CN205502024U - Arch combination envelope that can partially retrieve - Google Patents

Arch combination envelope that can partially retrieve Download PDF

Info

Publication number
CN205502024U
CN205502024U CN201620264152.7U CN201620264152U CN205502024U CN 205502024 U CN205502024 U CN 205502024U CN 201620264152 U CN201620264152 U CN 201620264152U CN 205502024 U CN205502024 U CN 205502024U
Authority
CN
China
Prior art keywords
pile
jet grouting
grouting pile
cast
situ bored
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620264152.7U
Other languages
Chinese (zh)
Inventor
程强强
陈年和
孙武
曹洪吉
周国庆
王磊
郭牡丹
王玮
赵志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jianzhu Institute
Original Assignee
Jiangsu Jianzhu Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jianzhu Institute filed Critical Jiangsu Jianzhu Institute
Priority to CN201620264152.7U priority Critical patent/CN205502024U/en
Application granted granted Critical
Publication of CN205502024U publication Critical patent/CN205502024U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides an arch combination envelope that can partially retrieve, includes a plurality of drilling bored concrete piles, a plurality of drilling bored concrete pile intervals set up the permutation formula that forms structure, be provided with between every two adjacent drilling bored concrete piles a plurality of mutual interlocks together, be the high pressure jet grouting pile that the arch was arranged, drilling bored concrete pile and the adjacent mutual interlock of high pressure jet grouting pile, insert H shaped steel in each high pressure jet grouting pile, inserted the steel reinforcement cage in each drilling bored concrete pile. Compared with the prior art, the utility model discloses with H shaped steel, high pressure jet grouting pile and drilling bored concrete pile effective combination, form the arch combining form, but the pressure of the effective resistance foundation ditch outside soil body, water, the stiffness is better, simultaneously, adjacent drilled pile and high pressure jet grouting pile, the mutual interlock of adjacent high pressure jet grouting pile, high pressure jet grouting pile interpolation H shaped steel have improved whole load -carrying properties, overall simple structure, and construction cost is lower, and the stiffness is big, sealing effect good, has ensured envelope's security performance.

Description

A kind of can be partially recycled arch combined enclosure structure
Technical field
This utility model relates to a kind of foundation pit enclosure structure, a kind of can be partially recycled arch combined enclosure structure, belong to base pit engineering technical field.
Background technology
At present, along with the minimizing of building site, underground space development is increasingly subject to people's attention, and the design of thing followed foundation pit enclosure, construction also get more and more.Traditional foundation pit enclosure structure is to design and construct according to the cross sectional shape of foundation ditch, the place general at some geological conditions, the excavation of foundation pit degree of depth is the biggest, use the building enclosure form of armored concrete material, such as diaphram wall form, drilling pouring stake stake form, interlocking pile form etc., they integral rigidities are relatively big, but construction cost is higher and speed of application is slower;Using the building enclosure form of soil mass consolidation, such as cement mixing method form, high-pressure rotary jet grouting pile form etc., they construction costs are relatively low, but integral rigidity is poor.
Summary of the invention
According to the deficiencies in the prior art, it is provided that a kind of can be partially recycled arch combined enclosure structure, improve building enclosure integral rigidity simultaneously, reduce cost, strengthen gear soil and stagnant water effect.
This utility model is realized by techniques below scheme:
A kind of can be partially recycled arch combined enclosure structure, including multiple cast-in-situ bored piles, multiple cast-in-situ bored piles interval arranges formation entire column type structure, be each provided with between the most adjacent two cast-in-situ bored piles multiple being mutually twisted together, the high-pressure rotary jet grouting pile of domed layout, described cast-in-situ bored pile is mutually twisted with adjacent high-pressure rotary jet grouting pile;Each high-pressure rotary jet grouting pile has been inserted into H profile steel, and each cast-in-situ bored pile has been inserted into steel reinforcement cage.
Preferably, the central spot of the plurality of cast-in-situ bored pile, on same level line, constitutes the edge line of foundation ditch.
Preferably, the diameter of section of described high-pressure rotary jet grouting pile is less than the diameter of section of cast-in-situ bored pile.
Preferably, the diameter of section of described high-pressure rotary jet grouting pile is less than 800mm.
Preferably, the diameter of section of described cast-in-situ bored pile is less than 1000mm.
Preferably, adjacent high-pressure rotary jet grouting pile is mutually twisted size not less than 50mm.
Preferably, cast-in-situ bored pile is mutually twisted size not less than 50mm with adjacent high-pressure rotary jet grouting pile.
Preferably, the length of described H profile steel and the length of steel reinforcement cage are equal.
This utility model beneficial effect:
Compared with prior art, this utility model, by H profile steel, high-pressure rotary jet grouting pile and cast-in-situ bored pile efficient combination, forms arch combining form, is effective against the pressure of the soil body outside foundation ditch, water body, and integral rigidity is preferable;Meanwhile, adjacent drilled pile and high-pressure rotary jet grouting pile, adjacent high-pressure rotary jet grouting pile are mutually twisted, high-pressure rotary jet grouting pile interpolation H profile steel, improve integrated carrying performance, population structure is simple, construction cost is relatively low, and integral rigidity is big, stagnant water effect good, it is ensured that the security performance of building enclosure.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is sequence of construction figure of the present utility model;
In figure: 1, high-pressure rotary jet grouting pile, 2, cast-in-situ bored pile, 3, H profile steel, 4, steel reinforcement cage.
Detailed description of the invention
Below in conjunction with accompanying drawing, by specific embodiment, this utility model is further described.
A kind of can be partially recycled arch combined enclosure structure, including multiple cast-in-situ bored piles 2, multiple cast-in-situ bored piles 2 interval arranges formation entire column type structure, the central spot of multiple cast-in-situ bored piles 2 is on same level line, constitute the edge line of foundation ditch, be each provided with between the most adjacent two cast-in-situ bored piles 2 multiple being mutually twisted together, the high-pressure rotary jet grouting pile 1 of domed layout, form arch combined enclosure structure, increase the integral rigidity of building enclosure
Adjacent high-pressure rotary jet grouting pile 1 is mutually twisted size not less than 50mm, increase the globality of building enclosure, improve gear soil, stagnant water effect, cast-in-situ bored pile 2 is mutually twisted with adjacent high-pressure rotary jet grouting pile 1, cast-in-situ bored pile 2 is mutually twisted size not less than 50mm with adjacent high-pressure rotary jet grouting pile 1, both are formed and are rigidly connected, the diameter of section of high-pressure rotary jet grouting pile 1 is less than the diameter of section of cast-in-situ bored pile 2, the diameter of section of high-pressure rotary jet grouting pile 1 is less than 800mm, and the diameter of section of cast-in-situ bored pile 2 is less than 1000mm;Each high-pressure rotary jet grouting pile 1 has been inserted into H profile steel 3, and each cast-in-situ bored pile 2 has been inserted into steel reinforcement cage 4, and the length of H profile steel 3 is equal with the length of steel reinforcement cage 4.
This utility model can be partially recycled arch combined enclosure structure construction order: arcuate arc top high-pressure rotary jet grouting pile 1 is constructed---insert the adjacent high-pressure rotary jet grouting pile of H profile steel 3---1 construct---inserts H profile steel 3---cast-in-situ bored pile 2 and constructs, accompanying drawing 2 is shown in Specific construction technological process, construct again after the H profile steel 3 that is required for constructing timely after it is pointed out that the construction of each high-pressure rotary jet grouting pile 1 next root high-pressure rotary jet grouting pile 1.
------------------supply water supply, and---------H profile steel 3 is inserted in swing lifting---pile---to grout to jet groutinl to stirring pulping to lower playpipe to this utility model Construction Technique of High Pressure Revolving Spraying flow process: surveying setting-out to measure hole depth in rig pore-creating to determine position, hole.
This utility model, by H profile steel 3, high-pressure rotary jet grouting pile 1 and cast-in-situ bored pile 2 efficient combination, forms arch combining form, is effective against the pressure of the soil body outside foundation ditch, water body, and integral rigidity is preferable;Meanwhile, adjacent cast-in-situ bored pile 2 and high-pressure rotary jet grouting pile 1, adjacent high-pressure rotary jet grouting pile 1 are mutually twisted, high-pressure rotary jet grouting pile 1 interpolation H profile steel 3, improve integrated carrying performance, population structure is simple, construction cost is relatively low, and integral rigidity is big, stagnant water effect good, it is ensured that the security performance of building enclosure.

Claims (8)

1. one kind can be partially recycled arch combined enclosure structure, including multiple cast-in-situ bored piles (2), it is characterized in that: multiple cast-in-situ bored piles (2) interval arranges formation entire column type structure, be each provided with between the most adjacent two cast-in-situ bored piles (2) multiple being mutually twisted together, the high-pressure rotary jet grouting pile (1) of domed layout, described cast-in-situ bored pile (2) is mutually twisted with adjacent high-pressure rotary jet grouting pile (1);
Each high-pressure rotary jet grouting pile (1) has been inserted into H profile steel (3), and each cast-in-situ bored pile (2) has been inserted into steel reinforcement cage (4).
The most according to claim 1 a kind of can be partially recycled arch combined enclosure structure, it is characterised in that: the central spot of the plurality of cast-in-situ bored pile (2) on same level line, constitute foundation ditch edge line.
The most according to claim 1 a kind of can be partially recycled arch combined enclosure structure, it is characterised in that: the diameter of section of described high-pressure rotary jet grouting pile (1) is less than the diameter of section of cast-in-situ bored pile (2).
The most according to claim 3 a kind of can be partially recycled arch combined enclosure structure, it is characterised in that: the diameter of section of described high-pressure rotary jet grouting pile (1) be less than 800mm.
The most according to claim 3 a kind of can be partially recycled arch combined enclosure structure, it is characterised in that:
The diameter of section of described cast-in-situ bored pile (2) is less than 1000mm.
The most according to claim 1 a kind of can be partially recycled arch combined enclosure structure, it is characterised in that: adjacent high-pressure rotary jet grouting pile (1) is mutually twisted size not less than 50mm.
The most according to claim 1 a kind of can be partially recycled arch combined enclosure structure, it is characterised in that: cast-in-situ bored pile (2) is mutually twisted size not less than 50mm with adjacent high-pressure rotary jet grouting pile (1).
The most according to claim 1 a kind of can be partially recycled arch combined enclosure structure, it is characterised in that: the length of described H profile steel (3) is equal with the length of steel reinforcement cage (4).
CN201620264152.7U 2016-04-01 2016-04-01 Arch combination envelope that can partially retrieve Expired - Fee Related CN205502024U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620264152.7U CN205502024U (en) 2016-04-01 2016-04-01 Arch combination envelope that can partially retrieve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620264152.7U CN205502024U (en) 2016-04-01 2016-04-01 Arch combination envelope that can partially retrieve

Publications (1)

Publication Number Publication Date
CN205502024U true CN205502024U (en) 2016-08-24

Family

ID=56734448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620264152.7U Expired - Fee Related CN205502024U (en) 2016-04-01 2016-04-01 Arch combination envelope that can partially retrieve

Country Status (1)

Country Link
CN (1) CN205502024U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059881A (en) * 2017-04-12 2017-08-18 广东省基础工程集团有限公司 The foundation pit supporting method that a kind of campshed is combined with steel sheet pile
CN108824451A (en) * 2018-08-29 2018-11-16 武岳 Tunnel immediately adjacent to bridge section deep foundation pit supporting structure and construction method
CN110158649A (en) * 2019-06-05 2019-08-23 浙江交工集团股份有限公司 The construction method of Adjacent Underground Pipeline when a kind of caisson sinking construction
CN110206041A (en) * 2019-06-17 2019-09-06 中国十七冶集团有限公司 A kind of multi-arch type fashioned iron cement-soil pile and construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059881A (en) * 2017-04-12 2017-08-18 广东省基础工程集团有限公司 The foundation pit supporting method that a kind of campshed is combined with steel sheet pile
CN108824451A (en) * 2018-08-29 2018-11-16 武岳 Tunnel immediately adjacent to bridge section deep foundation pit supporting structure and construction method
CN108824451B (en) * 2018-08-29 2019-09-03 武岳 Tunnel immediately adjacent to bridge section deep foundation pit supporting structure and construction method
CN110158649A (en) * 2019-06-05 2019-08-23 浙江交工集团股份有限公司 The construction method of Adjacent Underground Pipeline when a kind of caisson sinking construction
CN110206041A (en) * 2019-06-17 2019-09-06 中国十七冶集团有限公司 A kind of multi-arch type fashioned iron cement-soil pile and construction method

Similar Documents

Publication Publication Date Title
CN205502024U (en) Arch combination envelope that can partially retrieve
CN103924602B (en) Deep Thick Soft Ground foundation ditch construction method
CN101560765A (en) Underground continuous wall construction technique of multi-spindle long spiral drill pipe occluding pile
CN101725155A (en) Multi-direction rotary jetting stirring grouting reinforcement construction method for constructing underground structure and soil body by cover excavation and underground excavation and supporting structure thereof
CN203684230U (en) Prefabricated double-row pile structure
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN204738302U (en) Multi -storey frame formula double row pile supporting construction
CN201321616Y (en) Deep foundation pit supporting, reinforcing, anti-seepage and waterproof structure
CN104863132A (en) Bougainvillea spectabilis willd-shaped cement-soil mixing pile and shaping method thereof
CN102888848A (en) Supporting structure for controlling stability of foundation ditch
CN203238642U (en) Supporting retaining wall of foundation pit
CN101139834A (en) Concrete pile structure
CN204491591U (en) A kind of triaxial cement mixing pile pile-forming equipment
CN102220764B (en) Construction method of deep foundation pit bracing system
CN203866852U (en) Anti-floating pile structure composited by deep spiral-spraying cement soil plate and anchor rod
CN108729457A (en) A kind of steel pipe pile cofferdam and its construction method for bridge deepwater foundation
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN201459708U (en) Rotatable multi-shaft drill hole irrigation concrete occlusion guard post wall
CN202830938U (en) Supporting structure for controlling foundation trench stability
CN105350544A (en) Waterproof curtain used for stone-contained area and construction method thereof
CN206015511U (en) One implant post steel pipe column
CN202139604U (en) Cast-in-situ abnormal reinforced concrete pile core cement soil underground continuous wall for retaining and protection for foundation excavation
CN206034430U (en) Single pile reducing inlays rock secant pile
CN103726673A (en) Novel after-rooting composite pile foundation
CN204401602U (en) A kind of rigid-flexible composite support water stop RCP stake

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160824

Termination date: 20170401

CF01 Termination of patent right due to non-payment of annual fee