CN205975648U - Freezing pipe curtain steel pipe - Google Patents

Freezing pipe curtain steel pipe Download PDF

Info

Publication number
CN205975648U
CN205975648U CN201620004379.8U CN201620004379U CN205975648U CN 205975648 U CN205975648 U CN 205975648U CN 201620004379 U CN201620004379 U CN 201620004379U CN 205975648 U CN205975648 U CN 205975648U
Authority
CN
China
Prior art keywords
pipe
freezing
steel pipe
curtain
curtain steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620004379.8U
Other languages
Chinese (zh)
Inventor
胡俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hainan University
Original Assignee
Hainan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hainan University filed Critical Hainan University
Priority to CN201620004379.8U priority Critical patent/CN205975648U/en
Application granted granted Critical
Publication of CN205975648U publication Critical patent/CN205975648U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model discloses a freezing pipe curtain steel pipe, including the pipe -roof steel pipe, be provided with a plurality of roots freezing pipe parallel with the pipe -roof steel pipe in the pipe -roof steel pipe, it has the filler to be full of in the space between pipe -roof steel pipe inner wall and the freezing pipe outer wall. When freezing pipe quantity in the pipe -roof steel pipe was the even number, per two freezing pipe were a set of, and are outside through the two piece freezing pipe tip UNICOMs of U type pipe with each group in pipe -roof steel pipe one end. When freezing pipe quantity in the pipe -roof steel pipe was the odd number, it can independent endless feed pipe all to put into in each freezing pipe. The utility model discloses make up pipe -roof steel pipe and freezing pipe, frozen soil wall between pipe -roof steel pipe and pipe -roof (wherein freezing pipe actively freeze institute forms) makes up the atress system of strutting jointly of the big rigidity of formation together, but the loss of effective control groundwater to the interval of pipe -roof steel pipe be can increase, thereby pipe -roof steel pipe quantity, construction and operation safety are reduced.

Description

Freezing pipe curtain steel pipe
Technical field
The utility model is related to a kind of brick or concrete duct, especially a kind of freezing pipe curtain steel pipe.
Background technology
With the acceleration of Urbanization Process In China, build Large Underground Structure under downtown roads or important building more next More.For shallow embedding big cross section, short-range city tunnel, uneconomical using shield construction, using cut and cover method to city City's productive life interference is larger.When geological conditions is poor, buried depth is shallower, Sensitive Buildings are arranged at top, if adopting shallow embedding Shallow mining method, surface subsidence is difficult to control to, once construction accident, will result in significant social influence.Therefore, how to look for The construction method wearing Sensitive Buildings under a kind of shallow large-section underground structure being suitable for saturation rich water soft soil layer is very heavy Will.
Pipe-roof method is exactly to head into steel pipe first with pipe-jacking technology in the underground structure surrounding planned to build, using lock between steel pipe Mouth etc. carries out sealing, forms the watertightness underground space, then under the protection of big rigidity pipe curtain, surrounds the scope soil body to pipe curtain and enters Row excavates and pours a kind of method of agent structure.Because pipe curtain forms big rigidity temporary support structures, it is possible to reduce during excavation The earth's surface deformation causing, it is to avoid produce impact to surrounding building, for shallow embedding big cross section weak soil, building be intensive, environment is protected Protect the engineering having high demands, there is unrivaled advantage.
Pipe-roof method has the characteristics that:
1st, soft soil layer big cross section pipe-roof method builds underground structure is usually to enter in the case of not having condition to take cut and cover method Row;
2nd, usual pipe-roof method build underground structure earthing ratio is shallower, needs to pass through sensitive pipeline, road and structures, over the ground The requirement of table deformation is higher;
3rd, it is applied to vcehicular tunnel, cross dimensions is than larger operating mode more;
4th, pipe-roof method can select different concrete engineering methods according to different stratum, surrounding enviroment and cross dimensions, that is, manage Curtain method can derive many different pipe-roofing method;
5th, pipe curtain construction should adopt push bench process, because the earth's surface that push bench process can meet minimum deforms, higher attitude Control accuracy.
The pipe-roofing method scope of application is wider, and from the point of view of the case history that abroad oneself has, pipe-roofing method is applied to backfill, sand The various stratum such as soil, clay, rock stratum, has broad application prospects.
In recent years, domestic more and more to pipe-roof method application, have also been made some improvement, occur in that " new pipe-roofing method " (New Tubular Roof Method, abbreviation NTR engineering method), also have person skilled to be called " method built in advance by pipe curtain ".It is main Technology path is:Or drawn cluster large diameter steel pipe pushing tow to stratum using more traditional pipe-jacking technology or shield technique In, in large diameter steel pipe, body is constructed, and joins together into the underground structure outline of design anticipation, then in the guarantor of shaped structure Shield is lower to excavate inside configuration stratum, and internal structure of constructing.
Because large diameter steel pipe defines big rigidity temporary support structures, it is possible to reduce the earth's surface deformation causing during excavation, Avoid producing impact to surrounding building, for shallow embedding big cross section weak soil, building is intensive, environmental protection requirement is high engineering, There is unrivaled advantage.
Pipe-roofing method, based on single tube jacking, relies on fore shaft to be connected to form pipe row in steel pipe side between each single tube, and Fore shaft space injection water-stop is to reach sealing requirement.After the completion of pipe row's jacking, form pipe curtain, then the soil body in pipe curtain is regarded Soil property situation decides whether to carry out consolidation process;Subsequently internally support while excavating, until pipe curtain section excavates insertion, then Pour internal structure.Pipe curtain can be various shapes, including semi-circular, round, door type, hollow etc..Pipe curtain is by rigid Steel pipe forms interim soil-baffling structure, with reduce during excavation to the disturbance of the neighbouring soil body and correspondingly reduction surrounding soil deformation, Reach and do not affect land operations during excavation and maintain the purpose of top buildings or structures and pipeline normal usage function.
However, when pipe curtain steel pipe is not linear but it may be difficult to ensure that the sealing between two push pipes latches into during shaped form Work(connects, and then is difficult to ensure that the water sealing effect of pipe curtain.Meanwhile, for ensureing the water sealing effect of pipe curtain, between linear pipe curtain push pipe Every close, so that pipe curtain push pipe increasing number, cause the waste of great manpower, material resources and financial resources.
Utility model content
The purpose of this utility model is for overcoming above-mentioned the deficiencies in the prior art, providing a kind of freezing pipe curtain steel pipe, it was both Can ensure that the water sealing effect of pipe curtain, the quantity of pipe curtain steel pipe can be reduced again, be particularly suitable for saturation rich water soft soil layer Shallow large-section underground structure under wear Sensitive Buildings construction when supporting construction in.
For achieving the above object, the utility model adopts following technical proposals:
A kind of freezing pipe curtain steel pipe, including pipe curtain steel pipe, is provided with some and is put down with pipe curtain steel pipe in described pipe curtain steel pipe The freezing pipe of row, described pipe curtain steel pipe inner wall and freeze between pipe outer wall space in be filled with filler.
When the freezing pipe quantity in pipe curtain steel pipe is even number, every two freezing pipes are one group, outside pipe curtain steel pipe one end Portion freezes tube end UNICOM by U-tube by two of each group.Low temperature refrigerant medium flows into from wherein freezing pipe, through U Type freezing pipe flows into second freezing pipe, then through second freezing pipe effuser curtain steel pipe, such circulation first makes in pipe curtain steel pipe Filler form Frozen Soil Cylinder, As time goes on make the soil body outside pipe curtain steel pipe form Frozen Soil Cylinder again.
When the freezing pipe quantity in pipe curtain steel pipe is odd number, all puts in each freezing pipe and be capable of independent loops Feed pipe.Low temperature refrigerant medium forms circulation by feed pipe in single freezing pipe, is now no longer provided with U-shaped freezing pipe, often Root freezing pipe is all an independent circulating unit.
Described filler is concrete, soil cement, clay, sand or water.
Described pipe curtain diameter of steel tube is 0.8m-2m.
Described freezing pipe material is seamless low carbon steel pipe, PVC, PPR, ABS or PE plastic tube;When using liquid nitrogen freezing, Using described plastic tube.
The described tube section that freezes is circular, I-shaped, X-shaped, T-shaped or Y shape.
The beneficial effects of the utility model are:
Pipe curtain steel pipe and freezing pipe are combined by the utility model, and the Frozen Soil Cylinder of pipe curtain steel pipe and pipe interlude is (wherein Freezing pipe actively freezes to be formed) together combination form the common supporting stress system of big rigidity, can effective control underground water Running off, and the spacing of pipe curtain steel pipe can be increased, thus reducing pipe curtain steel pipe quantity, constructing and operation security, be particularly suitable for using In supporting construction when wearing Sensitive Buildings construction under the shallow large-section underground structure of saturation rich water soft soil layer.
Brief description
Fig. 1 is embodiment 1 front view;
Fig. 2 is embodiment 1 rearview;
Fig. 3 is embodiment 1 side view;
Fig. 4 is embodiment 2 front view;
Fig. 5 is embodiment 2 side view;
Fig. 6 is the support construction process chart with freezing pipe curtain steel pipe;
Fig. 7 is pipe curtain steel pipe jacking construction process figure;
Fig. 8 is freezing engineering construction process figure;
Wherein, 1. freezing pipe, 2. filler, 3. pipe curtain steel pipe, 4.U type pipe, 5. feed pipe.
Specific embodiment
With reference to the accompanying drawings and examples the utility model is further illustrated.
Embodiment 1:
As shown in Figure 1-Figure 3, freezing pipe curtain steel pipe, including the pipe curtain steel pipe 3 of a diameter of 0.8m-2m, described pipe curtain steel pipe 3 In be provided with some freezing pipes 1 parallel with pipe curtain steel pipe 3, described pipe curtain steel pipe inner wall and freeze the space between pipe outer wall In be filled with filler 2.Filler 2 is concrete, soil cement, clay, sand or water.
When freezing pipe 1 quantity in pipe curtain steel pipe 3 is even number, every two freezing pipes 1 are one group, in pipe curtain steel pipe 3 one End outside by U-tube 4 by each group of two freezing pipes 1 end UNICOM.Low temperature refrigerant medium flows from wherein freezing pipe 1 Enter, flow into second freezing pipe 1 through U-tube 4, then through second freezing pipe 1 effuser curtain steel pipe 3, such circulation first makes pipe curtain Filler 2 in steel pipe 3 forms Frozen Soil Cylinder, As time goes on makes the soil body outside pipe curtain steel pipe 3 form Frozen Soil Cylinder again.
Freezing pipe 1 material is seamless low carbon steel pipe, PVC, PPR, ABS or PE plastic tube;When using liquid nitrogen freezing, adopt Plastic tube.Freezing pipe 1 section is circular, I-shaped, X-shaped, T-shaped or Y shape.
Embodiment 2:
As shown in Figure 4, Figure 5, freezing pipe curtain steel pipe, including the pipe curtain steel pipe 3 of a diameter of 0.8m-2m, described pipe curtain steel pipe 3 In be provided with some freezing pipes 1 parallel with pipe curtain steel pipe 3, described pipe curtain steel pipe inner wall and freeze the space between pipe outer wall In be filled with filler 2.Filler 2 is concrete, soil cement, clay, sand or water.
When freezing pipe 1 quantity in pipe curtain steel pipe 3 is odd number, all puts in each freezing pipe 1 and can independently follow The feed pipe 5 of ring.Low temperature refrigerant medium forms circulation by feed pipe in single freezing pipe 1, is now no longer provided with U-tube 4, Every freezing pipe 1 is all an independent circulating unit.
Freezing pipe 1 material is seamless low carbon steel pipe, PVC, PPR, ABS or PE plastic tube;When using liquid nitrogen freezing, adopt Plastic tube.Freezing pipe 1 section is circular, I-shaped, X-shaped, T-shaped or Y shape.
The construction technology of above-mentioned two embodiment is as shown in Figure 6.
The construction procedure forming supporting construction build underground structure with freezing pipe curtain steel pipe is as follows:
1st, upper pipe working well and received well are constructed;
2nd, steel pipe jacking, jacking order is symmetrically to be carried out from lower to upper on the basis of the axis of cross section;
Note:Steel pipe laying method has:Fixed (leading) to Drilling Method, horizontal spiral drilling method, ram pipe construction method, push bench process, micro- Type push bench process/micro-tunneling construction method, the most frequently used and it is recommended that push bench process.
3rd, in pipe curtain steel pipe 3, freezing pipe 1 is constructed, depending on the number of freezing pipe 1 is by designing.
4th, (filler 2 can be coagulation to inject filler 2 in the space between pipe curtain steel pipe 3 and wherein freezing pipe 1 Soil, soil cement, clay, sand are it might even be possible to be water).
5th, actively freeze to form Frozen Soil Cylinder.
6th, excavate in the supporting construction that freezing pipe curtain steel pipe is formed, support in excavation.
7th, construct internal structure paragraph by paragraph, ultimately form complete underground structure.
First, pipe curtain steel pipe pipe-jacking project arrangement and method for construction, technological process
(1) pipe curtain steel pipe situation
Pipe curtain steel pipe 3 diameter generally can take 0.8m-2m it is also possible to select bigger diameter according to concrete engineering situation.
(2) soil stabilization
First design requirement can be pressed to the soil body at hole before pipe curtain steel pipe push pipe jacking to reinforce, soil stabilization can be in active well Carry out during construction.
(3) through walls appear
First slice off pre-buried steel box outside plate before appearing, and water-stopping steel boxing is connected to the outside of pre-buried steel box, then will Watertight rubber circle is arranged on sealing steel loop.When preparing to appear, side block soil steel plate in steel box is sliced off, the reserved in the hole of cleaning Immediately tool heads are advanced embedded hole after debris, shorten the dead time, make watertight rubber circle hug tool heads shell and play sealing Effect.
To prevent tool heads from dropping when push pipe is through walls, at the initial stage through walls, less because burying, the deadweight of tool heads is only by two Point supports, and is wherein guide rail, on the other hand bury the shallower soil body.Therefore, when tool heads are through walls, one on the one hand be carried Initial angle (about 5 ') upwards, another aspect wall pipe bottom will have rest, and strengthens pipeline section and tool pipe, pipeline section and pipeline section Between connection.Additionally, the propulsion of tool pipe must be rapid, do not make the soil body open-assembly time in wall pipe oversize.
(4) normal jacking
Pipeline is appeared after success, starts normal jacking.While tube coupling advances, the push-bench semi shield oil cylinder cutting front soil body Discharge.Successively pushed ahead by tube coupling one, push-bench constantly advances last arrival received well, forms whole section of passage.
(5) pipe curtain steel pipe landing edge
Joint passes through welding annular and vertical stiffener reinforcing pipes end, increases its rigidity, the annular strength reinforced at it On plate, connecting bolt, carry out spacing and fixing in work progress.On socket, setting twice neoprene packing circle is prevented Water.Joint will have the adaptability of certain corner.
(6) enter received well
After push-bench reaches soil stabilization scope before received well, move speed should be slowed down, so that push-bench is slowly cut The soil body, forms a more complete sealing hole.Make the particular location of push-bench outlet by measurement, by received well tool heads position The concrete guard wall put cuts.When push-bench enters received well side, fast jacking wanted by push-bench, until push-bench ejects completely Received well.
(7) pipe curtain mud displacement
After pipe curtain jacking terminates, for prevent pipe curtain occur delayed sedimentation, by design requirement material by jack-in process Thixotropic slurry displace.Carried out using the system of pressure injection thixotropic slurry and pipeline during displacement.Pressure injection order:From first segment Guan Yi Secondary carry out backward.
(8) pipe curtain filling concrete and filling
After pipe curtain jacking finishes and then installs freezing pipe wherein, can be filled with using slightly expanded concrete, apply Hammering and ultrasound examination concrete compaction rate and whether closely connected and steel pipe between is used after work is complete.
(9) pipe curtain lubrication drag reduction
Using in the annulus between bentonite thixotropic slurry flow in pipes and surrounding soil layer, realization reduces jacking pipeline Frictional resistance and stratum between.Slip casting is three parts, and the slip casting at slurry and hole is mended in tail synchronous slip casting, pipeline along the line.Touch The basis becoming mud is made up of bentonite and water, in addition, according to the different soil body mix the outer-penetrating agent of different polymer Lai Adjust mud property to meet use requirement.
(10) pipe curtain steel pipe jacking construction flow process
Push pipe jacking construction flow process is as shown in Figure 7.
2nd, freezing engineering arrangement and method for construction, technological process
Freezing engineering construction process is as shown in Figure 8:
(1) freeze pipe construction
Freezing pipe is laid in pipe curtain steel pipe by design requirement, can arrange heating tube or pressure relief vent if necessary, to control Frost heaving processed.
(2) freezing pipe leak test
Carry out leak test after Freezing Station installation on request and vacuumize it is ensured that installation quality meets design requirement.
(3) freezing system installation and debugging
1. press 1.5 times of coefficient of refrigerating performance and match refrigeration plant.Refrigeration plant prepares 2 sets, a set of production, a set of emergent.
2. pipeline is connected with flange, expansion joint to be arranged, valve and survey in saline line and cooling water circulation pipeline The testing elements such as Wen Yi, pressure gauge, flowmeter.Saline line is after leak test, cleaning with polystyrene foam plastics insulation, insulation The outside plastic sheeting of layer is wrapped up.Collection brine distributing ring and the connection high-pressure rubber pipe of freezing pipe, the import and export of every freezing pipe are each One, valve of dress, to control flow.
3. the evaporimeter of freezing unit and cryogenic pipe cotton-wool insulation, brine tank and the salt water conduit tube thick polyphenyl of 50mm Vinylic foam plate is incubated.
4. unit fills fluorine and refrigerator refuels and carries out according to the requirement of equipment operating manual.Carry out refrigeration system first Leak detection and nitrogen rinse, and after guaranteeing system ne-leakage, then fill fluorine oiling.
5. debugged after equipment installs and test running.In test running, each shape such as pressure, temperature to be adjusted at any time State parameter, makes unit run under the conditions of the technical parameter about technological procedure and equipment requirement.
(4) actively freeze the stage.During freezing test running, timing detection brine temp, brine flow and frozen soil curtain Curtain spread scenarios, adjust freezing system operational factor if necessary.Freezing system enters after working well and actively freezes.Actively freeze Knot, it is simply that making full use of whole abilities of equipment, accelerates frozen soil development as early as possible, in design time, brine temp is dropped to design Temperature.
(5) safeguard according to observed temperature data, freezing the stage will judge whether Frozen Soil Cylinder is handed over circle and reached design thickness, Thermometric judges that Frozen Soil Cylinder friendship carries out inspecting hole examination again and digs after enclosing and reaching design thickness, confirms soil layer no circulating water in Frozen Soil Cylinder (except saturation water) is formally excavated again afterwards.
(6), after the completion for the treatment of internal seal water structure, set brine heater in brine tank, hypothermic saline is heated, right Frost wall carries out forced thaw, and using the mud sleeve grouting device previously reserved, is tracked formula thaw settlement grouting.Force solution Freeze and be conducted batch-wise using subregion.
Although the above-mentioned accompanying drawing that combines is described to specific embodiment of the present utility model, not new to this practicality The restriction of type protection domain, one of ordinary skill in the art should be understood that on the basis of the technical solution of the utility model, ability Field technique personnel do not need to pay the various modifications that creative work can make or deformation still in protection model of the present utility model Within enclosing.

Claims (5)

1. a kind of freezing pipe curtain steel pipe, is characterized in that, including pipe curtain steel pipe, is provided with some and pipe curtain in described pipe curtain steel pipe The parallel freezing pipe of steel pipe, described pipe curtain steel pipe inner wall and freeze between pipe outer wall space in be filled with filler;
When the freezing pipe quantity in pipe curtain steel pipe is even number, every two freezing pipes are one group, logical outside pipe curtain steel pipe one end Cross U-tube and freeze tube end UNICOM by two of each group;
When the freezing pipe quantity in pipe curtain steel pipe is odd number, each freezing pipe is all put into the feed flow being capable of independent loops Pipe.
2. freezing pipe curtain steel pipe as claimed in claim 1, is characterized in that, described filler be concrete, soil cement, clay, Sand or water.
3. freezing pipe curtain steel pipe as claimed in claim 1, is characterized in that, described pipe curtain diameter of steel tube is 0.8m-2m.
4. freezing pipe curtain steel pipe as claimed in claim 1, is characterized in that, described freezing pipe material be seamless low carbon steel pipe, PVC, PPR, ABS or PE plastic tube;When using liquid nitrogen freezing, using described plastic tube.
5. freezing pipe curtain steel pipe as claimed in claim 1, is characterized in that, described freeze tube section be circular, I-shaped, X-shaped, T-shaped or Y shape.
CN201620004379.8U 2016-01-05 2016-01-05 Freezing pipe curtain steel pipe Expired - Fee Related CN205975648U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620004379.8U CN205975648U (en) 2016-01-05 2016-01-05 Freezing pipe curtain steel pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620004379.8U CN205975648U (en) 2016-01-05 2016-01-05 Freezing pipe curtain steel pipe

Publications (1)

Publication Number Publication Date
CN205975648U true CN205975648U (en) 2017-02-22

Family

ID=58018455

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620004379.8U Expired - Fee Related CN205975648U (en) 2016-01-05 2016-01-05 Freezing pipe curtain steel pipe

Country Status (1)

Country Link
CN (1) CN205975648U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589706A (en) * 2018-05-11 2018-09-28 佳琳 A kind of compound frozen soil steel pipe pile construction method
CN111472367A (en) * 2020-03-19 2020-07-31 中国矿业大学 Freezing anchoring combined freezing cold plate and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589706A (en) * 2018-05-11 2018-09-28 佳琳 A kind of compound frozen soil steel pipe pile construction method
CN111472367A (en) * 2020-03-19 2020-07-31 中国矿业大学 Freezing anchoring combined freezing cold plate and method

Similar Documents

Publication Publication Date Title
CN205975649U (en) Freezing pipe curtain steel pipe supporting construction
CN104963334B (en) Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement
CN108035335B (en) Method for constructing shaft type underground parking garage by freezing method
CN102913250B (en) Shield tunnel-entering construction method at stratum rich in water powder and soil powder sand
CN104832196B (en) Pipe curtain freezing process supporting construction and its construction method
CN104806253B (en) A kind of construction method punched between rectangular top pipe passage
CN105003270B (en) Underwater tunnel construction method suitable for ultra-shallow earthing conditions
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN108843328A (en) A kind of Metro Connection Passage excavation construction support construction method
CN105908765B (en) For protecting the open trench tunnel water sealing structure and construction method of groundwater environment
CN104074525A (en) Full-sectional grouting, rectangular horizontal freezing and pipe roof combined reinforcing structure and method
CN111593726A (en) Joint reinforcement method for underground tunnel penetrating sensitive pipeline of water-rich stratum and butt joint of existing structure MJS + artificial freezing
CN106761814A (en) A kind of pipe curtain and bamboo reinforcement grouted anchor bar combined retaining structure and method
CN105926636A (en) Freezing bottom-sealing construction method for deep foundation pit
CN109296371A (en) MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station
CN104675405B (en) Rectangular pipe jacking machine tunnel entering auxiliary structure and construction method
CN111810198A (en) Tunnel earth surface directional large-caliber deep hole grouting device and grouting method
CN105937397A (en) Segmented excavation freezing method reinforcing construction method for deep tunnel
CN108825247B (en) External inclination side wall horizontal bottom-making basin-shaped freezing water stop construction method for 8 pilot tunnel PBA construction method
Hu et al. Application of liquid nitrogen freezing to recovery of a collapsed shield tunnel
CN105064335A (en) Ultrahigh pressure rotary jet grouting method suitable for sandy cobble stratum shield end well reinforcement
CN105927234A (en) Construction method for reinforcing and excavating horizontal tunnel by multi-vertical-shaft freezing method
CN103924980B (en) Remove obstacles construction method
CN205975648U (en) Freezing pipe curtain steel pipe
CN107829747B (en) Construction method suitable for shallow-buried underground excavation tunnel in expansive soil area

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170222

Termination date: 20190105