefabricated components 10 are installed by module, plate stitch processing and room node installation connect into assembled Building.
It is good to be put into prior colligation by the steel mold of concrete prefabricated element 10 with different size and shape for prefabricated components 10 Reinforcing bar, all kinds of built-in fittings, by processing factory, Zong Bao, management concealment acceptance after-pouring concrete, prefabricated components 10 are made.
After the type concrete steam of prefabricated components 10 maintenance 6-9 hours, it is stripped when concrete strength is up to 70%.
Module installation includes shear wall, column template, elevator hoistways inner template, form bracing and sets up, installs superposed type building The 6 sections of bench installations of plate and lifting stair.
Plate stitch, which is handled, includes floor piece cracking resistance reinforcement installation, and preheating embedding line and surfacing steel bar colligation, floor mix in floor Solidifying soil cast connection and vertical and horizontal seam water-proofing treatment.
As shown in Fig. 2 room node installation is including doing, the high armored concrete of 200mm leads wall 11 and polyethylene foamed rod 12 is beaten Glue, or whole cast concrete walls and roofing.
As shown in figure 3, vertical and horizontal water-proofing treatment uses the gluing of outer stopper polyethylene foamed rod 12, inside is stopped using hollow rubber Water band 13.
Using building, finishing integrated design, construction, perfect condition is that finishing can synchronously be carried out with main body construction, design Standardization and management informationization, component gets over standard, and production efficiency is higher, and corresponding component cost will decline, and coordinates work The digital management of factory, the cost performance meeting more and more higher of whole assembled architecture, meets the requirement of green building.
Assembled architecture design and construction follow specification《Assembled integral concrete residence System Design code》DG/TJ08- 2071-2010、《Assembled entirety mixed mud structure construction and inspection of quality specification》DGJ08-2117-2012 and《Light section Structure residence technology code》JGJ209-2010.
The utility model uses the building that is formed in assemble in site of prefabricated component, and wall can be dismantled repeatedly, can be with Recycling will not produce building waste due to demolishing walls, and construction speed is fast, and climate conditionality is small, and saving labour simultaneously can Improve construction quality.
It is above-mentioned that technology contents of the present utility model are only further illustrated with embodiment, in order to reader is easier to understand, But embodiment of the present utility model is not represented is only limitted to this, any technology extension or recreation done according to the utility model, By protection of the present utility model.The scope of protection of the utility model is defined by claims.

Claims (7)

1. assembled architecture, it is characterised in that:Including mainly have Side fascia, lining, superimposed sheet, balcony, air-conditioning plate, stair, Steel joist, steel structure column, steel structure girder and prefabricated components, which make, to be formed;The Side fascia is provided with wall board connector and plate stitch is handled Part, the prefabricated components are provided with machinery production concrete reinforcing steel cage, the superimposed sheet installation support Side fascia, lining installation Inside Side fascia, the prefabricated construction is installed by module, plate stitch processing and room node installation connect into assembled Building.
2. assembled architecture according to claim 1, it is characterised in that:The prefabricated components are by with different size and shape Concrete prefabricated components steel mould has, and is put into the good reinforcing bar of prior colligation, all kinds of built-in fittings, and prefabricated structure is made in casting concrete Part.
3. assembled architecture according to claim 2, it is characterised in that:The prefabricated components type concrete steam conserves 6-9 After hour, it is stripped when concrete strength is up to 70%.
4. assembled architecture according to claim 1, it is characterised in that:The module installation includes shear wall, post mould Plate, elevator hoistways inner template, form bracing are set up, install superposed type floor and the bench installation of lifting staristep.
5. assembled architecture according to claim 1, it is characterised in that:The plate stitch processing includes floor piece cracking resistance steel Muscle is installed, preheating embedding line and surfacing steel bar colligation in floor, floorslab concrete pouring connection and vertical and horizontal seam water-proofing treatment.
6. assembled architecture according to claim 5, it is characterised in that:The vertical and horizontal seam water-proofing treatment is steeped using outer stopper Foam polyethylene gluing, inside use hollow rubber waterstop.
7. assembled architecture according to claim 1, it is characterised in that:The room node installation includes doing 200mm height Armored concrete leads wall, or whole cast concrete walls and roofing.
CN201720652798.7U 2017-06-07 2017-06-07 Assembled architecture Active CN207032468U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720652798.7U CN207032468U (en) 2017-06-07 2017-06-07 Assembled architecture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720652798.7U CN207032468U (en) 2017-06-07 2017-06-07 Assembled architecture

Publications (1)

Publication Number Publication Date
CN207032468U true CN207032468U (en) 2018-02-23

Family

ID=61471154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720652798.7U Active CN207032468U (en) 2017-06-07 2017-06-07 Assembled architecture

Country Status (1)

Country Link
CN (1) CN207032468U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610648A (en) * 2018-12-20 2019-04-12 五冶集团上海有限公司 Piece processing method before a kind of assembled architecture concrete members pour
WO2020258122A1 (en) * 2019-06-24 2020-12-30 长沙远大住宅工业集团股份有限公司 3c modularization method for building design, fabrication and construction
WO2020258123A1 (en) * 2019-06-24 2020-12-30 长沙远大住宅工业集团股份有限公司 Modularization method for building design, fabrication and construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610648A (en) * 2018-12-20 2019-04-12 五冶集团上海有限公司 Piece processing method before a kind of assembled architecture concrete members pour
WO2020258122A1 (en) * 2019-06-24 2020-12-30 长沙远大住宅工业集团股份有限公司 3c modularization method for building design, fabrication and construction
WO2020258123A1 (en) * 2019-06-24 2020-12-30 长沙远大住宅工业集团股份有限公司 Modularization method for building design, fabrication and construction

Similar Documents

Publication Publication Date Title
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN103015565B (en) Prefabricated and assembled type integrated reinforced concrete load bearing wall and building construction method
CN104947792B (en) Green light steel assembling house and installation method are built in a kind of letter
CN201687102U (en) Assembled integral type shear wall structure system
CN207032468U (en) Assembled architecture
CN108914965A (en) The continuous construction method of aluminum alloy mould plate for pipe gallery
CN105275209A (en) Special-shaped spatial curved surface water concrete construction method
CN204531076U (en) Light steel latticework cast-in-place foamed concrete combined wall
CN104695662B (en) Stone facing prefabricated outer wall panel and its production method and external wall system
CN202787570U (en) Prefabricated integral reinforced concrete load bearing wall
CN204491984U (en) Stone facing precast wall panel and external wall system
CN203834771U (en) Prefabricated light floor cover plate and industrial building floor plate structure
CN101318350A (en) Concrete cavity die component forming method
CN107747378A (en) The body composite board processing method of Fast Installation heat insulation decorative load-bearing one
CN106223460B (en) The prefabricated construction method of large scale wallboard
CN210950229U (en) Embedded device for gas inlet pipe sleeve in indoor shear wall
CN208803614U (en) Light steel grating concrete folding plate
CN101886470B (en) Construction method of exposed concrete ribbed beams
CN106320569A (en) Assembly-type shear wall embedded steel bar connection process
CN206888274U (en) Composite plate shear wall ring anchor connecting node
CN203361332U (en) Prefabricated assembly type frame structure
CN102787717B (en) Self-supporting combined steel template construction method
CN108999326A (en) Light steel grating concrete folding plate
CN205224420U (en) Anticorrosive industry factory building precast concrete stand
CN205444514U (en) Bearing light insulation intergral template

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant