CN103758134B - A kind of construction method combining Double-row Piles Support system - Google Patents

A kind of construction method combining Double-row Piles Support system Download PDF

Info

Publication number
CN103758134B
CN103758134B CN201410033020.9A CN201410033020A CN103758134B CN 103758134 B CN103758134 B CN 103758134B CN 201410033020 A CN201410033020 A CN 201410033020A CN 103758134 B CN103758134 B CN 103758134B
Authority
CN
China
Prior art keywords
piles
row
pile
cement
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410033020.9A
Other languages
Chinese (zh)
Other versions
CN103758134A (en
Inventor
秦会来
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Engineering Corp Ltd CSCEC
Original Assignee
China State Construction Engineering Corp Ltd CSCEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Engineering Corp Ltd CSCEC filed Critical China State Construction Engineering Corp Ltd CSCEC
Priority to CN201410033020.9A priority Critical patent/CN103758134B/en
Publication of CN103758134A publication Critical patent/CN103758134A/en
Application granted granted Critical
Publication of CN103758134B publication Critical patent/CN103758134B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

一种组合双排桩支护体系的施工方法,所述支护体系包括有前排桩、前排桩桩顶冠梁、后排桩、后排桩桩顶冠梁和连系梁,所述前排桩为平行间隔设置的一排钢筋混凝土桩,所述后排桩为型钢水泥土搅拌桩墙,所述连系梁为双肢连系梁;所述型钢水泥土搅拌桩墙中的内插型钢为H型钢,并且H型钢的上端部外露在后排桩桩顶冠梁的上方;所述前排桩与后排桩之间还设有浅层加固水泥土桩,并且浅层加固水泥土桩与型钢水泥土搅拌桩墙整体搭接连接在一起。本支护体系即克服了需截水基坑工程中普通双排桩支护结构需增设止水帷幕的缺陷,又克服了型钢水泥土搅拌桩墙刚度低的缺陷,实现了支护结构挡土与隔水的统一,大大地降低了支护工程造价。

A construction method for a combined double-row pile support system, the support system includes a front row of piles, a front row of pile crown beams, a rear row of piles, a rear row of pile crown beams and a connecting beam, the front row The piles are a row of reinforced concrete piles set at parallel intervals, the rear row of piles is a steel cement-soil mixing pile wall, and the connecting beam is a double-leg connecting beam; the inserted steel in the steel cement-soil mixing pile wall is H shaped steel, and the upper end of the H-shaped steel is exposed above the top crown beam of the rear row of piles; there is also a shallow reinforced cement-soil pile between the front row of piles and the rear row of piles, and the shallow reinforced cement-soil pile and the shaped steel The cement-soil mixing pile wall is integrally lapped and connected together. This support system not only overcomes the defect of adding a water-stop curtain to the ordinary double-row pile support structure in the foundation pit project that needs water interception, but also overcomes the defect of low rigidity of the steel cement-soil mixing pile wall, and realizes the soil retaining structure of the support structure. The unity with the water barrier greatly reduces the cost of the support project.

Description

一种组合双排桩支护体系的施工方法A construction method of combined double-row pile support system

技术领域 technical field

本发明涉及一种建筑基坑支护体系及其施工方法。 The invention relates to a building foundation pit support system and a construction method thereof.

背景技术 Background technique

悬臂式型钢水泥土搅拌桩墙(也称SMW工法)和前后排均为钢筋混凝土桩的普通双排桩支护结构是近些年来在基坑工程中应用越来越多的支护形式。 Cantilever type steel-cement-soil mixing pile wall (also known as SMW construction method) and ordinary double-row pile support structure with reinforced concrete piles in the front and rear rows are more and more support forms used in foundation pit engineering in recent years.

所述悬臂式型钢水泥土搅拌桩墙多用于软土、粉土、细砂等非坚硬地质条件下,是一种在水泥土搅拌桩内插入H型钢而形成的复合挡土隔水结构,具有高截水性、经济、施工污染小、对周围环境影响小等特点,而且在地下室施工完成后,可以将型钢水泥土搅拌桩墙中的H型钢拔出,然后予以回收和再利用,不仅可以节约资源,也避免了围护体在地下室施工完毕后永久遗留于地下、成为后续其它地下工程施工的障碍物。型钢水泥土搅拌桩墙的缺点是,由于型钢水泥土搅拌桩墙的主要抗侧力元件为型钢,因此刚度较低,抗侧移刚度不足,不利于控制变形,并且对于较深的基坑,型钢水泥土搅拌桩墙还需与内支撑或锚杆(锚索)联合使用,施工不方便,效率低。 The cantilever-type steel cement-soil mixing pile wall is mostly used in non-hard geological conditions such as soft soil, silt, and fine sand. It is a composite soil-retaining and water-proof structure formed by inserting H-shaped steel into the cement-soil mixing pile. It has the characteristics of high water interception, economy, low construction pollution, and small impact on the surrounding environment. After the basement construction is completed, the H-shaped steel in the steel-cement-soil mixing pile wall can be pulled out, and then recycled and reused, which can not only save It also prevents the enclosure from being permanently left underground after the construction of the basement and becoming an obstacle to other subsequent underground constructions. The disadvantage of the steel-cement-soil mixing pile wall is that the main anti-lateral force element of the steel-cement-soil mixing pile wall is steel, so the rigidity is low, and the anti-side movement stiffness is insufficient, which is not conducive to controlling deformation, and for deep foundation pits, The steel-cement-soil mixing pile wall also needs to be used in combination with internal supports or anchor rods (anchor cables), which is inconvenient for construction and low in efficiency.

所述普通双排桩支护结构由前排钢筋混凝土桩、后排钢筋混凝土桩、前后排桩压顶冠梁和连系梁构成,该支护结构利用前后排桩和连系梁形成空间门架,具有抗侧移刚度大的特点,且坑内无需设置内撑或锚索,所以极大地方便了施工,可缩短施工工期。普通双排桩支护结构的缺点是,对于需要截水的基坑工程,由于前后排分离式钢筋混凝土桩无法形成止水帷幕,所以需要另设止水帷幕,因此增加了施工工序和工程造价。 The ordinary double-row pile support structure is composed of a front row of reinforced concrete piles, a rear row of reinforced concrete piles, a front and rear row of pile crown beams and a connecting beam. It has the characteristics of high anti-sway rigidity, and there is no need to set inner supports or anchor cables in the pit, so it greatly facilitates the construction and shortens the construction period. The disadvantage of the ordinary double-row pile support structure is that for the foundation pit project that needs water interception, since the front and rear rows of separated reinforced concrete piles cannot form a water-stop curtain, it is necessary to set up another water-stop curtain, thus increasing the construction process and project cost .

发明内容 Contents of the invention

本发明的目的是提供一种组合双排桩支护体系的施工方法,要解决在需要截水的基坑工程中,采用普通双排桩支护结构工程造价太高,采用悬臂式型钢水泥土搅拌桩墙又不能满足基坑工程安全和变形控制要求的问题。 The purpose of the present invention is to provide a construction method for a combined double-row pile support system. It is necessary to solve the problem that in the foundation pit project that needs water interception, the cost of the ordinary double-row pile support structure is too high, and the use of cantilever type steel cement soil The mixing pile wall cannot meet the safety and deformation control requirements of the foundation pit engineering.

为实现上述目的,本发明采用如下技术方案:一种组合双排桩支护体系,包括有前排桩、前排桩桩顶冠梁、后排桩、后排桩桩顶冠梁和连系梁,其特征在于:所述前排桩为平行间隔设置的一排钢筋混凝土桩,所述后排桩为型钢水泥土搅拌桩墙,所述连系梁为双肢连系梁;所述型钢水泥土搅拌桩墙中的内插型钢为H型钢,并且H型钢的上端部外露在后排桩桩顶冠梁的上方;所述前排桩与后排桩之间还设有浅层加固水泥土桩,并且浅层加固水泥土桩与型钢水泥土搅拌桩墙整体搭接连接在一起。 In order to achieve the above object, the present invention adopts the following technical scheme: a combined double-row pile support system, including a front row of piles, a front row of pile crown beams, a rear row of piles, a rear row of pile crown beams and a connecting beam, It is characterized in that: the front row of piles is a row of reinforced concrete piles arranged at parallel intervals, the rear row of piles is a steel cement-soil mixing pile wall, and the connecting beam is a double-leg connecting beam; the steel cement-soil mixing pile The inserted steel in the wall is H-shaped steel, and the upper end of the H-shaped steel is exposed above the crown beam of the rear row of piles; there is also a shallow reinforced cement-soil pile between the front row of piles and the rear row of piles, and The shallow reinforcement cement-soil pile is integrally lapped and connected with the steel-cement-soil mixing pile wall.

所述浅层加固水泥土桩可由前排浅层加固水泥土桩和后排浅层加固水泥土桩两排桩组成,并且前排浅层加固水泥土桩与后排浅层加固水泥土桩整体搭接连接在一起。 The shallow reinforced cement-soil piles can be composed of two rows of front row shallow reinforced cement-soil piles and rear shallow reinforced cement-soil piles, and the front row shallow reinforced cement-soil piles and the rear shallow reinforced cement-soil piles are integrated Lap joints are joined together.

所述浅层加固水泥土桩的桩间距可与前排桩的桩间距相同。 The pile spacing of the shallow reinforced cement-soil piles can be the same as that of the front row of piles.

所述型钢水泥土搅拌桩墙中的内插型钢的间距可以是前排桩的桩间距的一倍、两倍或三倍。 The spacing of the inserted section steel in the section steel cement-soil mixing pile wall can be one time, two times or three times of the pile spacing of the front row of piles.

所述H型钢的上端部上可设有型钢起吊孔。 The upper end of the H-section steel may be provided with a section steel lifting hole.

所述双肢连系梁的两肢之间的净距可为H型钢的翼缘宽度加上60mm。 The net distance between the two limbs of the double-leg connecting beam can be the flange width of the H-shaped steel plus 60mm.

所述H型钢的上端部在冠梁上方的外露的长度可为不小于500mm。 The exposed length of the upper end of the H-shaped steel above the crown beam may be no less than 500 mm.

所述前排桩中的前排桩主筋可在桩顶锚入到前排桩桩顶冠梁中,并且锚固长度不小于1.5倍的受拉锚固长度。 The main reinforcement of the front row of piles in the front row of piles can be anchored into the crown beam of the front row of piles at the top of the pile, and the anchorage length is not less than 1.5 times the tensile anchorage length.

所述连系梁中的纵向主筋可锚入到前排桩桩顶冠梁和后排桩桩顶冠梁中,并且锚固长度不小于1.5倍的受拉锚固长度。 The longitudinal main reinforcement in the connecting beam can be anchored into the top crown beam of the front row of piles and the top crown beam of the rear row of piles, and the anchorage length is not less than 1.5 times the tensile anchorage length.

一种应用一种组合双排桩支护体系的施工方法,其特征在于施工步骤如下:步骤一、根据拟建场地的水文地质条件、基坑工程几何参数、基坑工程隔水、抗渗稳定性要求,计算出施工一种组合双排桩支护体系所需要的各个技术参数;步骤二、根据拟建工程场地条件及周边环境条件,选择具体位置,用三轴水泥土搅拌桩机开始施工一段后排桩的水泥土搅拌桩和一段浅层加固水泥土桩,在该段已施工的后排桩的水泥土搅拌桩凝结硬化前、三轴水泥土搅拌桩机移位施工下一段后排桩的水泥土搅拌桩时,开始内插型钢插入水泥土搅拌桩施工工序,内插型钢插入水泥土搅拌桩施工工序在相应位置处的水泥土搅拌桩施工完成30分钟内开展,型钢露出的高度需满足上穿后排桩桩顶冠梁以及拔出预留高度要求;步骤三、不断重复步骤二,直至按设计要求施工完成所有的后排桩、内插型钢和浅层加固水泥土桩;步骤四、施工前排桩、前排桩桩顶冠梁、后排桩桩顶冠梁和连系梁;步骤五、待后排桩满足抗渗要求时,开展基坑工程降水,待一种组合双排桩支护体系各部分均满足强度要求时,开展基坑土方开挖;步骤六、基坑开挖到设计深度后,开始地下结构施工;步骤七、地下结构施工出地坪,结构与基坑坑壁之间的空隙回填压实后,拔除内插型钢,内插型钢留下的空隙注浆封填。 A construction method using a combined double-row pile support system, characterized in that the construction steps are as follows: Step 1, according to the hydrogeological conditions of the proposed site, the geometric parameters of the foundation pit engineering, the water resistance of the foundation pit engineering, and the anti-seepage stability According to the specific requirements, calculate the various technical parameters required for the construction of a combined double-row pile support system; Step 2, according to the proposed project site conditions and surrounding environmental conditions, select a specific location, and start construction with a three-axis cement-soil mixing pile machine A section of cement-soil mixing piles in the back row of piles and a section of shallow reinforced cement-soil piles. Before the cement-soil mixing piles of the back row of piles in this section are solidified and hardened, the three-axis cement-soil mixing pile machine is shifted to construct the next section of the back row When the cement-soil mixing pile is used for the pile, the construction process of inserting the steel into the cement-soil mixing pile is started. The construction process of inserting the steel into the cement-soil mixing pile is carried out within 30 minutes after the construction of the cement-soil mixing pile at the corresponding position is completed. The exposed height of the steel It is necessary to meet the requirements for the top crown beam of the back row of piles and pull out the reserved height; step 3, repeat step 2 until the construction of all the back row of piles, interpolated steel and shallow reinforced cement soil piles is completed according to the design requirements; Step 4: Construct the front row of piles, the front row of pile crown beams, the rear row of pile crown beams and the connecting beam; Step 5, when the rear row of piles meets the anti-seepage requirements, carry out the dewatering of the foundation pit, and wait for a combined double When all parts of the pile row support system meet the strength requirements, excavation of the foundation pit earthwork is carried out; step 6, after the foundation pit is excavated to the design depth, the construction of the underground structure begins; After the gap between the pit walls is backfilled and compacted, the inserted section steel is removed, and the gap left by the inserted section steel is grouted and sealed.

与现有技术相比本发明具有以下特点和有益效果:本发明是一种集挡土隔水功能于一体的新型基坑支护结构形式,尤其适合用于软土、粉土、细砂等地质条件下需要隔水的深基坑工程,属地基基础领域。 Compared with the prior art, the present invention has the following characteristics and beneficial effects: the present invention is a new type of foundation pit support structure that integrates soil retaining and water-proof functions, and is especially suitable for soft soil, silt, fine sand, etc. The deep foundation pit engineering requiring water isolation under geological conditions belongs to the field of foundation foundation.

本发明由位于前排的前排钢筋混凝土桩和前排桩桩顶冠梁,位于后排的后排型钢水泥土搅拌桩墙和后排桩墙顶冠梁(即后排桩桩顶冠梁),以及前后排桩间的双肢连系梁组成,是一种空间门架式支护结构体系,可承担水土压力荷载,具有抗侧移刚度大的优点,可有效地控制基坑的侧移变形。 The present invention consists of the front row of reinforced concrete piles and the front row of pile crown beams located in the front row, the rear row of shaped steel cement soil mixing pile walls and the rear row of pile wall crown beams located in the rear row (i.e. the rear row of pile crown beams) ), and the double-limb connecting beams between the front and rear rows of piles, it is a space gantry type support structure system, which can bear water and soil pressure loads, has the advantage of high rigidity against lateral movement, and can effectively control the side of the foundation pit. shift deformation.

普通双排桩支护结构的计算和实测结果表明,前排桩受压,后排桩受拉,本发明充分利用了双排桩的这一受力特点,将抗压能力好的钢筋混凝土桩作为前排桩,将抗拉性能好的H型钢作为后排桩,充分发挥了材料的性能。 The calculation and actual measurement results of the ordinary double-row pile support structure show that the front row of piles is under compression and the rear row of piles is under tension. As the front row of piles, the H-shaped steel with good tensile performance is used as the rear row of piles, which fully exerts the performance of the material.

本发明充分利用了普通双排桩支护结构和型钢水泥土搅拌桩墙两者的优点,即克服了需截水基坑工程中普通双排桩支护结构需增设止水帷幕的缺陷,又克服了型钢水泥土搅拌桩墙刚度低的缺陷。 The invention makes full use of the advantages of both the common double-row pile support structure and the shaped steel cement-soil mixing pile wall, which overcomes the defect that the common double-row pile support structure needs to be equipped with a water-stop curtain in foundation pit projects requiring water interception, and also It overcomes the defect of low rigidity of the steel cement soil mixing pile wall.

本发明用型钢水泥土搅拌桩墙取代普通双排桩支护结构中的后排钢筋混凝土桩,型钢水泥土搅拌桩墙具有止水、隔水、防渗功能,因此解决了基坑工程的隔水问题,克服了普通双排桩需要增设止水帷幕的缺陷,实现了支护结构挡土与隔水的统一,所以无需另设止水帷幕,大大地降低了支护工程造价,减少了施工工序,节约了施工工期。 The invention replaces the rear row of reinforced concrete piles in the ordinary double-row pile support structure with the steel-cement-soil mixing pile wall. The steel-cement-soil mixing pile wall has the functions of water stop, water isolation and seepage prevention, so it solves the problem of foundation pit engineering The water problem overcomes the defect that ordinary double-row piles need to add a water-stop curtain, and realizes the unity of soil retaining and water-proofing of the support structure, so there is no need to set up another water-stop curtain, which greatly reduces the cost of the support project and reduces the construction cost. process, saving the construction period.

本发明中的后排型钢水泥土搅拌桩墙中的H型钢,在地下结构施工出地坪,结构与基坑间空隙回填后,即可拔出回收再利用,极大地降低了支护工程造价,节约了资源,也避免了给后续其他紧邻地下工程的施工造成障碍。 The H-shaped steel in the back-row steel-cement-soil mixing pile wall in the present invention can be pulled out and recycled after the ground is constructed in the underground structure, and the gap between the structure and the foundation pit is backfilled, which greatly reduces the cost of support engineering , which saves resources and avoids causing obstacles to the subsequent construction of other adjacent underground projects.

本发明还克服了型钢水泥搅拌桩墙抗侧移刚度不足的缺陷,对于一般深基坑工程,无需在坑内设置内支撑或锚杆(锚索),极大地方便了基坑内土方开挖和地下结构施工,提高了施工效率。 The invention also overcomes the defect of insufficient lateral displacement rigidity of the steel cement mixing pile wall. For general deep foundation pit engineering, there is no need to set internal supports or anchor rods (anchor cables) in the pit, which greatly facilitates the excavation of earthwork in the foundation pit and underground construction. Structural construction improves construction efficiency.

本发明在前排钢筋混凝土桩和后排型钢水泥土搅拌桩墙之间设置浅层加固水泥土桩(浅层加固水泥土搅拌桩),这样设计提高了前排桩和后排桩墙间协同工作刚度,同时也提高了前排桩和后排桩之间主动区土体的强度,降低了作用于支护结构上的荷载,有利于支护结构的受力和稳定。 In the present invention, shallow reinforcement cement soil piles (shallow reinforcement cement soil mixing piles) are arranged between the front row of reinforced concrete piles and the rear row of shaped steel cement soil mixing pile walls. This design improves the synergy between the front row of piles and the rear row of pile walls. The working stiffness also improves the strength of the soil in the active area between the front row of piles and the rear row of piles, reduces the load acting on the support structure, and is beneficial to the stress and stability of the support structure.

本发明在靠近用地红线的一侧(即后排)用型钢水泥土搅拌桩墙取代普通的钻孔灌注而成的钢筋混凝土桩,可以显著地降低钻孔灌注桩成孔施工对基坑周边环境的不利影响。具体来说,型钢水泥土搅拌桩墙在施工时采用三轴搅拌桩机就地切削土体,并使土体与水泥浆液充分拌合形成水泥土,用低压持续注入的水泥浆液置换处于流动状态的水泥土,保持地下水泥土总量平衡,所以无需钻孔,不存在普通双排桩施工时的塌孔现象,因此可以减少对周围土体的扰动,降低对周边管线、地下建筑构等的危害,有效地保护周边环境。 The present invention replaces the reinforced concrete pile formed by ordinary borehole pouring with a steel cement-soil mixing pile wall on the side (that is, the back row) near the red line of the land, which can significantly reduce the impact on the surrounding environment of the foundation pit during the borehole construction. adverse effects. Specifically, a three-axis mixing pile machine is used to cut the soil mass on site during the construction of the section steel cement-soil mixing pile wall, and the soil mass and cement slurry are fully mixed to form cement-soil, which is replaced by low-pressure continuous injection of cement slurry in a flowing state. The cement-soil in the ground maintains the balance of the total amount of underground cement-soil, so there is no need to drill holes, and there is no hole collapse phenomenon during the construction of ordinary double-row piles, so it can reduce the disturbance to the surrounding soil and reduce the damage to the surrounding pipelines and underground structures. , effectively protect the surrounding environment.

本发明先施工靠近用地红线一侧(即后排)的型钢水泥土搅拌桩墙,后施工位于前排的钢筋混凝土桩,先施工的型钢水泥土搅拌桩墙在后施工的钢筋混凝土桩与周边环境介质之间形成隔离帷幕,降低了钢筋混凝土桩成孔施工所诱发土体损伤对周围环境介质的不利影响,有效地保护了周边环境。 In the present invention, the steel-cement-soil mixing pile wall close to the land use red line side (i.e. the back row) is constructed first, and then the reinforced concrete piles located in the front row are constructed. An isolation curtain is formed between the environmental media, which reduces the adverse effect of soil damage induced by the reinforced concrete pile hole-forming construction on the surrounding environmental media, and effectively protects the surrounding environment.

附图说明 Description of drawings

下面结合附图对本发明做进一步详细的说明。 The present invention will be described in further detail below in conjunction with the accompanying drawings.

图1为本发明的立体布置示意图。 Fig. 1 is a schematic diagram of the three-dimensional arrangement of the present invention.

图2为本发明双排桩支护力学计算模型示意图。 Fig. 2 is a schematic diagram of the mechanical calculation model of double-row pile support of the present invention.

图3为本发明的俯视示意图。 Fig. 3 is a schematic top view of the present invention.

图4为本发明的桩体布置俯视示意图。 Fig. 4 is a schematic top view of pile arrangement of the present invention.

附图标记:1-前排桩、2-前排桩桩顶冠梁、3-后排桩、4-内插型钢、5-后排桩桩顶冠梁、6-连系梁、7-浅层加固水泥土桩、7.1-前排浅层加固水泥土桩、7.2-后排浅层加固水泥土桩、8-型钢起吊孔。 Reference signs: 1-front row of piles, 2-front row of pile crown beams, 3-rear row of piles, 4-interpolated steel, 5-rear row of pile crown beams, 6-connecting beams, 7- Shallow reinforced cement-soil piles, 7.1-front shallow reinforced cement-soil piles, 7.2-rear shallow reinforced cement-soil piles, 8-shaped steel lifting holes.

具体实施方式 Detailed ways

实施例参见图1-4所示,这种组合双排桩支护体系,包括有前排桩1、前排桩桩顶冠梁2、后排桩3、后排桩桩顶冠梁5和连系梁6。 Referring to the embodiment shown in Figures 1-4, this combined double-row pile support system includes a front row of piles 1, a front row of pile crown beams 2, a rear row of piles 3, a rear row of pile crown beams 5 and Connection beam 6.

所述前排桩1为平行间隔设置的一排钢筋混凝土桩,所述后排桩3为型钢水泥土搅拌桩墙,所述连系梁6为双肢连系梁(便于型钢水泥土搅拌桩墙中的型钢拔除)。 The front row of piles 1 is a row of reinforced concrete piles arranged at parallel intervals, the rear row of piles 3 is a shaped steel cement-soil mixing pile wall, and the connecting beam 6 is a double-leg connecting beam (to facilitate the formation of the shaped steel cement-soil mixing pile wall). removal of profiled steel in the wall).

所述型钢水泥土搅拌桩墙中的内插型钢4为H型钢,并且H型钢的上端部外露在后排桩桩顶冠梁5的上方。本实施例中,H型钢的上端部上还设有型钢起吊孔8,并且H型钢在桩顶冠梁上的外露长度为不小于500mm。 The inserted section steel 4 in the section steel cement-soil mixing pile wall is an H-section steel, and the upper end of the H-section steel is exposed above the crown beam 5 of the rear row of piles. In this embodiment, the upper end of the H-shaped steel is also provided with a steel lifting hole 8, and the exposed length of the H-shaped steel on the crown beam of the pile top is not less than 500 mm.

所述前排桩1与后排桩3之间还设有浅层加固水泥土桩7,并且浅层加固水泥土桩7与型钢水泥土搅拌桩墙整体搭接连接在一起。浅层加固水泥土桩7仅需要在支护体系上部设置。 Between the front row of piles 1 and the back row of piles 3, there is also a shallow reinforced cement-soil pile 7, and the shallow reinforced cement-soil pile 7 is integrally connected with the steel cement-soil mixing pile wall. The shallow reinforcement cement-soil pile 7 only needs to be arranged on the upper part of the support system.

所述浅层加固水泥土桩7的排数和搭接宽度可根据前、后排桩间距确定。本实施例中,浅层加固水泥土桩7由前排浅层加固水泥土桩7.1和后排浅层加固水泥土桩7.2两排桩组成,并且前排浅层加固水泥土桩与后排浅层加固水泥土桩7.2整体搭接连接在一起。当然,在其它实施例中,浅层加固水泥土桩7也可以只有一排桩,也可以是三排桩或更多排桩. The number of rows and the overlap width of the shallow reinforced cement-soil piles 7 can be determined according to the distance between the front and rear rows of piles. In the present embodiment, the shallow reinforcement cement soil pile 7 is made up of front row shallow reinforcement cement soil pile 7.1 and rear row shallow reinforcement cement soil pile 7.2 two rows of piles, and front row shallow reinforcement cement soil pile and back row shallow Layer-reinforced cement-soil piles 7.2 are integrally lapped and connected together. Of course, in other embodiments, the shallow reinforced cement-soil piles 7 may also have only one row of piles, or three or more rows of piles.

本实施例中,浅层加固水泥土桩7之间的桩间距与前排桩1之间的桩间距相同,在其它实施例中,浅层加固水泥土桩7的桩间距与前排桩1的桩间距也可以不相同。 In this embodiment, the pile spacing between the shallow reinforced cement-soil piles 7 is the same as the pile spacing between the front row of piles 1. The pile spacing can also be different.

本实施例中,型钢水泥土搅拌桩墙中的型钢的间距是前排桩1的桩间距的一倍,即型钢水泥土搅拌桩墙中的型钢的间距与前排桩1的桩间距相同。在其它实施例中,型钢水泥土搅拌桩墙中的型钢的间距是前排桩1的桩间距的两倍或三倍。 In this embodiment, the distance between the steel sections in the steel-cement-soil mixing pile wall is twice that of the front row of piles 1, that is, the distance between the steel sections in the steel-cement-soil mixing pile wall is the same as that of the front row of piles 1. In other embodiments, the spacing of the section steel in the section steel cement-soil mixing pile wall is twice or three times the pile spacing of the front row of piles 1 .

所述双肢连系梁的两肢之间的净距a为H型钢的翼缘宽度b加上约60mm。 The net distance a between the two limbs of the double-leg connecting beam is the flange width b of the H-shaped steel plus about 60mm.

所述前排桩1中的前排桩主筋在桩顶锚入到前排桩桩顶冠梁2中,并且锚固长度不小于1.5倍的受拉锚固长度。 The main reinforcement of the front row of piles 1 is anchored into the top crown beam 2 of the front row of piles at the top of the pile, and the anchorage length is not less than 1.5 times the tensile anchorage length.

所述连系梁6中的纵向主筋锚入到前排桩桩顶冠梁2和后排桩桩顶冠梁5中,并且锚固长度不小于1.5倍的受拉锚固长度。 The longitudinal main reinforcement in the connecting beam 6 is anchored into the top crown beam 2 of the front row of piles and the crown beam 5 of the rear row of piles, and the anchorage length is not less than 1.5 times the tensile anchorage length.

本发明在进行强度、稳定和变形计算时,按由前排桩1、前排桩桩顶冠梁2、型钢4、后排型钢水泥土搅拌桩墙顶冠梁5、双肢连系梁6组成的双排桩进行计算求得,并根据设计要求确定前排桩的直径、配筋、嵌固深度和水平向间距,以及型钢水泥土搅拌桩墙中的型钢的型号,双肢连续梁的截面尺寸、混凝土等级和配筋。 When the present invention calculates the strength, stability and deformation, it consists of the front row of piles 1, the front row of pile crown beams 2, the section steel 4, the back row of section steel cement soil mixing pile wall top crown beams 5, and the double limb connecting beams 6. Calculate and obtain the double-row piles, and determine the diameter, reinforcement, embedding depth and horizontal spacing of the front row of piles according to the design requirements, as well as the type of steel in the steel-cement-soil mixing pile wall, and the double-leg continuous beam. Section size, concrete grade and reinforcement.

所述型钢水泥土搅拌桩墙中的水泥土桩的长度由型钢长度和基坑止水、防渗共同决定(由型钢长度和基坑止水、防渗要求确定的大者取值),型钢水泥土搅拌桩墙中的水泥土桩的桩身强度需满足止水和强度计算要求。 The length of the cement-soil pile in the section steel cement-soil mixing pile wall is determined by the length of the section steel and the foundation pit water stop and anti-seepage (the larger value determined by the section steel length and the foundation pit water stop and anti-seepage requirements), the section steel The pile body strength of the cement-soil pile in the cement-soil mixing pile wall must meet the requirements of water stop and strength calculation.

这种应用一种组合双排桩支护体系的施工方法,其施工步骤如下。 This construction method using a combined double-row pile support system has the following construction steps.

步骤一、根据拟建场地的水文地质条件、基坑工程几何参数、基坑工程隔水、抗渗稳定性要求,计算出施工一种组合双排桩支护体系所需要的各个技术参数。具体来说,先根据拟建场地的水文地质条件和基坑工程几何参数,进行支护结构强度、支护体系稳定性及变形计算,确定前排桩1的直径、混凝强度等级、截面配筋、嵌固深度以及水平间距等,型钢4的型号和长度,连系梁6的截面尺寸、混凝土等级和配筋等。然后根据基坑工程隔水、抗渗稳定性要求和型钢4的计算长度,确定后排桩3的长度。后排桩3的桩身强度应满足计算要求,渗透系数满足止水要求。 Step 1. According to the hydrogeological conditions of the proposed site, the geometric parameters of the foundation pit engineering, the water insulation and anti-seepage stability requirements of the foundation pit engineering, calculate the various technical parameters required for the construction of a combined double-row pile support system. Specifically, according to the hydrogeological conditions of the proposed site and the geometric parameters of the foundation pit engineering, the strength of the support structure, the stability of the support system and the deformation calculation are carried out to determine the diameter, concrete strength grade and section configuration of the front row of piles 1. Reinforcement, embedding depth and horizontal spacing, etc., type and length of section steel 4, section size of connecting beam 6, concrete grade and reinforcement, etc. Then, the length of the rear row of piles 3 is determined according to the water-resistance and anti-seepage stability requirements of the foundation pit engineering and the calculated length of the section steel 4. The pile body strength of the rear row of piles 3 should meet the calculation requirements, and the permeability coefficient should meet the water stop requirements.

步骤二、根据拟建工程场地条件及周边环境条件,选择具体位置,用三轴水泥土搅拌桩机开始施工一段后排桩3的水泥土搅拌桩和一段浅层加固水泥土桩7,在该段已施工的后排桩3的水泥土搅拌桩凝结硬化前、三轴水泥土搅拌桩机移位施工下一段后排桩3的水泥土搅拌桩时,开始内插型钢4插入水泥土搅拌桩施工工序,内插型钢4插入水泥土搅拌桩施工工序在相应位置处的水泥土搅拌桩施工完成30分钟内开展,型钢露出的高度需满足上穿后排桩桩顶冠梁5以及拔出预留高度要求。 Step 2. Select a specific location according to the site conditions of the project to be built and the surrounding environmental conditions, and use a three-axis cement-soil mixing pile machine to start construction of a section of cement-soil mixing piles for the rear row of piles 3 and a section of shallow reinforced cement-soil piles 7. Before the cement-soil mixing pile of the rear row of piles 3 that has been constructed is solidified and hardened, when the three-axis cement-soil mixing pile machine is shifted to construct the cement-soil mixing pile of the next rear row of piles 3, the interpolated steel 4 is inserted into the cement-soil mixing pile The construction process, the construction process of inserting section steel 4 into the cement-soil mixing pile shall be carried out within 30 minutes after the construction of the cement-soil mixing pile at the corresponding position is completed. Stay height required.

步骤三、不断重复步骤二,直至按设计要求施工完成所有的后排桩3、内插型钢4和浅层加固水泥土桩7。 Step 3: Step 2 is repeated continuously until all rear row piles 3, interpolated section steel 4 and shallow reinforced cement-soil piles 7 are completed according to the design requirements.

步骤四、施工前排桩1、前排桩桩顶冠梁2、后排桩桩顶冠梁5和连系梁6。具体来说,施工前排桩1(前排桩1的桩顶主筋预留长度需满足锚固要求)的同时,随前排桩施工分步进行排桩桩顶冠梁2、后排桩桩顶冠梁5和连系梁6的施工,排桩桩顶冠梁2、后排桩桩顶冠梁5和连系梁6的施工过程是,先绑扎前排桩桩顶冠梁的钢筋、后排桩桩顶冠梁的的钢筋、以及连系梁的钢筋,然后进行混凝土整体浇注。 Step 4, construct the front row of piles 1, the front row of pile crown beams 2, the back row of pile crown beams 5 and the connecting beam 6. Specifically, while constructing the front row of piles 1 (the reserved length of the main reinforcement of the pile top of the front row of piles 1 needs to meet the anchorage requirements), at the same time as the construction of the front row of piles, the crown beam 2 of the row of piles and the pile top of the rear row of piles are carried out step by step. The construction of crown beam 5 and connecting beam 6, the construction process of row pile top crown beam 2, back row pile top crown beam 5 and connection beam 6 is to bind the reinforcing bar of front row pile top crown beam earlier, and then The steel bars of the top crown beam of the row piles and the steel bars of the connecting beam are then poured into concrete as a whole.

步骤五、待后排桩3满足抗渗要求时,开展基坑工程降水,待一种组合双排桩支护体系各部分均满足强度要求时,开展基坑土方开挖。 Step 5: When the rear row of piles 3 meets the anti-seepage requirements, the foundation pit engineering dewatering is carried out, and when all parts of a combined double-row pile support system meet the strength requirements, the foundation pit excavation is carried out.

步骤六、基坑开挖到设计深度后,开始地下结构施工。 Step 6: After the foundation pit is excavated to the design depth, the underground structure construction starts.

步骤七、地下结构施工出地坪,结构与基坑坑壁之间的空隙回填压实后,拔除内插型钢(即型钢水泥土搅拌桩墙中的型钢在使用完成后回收),内插型钢留下的空隙注浆封填。 Step 7: After the construction of the underground structure, the floor is removed, and the gap between the structure and the wall of the foundation pit is backfilled and compacted, and the inserted steel is removed (that is, the steel in the steel cement-soil mixing pile wall is recycled after use), and the inserted steel Fill the gap left by grouting.

本说明书实施例所述的内容仅仅是对本发明构思的实现形式的列举,本发明的保护范围不应当被视为仅限于实施例所陈述的具体形式,本发明的保护范围也及于本领域技术人员根据本发明构思所能够想到的等同技术手段。 The content described in the embodiments of this specification is only an enumeration of the implementation forms of the present invention, and the protection scope of the present invention should not be regarded as limited to the specific forms stated in the embodiments. Equivalent technical means that a person can think of based on the concept of the present invention.

Claims (9)

1.一种组合双排桩支护体系的施工方法,其中组合双排桩支护体系包括有前排桩(1)、前排桩桩顶冠梁(2)、后排桩(3)、后排桩桩顶冠梁(5)和连系梁(6),所述前排桩(1)为平行间隔设置的一排钢筋混凝土桩,所述后排桩(3)为型钢水泥土搅拌桩墙,所述连系梁(6)为双肢连系梁;所述型钢水泥土搅拌桩墙中的内插型钢(4)为H型钢,并且H型钢的上端部外露在后排桩桩顶冠梁(5)的上方;所述前排桩(1)与后排桩(3)之间还设有浅层加固水泥土桩(7),并且浅层加固水泥土桩(7)与型钢水泥土搅拌桩墙整体搭接连接在一起,其特征在于施工步骤如下: 1. A construction method for a combined double-row pile support system, wherein the combined double-row pile support system includes a front row of piles (1), a front row of pile crown beams (2), a rear row of piles (3), The rear row of pile crown beams (5) and connecting beams (6), the front row of piles (1) are a row of reinforced concrete piles arranged in parallel intervals, and the rear row of piles (3) are shaped steel cement soil mixing In the pile wall, the connecting beam (6) is a double-leg connecting beam; the inserted section steel (4) in the section steel cement-soil mixing pile wall is H-shaped steel, and the upper end of the H-shaped steel is exposed on the back row of piles The top of the crown beam (5); between the front row of piles (1) and the rear row of piles (3), there is also a shallow reinforced cement-soil pile (7), and the shallow reinforced cement-soil pile (7) and The steel-cement-soil mixing pile wall is integrally lapped and connected together, which is characterized in that the construction steps are as follows: 步骤一、根据拟建场地的水文地质条件、基坑工程几何参数、基坑工程隔水、抗渗稳定性要求,计算出施工一种组合双排桩支护体系所需要的各个技术参数; Step 1. According to the hydrogeological conditions of the proposed site, the geometric parameters of the foundation pit engineering, the water insulation of the foundation pit engineering, and the anti-seepage stability requirements, calculate the various technical parameters required for the construction of a combined double-row pile support system; 步骤二、根据拟建工程场地条件及周边环境条件,选择具体位置,用三轴水泥土搅拌桩机开始施工一段后排桩(3)的水泥土搅拌桩和一段浅层加固水泥土桩(7),在该段已施工的后排桩(3)的水泥土搅拌桩凝结硬化前、三轴水泥土搅拌桩机移位施工下一段后排桩(3)的水泥土搅拌桩时,开始内插型钢(4)插入水泥土搅拌桩施工工序,内插型钢(4)插入水泥土搅拌桩施工工序在相应位置处的水泥土搅拌桩施工完成30分钟内开展,型钢露出的高度需满足上穿后排桩桩顶冠梁(5)以及拔出预留高度要求; Step 2. According to the site conditions of the proposed project and the surrounding environmental conditions, select a specific location, and use a three-axis cement-soil mixing pile machine to start construction of a section of cement-soil mixing piles for the rear row of piles (3) and a section of shallow reinforced cement-soil piles (7 ), before the cement-soil mixing piles of the rear row of piles (3) that have been constructed in this section are solidified and hardened, and when the three-axis cement-soil mixing pile machine is shifted to construct the cement-soil mixing piles of the next row of piles (3), the internal The construction process of inserting steel (4) into the cement-soil mixing pile, and the construction process of inserting the steel (4) into the cement-soil mixing pile shall be carried out within 30 minutes after the construction of the cement-soil mixing pile at the corresponding position. Requirements for the top crown beam (5) of the rear row of piles and the reserved height for pulling out; 步骤三、不断重复步骤二,直至按设计要求施工完成所有的后排桩(3)、内插型钢(4)和浅层加固水泥土桩(7); Step 3: Repeat Step 2 continuously until all the rear row of piles (3), interpolated section steel (4) and shallow reinforced cement-soil piles (7) are completed according to the design requirements; 步骤四、施工前排桩(1)、前排桩桩顶冠梁(2)、后排桩桩顶冠梁(5)和连系梁(6); Step 4, constructing the front row of piles (1), the front row of pile crown beams (2), the back row of pile crown beams (5) and the connecting beams (6); 步骤五、待后排桩(3)满足抗渗要求时,开展基坑工程降水,待一种组合双排桩支护体系各部分均满足强度要求时,开展基坑土方开挖; Step 5. When the rear row of piles (3) meets the anti-seepage requirements, carry out the dewatering of the foundation pit engineering, and when all parts of a combined double-row pile support system meet the strength requirements, carry out the excavation of the foundation pit; 步骤六、基坑开挖到设计深度后,开始地下结构施工; Step 6: After the foundation pit is excavated to the design depth, the construction of the underground structure begins; 步骤七、地下结构施工出地坪,结构与基坑坑壁之间的空隙回填压实后,拔除内插型钢,内插型钢留下的空隙注浆封填。 Step 7: After the construction of the underground structure, the floor is removed, the gap between the structure and the wall of the foundation pit is backfilled and compacted, and the inserted section steel is removed, and the gap left by the inserted section steel is grouted and sealed. 2.根据权利要求1所述的一种组合双排桩支护体系的施工方法,其特征在于:所述浅层加固水泥土桩(7)由前排浅层加固水泥土桩(7.1)和后排浅层加固水泥土桩(7.2)两排桩组成,并且前排浅层加固水泥土桩与后排浅层加固水泥土桩(7.2)整体搭接连接在一起。 2. The construction method of a combined double-row pile support system according to claim 1, characterized in that: the shallow reinforced cement-soil pile (7) consists of the front row of shallow reinforced cement-soil piles (7.1) and The back row of shallow reinforced cement soil piles (7.2) consists of two rows of piles, and the front row of shallow reinforced cement soil piles and the rear row of shallow reinforced cement soil piles (7.2) are integrally connected together. 3.根据权利要求1所述的一种组合双排桩支护体系的施工方法,其特征在于:所述浅层加固水泥土桩(7)的桩间距与前排桩(1)的桩间距相同。 3. The construction method of a combined double-row pile support system according to claim 1, characterized in that: the pile spacing of the shallow reinforced cement-soil piles (7) and the pile spacing of the front row of piles (1) same. 4.根据权利要求1所述的一种组合双排桩支护体系的施工方法,其特征在于:所述型钢水泥土搅拌桩墙中的内插型钢(4)的间距是前排桩(1)的桩间距的一倍、两倍或三倍。 4. The construction method of a combined double-row pile support system according to claim 1, characterized in that: the distance between the interpolated steel (4) in the steel-cement-soil mixing pile wall is the same as that of the front row of piles (1 ) is one, two or three times the pile spacing. 5.根据权利要求1所述的一种组合双排桩支护体系的施工方法,其特征在于:所述H型钢的上端部上设有型钢起吊孔(8)。 5. The construction method of a combined double-row pile support system according to claim 1, characterized in that: the upper end of the H-shaped steel is provided with a steel lifting hole (8). 6.根据权利要求1所述的一种组合双排桩支护体系的施工方法,其特征在于:所述双肢连系梁的两肢之间的净距(a)为H型钢的翼缘宽度(b)加上60mm。 6. The construction method of a combined double-row pile support system according to claim 1, characterized in that: the clear distance (a) between the two limbs of the double-leg connecting beam is the flange of H-shaped steel Width (b) plus 60mm. 7.根据权利要求1所述的一种组合双排桩支护体系的施工方法,其特征在于:所述H型钢的上端部在冠梁上方的外露的长度为不小于500mm。 7. The construction method of a combined double-row pile support system according to claim 1, characterized in that: the exposed length of the upper end of the H-shaped steel above the crown beam is not less than 500mm. 8.根据权利要求1所述的一种组合双排桩支护体系的施工方法,其特征在于:所述前排桩(1)中的前排桩主筋在桩顶锚入到前排桩桩顶冠梁(2)中,并且锚固长度不小于1.5倍的受拉锚固长度。 8. The construction method of a combined double-row pile support system according to claim 1, characterized in that: the main reinforcement of the front row of piles in the front row of piles (1) is anchored into the front row of piles at the top of the pile In the crown beam (2), and the anchorage length is not less than 1.5 times the tensile anchorage length. 9.根据权利要求1所述的一种组合双排桩支护体系的施工方法,其特征在于:所述连系梁(6)中的纵向主筋锚入到前排桩桩顶冠梁(2)和后排桩桩顶冠梁(5)中,并且锚固长度不小于1.5倍的受拉锚固长度。 9. The construction method of a combined double-row pile support system according to claim 1, characterized in that: the longitudinal main reinforcement in the connecting beam (6) is anchored into the top crown beam (2 ) and the top crown beam (5) of the rear row of piles, and the anchorage length is not less than 1.5 times the tensile anchorage length.
CN201410033020.9A 2014-01-24 2014-01-24 A kind of construction method combining Double-row Piles Support system Expired - Fee Related CN103758134B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410033020.9A CN103758134B (en) 2014-01-24 2014-01-24 A kind of construction method combining Double-row Piles Support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410033020.9A CN103758134B (en) 2014-01-24 2014-01-24 A kind of construction method combining Double-row Piles Support system

Publications (2)

Publication Number Publication Date
CN103758134A CN103758134A (en) 2014-04-30
CN103758134B true CN103758134B (en) 2015-09-30

Family

ID=50525443

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410033020.9A Expired - Fee Related CN103758134B (en) 2014-01-24 2014-01-24 A kind of construction method combining Double-row Piles Support system

Country Status (1)

Country Link
CN (1) CN103758134B (en)

Families Citing this family (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104594360A (en) * 2014-12-31 2015-05-06 云南建工基础工程有限责任公司 Composite double-row pile foundation pit supporting structure
CN104762975B (en) * 2015-02-10 2016-05-25 云南建工基础工程有限责任公司 A kind of H type Double-row-piles Structure that adds core rotary churning pile that is provided with
CN104695446B (en) * 2015-03-13 2016-08-24 朱奎 Basement construction method for supporting
CN106087975B (en) * 2015-11-20 2020-09-22 上海市政工程设计研究总院(集团)有限公司 Pile top ring beam structure based on SMW (soil mixing wall) construction method and construction method thereof
CN105714831A (en) * 2016-02-03 2016-06-29 华侨大学 Abnormal-shape double-row pile for supporting foundation pit side wall and construction method of abnormal-shape double-row pile
CN105714830B (en) * 2016-02-03 2017-09-26 华侨大学 It is a kind of to be used for the connecting plate of special-shaped double-row pile
CN105755948A (en) * 2016-04-15 2016-07-13 上海市城市建设设计研究总院 Trestle structure combined with smw (soil mixing wall) working method enclosure
CN106284296B (en) * 2016-09-28 2019-04-23 南京工业大学 Supporting structure of double-row steel sheet piles and construction method thereof
CN107842026A (en) * 2017-12-01 2018-03-27 深圳大学 The foundation pit supporting construction and method that a kind of horizontal ground-connecting-wall mixes with double-row pile
CN109403347B (en) * 2018-11-26 2024-01-23 中建一局集团建设发展有限公司 A frame-type double-row pile cement-soil wall foundation pit enclosure structure and its construction method
CN109778867A (en) * 2018-12-28 2019-05-21 上海建工集团股份有限公司 A kind of self-supporting Composite Enclosure Structure and its construction method
CN110820763A (en) * 2019-11-29 2020-02-21 兰州理工大学 Truss type cast-in-situ bored pile supporting method for mucky soil deep foundation pit
CN111472348B (en) * 2020-04-23 2021-10-15 浙江大学医学院附属妇产科医院 Steel and concrete combined underground diaphragm wall structure and its construction method
CN112627188B (en) * 2020-12-04 2022-12-06 广东珠江工程总承包有限公司 Deep foundation pit supporting structure and construction method thereof
CN113152427A (en) * 2021-05-07 2021-07-23 深圳大学 Protection structure and method for adjacent underground pipeline of riprap reclamation sea area excavation project
CN113250204A (en) * 2021-06-03 2021-08-13 中交四航工程研究院有限公司 Steel pipe pile and cement mixing pile combined supporting structure and construction method thereof
CN113338304A (en) * 2021-06-28 2021-09-03 河北工业大学 HZ type foundation pit support structure combined with prestressed anchor cables and use method
CN113585277A (en) * 2021-07-08 2021-11-02 中建一局集团第五建筑有限公司 Complicated-terrain foundation pit supporting and connecting structure and construction method thereof
CN113605398B (en) * 2021-07-14 2023-04-07 广州市设计院集团有限公司 Foundation pit supporting mechanism
CN113404060A (en) * 2021-08-03 2021-09-17 建研地基基础工程有限责任公司 Rigid rib wall type pile wall foundation pit supporting structure and construction method
CN113718797A (en) * 2021-10-07 2021-11-30 南通大学 Double-row pile and multilayer composite three-dimensional fabric waterproof curtain integrated foundation pit supporting structure and construction method thereof
CN114108695B (en) * 2021-11-15 2023-02-03 中冶集团武汉勘察研究院有限公司 Assembled underground cylinder structure and construction method thereof
CN114960729A (en) * 2022-05-11 2022-08-30 浙江省钱塘江管理局勘测设计院 Method for improving fortification standard of existing vertical scour prevention structure of dike foot
CN114892712B (en) * 2022-06-22 2024-06-28 上海城建市政工程(集团)有限公司 Construction method of micro-disturbance assembled soil retaining structure
CN115182358A (en) * 2022-07-15 2022-10-14 中铁隧道集团三处有限公司 Microbial double-row pile foundation pit supporting structure
CN115045299B (en) * 2022-07-26 2024-02-02 杭州市西站枢纽开发有限公司 Deep foundation pit side wall reinforcing structure with electroosmosis drainage function and construction method
CN116950087A (en) * 2023-08-04 2023-10-27 广州科技职业技术大学 An unsupported combined deep foundation pit support structure
CN119221484A (en) * 2024-10-24 2024-12-31 上海建工四建集团有限公司 A multifunctional double-row pile support structure for water plants and its construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090029993A (en) * 2007-09-19 2009-03-24 주식회사 한미파슨스건축사사무소 Underground structure and underground structure construction method using soil wall supported by steel film action
CN201241327Y (en) * 2008-05-28 2009-05-20 天津大学建筑设计研究院 Section steel and soil cement composite double rows pile
CN202689008U (en) * 2012-06-11 2013-01-23 东南大学 Supporting structure for double-row prefabricated high-strength concrete thin-walled steel pipe pile foundation pit
CN202989937U (en) * 2012-12-05 2013-06-12 昆明理工大学 Grille-type double-row pile supporting structure
CN203729308U (en) * 2014-01-24 2014-07-23 中国建筑股份有限公司 Double-row pile supporting system of reinforced concrete pile combined structural steel cement mixing pile wall

Also Published As

Publication number Publication date
CN103758134A (en) 2014-04-30

Similar Documents

Publication Publication Date Title
CN103758134B (en) A kind of construction method combining Double-row Piles Support system
CN103774675B (en) Combined double-row-pile combined vertical prestress anchor rod supporting system and construction method thereof
CN203729308U (en) Double-row pile supporting system of reinforced concrete pile combined structural steel cement mixing pile wall
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN1837511B (en) A double-row cofferdam and its manufacturing method
CN205742213U (en) Foundation pit supporting construction
CN105525627B (en) A kind of two-way anchor fixed board retaining wall and its construction method
CN103898916B (en) Mini stake Composite Braced Retaining Structure and construction method
CN203905018U (en) Supporting and protecting system with combined double-row piles in combination with oblique anchors
CN103321246B (en) Construction Method of Foundation Pit Using Underground Diaphragm Wall
CN109457709A (en) A kind of supporting construction and construction method of double-row pile combination wide-angle anchor cable
CN107012871B (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction
CN110820732A (en) Cast-in-situ bored pile suitable for karst area with connectivity channel and pile forming method
CN109914422A (en) A kind of steel pipe and soil nail combined foundation pit supporting structure and construction method
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN206034454U (en) Supporting construction
CN203729309U (en) Support system with combined double-row piles combined with vertical prestressed anchor bolts
CN213571956U (en) Combined construction method pile supporting structure
CN205062820U (en) Double row pile supporting construction of stagnant water stake interpolation precast pile combination bored concrete pile
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN106120791A (en) Without making vertical supporting system underground structure covered back-digging construction method in advance
CN109538236A (en) A kind of tunnel structure and tunnel construction method
CN211285658U (en) Structure capable of carrying out deep water area hollowing repair in rapid stream state
CN110939139B (en) Pile-sheet wall structure and construction method based on rigid contact of special-shaped retaining wall behind piles

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150930

Termination date: 20200124

CF01 Termination of patent right due to non-payment of annual fee