CN206337556U CN201621003571.1U CN201621003571U CN206337556U CN 206337556 U CN206337556 U CN 206337556U CN 201621003571 U CN201621003571 U CN 201621003571U CN 206337556 U CN206337556 U CN 206337556U
Authority
CN
China
Prior art keywords
pile
end plate
prefabricated
behind shaft
drift lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621003571.1U
Other languages
Chinese (zh)
Inventor
高强
孙飞
俞建金
方咸美
李虎
全程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Academy Of Building Ltd By Share Ltd
Original Assignee
Jiangsu Academy Of Building Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Academy Of Building Ltd By Share Ltd filed Critical Jiangsu Academy Of Building Ltd By Share Ltd
Priority to CN201621003571.1U priority Critical patent/CN206337556U/en
Application granted granted Critical
Publication of CN206337556U publication Critical patent/CN206337556U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of grouting behind shaft or drift lining Prefabricated hollow pile, including:Prefabricated pile, end plate and pile top, the end plate is arranged at the bottom of prefabricated pile, the pile top is arranged at the downside of end plate, cavity is offered inside the prefabricated pile, inserted with Grouting Pipe in cavity, some injected holes are uniformly offered on the upside of the prefabricated pile bottom, end plate, the injected hole is connected to Grouting Pipe, one layer of rubber sleeve is coated with the outside of the injected hole.Through the above way, the utility model can protect injected hole not to be blocked in piling, it is ensured that Grouting Pipe is reliably connected.

Description

A kind of grouting behind shaft or drift lining Prefabricated hollow pile
Technical field
The utility model is related to building field, more particularly to a kind of grouting behind shaft or drift lining Prefabricated hollow pile.
Background technology
Pile foundation is a kind of wide variety of deep foundation form, be mainly used in deep soft soil, soil property it is uneven and Exist and built on the place of oscillatory load various build(Structure)The occasion of thing is built, construction skyscraper, heavy_weight factory is particularly applicable in With the occasion of the building with particular/special requirement.Pile foundation is broadly divided into reinforced concrete pile and steel-pipe pile, at present using more For reinforced concrete pile, reinforced concrete pile is broadly divided into bored concrete pile and prefabricated pile.
In recent years, prefabricated pile has the trend increased in some regional uses, and main cause is that prefabricated pile has quality steady The advantages of fixed reliability, relatively low cost, short time limit, simple construction technology.Comparatively speaking, construction process of bored concrete pile is complicated, and easily hair Make trouble former, reliability is not so good as prefabricated pile.Prefabricated pile is broadly divided into solid pile and hollow pile by its cross sectional shape.Because report is surveyed on ground Simply indirect selects hole, it is impossible to show the whole circumstances of the soil body, therefore to improve the bearing capacity of pile body, using precast hollow Stake pile-end post-grouting method is a selection well.
Conventional prefabricated pile post-grouting method mainly has following several at present:
(1)Perforate in pile top, after stake is sink to precalculated position, insertion Grouting Pipe carries out slip casting;
(2)Pile top is not set, after stake is sink to precalculated position, insertion Grouting Pipe carries out slip casting.
The deficiency of existing method:(1)Perforate in pile top, easily blocks injected hole, causes slip casting to fail;(2)If prefabricated sky Heart stake is not provided with pile top, then in pile driving process, and the soil body can enter stake chamber, leads to not insertion Grouting Pipe and carries out slip casting.
Utility model content
The utility model can protect injected hole mainly solving the technical problems that provide a kind of grouting behind shaft or drift lining Prefabricated hollow pile It is not blocked, it is ensured that Grouting Pipe is reliably connected.
In order to solve the above technical problems, the technical scheme that the utility model is used is:There is provided a kind of grouting behind shaft or drift lining prefabricated Hollow pile, including:Prefabricated pile, end plate and pile top, the end plate are arranged at the bottom of prefabricated pile, and the pile top is arranged at end plate Downside, cavity is offered inside the prefabricated pile, inserted with Grouting Pipe in cavity, in the prefabricated pile bottom, end plate Upside uniformly offers some injected holes, and the injected hole is connected to Grouting Pipe, and one layer is coated with the outside of the injected hole Rubber sleeve.
It is preferred that, the bottom of the cavity is set to turbination.
It is preferred that, a facing is provided with below the cavity bottom turbination.
It is preferred that, the bottom of the Grouting Pipe is set to external screw thread, and the external screw thread and silk facing phase of slip casting bottom of the tube Match somebody with somebody.
It is preferred that, the injected hole with diameter greater than 10mm.
It is preferred that, the diameter of the silk facing is set to 30 ~ 60mm.
The beneficial effects of the utility model are:The utility model 1, one layer of rubber sleeve is arranged on the outside of injected hole so that Injected hole is not easily blocked, reliable in quality;2nd, cavity bottom is arranged to turbination, for placing silk facing, reliable fixed silk tooth Position is covered, and is connected using silk facing and slip casting bottom of the tube, connection is reliable, slip casting process stabilization.
Brief description of the drawings
Fig. 1 is a kind of structural representation of the preferred embodiment of grouting behind shaft or drift lining Prefabricated hollow pile one of the utility model;
Fig. 2 is shown Fig. 1 sectional view;
Fig. 3 is shown Fig. 1 top view;
The mark of each part is as follows in accompanying drawing:1st, prefabricated pile, 2, pile top, 3, end plate, 4, cavity, 5, Grouting Pipe, 6, silk tooth Set, 7, injected hole, 8, rubber sleeve.
Embodiment
Preferred embodiment of the present utility model is described in detail below in conjunction with the accompanying drawings, so that advantage of the present utility model It can be easier to be readily appreciated by one skilled in the art with feature, so as to make protection domain of the present utility model apparent clear and definite Define.
Fig. 1 to Fig. 3 is referred to, the utility model embodiment includes:
A kind of grouting behind shaft or drift lining Prefabricated hollow pile, including:Prefabricated pile 1, end plate 3 and pile top 2, the end plate 3 are arranged at prefabricated pile 1 Bottom, the pile top 2 is arranged at the downside of end plate 3, cavity 4 is offered inside the prefabricated pile 1, in the interpolation of cavity 4 Enter to have Grouting Pipe 5, uniformly offer some injected holes 7 in the bottom of prefabricated pile 1, the upside of end plate 3, the injected hole 7 is connected To Grouting Pipe 5, one layer of rubber sleeve 8 is coated with the outside of the injected hole 7.
In order to ensure to be not plugged up in injected hole 7 in piling, rubber sleeve 8 uses totally enclosed structure, is driving piles Cheng Hou, using giant toward water filling in injected hole 7, the rubber sleeve 8 at injected hole is punctured by hydraulic pressure.
In order to ensure stability during slip casting, the bottom of the cavity 4 is set to turbination, and the bottom of the cavity 4 It is provided with a facing 6 below portion's turbination, the bottom of the Grouting Pipe 5 is set to external screw thread, and the bottom of Grouting Pipe 5 External screw thread matches with silk facing 6, during installation, by Grouting Pipe 5 and the rotation matching of silk facing 6 so that will not be let out during slip casting Leakage, improves the stability of slip casting.
Further, the diameter of the injected hole 7 is set to 10mm, and the quantity of injected hole 7 is set to 3, the silk tooth The diameter of set 6 is set to 30mm, and the diameter of injected hole 7 is less than the diameter of silk facing 6 so that have enough pressure in injected hole 7.
Embodiment of the present utility model is the foregoing is only, the scope of the claims of the present utility model is not thereby limited, it is every The equivalent structure or equivalent flow conversion made using the utility model specification and accompanying drawing content, or be directly or indirectly used in Other related technical fields, are similarly included in scope of patent protection of the present utility model.

Claims (6)

1. a kind of grouting behind shaft or drift lining Prefabricated hollow pile, it is characterised in that including:Prefabricated pile, end plate and pile top, the end plate are arranged at pre- The bottom of stake processed, the pile top is arranged at the downside of end plate, and cavity is offered inside the prefabricated pile, is inserted in cavity There is Grouting Pipe, some injected holes are uniformly offered on the upside of the prefabricated pile bottom, end plate, the injected hole is connected to slip casting Pipe, is coated with one layer of rubber sleeve on the outside of the injected hole.
2. a kind of grouting behind shaft or drift lining Prefabricated hollow pile according to claim 1, it is characterised in that the bottom of the cavity is set to Turbination.
3. a kind of grouting behind shaft or drift lining Prefabricated hollow pile according to claim 2, it is characterised in that the cavity bottom turbination Lower section be provided with a facing.
4. a kind of grouting behind shaft or drift lining Prefabricated hollow pile according to claim 1, it is characterised in that the bottom of the Grouting Pipe is set External screw thread for external screw thread, and slip casting bottom of the tube matches with silk facing.
5. a kind of grouting behind shaft or drift lining Prefabricated hollow pile according to claim 1, it is characterised in that the injected hole with diameter greater than 10mm。
6. a kind of grouting behind shaft or drift lining Prefabricated hollow pile according to claim 3, it is characterised in that the diameter of the silk facing is set For 30~60mm.
CN201621003571.1U 2016-08-31 2016-08-31 A kind of grouting behind shaft or drift lining Prefabricated hollow pile Active CN206337556U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621003571.1U CN206337556U (en) 2016-08-31 2016-08-31 A kind of grouting behind shaft or drift lining Prefabricated hollow pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621003571.1U CN206337556U (en) 2016-08-31 2016-08-31 A kind of grouting behind shaft or drift lining Prefabricated hollow pile

Publications (1)

Publication Number Publication Date
CN206337556U true CN206337556U (en) 2017-07-18

Family

ID=59299826

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621003571.1U Active CN206337556U (en) 2016-08-31 2016-08-31 A kind of grouting behind shaft or drift lining Prefabricated hollow pile

Country Status (1)

Country Link
CN (1) CN206337556U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110144894A (en) * 2019-05-16 2019-08-20 广州市鲁班建筑科技集团股份有限公司 A kind of pile end grouting miniature steel pipe static pressed pile
CN110241813A (en) * 2019-05-16 2019-09-17 国家电网有限公司 A kind of buried prefabricated tubular pile of transmission line of electricity brill
CN114703842A (en) * 2022-03-30 2022-07-05 中国人民解放军91053部队 Coral sand foundation drilling type prefabricated hollow pipe pile and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110144894A (en) * 2019-05-16 2019-08-20 广州市鲁班建筑科技集团股份有限公司 A kind of pile end grouting miniature steel pipe static pressed pile
CN110241813A (en) * 2019-05-16 2019-09-17 国家电网有限公司 A kind of buried prefabricated tubular pile of transmission line of electricity brill
CN114703842A (en) * 2022-03-30 2022-07-05 中国人民解放军91053部队 Coral sand foundation drilling type prefabricated hollow pipe pile and construction method

Similar Documents

Publication Publication Date Title
CN1837511B (en) Double-rowed cofferdam and method for manufacturing the same
CN103758134B (en) A kind of construction method combining Double-row Piles Support system
CN104234055B (en) A kind of prefabricated pile post-grouting device and technique thereof
CN208167713U (en) A kind of film bag grouting and reinforcing type filling pile structure
CN206941608U (en) A kind of diaphram wall foundation pit supporting construction
CN206337556U (en) A kind of grouting behind shaft or drift lining Prefabricated hollow pile
CN104005404A (en) Prestressed pipe pile coated with active material pile body and construction method
CN106368219A (en) Supporting reinforcing structure of deep foundation pit and construction method
CN208472708U (en) A kind of grouting behind shaft or drift lining filling pile structure
CN201245839Y (en) Composite bearing pile of concrete stirring soil implanted prefabricated reinforced concrete core rod
CN111364449A (en) Construction method and structure for penetrating karst cave of precast tubular pile
CN205502024U (en) Arch combination envelope that can partially retrieve
CN104389305B (en) A kind of back-up sand bamboo joint pile and construction method thereof
CN101173515B (en) Steel pipe pile foundation built by planting steel stick and building method thereof
CN104196013B (en) A kind of composite Y shape stake and construction method thereof
CN109826226A (en) Historical building timber strengthening of foundation method
CN212052717U (en) Structure for penetrating karst cave of precast tubular pile
CN206512727U (en) A kind of miniature steel pipe pile supporting construction of combination High Pressure Grouting Technology
CN103114576A (en) Post grouting construction method for cast-in-place concrete pile
CN108625388A (en) A kind of sleeve combination formula large diameter single pile foundation and its construction method suitable for Shallow Bedrock geological conditions
CN105113492A (en) Construction method of composite pile applicable to cohesive soil, sandy soil and muddy soil foundations
CN208685596U (en) A kind of prefabricated pouring mortar pile
CN204238209U (en) A kind of back-up sand bamboo joint pile
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN201635072U (en) Centrally grouted static-pressured anchor pile former

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant