CN206768831U - Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe - Google Patents

Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe Download PDF

Info

Publication number
CN206768831U
CN206768831U CN201720006185.6U CN201720006185U CN206768831U CN 206768831 U CN206768831 U CN 206768831U CN 201720006185 U CN201720006185 U CN 201720006185U CN 206768831 U CN206768831 U CN 206768831U
Authority
CN
China
Prior art keywords
anchor cable
steel pipe
steel
sheet pile
tie beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720006185.6U
Other languages
Chinese (zh)
Inventor
谢晓东
周玉石
张群
谢曙东
谢益飞
赵伟明
黄立伟
鲍国强
汤武
沈丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI CHENGDI ROCK-SOIL DESIGN Co.,Ltd.
Shanghai chengdixiangjiang Data Technology Co.,Ltd.
Original Assignee
Shanghai City Ground Ground Design Co Ltd
SHANGHAI CHENGDI CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai City Ground Ground Design Co Ltd, SHANGHAI CHENGDI CONSTRUCTION CO Ltd filed Critical Shanghai City Ground Ground Design Co Ltd
Priority to CN201720006185.6U priority Critical patent/CN206768831U/en
Application granted granted Critical
Publication of CN206768831U publication Critical patent/CN206768831U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

It the utility model is related to support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe, it is characterised in that the building enclosure includes bear down on one collar tie beam, H profile steel, U-shaped steel sheet pile and one group of steel pipe, one group of anchor cable;The H profile steel, U-shaped steel sheet pile are inserted in nature soil layer and are vertically arranged with the collar tie beam that bears down on one;One end of the steel pipe is connected with the collar tie beam that bears down on one, and with the H profile steel, the angled setting of U-shaped steel sheet pile;The anchor cable sets in 15 °~85 ° angles with the H profile steel, U-shaped steel sheet pile, and is anchored at collar tie beam top of bearing down on one.The utility model has the advantages that:H profile steel, U-shaped steel sheet pile are prefabricated, good water insulation effect, construction is simple, efficiency high, and steel reusable edible is cost-effective.

Description

Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe
Technical field
The utility model belongs to base pit engineering technical field, and in particular to support, anchor cable post-tensioning HU types are gone along with sb. to guard him before a kind of steel pipe Structure and its application process.
Background technology
For the base pit engineering in the range of cutting depth 5m, the building enclosure form one used at present in existing support technology As using Cement-soil Gravity enclosure wall, shaped steel Soil-cement Wall, slope excavate.
Cement-soil Gravity enclosure wall is characterized in " grid-like " soil cement of the soil-baffling structure by multiple row lap connection in length and breadth Stake composition, is using cement based material as curing agent, is stirred curing agent and foundation soil by force using shotcrete construction by Mixing Machine Mix, formed lap connection, have the reinforcing body barricade of certain thickness and building-in depth, conduct oneself with dignity by wall, wall bottom frictional resistance and The passive earth pressure stabilization wall of the following soil body in excavation of foundation pit face before wall, to meet the monolithic stability of enclosure wall, stability against over turning, resist Sliding stable and control deformation of wall etc. requires.Its advantage is:Without support in general hole, it is easy to quickly cut the earth, has earth-retaining concurrently and stop The dual-use function of water.Shortcoming is:Bit andits control ability is weaker, construction quality is unmanageable, economy is general.
Shaped steel Soil-cement Wall be in the triaxial cement stake of lap connection insert shaped steel formed compound earth-retaining every Water-bound.Its advantage is:It is wider to be applicable soil property scope, it is small to surrounding environment influence, barrier performance is good, environmental protection and energy saving, is applicable soil Layer scope wide, short time limit, reduced investment etc..Shortcoming is:For 5m within every meter of cost of foundation ditch it is higher and change with the duration, and Construction requirement is higher, and cement piling quality is difficult to control.
It is a kind of Pit Excavation Methods for setting oblique slight slope using staying that slope, which is excavated, it is characterized in that under non-support measure, By increasing width suitable for reading of cutting the earth, while take classification slope, bank protection, precipitation etc. to maintain the ancillary method of stability of slope, can prevent Only native wall avalanche, stability of slope in digging process is kept, there is the advantages of duration is shorter, low cost, shortcoming is slope slope than wanting Ask larger, stability of slope requirement and width requirement suitable for reading need to be met simultaneously, and surrounding enviroment are had a great influence.
In summary, current foundation pit supporting construction can not also recycle and reuse, also without both economical and safe Go along with sb. to guard him mode.
Utility model content
The purpose of this utility model is according in place of above-mentioned the deficiencies in the prior art, there is provided before a kind of steel pipe after support, anchor cable Draw HU type building enclosures, the building enclosure by outside foundation ditch sideline certain distance set by the collar tie beam that bears down on one, H profile steel, U-shaped steel plate The fabricated construction that stake and one group of steel pipe, one group of anchor cable form, to reach enhancing foundation ditch crater wall stability and building enclosure The controllable purpose of cost.
The utility model purpose is realized and completed by following technical scheme:
Before a kind of steel pipe support, anchor cable post-tensioning HU type building enclosures, it is characterised in that the building enclosure include bear down on one collar tie beam, H profile steel, U-shaped steel sheet pile and one group of steel pipe, one group of anchor cable;The H profile steel, U-shaped steel sheet pile be inserted in nature soil layer and with institute The collar tie beam that bears down on one is stated to be vertically arranged;One end of the steel pipe is connected with the collar tie beam that bears down on one, and with the H profile steel, U-shaped steel plate Stake is set in 15 °~85 ° angles;The anchor cable sets in 15 °~85 ° angles with the H profile steel, U-shaped steel sheet pile, and is anchored at Bear down on one collar tie beam top.
The steel pipe is at least made up of row's steel pipe, the anchor cable is at least made up of row's anchor cable.
The H profile steel, U-shaped steel sheet pile, connect arrangement with U-shaped steel sheet pile interval by H profile steel and form.
Described being connected refers to there is at least one set of positioning hole on the collar tie beam that bears down on one, and anchor cable stretches into corresponding In the positioning hole, fixed by anchorage and the collar tie beam that bears down on one, steel pipe, H profile steel, U-shaped steel sheet pile and the collar tie beam company of bearing down on one It is integrated, H profile steel, U-shaped steel sheet pile top stretch out collar tie beam top and be no less than 500mm.
Described anchor cable construction one end in the soil body is provided with anchoring body.
Described anchor cable is used to carry out tensioning with command displacement.
The utility model has the advantages that having both earth-retaining, sealing multiple action, soil deformation is constrained, enhances Foundation Pit It wall stability, can uprightly excavate, avoid the problem of conventional slope excavation method occupied ground face is big, while eliminate conventional water Soil gravity type enclosure wall, overcome its speed of application slow, the shortcomings of cost is high, and wall quality is difficult to control, and cost is controllable, gram Taken shaped steel Soil-cement Wall cost because the duration change the shortcomings that, can it is wide be applied to 7m within base pit engineering;Utilize H types The characteristics of steel, U-shaped steel sheet pile, steel pipe and anchor cable can be reclaimed conveniently, it is recyclable after construction, recycle, economy can Greatly enhance.
Brief description of the drawings
Fig. 1 is foundation pit enclosure diagrammatic cross-section
1 bears down on one the anchorage 10 of 8 anchoring body of collar tie beam 2U shaped steel plate pile 3H shaped steel 4 steel pipe, 5 high-pressure rotary jet grouting pile, 6 accessory bed course, 7 anchor cables 9 Positioning hole
Fig. 2 is building enclosure horizontal layout form
1 bears down on one the anchorage of collar tie beam 2U shaped steel plate pile 3H shaped steel 9
Fig. 3 is foundation pit enclosure diagrammatic cross-section after steel pipe is removed
1 bears down on one the anchorage of 8 anchoring body of collar tie beam 2U shaped steel plate pile 3H shaped steel 5 high-pressure rotary jet grouting pile, 6 accessory bed course, 7 anchor cables 9 The bottom plate of 10 positioning hole, 11 load transfering strip 12
Embodiment
The utility model is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with the utility model Implemented premised on technical scheme, give detailed embodiment and specific operating process, but guarantor of the present utility model Shield scope is not limited to following embodiments.
Embodiment
As shown in figure 1, support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe, the building enclosure include the collar tie beam that bears down on one 1st, 4, one groups of H profile steel 3, U-shaped steel sheet pile 2 and one group of steel pipe anchor cables 7;The H profile steel 3, U-shaped steel sheet pile 2 are inserted in nature soil layer In and be vertically arranged with the collar tie beam 1 that bears down on one;One end of the steel pipe 4 is connected with the collar tie beam 1 that bears down on one, and with the H Shaped steel 3, the 2 angled setting of U-shaped steel sheet pile;The anchor cable 7 is set with the H profile steel 3, U-shaped steel sheet pile 2 in 15 °~85 ° angles Put, and be anchored at the collar tie beam 1 that bears down on one and push up.
Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe involved by the utility model, are constructed using skirt piles machine X, It is concretely comprised the following steps:
1) smooth construction site, full pattern is released according to construction drawing;
2) after H profile steel 3, U-shaped steel sheet pile 2, steel pipe 4, the site acceptance of anchor cable 7, stack to the position for being easy to construction;
3) at a certain distance from being stepped back in foundation ditch sideline, machinery is started, the step 2) H profile steel 3, U-shaped steel sheet pile 2 is vertical Insert in nature soil layer;
4) on the inside of oblique foundation ditch construction high-pressure rotary jet grouting pile 5 to bottom of foundation ditch certain depth;
5) start manipulator, will have been constructed in the oblique insertion 4) of steel pipe 4 in high-pressure rotary jet grouting pile 5;
6) collar tie beam 1 is beared down on one so that the top of the H profile steel 3, U-shaped steel sheet pile 2 and steel pipe 4 is integral described in pouring Structure, and pre-buried positioning hole 10 and anchorage 9;
7) the construction anchor cable 7 after the collar tie beam 1 that bears down on one in 6) reaches intensity, and collar tie beam 1 is anchored at by pre-buried positioning hole 10 Top (anchor cable 7 can anchoring or later stage tensioning again after tensioning);
8) fluting uprightly excavates the H profile steel 3, the soil body of the inner side of U-shaped steel sheet pile 2, and pours arrangement of reinforcement pad in time at hole bottom Layer 6;
9) soil body in slope excavation pit, construct bottom plate 12 and load transfering strip 11;
10) after 9) bottom plate 12 and load transfering strip 11 reach intensity, support steel pipe 4 before removing;
11) construct after underground structure extremely ± 0.00, backfill.

Claims (6)

1. support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe, it is characterised in that the building enclosure includes bear down on one collar tie beam, H Shaped steel, U-shaped steel sheet pile and one group of steel pipe, one group of anchor cable;The H profile steel, U-shaped steel sheet pile be inserted in nature soil layer and with it is described The collar tie beam that bears down on one is vertically arranged;One end of the steel pipe is connected with the collar tie beam that bears down on one, and with the H profile steel, U-shaped steel sheet pile Set in 15 °~85 ° angles;The anchor cable sets in 15 °~85 ° angles with the H profile steel, U-shaped steel sheet pile, and is anchored at pressure Collar back.
2. support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe according to claim 1, it is characterised in that the steel Pipe is at least made up of row's steel pipe, the anchor cable is at least made up of row's anchor cable.
3. support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe according to claim 1, it is characterised in that the H types Steel, U-shaped steel sheet pile, connect arrangement with U-shaped steel sheet pile interval by H profile steel and form.
4. support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe according to claim 1, it is characterised in that described It is connected and refers to that there is at least one set of positioning hole on the collar tie beam that bears down on one, anchor cable is stretched into the corresponding positioning hole, Fixed by anchorage and the collar tie beam that bears down on one, steel pipe, H profile steel, U-shaped steel sheet pile and the collar tie beam that bears down on one are connected as a single entity, H profile steel, U Shape steel plate stake top stretches out collar tie beam top and is no less than 500mm.
5. support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe according to claim 1, it is characterised in that described Anchor cable construction one end in the soil body is provided with anchoring body.
6. support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe according to claim 1, it is characterised in that described Anchor cable is used to carry out tensioning with command displacement.
CN201720006185.6U 2017-01-04 2017-01-04 Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe Active CN206768831U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720006185.6U CN206768831U (en) 2017-01-04 2017-01-04 Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720006185.6U CN206768831U (en) 2017-01-04 2017-01-04 Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe

Publications (1)

Publication Number Publication Date
CN206768831U true CN206768831U (en) 2017-12-19

Family

ID=60648201

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720006185.6U Active CN206768831U (en) 2017-01-04 2017-01-04 Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe

Country Status (1)

Country Link
CN (1) CN206768831U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265726A (en) * 2017-01-04 2018-07-10 上海城地建设股份有限公司 Support, anchor cable post-tensioning HU types building enclosure and its application process before a kind of steel pipe
CN108385692A (en) * 2018-01-18 2018-08-10 武汉中力岩土工程有限公司 Deep basal pit shear connector support system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108265726A (en) * 2017-01-04 2018-07-10 上海城地建设股份有限公司 Support, anchor cable post-tensioning HU types building enclosure and its application process before a kind of steel pipe
CN108385692A (en) * 2018-01-18 2018-08-10 武汉中力岩土工程有限公司 Deep basal pit shear connector support system

Similar Documents

Publication Publication Date Title
CN102094425B (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN103410156B (en) Support space enclosing structure and application process thereof before a kind of recyclable vertical type steel pipe
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN111271066B (en) Bias-pressure hole-entering oblique crossing positive construction method
CN205975658U (en) Steel platform tower crane foundation
CN103114595A (en) Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN105625420A (en) Extension type manual hole digging pile support structure and construction method thereof
CN101824825B (en) Deep foundation pit open cutting construction method
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN206768831U (en) Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe
CN107326896A (en) One kind combination steel construction support pile and construction method
CN207159990U (en) One kind combination steel construction support pile
CN206768832U (en) Support, anchor cable post-tensioning H type component building enclosures before a kind of steel pipe
CN108330963A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN107503354A (en) A kind of tower crane goes along with sb. to guard him bracing reinforcement and excavation method
CN108265726A (en) Support, anchor cable post-tensioning HU types building enclosure and its application process before a kind of steel pipe
CN206256451U (en) H type component building enclosures are supportted before a kind of steel pipe
CN214194751U (en) Intercepting drain structure suitable for steep rock slope
CN211950500U (en) Bias hole-entering structure
CN212405174U (en) Supporting structure and building of soft rock foundation pit at lower part of upper soil layer
CN205088687U (en) Supporting structure of strut foundation ditch
CN1514073A (en) Supporitng structure of breast wall
CN108005086A (en) A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 201806, B, Lane 518, Lane 1, Heng Yong Road, Shanghai, Jiading District 502-1

Co-patentee after: SHANGHAI CHENGDI ROCK-SOIL DESIGN Co.,Ltd.

Patentee after: Shanghai chengdixiangjiang Data Technology Co.,Ltd.

Address before: 201806, B, Lane 518, Lane 1, Heng Yong Road, Shanghai, Jiading District 502-1

Co-patentee before: SHANGHAI CHENGDI ROCK-SOIL DESIGN Co.,Ltd.

Patentee before: SHANGHAI CHENGDI CONSTRUCTION Co.,Ltd.

CP01 Change in the name or title of a patent holder