- Prior art keywords
- pile
- drilling rod
- drilling
- drill bushing
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The utility model belongs to the technical field of construction basis drilling tool is used, specifically disclose a novel long spiral drilling filling pile pile jacking cap integrated construction device, including automatic walking car, and the power distribution control chamber of setting on automatic walking car, three -doors head pulley, machine and support are raised to main the commentaries on classics, and both ends difference linking bridge's frame bracing piece, and the for sleeping in first saddle of setting on the support, reach the power transmission box of being connected with the first saddle that crouches, reach the drilling rod of being connected with the power transmission box, and the drilling rod blade of setting on the drilling rod, and the drill bushing of setting at drilling rod blade end, wherein, the inside screwed connection groove that is provided with of drill bushing, and the one side and the supports active connections of drill bushing, and the alloy bit of setting at the drilling rod tip. The utility model discloses, solve current long auger drilling inefficiency and overall structure unstability and prestressing force and do not reached the problem that production construction required, its reasonable in design, satisfied the construction standard requirement, can quick, high -quality messengers pile body, the shaping that can unify of pile cover concrete, saving raw and other materials, reduction in production cost.
Description
Technical field
The utility model belongs to construction basis drilling tool applied technical field, and in particular to a kind of new long auger
Bored concrete pile pile jacking cap integrative construction device, quick, high-quality can enable pile body, pile cover concrete integrated molding.
Background technology
Long-spiral drilling machine, it includes hydraulic moving mechanism pile frame and drilling system two parts.Pile frame adopts hydraulic walking chassis,
High degree of automation, can voluntarily walk and 360 degree revolution, be provided with four hydraulic legs and one walking oil cylinder with aid in walking and
Revolution increases complete machine stability during construction simultaneously, can whole machine be transported through.Column is folding box column, and flange connects
Mode, column is using two pieces high thickness masks and uses large-sized bender brake techniques, and Jing twice weld seams are welded simultaneously vertical
Four reinforcements are welded with inside post every 60cm to fix, increase column torsion resistant and bending resistant.Column is by two luffing hydraulic jack controls
Make its landing.Drilling system includes unit head and drilling tool, and output shaft and the spiral drill of unit head are hollow type, and stake machine is adopted
Long spire pore-forming, can carry out pump concrete CFG pile driving constructions by drilling rod central tube by concrete or mud.
Existing structure designs long-spiral drilling machine, although it can complete the pile body of conventional need, the life of pile cover concrete formation
Construction requirement is produced, but pile body can not be realized, the production that the production and construction requirement of pile cover concrete integrated molding is i.e. current is applied
Work separately to complete low time-consuming efficiency and integrally-built stability and prestressing force do not reach production and construction requirement, while existing
Mixed mud raw materials consumption is larger in construction operation, increased production cost, and this is current urgently to be resolved hurrily.
Therefore, based on the problems referred to above, the utility model provides a kind of new long screw auger drilling deposited pile pile jacking cap integration
Constructing device.
Utility model content
Utility model purpose:The purpose of this utility model is to provide a kind of new long screw auger drilling deposited pile pile jacking cap one
Change constructing device, the existing long screw auger engine efficiency of solution is low and overall structure unstability and prestressing force do not reach production and construction
The problem of requirement, its is reasonable in design, meet construction reference requirement, quick, high-quality can enable pile body, pile cover concrete integrally
Chemical conversion type, has saved raw material, has reduced production cost.
Technical scheme:The utility model provides a kind of new long screw auger drilling deposited pile pile jacking cap integrative construction device,
Including automatic walking car, and the electric distribution operating room on automatic walking car, three head pulleys are arranged on, and are arranged on certainly
Main turning hoisting machine on dynamic walking car and between electric distribution operating room, three head pulleys, and it is arranged on automatic walking
Car and the support on the outside of three head pulleys, and the frame support bar of two ends difference connecting bracket, and be arranged on support
Sleeping head saddle, and the power transmission casing being connected with sleeping head saddle, and the drilling rod being connected with power transmission casing, and it is arranged on brill
Drilling rod blade on bar, and the drill bushing of drilling rod blade tip is arranged on, wherein, drill bushing is internally provided with spiral link slot, and bores
The side of set is flexibly connected with support, and is arranged on the alloy bit of drill rod end.
The technical program, the support is barrel-type supporting structure.
The technical program, the power transmission casing is double-motor power transmission case body and power is 55KW.
The technical program, the drilling rod blade, the diameter of drill bushing are respectively 500mm, 1000mm.
Compared with prior art, a kind of new long screw auger drilling deposited pile pile jacking cap integrative construction device of the utility model
Beneficial effect be:1st, overall construction design rationally, controls construction operation safety and construction quality is stable;2nd, solve existing
Long screw auger engine efficiency is low and overall structure unstability and prestressing force do not reach the problem of production and construction requirement, and its design is closed
Manage, meet construction reference requirement, quick, high-quality can enable pile body, pile cover concrete integrated molding, saved former material
Material, reduction production cost(This integrated apparatus is practical in the construction of deep cyclopentadienyl railway).
Description of the drawings
Fig. 1 is that a kind of structure of new long screw auger drilling deposited pile pile jacking cap integrative construction device of the present utility model is shown
It is intended to;
Fig. 2 is a kind of drilling rod leaf of new long screw auger drilling deposited pile pile jacking cap integrative construction device of the present utility model
The partial enlargement structural representation of piece, drill bushing;
Fig. 3 is a kind of construction stream of new long screw auger drilling deposited pile pile jacking cap integrative construction device of the present utility model
Journey flow diagram;
Wherein, sequence number mark is as follows in figure:The automatic walking cars of 1-, 2- electric distribution operating rooms, the main turning hoisting machines of 3-, 4- tri-
The sleeping head saddle of door head pulley, 5- supports, 6- frame support bars, 7-, 8- power transmission casings, 9- drilling rods, 10- drilling rod blades, 11-
Spiral link slot, 12- alloy bits, 13- drill bushings.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment, the utility model is further elucidated.
As shown in Figure 1, Figure 2 with a kind of new long screw auger drilling deposited pile pile jacking cap integrative construction device shown in Fig. 3, bag
Automatic walking car 1, and 2, the three head pulleys 4 of electric distribution operating room being arranged on automatic walking car 1 are included, and is arranged on
Automatically the main turning hoisting machine 3 on walking car 1 and between 2, three head pulleys 4 of electric distribution operating room, and be arranged on automatically
Walking car 1 and the support 5 on the outside of three head pulleys 4, and the frame support bar 6 of two ends difference connecting bracket 5, and arrange
Sleeping head saddle 7 on support 5, and the power transmission casing 8 being connected with sleeping head saddle 7, and be connected with power transmission casing 8
Drilling rod 9, and the drilling rod blade 10 being arranged on drilling rod 9, and the drill bushing 13 of the end of drilling rod blade 10 is arranged on, wherein, drill bushing 13
Spiral link slot 11 is internally provided with, and the side of drill bushing 13 is flexibly connected with support 5(It is provided between drill bushing and support mutually
Slide plate, the chute for using cooperatively, does not mark in figure), and the alloy bit 12 for being arranged on the end of drilling rod 9.
It is further preferred that support 5 is barrel-type supporting structure, its positioning support it is firm stable and be easily installed dismounting,
Safeguard;Power transmission casing 8 is 55KW for the power of double-motor power transmission case body and power transmission casing 8, for drilling rod 9
There is provided sufficient power support, it is ensured that can drive the drilling rod 9 of multiple different-diameter sizes carries out efficient construction operation;Drilling rod leaf
Piece 10, the diameter of drill bushing 13 are respectively 500mm, 1000mm, wherein, during construction operation, the spiral link slot of the inner surface of drill bushing 13
11 are used to support the protection i.e. joint face of the two to be helical structure connection the formation of drilling rod blade 10, can guarantee that drilling rod blade 10 exists
Do not incline in construction operation so that drilling meets construction requirement, and controls along counter-rotating stable, accurate.
Embodiment
Further as shown in Figure 1, Figure 2 and Figure 3, when alloy bit 12 creeps into when drill-pouring is constructed, drill bit position peace
Dress enlarged footing drilling tool(Enlarged footing drilling tool is not marked in figure),(Stake diameter can be with 80cm, it is also possible to 1m, straight with job site pile cover
Depending on footpath), the general depth of enlarged footing drilling tool is 60cm, and enlarged footing is partially into after soil layer 60cm, can automatically disengage drilling rod, enlarged footing
Drilling tool rests on 60cm depth soil layers position, makes drilling rod continue to creep into designing pile length position, is lifted and fills concrete, mentions on drilling rod
Top 60cm positions, then take enlarged footing drilling tool and up carry together, and make the 1m diameters of enlarged footing drilling tool fill concrete together,
Reach pile body, pile cover concrete energy integrated molding.
The above is only preferred embodiment of the present utility model, it is noted that for the common skill of the art
For art personnel, on the premise of without departing from the utility model principle, some improvement can also be made, these improvement also should be regarded as
Protection domain of the present utility model.
Claims (4)
1. a kind of new long screw auger drilling deposited pile pile jacking cap integrative construction device, it is characterised in that:Including automatic stride
Formula car(1), and it is arranged on automatic walking car(1)On electric distribution operating room(2), three head pulleys(4), and arrange
In automatic walking car(1)Above and positioned at electric distribution operating room(2), three head pulleys(4)Between main turning hoisting machine(3), and
It is arranged on automatic walking car(1)And positioned at three head pulleys(4)The support in outside(5), and two ends difference connecting bracket(5)'s
Frame support bar(6), and it is arranged on support(5)On sleeping head saddle(7), and with sleeping head saddle(7)The power transmission box of connection
Body(8), and with power transmission casing(8)The drilling rod of connection(9), and it is arranged on drilling rod(9)On drilling rod blade(10), and arrange
In drilling rod blade(10)The drill bushing of end(13), wherein, drill bushing(13)It is internally provided with spiral link slot(11), and drill bushing(13)
Side and support(5)It is flexibly connected, and is arranged on drilling rod(9)The alloy bit of end(12).
2. a kind of new long screw auger drilling deposited pile pile jacking cap integrative construction device according to claim 1, its feature
It is:The support(5)For barrel-type supporting structure.
3. a kind of new long screw auger drilling deposited pile pile jacking cap integrative construction device according to claim 1, its feature
It is:The power transmission casing(8)It is 55KW for double-motor power transmission case body and power.
4. a kind of new long screw auger drilling deposited pile pile jacking cap integrative construction device according to claim 1, its feature
It is:The drilling rod blade(10), drill bushing(13)Diameter be respectively 500mm, 1000mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620557416.8U CN206090538U (en) | 2016-06-12 | 2016-06-12 | Novel long spiral drilling filling pile pile jacking cap integrated construction device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620557416.8U CN206090538U (en) | 2016-06-12 | 2016-06-12 | Novel long spiral drilling filling pile pile jacking cap integrated construction device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206090538U true CN206090538U (en) | 2017-04-12 |
Family
ID=58471791
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620557416.8U Expired - Fee Related CN206090538U (en) | 2016-06-12 | 2016-06-12 | Novel long spiral drilling filling pile pile jacking cap integrated construction device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206090538U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105862733A (en) * | 2016-06-12 | 2016-08-17 | 江苏昌鑫基础工程有限公司 | Novel long spiral drilling hole cast-in-situ pile top and cap integrated construction device |
-
2016
- 2016-06-12 CN CN201620557416.8U patent/CN206090538U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105862733A (en) * | 2016-06-12 | 2016-08-17 | 江苏昌鑫基础工程有限公司 | Novel long spiral drilling hole cast-in-situ pile top and cap integrated construction device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102002941B (en) | Large-aperture long screw rig, reinforcement cage concreting device and fabricating method of large-aperture deep pile | |
CN110374500B (en) | Grouped drilling and pile planting construction method | |
CN100572676C (en) | Large area sawed joint cutting construction method of concrete gravity dam cross joint | |
CN206090539U (en) | Long spiral drilling filling pile pile jacking cap integrated construction device of PLC control | |
CN107939277B (en) | Low-clearance double-rotary drilling machine and construction method thereof | |
CN206090538U (en) | Novel long spiral drilling filling pile pile jacking cap integrated construction device | |
CN105927154A (en) | Spiral drilling and pouring device applied to pile top and pile cap integrated construction | |
CN206053840U (en) | A kind of long screw auger drilling deposited pile pile jacking cap integrative construction device | |
CN206053838U (en) | A kind of auger boring device for casting for being applied to stake top pile cover integrated construction | |
CN105862732A (en) | PLC-controlled (programmable logic controller controlled) integrated construction apparatus for long-spiral cast-in-place bored pile top cap | |
CN105862733A (en) | Novel long spiral drilling hole cast-in-situ pile top and cap integrated construction device | |
CN206053870U (en) | A kind of boring assemblies of long screw auger drilling deposited pile pile jacking cap integrated construction | |
CN102322138A (en) | The modular sliding formwork | |
CN110331936B (en) | Combined drilling bottom-expanding pile-planting construction method | |
CN102251522B (en) | Filling pile coring method and combined concrete coring device | |
CN105888576A (en) | Drilling assembly for integrated construction of long spiral bored perfusion pile top and cap | |
CN206053839U (en) | It is applied to the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction | |
CN206873531U (en) | Guide rod type revolution cutting chute forming machine | |
CN212003077U (en) | Drill rod guiding device of rotary drilling rig | |
CN201535071U (en) | Retractor for quickly adjusting verticality of steel column | |
CN210530745U (en) | Combined drilling bottom-expanding pile-planting system | |
CN105927152A (en) | Pile body and pile cap integrated construction device for long spiral bored pile | |
CN212983846U (en) | Concrete-poured spiral building pile | |
CN201428378Y (en) | Drill for recycling tower crane foundation screws | |
CN106522830A (en) | Split-type spiral drilling machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: Room 609, Wanda Center Office Building, Yixing City, Wuxi City, Jiangsu Province Patentee after: Jiangsu Changxin Foundation Engineering Group Co.,Ltd. Address before: Room 609, Wanda Center Office Building, Yixing City, Wuxi City, Jiangsu Province Patentee before: JIANGSU CHANGXIN BASIC ENGINEERING CO.,LTD. |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170412 |