CN212983846U - Concrete-poured spiral building pile - Google Patents

Concrete-poured spiral building pile Download PDF

Info

Publication number
CN212983846U
CN212983846U CN202021011672.XU CN202021011672U CN212983846U CN 212983846 U CN212983846 U CN 212983846U CN 202021011672 U CN202021011672 U CN 202021011672U CN 212983846 U CN212983846 U CN 212983846U
Authority
CN
China
Prior art keywords
support column
supporting column
drill bit
column
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021011672.XU
Other languages
Chinese (zh)
Inventor
吴玉虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021011672.XU priority Critical patent/CN212983846U/en
Application granted granted Critical
Publication of CN212983846U publication Critical patent/CN212983846U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a concrete-poured spiral building pile, including first support column, second support column and third support column, the top of first support column, second support column and third support column inboard all is provided with the internal thread pipe, the bottom of first support column and second support column inboard is provided with the screwed pipe, and screwed pipe and internal thread pipe mutual adaptation, the bottom of third support column is provided with the drill bit, the both sides of the outside bottom of first support column, the both sides of the outside top of second support column and bottom and the both sides of the outside top of third support column all are provided with the fixed block; the utility model discloses the device can carry out the dismouting to whole device through mutually supporting of the supplementary inserted bar of first support column, fixed block, second support column, third support column, screwed pipe, threaded rod and second, can help operating personnel to assemble whole device on the one hand, and on the other hand makes things convenient for operating personnel to transport.

Description

Concrete-poured spiral building pile
Technical Field
The utility model relates to a construction technical field specifically is a concrete filling spiral building pile.
Background
With the continuous development of social economy, the building industry is rapidly developed; at present, when a building is built on a building site, piles are required to be piled on the ground; however, most of the existing piling technologies are that holes are drilled in the ground, and concrete is poured into the holes after the reinforcing steel bar frames are placed into the drilled holes;
and current concrete fills spiral building pile, still has comparatively obvious problem: 1. most of the existing devices are integrated, the effect of disassembling the devices is poor, on one hand, the operation personnel assemble the whole devices more complexly, and on the other hand, the operation personnel are inconvenient to transport; 2. the existing device can generate large shaking during perfusion, the device needs to be assisted and fixed, but the existing device has poor effect of assisting and fixing the device, and the stability of fixing the device is further reduced; 3. the effect of taking out unnecessary earth is lower when installing, and the operating personnel of being inconvenient for installs it.
Disclosure of Invention
An object of the utility model is to provide a concrete filling spiral building pile to propose current concrete filling spiral building pile in solving above-mentioned background art, still have comparatively obvious problem: 1. most of the existing devices are integrated, the effect of disassembling the devices is poor, on one hand, the operation personnel assemble the whole devices more complexly, and on the other hand, the operation personnel are inconvenient to transport; 2. the existing device can generate large shaking during perfusion, the device needs to be assisted and fixed, but the existing device has poor effect of assisting and fixing the device, and the stability of fixing the device is further reduced; 3. the effect of taking out unnecessary earth is lower when installing, the problem of being not convenient for operating personnel to install it.
In order to achieve the above object, the utility model provides a following technical scheme: a concrete-poured spiral building pile comprises a first supporting column, a second supporting column and a third supporting column, wherein internal thread pipes are arranged at the inner tops of the first supporting column, the second supporting column and the third supporting column, threaded pipes are arranged at the inner bottoms of the first supporting column and the second supporting column and are matched with the internal thread pipes, a drill bit is arranged at the bottom of the third supporting column, fixing blocks are arranged on the two sides of the outer bottom of the first supporting column, the two sides of the outer top and the bottom of the second supporting column and the two sides of the outer top of the third supporting column, a threaded rod is sleeved inside the fixing blocks, crossed supporting rods are arranged at the inner bottoms of the first supporting column and the second supporting column, first auxiliary inserting rods are symmetrically arranged on the two sides of the inner portion of the drill bit and extend to the outer portion of the drill bit, a first collecting groove is arranged at the inner top of the drill bit, the bilateral symmetry at first collecting vat top is provided with the gyro wheel, and the gyro wheel laminates with the inner wall of drill bit each other, the inside top of first support column and second support column is provided with supplementary fixed subassembly, the intermediate position department of the inside one side of first support column and second support column is provided with the bracing piece, the outside of first support column and second support column evenly overlaps and is equipped with the thread.
Preferably, supplementary fixed subassembly includes supplementary inserted bar of second, hinge bar and second collecting vat, the supplementary inserted bar of second is located the top of the inside both sides of first support column and second support column, and the supplementary inserted bar of second extends to the outside of first support column and second support column, and is two sets of one side that the supplementary inserted bar of second is close to each other articulates there is the hinge bar, the top of hinge bar articulates there is the second collecting vat.
Preferably, the first collecting groove is made of a V-shaped structure, and the first collecting groove and the first auxiliary inserting rod are attached to each other.
Preferably, the second collecting groove is made of an arc-shaped structure, and the second collecting groove is matched with the supporting rod.
Preferably, the middle position inside the fixed block is provided with an internal thread hole, and the internal thread hole is matched with the threaded rod.
Preferably, the drill bit and the third support column are welded to each other, and the outer side of the drill bit is provided with threads.
Compared with the prior art, the beneficial effects of the utility model are that: this spiral building pile that concrete pours into can carry out the dismouting to the whole of device, and the operating personnel of being convenient for installs and transports, can also carry out auxiliary stay to whole device to can also take out unnecessary earth:
1. the whole device can be disassembled and assembled through the mutual matching of the first support column, the fixed block, the second support column, the third support column, the threaded pipe, the threaded rod and the second auxiliary insertion rod, so that on one hand, an operator can be helped to assemble the whole device, and on the other hand, the operator can conveniently transport the device;
2. through the mutual matching of the first auxiliary insertion rod, the first collecting groove, the roller, the supporting rod, the second auxiliary insertion rod, the hinge rod and the second collecting groove, the first auxiliary insertion rod and the second auxiliary insertion rod can be ejected out during pouring, so that the whole device is subjected to auxiliary fixing, and the fixing stability of the device is further improved;
3. through mutually supporting of first support column, second support column and thread, can take out unnecessary earth when installing, the operating personnel of being convenient for installs it.
Drawings
Fig. 1 is a front sectional view of the present invention;
FIG. 2 is a front view of the present invention;
fig. 3 is a top view of the present invention;
fig. 4 is an enlarged schematic view of a structure in fig. 1 according to the present invention.
In the figure: 1. a first support column; 2. a cross-shaped support bar; 3. a fixed block; 4. a second support column; 5. a third support column; 6. a drill bit; 7. a first auxiliary insertion rod; 8. a first holding tank; 9. a roller; 10. a threaded pipe; 11. a threaded rod; 12. a support bar; 13. a second auxiliary insertion rod; 14. an internally threaded tube; 15. screw teeth; 16. a hinged lever; 17. a second holding tank.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides an embodiment: a concrete-poured spiral building pile comprises a first supporting column 1, a second supporting column 4 and a third supporting column 5, wherein the tops of the inner sides of the first supporting column 1, the second supporting column 4 and the third supporting column 5 are all provided with an internal threaded pipe 14, redundant soil can be taken out when the building pile is installed, and an operator can conveniently install the building pile, the bottoms of the inner sides of the first supporting column 1 and the second supporting column 4 are provided with threaded pipes 10, the threaded pipes 10 and the internal threaded pipes 14 are mutually adaptive, the bottom of the third supporting column 5 is provided with a drill bit 6, the two sides of the bottom of the outer side of the first supporting column 1, the two sides of the top and the bottom of the outer side of the second supporting column 4 and the two sides of the top of the outer side of the third supporting column 5 are all provided with fixing blocks 3, a threaded rod 11 is sleeved inside each fixing block 3, the whole device can be disassembled and assembled, on the other hand, the transportation is convenient for operators, the bottom parts of the inner parts of the first supporting column 1 and the second supporting column 4 are provided with the crossed supporting rods 2, the two sides of the inner part of the drill bit 6 are symmetrically provided with the first auxiliary inserted rods 7, the first auxiliary inserted bar 7 extends to the outside of the drill bit 6, the top of the inside of the drill bit 6 is provided with a first collecting groove 8, the first auxiliary inserted bar 7 and the second auxiliary inserted bar 13 can be ejected out during pouring, the whole device is fixed in an auxiliary way, so that the stability of the device is improved, the two sides of the top of the first collecting tank 8 are symmetrically provided with rollers 9, and the inner wall of gyro wheel 9 and drill bit 6 is laminated each other, and the inside top of first support column 1 and second support column 4 is provided with supplementary fixed subassembly, and the intermediate position department of the inside one side of first support column 1 and second support column 4 is provided with bracing piece 12, and the outside of first support column 1 and second support column 4 is evenly overlapped and is equipped with thread 15.
Further, supplementary fixed subassembly includes the supplementary inserted bar 13 of second, articulated rod 16 and second collecting vat 17, and the supplementary inserted bar 13 of second is located the top of the inside both sides of first support column 1 and second support column 4, and the supplementary inserted bar 13 of second extends to the outside of first support column 1 and second support column 4, and one side that two sets of supplementary inserted bars 13 of second are close to each other articulates there is articulated rod 16, and articulated rod 16's top articulates there is second collecting vat 17, is convenient for fix.
Further, first collecting vat 8 is made by V style of calligraphy structure, and first collecting vat 8 and first supplementary inserted bar 7 laminate each other, are convenient for promote.
Further, the second collecting groove 17 is made of an arc-shaped structure, and the second collecting groove 17 is matched with the supporting rod 12, so that the collection is convenient.
Further, the inside intermediate position department of fixed block 3 is provided with the internal thread hole, and the internal thread hole and 11 mutual adaptations of threaded rod, the block of being convenient for.
Further, the drill bit 6 and the third support column 5 are welded to each other, and the outer side of the drill bit 6 is provided with threads, so that the drill bit is convenient to rotate.
The working principle is as follows: when the device is used, the first support column 1 is taken up, the threaded pipe 10 is driven to be inserted into the inner part of the internal threaded pipe 14 through the first support column 1, the second support column 4 and the third support column 5 are spliced, then the threaded rod 11 is inserted into the inner parts of the fixed blocks 3, the two groups of fixed blocks 3 are driven to be fixed by rotating the threaded rod 11, then the whole device is rotated, the drill bit 6 is driven to rotate through the rotating force, the device is driven to be inserted into soil through the drill bit 6, and in the inserting process, the soil is taken out through the screw teeth 15;
after the installation is accomplished, toward first support column 1, the inside concreting of second support column 4 and third support column 5, it descends to drive second collecting vat 17 through the concrete, it outwards carries out the top through second collecting vat 17 drive hinge bar 16, then promote the supplementary inserted bar 13 of second and outwards remove through hinge bar 16, it is supplementary fixed to carry out through the supplementary inserted bar 13 of second, then support second collecting vat 17 through bracing piece 12, support the inside of first support column 1 and second support column 4 through crossing bracing piece 2, fall on the top of first collecting vat 8 through the concrete that fills, it rolls in the outside of drill bit collecting vat 6 to drive gyro wheel 9 through first collecting vat 8, drive two sets of first supplementary inserted bars 7 outwards to extend through first collecting vat 8, carry out the auxiliary stay to it through first supplementary inserted bar 7.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a spiral building pile is filled to concrete, includes first support column (1), second support column (4) and third support column (5), its characterized in that: the top of the inner sides of the first supporting column (1), the second supporting column (4) and the third supporting column (5) is provided with an internal threaded pipe (14), the bottom of the inner sides of the first supporting column (1) and the second supporting column (4) is provided with a threaded pipe (10), the threaded pipe (10) is matched with the internal threaded pipe (14), the bottom of the third supporting column (5) is provided with a drill bit (6), the two sides of the outer side bottom of the first supporting column (1), the two sides of the outer side top and the bottom of the second supporting column (4) and the two sides of the outer side top of the third supporting column (5) are provided with fixed blocks (3), a threaded rod (11) is sleeved inside the fixed blocks (3), the bottom of the inner parts of the first supporting column (1) and the second supporting column (4) is provided with a crossed supporting rod (2), the two sides of the inner parts of the drill bit (6) are symmetrically provided with first auxiliary, and first supplementary inserted bar (7) extend to the outside of drill bit (6), the inside top of drill bit (6) is provided with first collecting vat (8), the bilateral symmetry at first collecting vat (8) top is provided with gyro wheel (9), and laminates each other with the inner wall of drill bit (6) gyro wheel (9), the inside top of first support column (1) and second support column (4) is provided with supplementary fixed subassembly, the intermediate position department of the inside one side of first support column (1) and second support column (4) is provided with bracing piece (12), the even cover in the outside of first support column (1) and second support column (4) is equipped with thread (15).
2. The concrete-poured spiral building pile according to claim 1, wherein: supplementary fixed subassembly includes supplementary inserted bar (13), articulated rod (16) and second collecting vat (17) of second, supplementary inserted bar (13) of second is located the top of the inside both sides of first support column (1) and second support column (4), and the supplementary inserted bar (13) of second extends to the outside of first support column (1) and second support column (4), and is two sets of one side that supplementary inserted bar (13) of second are close to each other articulates there is articulated rod (16), the top of articulated rod (16) articulates there is second collecting vat (17).
3. The concrete-poured spiral building pile according to claim 1, wherein: the first collecting groove (8) is made of a V-shaped structure, and the first collecting groove (8) is attached to the first auxiliary inserting rod (7).
4. The concrete-poured spiral building pile according to claim 2, wherein: the second collecting groove (17) is made of an arc-shaped structure, and the second collecting groove (17) is matched with the supporting rod (12).
5. The concrete-poured spiral building pile according to claim 1, wherein: the middle position department of fixed block (3) inside is provided with the internal thread hole, and internal thread hole and threaded rod (11) mutual adaptation.
6. The concrete-poured spiral building pile according to claim 1, wherein: the drill bit (6) and the third supporting column (5) are welded with each other, and threads are arranged on the outer side of the drill bit (6).
CN202021011672.XU 2020-06-05 2020-06-05 Concrete-poured spiral building pile Expired - Fee Related CN212983846U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021011672.XU CN212983846U (en) 2020-06-05 2020-06-05 Concrete-poured spiral building pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021011672.XU CN212983846U (en) 2020-06-05 2020-06-05 Concrete-poured spiral building pile

Publications (1)

Publication Number Publication Date
CN212983846U true CN212983846U (en) 2021-04-16

Family

ID=75423942

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021011672.XU Expired - Fee Related CN212983846U (en) 2020-06-05 2020-06-05 Concrete-poured spiral building pile

Country Status (1)

Country Link
CN (1) CN212983846U (en)

Similar Documents

Publication Publication Date Title
CN106193141B (en) A kind of impaired pier footing method for reinforcing of earthquake
CN106640149A (en) Steel arch frame suitable for semi-automatic installation of large cross-section tunnel and installation method of steel arch frame
CN101255691B (en) Construction method for complete casing tube thin wall filling pile and movable internal mold
CN204753628U (en) Guider that hangs down is transferred to contrary way of doing things steel -pipe column that can have enough to meet need
CN212983846U (en) Concrete-poured spiral building pile
CN214460467U (en) Construction supporting device of town road drainage structures
CN101725147B (en) Construction process of first-inserting last-jetting type steel churning pile enclosing structure under low net space
CN208415303U (en) A kind of branch module being used to support connection concrete-placing reinforcing steel bar cage and template
CN207863185U (en) A kind of Novel steel pipe concrete pole splicing apparatus of band edge sleeve-board cylinder
CN206128787U (en) Assembled dregs strorage device
CN104878775A (en) Turnable top-down method steel pipe column verticality adjusting guide device and construction method thereof
CN209874150U (en) Take assembled shear force wall of corner
CN206053840U (en) A kind of long screw auger drilling deposited pile pile jacking cap integrative construction device
CN206053838U (en) A kind of auger boring device for casting for being applied to stake top pile cover integrated construction
CN208415304U (en) A kind of casting system of fit drawing die plate minitype underground pipe gallery
CN209686411U (en) A kind of formwork bracing system of internal support of foundation pit beam
CN206887984U (en) A kind of photovoltaic generation support steel bar concrete reinforcement steel pipe pile foundation
CN206053870U (en) A kind of boring assemblies of long screw auger drilling deposited pile pile jacking cap integrated construction
CN110965787A (en) Reverse construction method construction wall body reinforcing bar location structure
CN207161020U (en) One kind is used for aided oil drill rod connecting device
CN206941883U (en) Assembled is without interior weldering combined steel plate shearing force wall
CN206752474U (en) A kind of foundation pit steel support bracket pre-embedded device
CN101914990B (en) Beam-type transition layer cast-in-situ crossbeam construction formwork supporting system
CN206768843U (en) One kind combination strength stem
CN206768852U (en) Combine strength stem suspension column supporting construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210416

CF01 Termination of patent right due to non-payment of annual fee