CN206128656U - A instrument for transporting installation roof boarding - Google Patents
A instrument for transporting installation roof boarding Download PDFInfo
- Publication number
- CN206128656U CN206128656U CN201620773711.7U CN201620773711U CN206128656U CN 206128656 U CN206128656 U CN 206128656U CN 201620773711 U CN201620773711 U CN 201620773711U CN 206128656 U CN206128656 U CN 206128656U
- Authority
- CN
- China
- Prior art keywords
- vertical rod
- bearing
- instrument
- cross bar
- roof boarding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Problem to the roof boarding installation, the utility model provides an instrument for transporting installation roof boarding which comprises support, wheel, pole setting, bracing, horizontal pole and the jack. Wherein, be equipped with the wheel in the bottom of support. Top at the support is equipped with the pole setting. Be equipped with the bracing between 1 in pole setting and support. Top in the pole setting is equipped with the horizontal pole. One end at the horizontal pole is equipped with the jack. Be used for lifting by crane building material through the jack. Profitable technological effect: the utility model discloses stable in structure simple and practical, easily dismantlement, convenient to use, reduce installer labour simultaneously, reduced the safe risk scheduling problem in the installer installation.
Description
Technical field
The utility model belongs to Architectural Equipment technical field, and in particular to for the instrument that roof boarding is installed in transport.
Background technology
With the fast development of urban track traffic, newly-built a large amount of rolling stock sections make regular check on maintenance for train, due to car
Section area is larger, and light-duty swollen masonry building panel is adopted building roof more, because it has design, application, installs and compare easily
Feature and it is applied widely the characteristics of, therefore suffer from the popular welcome of building field.
But, at present conventional roof boarding hanging method is:Roof boarding is lifted to installation roofing using crane
On, then to be transported to mount point using flat car or small handcart, then a dead lift installation, its defect mainly has following side
Face:
1st, lift to roofing, need manually to carry out being carried on flat car or small handcart, roof boarding is weighed about per block
300kg, needs 4 workers carries, lavishes labor on.
2nd, need manually to unload to mount point to designated mounting point in transport, workman needs to stand on girder steel, exists larger
Security risk.
3rd, in installation process, need to adjust roof boarding installation site, using manual adjustment, more difficultly, and exist larger
Security risk.
Utility model content
For the problems referred to above, the utility model provides the instrument for installing roof boarding for transport, by the utility model, carries
High installation personnel transport material, mounting material efficiency in roof boarding installation process, and increase installation personnel safety guarantee.This
Utility model is specific as follows:
For transporting the instrument for installing roof boarding, including bearing 1, wheel 2, vertical rod 3, diagonal brace 4, cross bar 5 and jack 6.Its
In,
Wheel 2 is provided with the bottom of bearing 1.
Vertical rod 3 is provided with the top of bearing 1.Diagonal brace 4 is provided between vertical rod 3 and bearing 1.
Cross bar 5 is provided with the top of vertical rod 3.Jack 6 is provided with one end of cross bar 5.It is used to lift by crane Building wood by jack 6
Material 8.
Beneficial technique effect
The utility model Stability Analysis of Structures is simple and practical, be readily disassembled, it is easy to use, while reducing installation personnel work
Power, reduce installation personnel installation process in security risk the problems such as.
1st, Stability Analysis of Structures of the present utility model, fastness is strong, and has certain gravity energy to prevent from toppling.
2nd, after using the utility model, installation personnel can be lifted by crane in work progress all of machinery, save big
Amount labour.
3rd, in traditional installation process, non-installation region only has girder steel, is unfavorable for that installation personnel is stood and operated, this reality
With it is new roof boarding can be mounted directly in place after, workmen goes forward to be operated again, reduce installation personnel during peace
Full blast danger.
Description of the drawings
Fig. 1 is schematic perspective view of the present utility model.
Fig. 2 is the front view of Fig. 1.
Fig. 3 is the left view of Fig. 1.
Fig. 4 is the structural representation of bearing 1 in FIG.
Fig. 5 is to be provided with the schematic diagram of guide rail 9 in the bottom of structure shown in Fig. 2.
Specific embodiment
Design feature of the present utility model is described in detail in conjunction with accompanying drawing.
Referring to Fig. 1,2 and 3, for transporting the instrument for installing roof boarding, including bearing 1, wheel 2, vertical rod 3, diagonal brace 4, horizontal stroke
Bar 5 and jack 6.Wherein,
Wheel 2 is provided with the bottom of bearing 1.
Vertical rod 3 is provided with the top of bearing 1.Diagonal brace 4 is provided between vertical rod 3 and bearing 1.
Cross bar 5 is provided with the top of vertical rod 3.Jack 6 is provided with one end of cross bar 5.It is used to lift by crane Building wood by jack 6
Material 8.
Referring to Fig. 1 and 4, furtherly, bearing 1 is rectangular.Reinforcement is provided with the bearing 1 of rectangle.The four of bearing 1
Angle is respectively equipped with a wheel 2.The wheel 2 is simple wheels or the wheel with turning to.
Referring to Fig. 1 to 3, furtherly, three vertical rods 3 are provided with bearing 1.Three vertical rods 3 are along arranged in a straight line.
Referring to Fig. 1 and 2, furtherly, the length of three vertical rods 3 is successively decreased one by one, and the top of three vertical rods 3 is conllinear.
Referring to Fig. 1 and 4, furtherly, the length of cross bar 5 is more than 2 times of the length of bearing 1.Prolong at the two ends of cross bar 5
The outside of bearing 1 is extended, as shown in Fig. 1,2,4 and 5.
Referring to Fig. 1,2 and 4, furtherly, set between the shaft of cross bar 5 near jack 6 and the vertical rod 3 near jack 6
There is knighthead 7.
Furtherly, bearing 1 is welded by 10# channel-section steels.The material of vertical rod 3 is 10# channel-section steels.Cross bar 5 is coating steel pipe.
Referring to Fig. 1 and 4, furtherly, bearing 1 is " mouth " the character form structure part being made up of 4 channel-section steels.
Reinforcement is provided between an opposite side of bearing 1.
A vertical rod is respectively provided with being respectively arranged at the two ends with place of a vertical rod 3, i.e. reinforcement are connected with bearing 1 for reinforcement
3, a vertical rod 3 is provided with the shaft of reinforcement.The vertical rod 3 is perpendicular with bearing 1.
The length of three vertical rods 3 is successively decreased one by one, and the top of three vertical rods 3 is conllinear.According to the length of vertical rod 3 successively decrease it is suitable
Sequence, three vertical rods 3 are referred to as successively the first vertical rod, the second vertical rod, the 3rd vertical rod.Order is this instrument near the side of the first vertical rod
Front end, near the 3rd vertical rod side be this instrument tail end.That is the first vertical rod is arranged on one end of reinforcement, the 3rd vertical rod
It is arranged on the other end of reinforcement.The second vertical rod is provided with the middle of the shaft of reinforcement.
The top of three vertical rods 3 is connected with the shaft of cross bar 5 jointly.The two ends of cross bar 5 all extend to the outer of bearing 1
Portion.
Knighthead 7 is provided between the shaft of cross bar 5 near jack 6 and the first vertical rod.
Furtherly, the four edges and reinforcement of bearing 1 are 10# channel-section steels.First vertical rod, the second vertical rod, the 3rd vertical rod
It is 10# channel-section steels.Cross bar 5 is coating steel pipe.
Referring to Fig. 1 and 2, furtherly, the side for remembering the bearing 1 being connected with the first vertical rod is front channel-section steel, with the 3rd vertical rod phase
The side of bearing 1 even is rear channel-section steel, then:A diagonal brace 4 is respectively provided between the two ends of front channel-section steel and the first vertical rod, it is vertical first
A diagonal brace 4 is provided between bar and reinforcement.A diagonal brace 4 is respectively provided between the two ends of rear channel-section steel and the 3rd vertical rod,
A diagonal brace 4 is provided between three vertical rods and reinforcement.
Furtherly, bearing 1 is the square frame that the length of side is 1.5m.The length of the first vertical rod is 1.3m, and the 3rd vertical rod 3 is
1.1m.The length of cross bar 5 is more than 6 meters.That is the length of cross bar 5 is longer than the length of bearing 1, by manually pushing down cross bar 5
Tail end, it is ensured that this instrument will not topple in handling roof boarding.
It is indeflectible wheel, as directional wheel positioned at 2 wheels 2 of this front tool.Positioned at the 2 of this instrument rear end
Individual wheel 2 is the wheel with turning to.
Referring to Fig. 5, furtherly, in the lower section near wheel 2 guide rail 9 is lined with.The guide rail 9 is channel-section steel or bamboo springboard.
Guide rail 9 is straight line or curve.Adopting the one side of guide rail 9 carries out guiding during handling for this instrument, it is ensured that workmen firmly carries out
Direction towards correct handling direction.On the other hand, using guide rail 9 this instrument of handling roof boarding can be avoided from not weighing wounded
The roof boarding completed, it is ensured that using safety.
Claims (10)
1. the instrument that roof boarding is installed in transport is used for, it is characterised in that including bearing (1), wheel (2), vertical rod (3), diagonal brace
(4), cross bar (5) and jack (6);Wherein, it is provided with wheel (2) in the bottom of bearing (1);Vertical rod is provided with the top of bearing (1)
(3);Diagonal brace (4) is provided between vertical rod (3) and bearing (1);Cross bar (5) is provided with the top of vertical rod (3);In cross bar (5)
One end is provided with jack (6).
2. it is according to claim 1 for transport install roof boarding instrument, it is characterised in that bearing (1) is rectangular;
Reinforcement is provided with the bearing (1) of rectangle;A wheel (2) is respectively equipped with the corner of bearing (1);It is provided with bearing (1)
Three vertical rods (3);Three vertical rods (3) are along arranged in a straight line.
3. it is according to claim 2 for transport install roof boarding instrument, it is characterised in that the length of three vertical rods (3)
Degree successively decreases one by one, and the top of three vertical rods (3) is conllinear.
4. the instrument that roof boarding is installed for transport according to claim 1, it is characterised in that the length of cross bar (5) is
More than 2 times of the length of bearing (1);The two ends of cross bar (5) all extend to the outside of bearing (1).
5. the instrument that roof boarding is installed for transport according to claim 1, it is characterised in that near jack (6)
Cross bar (5) shaft is provided with knighthead (7) between the vertical rod (3) of jack (6).
6. it is according to claim 1 for transport install roof boarding instrument, it is characterised in that bearing (1) is by 10# channel-section steels
It is welded;The material of vertical rod (3) is 10# channel-section steels;Cross bar (5) is coating steel pipe.
7. it is according to claim 1 for transport install roof boarding instrument, it is characterised in that bearing (1) is by 4 grooves
" mouth " character form structure part that steel is constituted;Reinforcement is provided between an opposite side of bearing (1);One is respectively arranged at the two ends with reinforcement
Root vertical rod (3), is provided with a vertical rod (3) on reinforcement;The vertical rod (3) is perpendicular with bearing (1);
The length of three vertical rods (3) is successively decreased one by one, and the top of three vertical rods (3) is conllinear;According to vertical rod (3) length successively decrease it is suitable
Sequence, three vertical rods (3) are referred to as successively the first vertical rod, the second vertical rod, the 3rd vertical rod;Order is this work near the side of the first vertical rod
The front end of tool, near the tail end that the side of the 3rd vertical rod is this instrument;The top of three vertical rods (3) jointly with the bar of cross bar (5)
Body is connected;The two ends of cross bar (5) all extend to the outside of bearing (1);
Knighthead (7) is provided between cross bar (5) shaft near jack (6) and the first vertical rod.
8. it is according to claim 7 for transport install roof boarding instrument, it is characterised in that the four edges of bearing (1),
And reinforcement is 10# channel-section steels;First vertical rod, the second vertical rod, the 3rd vertical rod are 10# channel-section steels;Cross bar (5) is coating steel pipe;
The side of the bearing (1) that note is connected with the first vertical rod is front channel-section steel, and the side of the bearing (1) being connected with the 3rd vertical rod is pit
Steel, then:A diagonal brace (4) is respectively provided between the two ends of front channel-section steel and the first vertical rod, is set between the first vertical rod and reinforcement
There is a diagonal brace (4);A diagonal brace (4) is respectively provided between the two ends of rear channel-section steel and the 3rd vertical rod, in the 3rd vertical rod and reinforcement
A diagonal brace (4) is provided between muscle.
9. the instrument that roof boarding is installed for transport according to claim 7, it is characterised in that bearing (1) is for the length of side
The square frame of 1.5m;The length of the first vertical rod is 1.3m, and the 3rd vertical rod (3) is 1.1m;The length of cross bar (5) is more than 6 meters;
2 wheels (2) positioned at this front tool are indeflectible wheel;2 wheels (2) positioned at this instrument rear end are band
The wheel of steering.
10. the instrument for installing roof boarding for transport according to claim 1 or 7, it is characterised in that near wheel
(2) guide rail (9) is lined with below;The guide rail (9) is channel-section steel or bamboo springboard.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620773711.7U CN206128656U (en) | 2016-07-21 | 2016-07-21 | A instrument for transporting installation roof boarding |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620773711.7U CN206128656U (en) | 2016-07-21 | 2016-07-21 | A instrument for transporting installation roof boarding |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206128656U true CN206128656U (en) | 2017-04-26 |
Family
ID=58562609
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620773711.7U Withdrawn - After Issue CN206128656U (en) | 2016-07-21 | 2016-07-21 | A instrument for transporting installation roof boarding |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206128656U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106437047A (en) * | 2016-07-21 | 2017-02-22 | 中铁四局集团建筑工程有限公司 | Plant roof panel transporting and mounting equipment |
-
2016
- 2016-07-21 CN CN201620773711.7U patent/CN206128656U/en not_active Withdrawn - After Issue
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106437047A (en) * | 2016-07-21 | 2017-02-22 | 中铁四局集团建筑工程有限公司 | Plant roof panel transporting and mounting equipment |
CN106437047B (en) * | 2016-07-21 | 2018-10-09 | 中铁四局集团建筑工程有限公司 | A kind of equipment transported for factory building roof plate with installing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103711301A (en) | Construction method and device for two-track movable electric basket and lifting hoist | |
CN102080384B (en) | Construction method for mounting lifter on top plate of underground parking garage | |
CN212079327U (en) | Hydraulic pressure regulation formula side wall template platform truck | |
CN103485574B (en) | A kind of granulation tower tower top structure of reinforced concrete method | |
CN206128656U (en) | A instrument for transporting installation roof boarding | |
CN106437047B (en) | A kind of equipment transported for factory building roof plate with installing | |
CN203247031U (en) | Hoisting device for curtain board transporting | |
CN107386119A (en) | A kind of variable cross-section beam sections type variable framework of steel reinforcement construction moulding bed device | |
CN201908665U (en) | Movable variable-cross section lining trolley | |
CN102777050A (en) | Assembly type jig frame for longspan pipe truss roof girder | |
CN106351431B (en) | The mobile working platform that can continuously construct for rail tunnel | |
CN210737374U (en) | Bridge deck concrete pavement construction platform | |
CN209889693U (en) | Combined steel pipe transportation tool | |
CN208266915U (en) | Underground pipe gallery overall movement full hall scaffold | |
CN206799012U (en) | A kind of concrete batten transport of small space and installation tool group | |
CN204873485U (en) | River course is bridge crane usefulness walking portal frame for pier | |
CN105089294B (en) | A kind of H profile steel beam form bracing structure | |
CN209942078U (en) | Large-span even strides factory building roof boarding installation dolly | |
CN210598156U (en) | Steel shotcrete demolishs auxiliary device | |
CN208023608U (en) | A kind of post-cast strip can have enough to meet the need steel channel formwork system | |
CN202047828U (en) | Movable and light-weight trolley formwork base plate system | |
CN202001022U (en) | Movable lining arch center formwork | |
CN114215339A (en) | Tool type ultrahigh-structure hanging basket suspension mechanism installation method | |
CN206843953U (en) | Sizing auxiliary construction platform in a kind of high-speed railway pier | |
CN207277893U (en) | A kind of section steel platform formwork erecting structure for high-altitude overhanging |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20170426 Effective date of abandoning: 20181009 |